CN214994501U - Floor accumulated water discharge structure for high-rise building construction - Google Patents

Floor accumulated water discharge structure for high-rise building construction Download PDF

Info

Publication number
CN214994501U
CN214994501U CN202120514792.XU CN202120514792U CN214994501U CN 214994501 U CN214994501 U CN 214994501U CN 202120514792 U CN202120514792 U CN 202120514792U CN 214994501 U CN214994501 U CN 214994501U
Authority
CN
China
Prior art keywords
ponding
building construction
rise building
sleeve
discharge structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202120514792.XU
Other languages
Chinese (zh)
Inventor
张利华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202120514792.XU priority Critical patent/CN214994501U/en
Application granted granted Critical
Publication of CN214994501U publication Critical patent/CN214994501U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Sewage (AREA)

Abstract

The utility model relates to a construction drainage equipment technical field specifically is a floor ponding discharge structure for high-rise building construction, gather the lower extreme of basin and install the raceway, and gather the upper surface mounting of basin and have spacing, spacing internally mounted has the net that leaks, the internally mounted who gathers the basin has the mounting bracket, install the motor on the mounting bracket, the live-rollers is installed to the output of motor, the upper end of live-rollers runs through the net that leaks and installs the installation cover. The utility model discloses simple structure does benefit to the filtration of grit, mud through being provided with of leaking the net, under the effect of motor, live-rollers, rotating turret and scraper blade, can avoid grit, mud to pile up and cause the jam on leaking the net effectively, improve equipment handles the efficiency of ponding, in addition, when ponding by water delivery pipe flow to sleeve in, ponding erodees curved vane to make curved vane rotate, further make ponding form the swirl, be favorable to the discharge of ponding.

