CN215462920U - Construction pavement spraying system - Google Patents

Construction pavement spraying system Download PDF

Info

Publication number
CN215462920U
CN215462920U CN202121548460.XU CN202121548460U CN215462920U CN 215462920 U CN215462920 U CN 215462920U CN 202121548460 U CN202121548460 U CN 202121548460U CN 215462920 U CN215462920 U CN 215462920U
Authority
CN
China
Prior art keywords
construction
water supply
spray
access road
drainage channel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121548460.XU
Other languages
Chinese (zh)
Inventor
樊志飞
陈开桥
刘亚明
刘立云
程建华
李先武
柴强
崔瑞飞
常飞飞
何占魁
吉雷雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
7th Engineering Co Ltd of MBEC
Original Assignee
7th Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 7th Engineering Co Ltd of MBEC filed Critical 7th Engineering Co Ltd of MBEC
Priority to CN202121548460.XU priority Critical patent/CN215462920U/en
Application granted granted Critical
Publication of CN215462920U publication Critical patent/CN215462920U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

The application relates to a construction access spraying system, and relates to the technical field of civil engineering construction. The both sides of the construction service aisle in this construction service aisle spray system are equipped with drainage channel respectively, drainage channel is the V-arrangement, construction service aisle both sides are located respectively to two sets of units that spray, and lie in between two drainage channel, each unit that sprays all includes one along the water supply assembly and the spray assembly on water supply assembly are located to a plurality of intervals of construction service aisle length direction setting, spray assembly includes spray bar and fixing base, the one end of spray bar is equipped with the shower head, the other end rotates and locates on the fixing base, the fixing base erects on water supply assembly and links to each other with construction service aisle, so that be used for with spray bar and water supply assembly respectively with construction service aisle fixed. The application provides a construction way spraying system easy dismounting can not produce destruction to the way, has solved among the correlation technique when adopting the watering lorry to spray water to the construction way water waste serious, and the big problem of operating personnel working strength.