Description

Floor accumulated water discharge structure for high-rise building construction
Technical Field
The utility model relates to a building construction drainage equipment technical field specifically is a floor ponding discharge structure for high-rise building construction.
Background
When being under construction to high-rise building, because rain insensitive device such as installation window this moment, inevitable meeting entering rainwater in the floor, the rainwater can flow outdoor through floor drain etc. otherwise can cause ponding indoors, when handling this type of ponding, often need build the water drainage tank temporarily and guide ponding and discharge.
But because can use a lot of cement and mortar etc. during the construction, cement and mortar are very easily dropped subaerial along with sewage collects at water drainage tank department, water drainage tank's delivery port blocks up, lead to the drainage to be obstructed, cause indoor ponding, cement and mortar etc. in case block up the delivery port and will be difficult to clear up, if not in time clear up, indoor will produce the peculiar smell after long-time ponding, in addition, ponding can be unfavorable for the going on of construction work, and current equipment is because the fixed of outlet pipe specification, lead to ponding discharge efficiency limited, therefore, technical personnel in the field provide a floor ponding discharge structure for high-rise building construction, in order to solve the problem that proposes in the above-mentioned background art.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a floor ponding discharge structure for high-rise building construction to solve the problem that proposes among the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a floor ponding discharge structure for high-rise building construction, includes and gathers the basin, gather the lower extreme in basin and install the raceway, and gather the upper end in basin and install spacing, spacing internally mounted has the net that leaks, the internally mounted who gathers the basin has the mounting bracket, install the motor on the mounting bracket, the live-rollers is installed to the output of motor, the upper end of live-rollers runs through the net that leaks and installs the installation cover, evenly install the rotating turret on the installation cover, the scraper blade that offsets with the net that leaks is installed to the below of rotating turret, the lower extreme movable mounting of raceway has the sleeve, the hole that leaks has evenly been seted up on telescopic surface, and telescopic inside middle part position department rotates and installs the pivot, evenly install curved blade in the pivot.
As a further aspect of the present invention: the water delivery device is characterized in that a control box is installed on one side of the water delivery pipe, a storage battery is installed inside the control box, and a controller is arranged inside the control box and below the storage battery.
As a further aspect of the present invention: the upper surface of the limiting frame is provided with an annular slide rail at a position close to the outer edge, and the lower end of the rotating frame is provided with a slide column which is connected with the annular slide rail in a sliding manner.
As a further aspect of the present invention: the water collecting tank is a bowl-shaped structural member, the surfaces of the water collecting tank and the water delivery pipe are both provided with an anticorrosive coating, and the anticorrosive coating is made of epoxy resin.
As a further aspect of the present invention: the limiting sliding grooves are evenly formed in the sleeve, the lower end of the water conveying pipe extends into the sleeve and is evenly provided with sliding blocks in sliding connection with the limiting sliding grooves, and buffer springs are arranged between the upper ends of the sliding blocks and the upper surface of the limiting sliding grooves.
As a further aspect of the present invention: the scraper blade is a rubber component, and the cross section of scraper blade is a triangle-shaped.
As a further aspect of the present invention: the joint of the limiting frame and the water collecting tank is provided with a sealing gasket, and the sealing gasket is a rubber component.
As a further aspect of the present invention: rubber gaskets are mounted on two side walls of the upper end of the annular slide rail, and the other sides of the two rubber gaskets are abutted to form a movable seal which is uniform.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model has the advantages of simple structure, the modern design, be provided with through leaking the net and do benefit to the grit, the filtration of mud, including a motor, the live-rollers, under the effect of rotating turret and scraper blade, can avoid the grit effectively, mud is piled up and is caused the jam on leaking the net, improve equipment handles the efficiency of ponding, in addition, when ponding by delivery pipe flow to sleeve in, ponding erodees cowl, thereby make cowl rotate, further make ponding form the swirl, be favorable to the discharge of ponding, in addition, under the impact force and the gravity of ponding and buffer spring's the effect, can make the sleeve activity, thereby be favorable to changing the distance of raceway to sleeve bottom, further can change the efficiency of water effectively, improve equipment discharges the ability of ponding.
Drawings
Fig. 1 is a schematic structural view of a floor standing water discharge structure for high-rise building construction;
FIG. 2 is an enlarged schematic view of the structure at A in FIG. 1;
fig. 3 is an internal structural view of a floor standing water discharge structure for high-rise building construction.
In the figure: 1. a water collecting tank; 2. a limiting frame; 3. a leakage net; 4. a rotating roller; 5. installing a sleeve; 6. a rotating frame; 7. a squeegee; 8. a water delivery pipe; 9. a control box; 10. a sleeve; 11. a water leakage hole; 12. a traveler; 13. an annular slide rail; 14. a motor; 15. a mounting frame; 16. a limiting chute; 17. a slider; 18. a buffer spring; 19. a rotating shaft; 20. an arc-shaped blade.
Detailed Description
Referring to fig. 1 to 3, in an embodiment of the present invention, a floor standing water discharging structure for high-rise building construction includes a water collecting tank 1, a water pipe 8 is installed at a lower end of the water collecting tank 1, a limiting frame 2 is installed at an upper end of the water collecting tank 1, a draining net 3 is installed inside the limiting frame 2, an installation frame 15 is installed inside the water collecting tank 1, a motor 14 is installed on the installation frame 15, a rotating roller 4 is installed at an output end of the motor 14, an upper end of the rotating roller 4 penetrates through the draining net 3 and is installed with an installation sleeve 5, a rotating frame 6 is evenly installed on the installation sleeve 5, a scraper 7 abutting against the draining net 3 is installed below the rotating frame 6, a sleeve 10 is movably installed at a lower end of the water pipe 8, water leaking holes 11 are evenly opened on a surface of the sleeve 10, a rotating shaft 19 is rotatably installed at a middle position inside the sleeve 10, and arc-shaped blades 20 are evenly installed on the rotating shaft 19, do benefit to the grit through being provided with of leaking net 3, the filtration of mud, it is rotatory to make rotor roll 4 drive installation cover 5 under the effect of motor 14, thereby make rotor turret 6 drive scraper blade 7 rotate, sliding connection through between traveller 12 and the annular slide rail 13, be favorable to rotor turret 6 and scraper blade 7 to rotate, thereby can avoid the grit effectively, mud is piled up on leaking net 3, further avoid leaking net 3 jam effectively, improve equipment handles the efficiency of ponding, in addition, when ponding flows to sleeve 10 in by raceway 8, ponding erodees cowl 20, thereby make cowl 20 rotate, further make ponding form the swirl, be favorable to the discharge of ponding.
In fig. 3, a control box 9 is installed on one side of the water pipe 8, a storage battery is installed inside the control box 9, which mainly plays a role of power supply, and a controller is arranged below the storage battery inside the control box 9, so as to facilitate the control of the device.
In fig. 2, the upper surface of the limiting frame 2 is provided with an annular slide rail 13 at a position close to the outer edge, the lower end of the rotating frame 6 is provided with a slide column 12 connected with the annular slide rail 13 in a sliding manner, and the rotating frame 6 and the scraper 7 are facilitated to rotate through the sliding connection between the slide column 12 and the annular slide rail 13, so that sand and slurry can be effectively prevented from being accumulated on the leakage net 3, the blockage of the leakage net 3 is further effectively avoided, and the efficiency of treating accumulated water by equipment is improved.
In fig. 1, the water collecting tank 1 is a bowl-shaped structural member, so that accumulated water can be drained conveniently, the surfaces of the water collecting tank 1 and the water delivery pipe 8 are both provided with an anticorrosive layer, and the anticorrosive layer is a coating made of epoxy resin and mainly plays roles of corrosion prevention and rust prevention.
In fig. 3, limiting sliding groove 16 has evenly been seted up to sleeve 10's inside, the lower extreme of raceway 8 extends to sleeve 10's inside and evenly installs slider 17 with limiting sliding groove 16 sliding connection, install buffer spring 18 between slider 17's upper end and limiting sliding groove 16's the upper surface, sliding connection through between limiting sliding groove 16 and the slider 17, be favorable to sleeve 10 activity, under buffer spring 18's effect, be favorable to changing the distance of raceway 8 to sleeve 10 bottom, further can change the efficiency of exhalant effectively, improve equipment ponding's ability.
In fig. 2, the scraper 7 is a rubber member, and the cross section of the scraper 7 is a triangle, so as to improve the capability of the scraper 7 in scraping sand and mud.
In fig. 1, a sealing gasket is arranged at the joint of the limiting frame 2 and the water collecting tank 1, and the sealing gasket is a rubber component, so that the connection stability between equipment parts is improved.
In fig. 1, rubber gaskets are mounted on two side walls of the upper end of the annular slide rail 13, the other sides of the two rubber gaskets abut against each other to form a movable seal, and when the sliding column 12 passes through, the movable seal is opened, so that silt is prevented from entering the annular slide rail 13 and is uniform.
The utility model discloses a theory of operation is: the utility model has simple structure and novel design, when in use, the arrangement of the leakage net 3 is favorable for filtering sand stone and slurry, the rotating roller 4 drives the installation sleeve 5 to rotate under the action of the motor 14, thereby the rotating frame 6 drives the scraper 7 to rotate, the rotating frame 6 and the scraper 7 are favorable for rotating through the sliding connection between the sliding column 12 and the annular sliding rail 13, thereby the sand stone and the slurry can be effectively prevented from being accumulated on the leakage net 3, the blockage of the leakage net 3 is further effectively avoided, the efficiency of the device for processing accumulated water is improved, in addition, when the accumulated water flows into the sleeve 10 from the water pipe 8, the arc-shaped blade 20 is washed by the accumulated water, thereby the arc-shaped blade 20 is rotated, the accumulated water is further enabled to form a vortex, the discharge of the accumulated water is favorable, in addition, under the impact force and the gravity of the accumulated water and the action of the buffer spring 18, the sleeve 10 can move, thereby being beneficial to changing the distance from the water pipe 8 to the bottom of the sleeve 10, further effectively changing the water outlet efficiency and improving the accumulated water discharging capacity of the equipment.
The above-mentioned, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (8)