Description

Construction pavement spraying system
Technical Field
The application relates to the technical field of civil engineering construction, in particular to a construction access spraying system.
Background
At present, along with infrastructure's acceleration, building site is everywhere visible in the city, and the environment is complicated among the building construction site, has piled up many building materials, consequently or causes can produce many dust in the work progress, the dust of production is dissipated outside can seriously influence the environment in city, even causes the inconvenience of near resident life, consequently, along with green construction, environmental protection construction requirement strengthens gradually, present building site construction pavement requires to keep moist constantly, in order to reduce the raise dust.
Among the correlation technique, the conventionality adopts the watering lorry to make a round trip to spill the dust fall, it can be effectively swift to the construction pavement moist, the effect that reduces the raise dust is obvious, but, adopt the watering lorry also to have some shortcomings, firstly, the watering of watering lorry takes more water, it is the road surface that can drench, but often can excessive drainage, secondly, in summer, because the temperature is higher, it is comparatively strong sunshine, the moisture on road surface evaporates soon, consequently, the number of times of watering can greatly increased when high temperature in summer, this driving watering lorry that needs operating personnel high frequency word carries out watering work, when causing the water waste in a large number, still can increase operating personnel's intensity of labour. In addition, a plurality of current spraying devices are generally fixed in a buried mode, the spraying devices can be well fixed in the fixed mode, but the spraying devices are high in destructiveness during disassembly, construction access needs to be chiseled open and then repaired, the workload is high, the buried devices are generally easy to destroy during disassembly, and the buried devices cannot be reused and are high in construction cost.
SUMMERY OF THE UTILITY MODEL
The embodiment of the application provides a construction access road spraying system to solve among the correlation technique when adopting the watering lorry to sprinkle water to construction access road, water waste is serious, and because the improper problem that causes reuse rate low, operating personnel working strength is big of fixed mode.
In a first aspect, a construction access way spray system is provided, which comprises:
the construction access road is provided with drainage channels on two sides respectively, and the drainage channels are in a V shape;
two sets of spray units, it is located respectively the construction pavement both sides are located two between the drainage channel, each spray unit all includes one and follows water supply assembly and a plurality of interval that construction pavement length direction set up locate spray assembly on the water supply assembly, spray assembly includes spray bar and fixing base, the one end of spray bar is equipped with the shower head, and the other end rotates to be located on the fixing base, the fixing base erect in water supply assembly go up and with the construction pavement links to each other, so that with spray bar and water supply assembly respectively with the construction pavement is fixed.
In some embodiments, the water supply assembly includes a main water supply pipeline and a plurality of branch water supply pipelines, the main water supply pipeline is arranged on one side of the construction access and laid along the length direction of the construction access, and the branch water supply pipelines are arranged at intervals along the length direction of the main water supply pipeline.
In some embodiments, the main and sub-feed water pipes are one of steel pipes and plastic pipes.
In some embodiments, the fixing seat comprises a fixing block, the fixing block is U-shaped, the size of the inner surface of the closed end of the fixing block is matched with the size of the cross section of the main water supply pipeline, a connecting block is arranged on the outer surface of the closed end, one end of the connecting block is fixedly connected with the closed end, and the other end of the connecting block is rotatably connected with the spray rod.
In some embodiments, a cushion is provided on the inner surface of the closed end of the mounting block.
In some embodiments, both sides of the open end of the fixing block horizontally extend towards the outside to form a fixing plate, at least one fixing through hole is formed in the fixing plate, and a fixing rivet for connecting the fixing plate and the construction access way is arranged on the fixing through hole.
In some embodiments, the inner side wall of the drainage channel is provided with a step structure, and the step surface of the step structure is an inclined surface with gradually reduced horizontal height towards the direction far away from the inner side wall of the drainage channel.
In some embodiments, a filter screen is arranged on one side of the step surface of the step structure, which is far away from the inner side wall of the drainage channel, along the length direction of the step surface.
In some embodiments, the spray header is rotatably disposed at a corresponding end of the spray rod and is connected to the spray rod through an electric spherical hinge rotating member, and the spray rod is hinged to the connecting block and rotates in a direction close to the construction access in a vertical plane where the spray rod is located.
In some embodiments, the distance between every two adjacent spraying assemblies is 15-20 m, a plurality of water pumps are arranged on each main water supply pipeline at intervals, and the distance between every two adjacent water pumps is 350-400 m.
The beneficial effect that technical scheme that this application provided brought includes:
the embodiment of the application provides a construction access road spraying system, it is different from the tradition and needs to bury the water supply assembly underground in the below of construction access road and carry out the mode of fixing, water supply assembly in this system locates on the road surface of construction access road, spray assembly includes spray bar and fixing base, set up the shower head at the top of spray bar, the bottom then fixes its self and water supply assembly jointly on the construction access road through the fixing base, be provided with the drainage channel who is the V-arrangement in addition in water supply assembly's both sides. This construction access road spraying system installation is dismantled conveniently, only need dismantle the installation fixing base can, and fixed also very firm, whole process is hardly destroyed to the construction access road, and the installation is dismantled very high-efficiently, the drainage channel of V-arrangement compares general straight following formula drainage channel in addition, it more does benefit to and collects unnecessary water, and the process of digging needs the soil of digging still less, correspond, also the same when filling out, labour saving and time saving when ageing and good drainage can be guaranteed to whole process.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings needed to be used in the description of the embodiments are briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present application, and it is obvious for those skilled in the art to obtain other drawings based on these drawings without creative efforts.
Fig. 1 is a schematic structural diagram of a construction access road spraying system provided in an embodiment of the present application;
fig. 2 is a schematic structural diagram of a spraying unit of the construction access road spraying system provided in the embodiment of the present application.
In the figure: 1-construction access, 2-spraying unit, 20-water supply component, 201-main water supply pipeline, 21-spraying component, 210-spraying rod, 211-fixing seat, 212-spraying head, 213-fixing block, 214-connecting block, 215-fixing plate, 3-drainage channel, 30-step structure and 4-filter screen.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present application clearer, the technical solutions in the embodiments of the present application will be clearly and completely described below with reference to the drawings in the embodiments of the present application, and it is obvious that the described embodiments are some embodiments of the present application, but not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present application.
The embodiment of the application provides a construction access road spraying system, which can solve the problems that in the related art, when a sprinkler is adopted for sprinkling water to a construction access road, water resource waste is serious, the repeated utilization rate is low due to the improper fixing mode, and the working strength of operators is high.
Referring to fig. 1, the construction access road spraying system comprises a construction access road 1 and two groups of spraying units 2, wherein two sides of the construction access road 1 are respectively provided with a drainage channel 3, the drainage channel 3 is in a V shape, the two groups of spraying units 2 are respectively arranged at two sides of the construction access road 1 and are positioned between the two drainage channels 3, each spraying unit 2 comprises a water supply component 20 arranged along the length direction of the construction access road 1 and a plurality of spraying components 21 arranged on the water supply component 20 at intervals, each spraying component 21 comprises a spraying rod 210 and a fixing seat 211, one end of each spraying rod 210 is provided with a spraying head 212, the other end of each spraying rod 210 is rotatably arranged on the fixing seat 211, the fixing seat 211 is erected on the water supply component 20 and is connected with the construction access road 1, so that the spraying rods 210 and the water supply components 20 are respectively fixed with the construction access road 1.
Further, water supply assembly 20 mainly includes main water supply pipe 201 and many branch water supply pipes, and main water supply pipe 201 locates one side of construction access 1 and lays along its length direction, and many branch water supply pipes set up along main water supply pipe 201's length direction interval, link to each other through the multi-way valve between with main water supply pipe 201.
Specifically, the main water supply pipe 201 and the branch water supply pipe are made of one of steel pipes and plastic pipes, and the combination manner may be various, for example, the first type is that the main water supply pipe 201 and the branch water supply pipe are made of steel pipes, the second type is that the main water supply pipe 201 is made of steel pipes, the branch water supply pipe is made of plastic pipes, the third type is that the main water supply pipe 201 is made of plastic pipes, the branch water supply pipe is made of steel pipes, and the fourth type is that the main water supply pipe 201 and the branch water supply pipe are made of plastic pipes. The selection of the material of main water supply pipeline 201 and branch water supply pipeline here mainly depends on the budget of construction and the actual environment of construction, and steel pipe intensity itself is good, and is longe-lived, is difficult for taking place the seepage, but whole price is on the high side, also is difficult for accomodating, and the plastic tubing is convenient to be accomodate, but its support nature is low, and takes place to leak after ageing or by other hard object fish tails easily.