1. The utility model provides a floor ponding discharge structure for high-rise building construction, includes and gathers basin (1), its characterized in that, gather the lower extreme of basin (1) and install raceway (8), and gather the upper end of basin (1) and install spacing (2), spacing (2) internally mounted has hourglass net (3), the internally mounted who gathers basin (1) has mounting bracket (15), install motor (14) on mounting bracket (15), rotor roll (4) are installed to the output of motor (14), the upper end of rotor roll (4) runs through hourglass net (3) and installs mounting sleeve (5), evenly install rotating turret (6) on mounting sleeve (5), scraper blade (7) that offset with hourglass net (3) are installed to the below of rotating turret (6), the lower extreme movable mounting of raceway (8) has sleeve (10), the surface of sleeve (10) has evenly seted up hole (11) that leaks, and the inside middle part position department of sleeve (10) rotates and installs pivot (19), evenly install arc blade (20) on pivot (19).
2. The floor ponding discharge structure for high-rise building construction according to claim 1, characterized in that a control box (9) is installed at one side of the water pipe (8), a storage battery is installed inside the control box (9), and a controller is located inside the control box (9) below the storage battery.
3. The floor accumulated water discharge structure for high-rise building construction according to claim 1, wherein an annular slide rail (13) is arranged at a position, close to the outer edge, of the upper surface of the limiting frame (2), and a slide column (12) in sliding connection with the annular slide rail (13) is installed at the lower end of the rotating frame (6).
4. The floor accumulated water discharge structure for high-rise building construction according to claim 1, wherein the water collection tank (1) is a bowl-shaped structural member, the surfaces of the water collection tank (1) and the water delivery pipe (8) are both provided with an anticorrosive coating, and the anticorrosive coating is a coating made of epoxy resin.
5. The floor accumulated water discharge structure for high-rise building construction according to claim 1, wherein a limiting sliding groove (16) is uniformly formed in the sleeve (10), the lower end of the water pipe (8) extends into the sleeve (10) and is uniformly provided with a sliding block (17) in sliding connection with the limiting sliding groove (16), and a buffer spring (18) is arranged between the upper end of the sliding block (17) and the upper surface of the limiting sliding groove (16).
6. A floor standing water drain structure for high-rise building construction according to claim 1, wherein the scraper (7) is a member of a rubber material, and the cross section of the scraper (7) is a triangle.
7. The floor accumulated water discharge structure for high-rise building construction according to claim 1, wherein a sealing gasket is arranged at the joint of the limiting frame (2) and the water collecting tank (1), and the sealing gasket is a rubber component.
8. The floor accumulated water discharge structure for high-rise building construction according to claim 3, wherein rubber gaskets are mounted on two side walls of the upper end of the annular slide rail (13), and the other sides of the two rubber gaskets abut against each other to form a movable seal.
CN202120514792.XU 2021-03-09 2021-03-09 Floor accumulated water discharge structure for high-rise building construction Expired - Fee Related CN214994501U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202120514792.XU CN214994501U (en) 2021-03-09 2021-03-09 Floor accumulated water discharge structure for high-rise building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202120514792.XU CN214994501U (en) 2021-03-09 2021-03-09 Floor accumulated water discharge structure for high-rise building construction