Further, the fixing seat 211 mainly includes a fixing block 213, the fixing block 213 is U-shaped, the size of the inner surface of the closed end of the fixing block is matched with the size of the cross section of the main water supply pipe 201, and when the fixing block is used specifically, the fixing block is clamped on the main water supply pipe 201 in a direction that the closed end is located above and the open end is located below. Be equipped with a connecting block 214 on the surface of blind end, connecting block 214 one end is fixed with the blind end and links to each other, the other end rotates with spray rod 210 and links to each other, can adjust spray rod 210's angle, because construction pavement 1 width broad can reach 12 meters, consequently, the region in the middle of the way probably does not spill water at all, when meetting the construction pavement 1 of width broad, then need adjust spray rod 210's angle, make it rotatory towards the center of pavement, make the position of shower head 212 be close to in the middle of the way more, guarantee that whole road surface homoenergetic spills water.
Further, when the main water supply pipe 201 is made of a steel pipe, the main water supply pipe may be rigidly connected to the fixing block 213, and the connection may be unstable, so that a buffer pad is disposed on the inner surface of the closed end of the fixing block 213 to ensure the stability of the connection.
Further, both sides of the open end of the fixing block 213 horizontally extend outward to form a fixing plate 215, at least one fixing through hole is formed on the fixing plate 215, and a fixing rivet for connecting the fixing plate 215 and the construction access 1 is formed on the fixing through hole.
Further, because the job site environment is more complicated, debris and dust are more, at the in-process of drainage, some earth or debris can be along with unnecessary rivers to the drainage channel 3 in, in order to prevent that these debris and earth from directly flowing to the drainage channel 3 bottom and hindering the drainage and do not salvage well, consequently all be equipped with stair structure 30 on the lateral wall of drainage channel 3, and stair structure 30's step face is the inclined plane that reduces gradually towards the direction level of keeping away from the 3 inside walls of drainage channel, can play and block the row of not influencing water when debris.
Furthermore, one side of the step surface of the step structure 30, which is far away from the inner side wall of the drainage channel 3, is provided with the filter screen 4 along the length direction, so that sundries and large soil can be further prevented from entering the drainage channel 3, and the step structure can be better salvaged and cleaned in the cleaning process.
Further, the spray header 212 is rotatably disposed at the corresponding end of the spray rod 210, and is connected to the spray rod 210 through an electric spherical hinge rotating member, and the spray rod 210 is hinged to the connecting block 214 and rotates in the vertical plane where the spray rod is located along the direction close to the construction access 1. Specifically, the rotation angle of the spray header 212 is almost 360 degrees, and the spraying is convenient for each area of the construction access 1.
Further, as shown in fig. 2, the distance between every two adjacent spraying assemblies 21 is 15-20 m, a plurality of water pumps are arranged on each main water supply pipeline 201 at intervals, the distance between every two adjacent water pumps is 350-400 m, and a filtering structure is arranged between each water pump and the main water supply pipeline 201 to ensure the smoothness of each pipeline. In addition, construction way 1 includes two-layerly from down supreme, is thick rubble layer and concrete surface course in proper order, and the thickness on thick rubble layer is 20 ~ 25cm, and the thickness on concrete surface course is 15 ~ 20cm, because water is all towards the road surface center at the injection, drenches the road surface of both sides in order to guarantee hydroenergy flow direction both sides to and discharge unnecessary water into drainage channel 3 in, the road center all has 2% slope along both sides, makes things convenient for the water at road center to arrange to both sides.
The construction access road spraying system is convenient and efficient to mount and dismount, only the mounting and fixing seat 211 needs to be dismounted, the fixing is very firm, the whole process almost does not damage the construction access road 1, the workload of constructors is greatly reduced, and the spraying units 2 can be repeatedly used as digging, chiseling, dismounting and mounting are not needed; in addition, the V-shaped drainage channel 3 is provided with the step structure 30 and the filter screen 4, so that redundant water can be collected, sundries and soil can be effectively prevented from entering the drainage channel 3 along with water flow, and the smoothness of drainage is guaranteed.
In the description of the present application, it should be noted that the terms "upper", "lower", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, which are only for convenience in describing the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed in a specific orientation, and operate, and thus, should not be construed as limiting the present application. Unless expressly stated or limited otherwise, the terms "mounted," "connected," and "connected" are intended to be inclusive and mean, for example, that they may be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present application can be understood by those of ordinary skill in the art as appropriate.
It is noted that, in the present application, relational terms such as "first" and "second", and the like, are used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising an … …" does not exclude the presence of other identical elements in a process, method, article, or apparatus that comprises the element.
The above description is merely exemplary of the present application and is presented to enable those skilled in the art to understand and practice the present application. Various modifications to these embodiments will be readily apparent to those skilled in the art, and the generic principles defined herein may be applied to other embodiments without departing from the spirit or scope of the application. Thus, the present application is not intended to be limited to the embodiments shown herein but is to be accorded the widest scope consistent with the principles and novel features disclosed herein.