Publications (1)

Publication Number Publication Date
CN214994501U true CN214994501U (en) 2021-12-03

Family

ID=79156100

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202120514792.XU Expired - Fee Related CN214994501U (en) 2021-03-09 2021-03-09 Floor accumulated water discharge structure for high-rise building construction

Country Status (1)

Country Link
CN (1) CN214994501U (en)

Similar Documents

Publication Publication Date Title
JPH0882298A (en) Drainage pump house and draining operation in drainage pump house
CN207078132U (en) A kind of Automatic Car Wash
CN208363235U (en) Overflow well with flow of intercepting pipeline controlled by floating barrel and pulley
CN214994501U (en) Floor accumulated water discharge structure for high-rise building construction
CN112282033B (en) Auxiliary drainage system for iron ore construction prevention and water control
CN112196435A (en) Household multi-control fire door
CN202555018U (en) Aerated grit structure with bridge type sand oil collector
CN108374471B (en) Drainage pump station
CN209323675U (en) One kind having the integrated prefabricated pumping plant of automatically cleaning
CN107178143B (en) Municipal administration rain, sewage sludge lifting system for pump station
CN113152637B (en) Integrated automatic intercepting well and intercepting method
CN111939704B (en) Dust collector for building engineering
CN214574444U (en) Water supply and drainage device for urban road
CN203821564U (en) Electric combined system pipe network shutoff well
CN215715978U (en) Prefabricated assembly type foundation's assembled building
CN213390457U (en) Anti-blocking floor drain
CN215759479U (en) Integrated automatic intercepting well
CN211753108U (en) Building sewage discharges filter equipment
CN211772815U (en) Bridge pipeline structure easy to clean
CN210412775U (en) Pipe fitting cutting equipment for hydraulic engineering
CN206246378U (en) Colliery face fault-free drag and suction device
CN219621840U (en) Anti-blocking device for water drainage pressure-reducing water outlet
CN218031593U (en) Non-return hinged water guide plate
CN104563277A (en) Folding gate type washing equipment for drainage network piping
CN217299262U (en) Municipal works pipeline drainage pull throughs

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20211203