Claims (10)

1. The utility model provides a construction way sprinkling system which characterized in that, it includes:
the construction access road (1) is provided with drainage channels (3) on two sides respectively, and the drainage channels (3) are V-shaped;
two sets of spray unit (2), it is located respectively construction way (1) both sides, and be located two between drainage channel (3), each spray unit (2) all include one along water supply assembly (20) and a plurality of interval that construction way (1) length direction set up locate spray assembly (21) on water supply assembly (20), spray assembly (21) are including spray bar (210) and fixing base (211), the one end of spray bar (210) is equipped with shower head (212), and the other end rotates to be located on fixing base (211), fixing base (211) erect water supply assembly (20) go up and with construction way (1) link to each other, in order to be used for with spray bar (210) and water supply assembly (20) respectively with construction way (1) is fixed.
2. The construction access road spray system of claim 1, wherein: feed water subassembly (20) including main water supply pipeline (201) and many branch water supply pipeline, main water supply pipeline (201) are located one side of construction water supply pipeline (1) is laid along its length direction, many divide water supply pipeline to follow the length direction interval of main water supply pipeline (201) sets up.
3. The construction access road spray system of claim 2, wherein: the main water supply pipeline (201) and the branch water supply pipeline are one of steel pipes and plastic pipes.
4. The construction access road spray system of claim 2, wherein: fixing base (211) include fixed block (213), fixed block (213) are the U-shaped, the size of the internal surface of its blind end with the cross section size matching of main water supply pipe (201), be equipped with a connecting block (214) on the surface of blind end, connecting block (214) one end with the blind end is fixed continuous, the other end with spray bar (210) rotate continuously.
5. The construction access road spray system of claim 4, wherein: the inner surface of the closed end of the fixed block (213) is provided with a buffer pad.
6. The construction access road spray system of claim 4, wherein: the both sides of the open end of fixed block (213) are respectively towards outside horizontal extension in order to form stationary blade (215), be equipped with an at least fixed through-hole on stationary blade (215), be equipped with on the fixed through-hole and be used for connecting stationary blade (215) and construction way (1) fixing rivet.
7. The construction access road spray system of claim 4, wherein: the inner side wall of the drainage channel (3) is provided with a step structure (30), and the step surface of the step structure (30) is an inclined surface which gradually reduces in horizontal height towards the direction far away from the inner side wall of the drainage channel (3).
8. The construction access road spray system of claim 7, wherein: and a filter screen (4) is arranged on one side, far away from the inner side wall of the drainage channel (3), of the step surface of the step structure (30) along the length direction of the filter screen.
9. The construction access road spray system of claim 4, wherein: the spray header (212) rotates and locates the corresponding end of spray bar (210) to rotate through electronic ball pivot with spray bar (210) link to each other, spray bar (210) are articulated with connecting block (214), and rotate along being close to in its vertical plane of place the direction of construction access way (1).
10. The construction access road spray system of claim 2, wherein: every two adjacent spray assembly (21) apart from being 15 ~ 20m, each all be equipped with a plurality of water pumps at the interval on main water supply pipe (201), every two adjacent the distance of water pump is 350 ~ 400 m.
CN202121548460.XU 2021-07-08 2021-07-08 Construction pavement spraying system Active CN215462920U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121548460.XU CN215462920U (en) 2021-07-08 2021-07-08 Construction pavement spraying system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121548460.XU CN215462920U (en) 2021-07-08 2021-07-08 Construction pavement spraying system

Publications (1)

Publication Number Publication Date
CN215462920U true CN215462920U (en) 2022-01-11

Family

ID=79725442

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121548460.XU Active CN215462920U (en) 2021-07-08 2021-07-08 Construction pavement spraying system

Country Status (1)

Country Link
CN (1) CN215462920U (en)

Similar Documents

Publication Publication Date Title
CN106836445A (en) A kind of trapezoidal gutter based on adjustable groove mould pours forming method
CN201072932Y (en) High altitude stereo greening groove
CN104652214A (en) Paving method of water-permeable pavement
CN111139919B (en) Municipal road construction structure and construction method thereof
CN215462920U (en) Construction pavement spraying system
CN205804423U (en) A kind of discharge structure of basement
CN210263929U (en) A preformed hole template for building civil engineering
KR20230135931A (en) Rainwater penetration drain gutter with water spray function
CN210959768U (en) Urban building water storage irrigation equipment
CN210917382U (en) Foundation pit supporting structure
CN109024147B (en) Comprehensive recycling system for sandbar water source and construction method thereof
CN213187511U (en) Watering device of municipal administration public works
CN211573593U (en) Water collecting and draining device for top plate of underground roadway
CN212993609U (en) Be used for municipal works rainwater automatic collection watering device
CN113897983A (en) Mountain reinforcing apparatus for mine ecological restoration
CN212910927U (en) Hydraulic engineering's ecological wall structure
CN217500503U (en) Multifunctional cover plate of underground reservoir
CN211006252U (en) Road roller for building engineering
CN213805712U (en) Water saving system for municipal building engineering
CN215168704U (en) Dustproof fender that encloses of highway construction
CN217870545U (en) Be used for highway side slope photovoltaic grillage drainage structures
CN110886378A (en) Construction method of water storage vibration reduction device installed under greening road and sidewalk
CN215405393U (en) Special brick that permeates water of dismouting of being convenient for in gardens
CN217028379U (en) Rail guard for civil engineering
CN217501296U (en) Rail for construction with dust fall function

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant