CN214833931U - Light gauge steel furred ceiling structure - Google Patents

Light gauge steel furred ceiling structure Download PDF

Info

Publication number
CN214833931U
CN214833931U CN202121685170.XU CN202121685170U CN214833931U CN 214833931 U CN214833931 U CN 214833931U CN 202121685170 U CN202121685170 U CN 202121685170U CN 214833931 U CN214833931 U CN 214833931U
Authority
CN
China
Prior art keywords
sleeve
groove
keel
main joist
light gauge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202121685170.XU
Other languages
Chinese (zh)
Inventor
王飞虎
付志杰
周成良
陈珍
郑亚雄
钱军
艾贝
王威
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Construction Engineering Group Decoration Engineering Co ltd
Original Assignee
Wuhan Construction Engineering Group Decoration Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Construction Engineering Group Decoration Engineering Co ltd filed Critical Wuhan Construction Engineering Group Decoration Engineering Co ltd
Priority to CN202121685170.XU priority Critical patent/CN214833931U/en
Application granted granted Critical
Publication of CN214833931U publication Critical patent/CN214833931U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The application relates to a light steel keel ceiling structure, which relates to the field of building ceilings and comprises a suspender, a sleeve, a main keel, an auxiliary keel and a positioning assembly; the upper end rigid coupling of jib on the wall body, the vertical slip cap of sleeve is located the lower extreme of jib, locating component locates on the sleeve, locating component is used for making the sleeve with relative position between the jib is fixed, the main joist is located telescopic lower extreme, the false keel rigid coupling in the lower surface of main joist, the main joist with the false keel vertically and horizontally staggered lays. This application has the height of being convenient for adjust fossil fragments, keeps the effect of the better roughness of fossil fragments.

Description

Light gauge steel furred ceiling structure
Technical Field
The application relates to the field of building suspended ceilings, in particular to a light steel keel suspended ceiling structure.
Background
The light steel keel is a novel building material, is suitable for modeling decoration of various building roofs, internal and external walls of buildings and a base material of a shed frame type suspended ceiling, and decorative panels such as gypsum boards are installed on the lower surface of the light steel keel after the light steel keel is installed so as to complete the work of the indoor suspended ceiling.
A chinese patent with application number CN201922456746.4 discloses a load-bearing light steel keel ceiling structure, which comprises a suspension rod, a first fixing frame, a second fixing frame, a third fixing frame, a fourth fixing frame, a first keel, a second keel and a third keel; the hanger rod is connected with the ceiling through a first fixing frame; the first keel is connected with the suspension rod through a second fixing frame, and the first keel is connected with the second keel through a third fixing frame; the second keel is connected with the third keel through a fourth fixing frame.
With respect to the related art among the above, the inventors consider that the following drawbacks exist: because the length of hang lever is invariable, its height can't change after consequently fossil fragments installation, and when the staff need adjust the roughness of fossil fragments, is difficult to realize.
SUMMERY OF THE UTILITY MODEL
In order to facilitate the height of adjusting the fossil fragments, keep the better roughness of fossil fragments, this application provides a light gauge steel furred ceiling structure.
The application provides a light gauge steel furred ceiling structure adopts following technical scheme:
a light steel keel suspended ceiling structure comprises a hanging rod, a sleeve, a main keel, a secondary keel and a positioning assembly;
the upper end rigid coupling of jib on the wall body, the vertical slip cap of sleeve is located the lower extreme of jib, locating component locates on the sleeve, locating component is used for making the sleeve with relative position between the jib is fixed, the main joist is located telescopic lower extreme, the false keel rigid coupling in the lower surface of main joist, the main joist with the false keel vertically and horizontally staggered lays.
Through adopting above-mentioned technical scheme, during the installation, with the upper end and the wall body fixed of jib, install the main joist in telescopic lower extreme, the staff slides the sleeve from top to bottom according to the predetermined height that sets up of main joist, can realize the not regulation of main joist co-altitude to the staff of being convenient for carries out the leveling to the main joist, simultaneously, makes the relative position between sleeve and the jib fixed through locating component, and then realizes the fixed of main joist position, convenient operation, swift.
Optionally, the positioning assembly includes: the spring, the limiting block and the toggle piece;
the internal perisporium of sleeve upper end has seted up the fixed slot, the spring level is located in the fixed slot, the one end of spring with the fixed slot is kept away from the inside wall rigid coupling of jib, the stopper is located the other end of spring, the stopper is close to the one end of spring is located all the time in the fixed slot, a plurality of spacing grooves have been seted up on the jib, and is a plurality of the spacing groove is laid along vertical direction interval, the stopper is kept away from the one end of spring with spacing groove grafting adaptation, be equipped with on the stopper and dial the piece, it is used for making to dial the piece the stopper can break away from the spacing groove.
By adopting the technical scheme, when the height of the main keel needs to be adjusted, the limiting block is separated from the limiting groove through the poking piece, so that a worker can conveniently slide up and down to adjust the position of the main keel; when the sliding sleeve makes the height of the main keel reach a preset position, under the action of the restoring force of the spring, one end, far away from the spring, of the limiting block is inserted into the limiting groove, so that the relative position between the suspender and the sleeve is fixed, and the operation is convenient and rapid.
Optionally, the toggle member includes: a connecting plate and a shifting plate;
the movable groove is formed in the upper end face of the sleeve and arranged in the diameter direction of the sleeve, the lower end of the movable groove is communicated with the fixed groove, the connecting plate is vertically arranged on the upper surface of the limiting block, the upper end of the connecting plate penetrates through the movable groove, the connecting plate is matched with the movable groove in a sliding mode, the sliding direction of the connecting plate is the same as the diameter direction of the sleeve, and the poking plate is arranged at the upper end of the connecting plate and located above the sleeve.
Through adopting above-mentioned technical scheme, when needs sliding sleeve, through dialling the board pulling connecting plate to keeping away from the one side motion of jib, and then drive the stopper and break away from convenient operation, swift from the spacing groove.
Optionally, the positioning assembly is a positioning bolt, a threaded through hole is formed in the outer peripheral wall of the upper end of the sleeve, the positioning bolt is assembled in the threaded through hole in a threaded mode, a plurality of thread grooves are formed in the hanger rod and are distributed at intervals in the vertical direction, and the free end of the positioning bolt is assembled with the thread grooves in a threaded mode.
By adopting the technical scheme, the fixing between the suspender and the sleeve can be realized by screwing the positioning bolt to be inserted into the thread groove; the positioning bolt is screwed to be separated from the thread groove, so that the height of the main keel can be conveniently adjusted by sliding the sleeve by a worker, and the operation is convenient.
Optionally, one side of the hanger rod is provided with a first sliding block, the inner peripheral wall of the sleeve is provided with a first sliding groove which is vertically distributed, and the first sliding block is in sliding fit with the first sliding groove.
Through adopting above-mentioned technical scheme, difficult emergence when the sleeve slides along vertical direction is rotated to be convenient for the accurate assembly between stopper and the spacing groove or between positioning bolt and the thread groove.
Optionally, the second spout of T shape is seted up to the main joist up end, the second spout is followed the length direction of main joist lays and both ends all are the opening form, telescopic lower extreme is equipped with the second slider of T shape, the second slider with the sliding adaptation of second spout, be equipped with the retaining member on the main joist, the retaining member is used for making the sleeve with relative position between the main joist is fixed.
By adopting the technical scheme, when the main keel is installed, the second sliding block slides into the second sliding groove from one side, the T-shaped second sliding groove and the T-shaped second sliding block are convenient for pre-supporting the main keel, and a worker does not need to always hold the main keel for installation during installation, so that labor is saved; the retaining member is convenient for the installation between main joist and the sleeve to be fixed, improves the efficiency of construction.
Optionally, the locking member is a locking bolt, the main keel is provided with a positioning hole communicated with the second sliding groove, the locking bolt is assembled at the positioning hole in a threaded manner, a locking groove is formed in a position, corresponding to the positioning hole, of the second sliding block, and the free end of the locking bolt is assembled with the locking groove in a threaded manner.
Through adopting above-mentioned technical scheme, twist and move the locking bolt and can realize the rigid coupling or the separation between main joist and the sleeve, convenient operation, swift.
Optionally, the positioning holes are multiple, and the positioning holes are arranged at intervals along the length direction of the main keel.
Through adopting above-mentioned technical scheme, a plurality of locating holes are convenient for connect fixedly between the different positions of main joist and the sleeve, improve the practicality of light gauge steel furred ceiling structure.
In summary, the present application includes at least one of the following beneficial technical effects:
1. when the device is installed, the upper end of the suspender is fixed with the wall body, the main keel is installed at the lower end of the sleeve, and the sleeve is vertically slid by a worker according to the preset height of the main keel, so that the different heights of the main keel can be adjusted, and the worker can level the main keel conveniently;
2. the limiting block is separated from the limiting groove through the poking piece, so that the worker can conveniently slide up and down to adjust the position of the main keel; when the sleeve is slid to enable the height of the main keel to reach a preset position, one end, far away from the spring, of the limiting block is inserted into the limiting groove under the action of the restoring force of the spring, so that the relative position between the suspender and the sleeve is fixed, and the operation is convenient and rapid;
the second spout of T shape and the second slider of T shape are convenient for carry out pre-supporting to the main joist, and the staff is hand the main joist always and is installed when need not the installation, uses manpower sparingly.
Drawings
FIG. 1 is a schematic overall structure diagram of a first embodiment of the present application;
FIG. 2 is a schematic view of the connection between the sleeve, the hanger bar and the positioning assembly according to an embodiment of the present disclosure;
FIG. 3 is a schematic view of the connection between the hanger bar, sleeve and main runner in one embodiment of the present application;
fig. 4 is a schematic structural diagram of a second embodiment of the present application.
Reference numerals: 1. a boom; 101. a limiting groove; 102. a thread groove; 103. a first slider; 2. a sleeve; 21. fixing grooves; 22. a movable groove; 23. a threaded through hole; 24. a second slider; 241. a locking groove; 25. a first chute; 3. a main keel; 31. a second chute; 32. a locking member; 321. locking the bolt; 33. positioning holes; 4. a false keel; 5. a positioning assembly; 51. a spring; 52. a limiting block; 53. a toggle piece; 531. a connecting plate; 532. dialing a plate; 54. positioning the bolt; 6. and a baffle plate.
Detailed Description
The present application is described in further detail below with reference to figures 1-4.
The embodiment of the application discloses light gauge steel furred ceiling structure.
Example 1
Referring to fig. 1, the light gauge steel suspended ceiling structure includes a hanger rod 1, a sleeve 2, a main keel 3, a cross keel 4 and a positioning assembly 5; the upper end welded mounting panel of jib 1, the mounting panel is fixed in on the wall body through a plurality of expansion bolts, the periphery side of 1 lower extreme of jib is located to 2 covers of sleeve, and vertical slip assembly between sleeve 2 and the jib 1, locating component 5 is located on sleeve 2, locating component 5 is used for making the relative position between sleeve 2 and the jib 1 fixed, main joist 3 slides and sets up the lower extreme of sleeve 2, be equipped with retaining member 32 on the main joist 3, retaining member 32 is used for making the relative position between main joist 3 and the sleeve 2 fixed, the lower surface of main joist 3 is fixed to false keel 4 rigid coupling, main joist 3 lays with false keel 4 vertically and horizontally staggered.
Referring to fig. 1 and 2, the positioning assembly 5 includes: a spring 51, a stop block 52 and a toggle piece 53; fixed slot 21 has been seted up to the internal perisporium of sleeve 2 upper end, in fixed slot 21 was located to the spring 51 level, jib 1's inside wall rigid coupling was kept away from with fixed slot 21 to spring 51's one end, stopper 52 rigid coupling in spring 51's the other end, stopper 52 is close to spring 51's one end and is located fixed slot 21 all the time, a plurality of spacing grooves 101 have been seted up on jib 1, a plurality of spacing grooves 101 are laid along vertical direction interval, spring 51's one end and spacing groove 101 grafting adaptation are kept away from to stopper 52.
To facilitate the disengagement of the stopper 52 from the stopper groove 101. The stopper 52 is provided with a toggle member 53, and the toggle member 53 comprises: a connecting plate 531 and a dial plate 532; activity groove 22 has been seted up to sleeve 2's up end, activity groove 22 is laid along sleeve 2's diameter direction, activity groove 22 lower extreme is linked together with fixed slot 21, the vertical rigid coupling of connecting plate 531 is in the upper surface of stopper 52, activity groove 22 is run through to the upper end of connecting plate 531, connecting plate 531 is the same with the diameter direction of activity groove 22 slip adaptation and slip direction and sleeve 2, the width in activity groove 22 is less than the width of fixed slot 21, dial the board 532 rigid coupling in the upper end of connecting plate 531 and be located sleeve 2's top, dial board 532 and connecting plate 531 integrated into one piece.
When the height of the main keel 3 needs to be adjusted, the connecting plate 531 is pulled to move towards one side far away from the hanger rod 1 through the pulling plate 532, so that the limiting block 52 is driven to be separated from the limiting groove 101, and a worker can conveniently slide up and down to adjust the position of the main keel 3; when the sliding sleeve 2 enables the height of the main keel 3 to reach a preset position, under the action of the restoring force of the spring 51, one end, far away from the spring 51, of the limiting block 52 is inserted into the limiting groove 101, so that the relative position between the suspender 1 and the sleeve 2 is fixed, and the operation is convenient and rapid.
Referring to fig. 2 and 3, one side of jib 1 sets up the first slider 103 of rigid coupling, and vertical first spout 25 of laying is seted up to the internal perisporium of sleeve 2, and first spout 25 upper end opening part rigid coupling has baffle 6 to prevent that jib 1 from deviating from sleeve 2, first slider 103 and first spout 25 slip adaptation are difficult for taking place to rotate when making sleeve 2 slide along vertical direction, are convenient for stopper 52 and spacing groove 101's accurate grafting.
The upper end surface of the main keel 3 is provided with a T-shaped second sliding groove 31, the second sliding groove 31 is distributed along the length direction of the main keel 3, two ends of the second sliding groove 31 are open, the lower end of the sleeve 2 is fixedly connected with a sealing plate, the lower surface of the sealing plate is fixedly connected with a T-shaped second sliding block 24, the second sliding block 24 and the second sliding groove 31 are matched in a sliding mode so as to pre-support the main keel 3, a worker does not need to always hold the main keel 3 for installation when the installation is carried out, and manpower is saved; the locking piece 32 is a locking bolt 321, a plurality of positioning holes 33 communicated with the second sliding groove 31 are formed in the main keel 3, the plurality of positioning holes 33 are arranged at intervals along the length direction of the main keel 3, the locking bolt 321 is assembled at the positioning holes 33 in a threaded mode, a locking groove 241 is formed in the position, corresponding to the positioning holes 33, of the second sliding block 24, and the free end of the locking bolt 321 is assembled with the locking groove 241 in a threaded mode to achieve connection and fixation between the main keel 3 and the suspender 1.
The implementation principle of the embodiment 1 is as follows: during installation, the upper end of the suspender 1 is fixed with a wall body, the main keel 3 is installed at the lower end of the sleeve 2, a worker can adjust the height of the main keel 3 according to the preset height of the main keel, the limiting block 52 is separated from the limiting groove 101 through the poking piece 53, the sleeve 2 slides up and down, the adjustment of different heights of the main keel 3 is realized, the worker can level the main keel 3 conveniently, after the main keel 3 is leveled, the limiting block 52 is inserted into the limiting groove 101 under the action of restoring force of the spring 51, the fixing between the suspender 1 and the sleeve 2 is realized, and finally the worker can install the auxiliary keel 4 on the lower surface of the leveled main keel 3 to finish the basic work of a suspended ceiling.
Example 2
Referring to fig. 4, the difference between this embodiment and embodiment 1 is that the positioning assembly 5 is a positioning bolt 54, a threaded through hole 23 is formed in the outer peripheral wall of the upper end of the sleeve 2, the positioning bolt 54 is threadedly assembled in the threaded through hole 23, a plurality of thread grooves 102 are formed in the suspension rod 1, the thread grooves 102 are arranged at intervals in the vertical direction, the free end of the positioning bolt 54 is threadedly assembled with the thread grooves 102, and the sliding and fixing of the sleeve 2 can be realized by screwing the bolt, which is simple to operate.
The above embodiments are preferred embodiments of the present application, and the protection scope of the present application is not limited by the above embodiments, so: all equivalent changes made according to the structure, shape and principle of the present application shall be covered by the protection scope of the present application.

Claims (8)

1. The utility model provides a light gauge steel furred ceiling structure which characterized in that: comprises a suspender (1), a sleeve (2), a main keel (3), an auxiliary keel (4) and a positioning component (5);
the upper end rigid coupling of jib (1) is on the wall body, sleeve (2) vertical slip cover is located the lower extreme of jib (1), locating component (5) are located on sleeve (2), locating component (5) are used for making sleeve (2) with relative position between jib (1) is fixed, main joist (3) are located the lower extreme of sleeve (2), false keel (4) rigid coupling in the lower surface of main joist (3), main joist (3) with false keel (4) vertically and horizontally staggered lays.
2. The light gauge steel ceiling construction of claim 1, wherein: the positioning assembly (5) comprises: the spring (51), the limiting block (52) and the toggle piece (53);
the inner peripheral wall of the upper end of the sleeve (2) is provided with a fixed groove (21), the spring (51) is horizontally arranged in the fixed groove (21), one end of the spring (51) is fixedly connected with the inner side wall of the fixing groove (21) far away from the suspender (1), the limiting block (52) is arranged at the other end of the spring (51), one end of the limiting block (52) close to the spring (51) is always positioned in the fixing groove (21), a plurality of limiting grooves (101) are arranged on the suspension rod (1), the limiting grooves (101) are arranged at intervals along the vertical direction, one end of the limiting block (52) far away from the spring (51) is in plug fit with the limiting groove (101), the limiting block (52) is provided with a poking piece (53), and the poking piece (53) is used for enabling the limiting block (52) to be separated from the limiting groove (101).
3. The light gauge steel ceiling construction of claim 2, wherein: the toggle piece (53) includes: a connecting plate (531) and a shifting plate (532);
the movable groove (22) has been seted up to the up end of sleeve (2), movable groove (22) are followed the diameter direction of sleeve (2) is laid, movable groove (22) lower extreme with fixed slot (21) are linked together, the vertical upper surface of locating stopper (52) of connecting plate (531), the upper end of connecting plate (531) is run through movable groove (22), connecting plate (531) with movable groove (22) slip adaptation and slip direction with the diameter direction of sleeve (2) is the same, dial board (532) and locate the upper end of connecting plate (531) and be located the top of sleeve (2).
4. The light gauge steel ceiling construction of claim 1, wherein: the positioning assembly (5) is a positioning bolt (54), a threaded through hole (23) is formed in the outer peripheral wall of the upper end of the sleeve (2), the positioning bolt (54) is assembled in the threaded through hole (23) in a threaded mode, a plurality of thread grooves (102) are formed in the suspension rod (1), the thread grooves (102) are distributed at intervals in the vertical direction, and the free end of the positioning bolt (54) is assembled with the thread grooves (102) in a threaded mode.
5. The light gauge steel ceiling construction of claim 1, wherein: one side of the suspender (1) is provided with a first sliding block (103), the inner peripheral wall of the sleeve (2) is provided with a first sliding groove (25) which is vertically distributed, and the first sliding block (103) is in sliding fit with the first sliding groove (25).
6. The light gauge steel ceiling construction of claim 1, wherein: second spout (31) of T shape are seted up to main joist (3) up end, second spout (31) are followed the length direction of main joist (3) is laid and both ends all are the opening form, the lower extreme of sleeve (2) is equipped with second slider (24) of T shape, second slider (24) with second spout (31) slip adaptation, be equipped with retaining member (32) on main joist (3), retaining member (32) are used for making sleeve (2) with relative position between main joist (3) is fixed.
7. The light gauge steel ceiling construction of claim 6, wherein: retaining member (32) are locking bolt (321), set up on main joist (3) with locating hole (33) that second spout (31) are linked together, locking bolt (321) screw assembly in locating hole (33) department, second slider (24) with locking groove (241) have been seted up to the corresponding department of locating hole (33), the free end of locking bolt (321) with locking groove (241) screw assembly.
8. The light gauge steel ceiling construction of claim 7, wherein: the positioning holes (33) are arranged in a plurality, and the positioning holes (33) are arranged at intervals along the length direction of the main keel (3).
CN202121685170.XU 2021-07-23 2021-07-23 Light gauge steel furred ceiling structure Active CN214833931U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202121685170.XU CN214833931U (en) 2021-07-23 2021-07-23 Light gauge steel furred ceiling structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202121685170.XU CN214833931U (en) 2021-07-23 2021-07-23 Light gauge steel furred ceiling structure

Publications (1)

Publication Number Publication Date
CN214833931U true CN214833931U (en) 2021-11-23

Family

ID=78833844

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202121685170.XU Active CN214833931U (en) 2021-07-23 2021-07-23 Light gauge steel furred ceiling structure

Country Status (1)

Country Link
CN (1) CN214833931U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115262845A (en) * 2022-06-23 2022-11-01 肇庆市建筑工程有限公司 Construction method of keel modular assembling modeling ceiling

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115262845A (en) * 2022-06-23 2022-11-01 肇庆市建筑工程有限公司 Construction method of keel modular assembling modeling ceiling
CN115262845B (en) * 2022-06-23 2024-04-30 肇庆市建筑工程有限公司 Construction method for joist modularized assembly modeling suspended ceiling

Similar Documents

Publication Publication Date Title
WO2018174488A1 (en) Finishing panel fixing device
CN206737222U (en) Cell cube section curtain wall installing device
CN204126102U (en) A kind of sheet material fast-assembling ceiling structure
CN102493622A (en) Wallboard installing component and method for installing decorative wallboard by using same
CN214833931U (en) Light gauge steel furred ceiling structure
WO2020143222A1 (en) Fabricated suspended ceiling structure and installation method therefor
CN112064856B (en) Suspended ceiling pre-hanging piece and floor structure of building with same
CN112112347A (en) Assembled mounting structure of integrated furred ceiling board
CN111188448B (en) Unit type adjustable suspended ceiling structure
CN213926998U (en) Assembled mounting structure of integrated furred ceiling board
CN206477536U (en) Combined joist frame for cladding wallboard
CN212715608U (en) Ceiling keel structure of prefabricated building
CN209874218U (en) Light keel decorative structure
CN109537793B (en) Suspended ceiling structure convenient to install and level and installation method thereof
CN113323238A (en) Adjustable mounting structure for assembled suspended ceiling
CN207079858U (en) It is interior to hang fast keel
CN206110421U (en) Stone material curtain adjustable combination pendant is hung futilely to back of body bolt formula
CN212405671U (en) Adjustable telescopic module applied to assembled decoration ceiling
CN206273939U (en) A kind of wall decoration suspension member that can be dismantled
CN213806092U (en) Ceiling connecting piece
CN206289817U (en) The mounting structure of curtain wall in a kind of adjustable stone material room
CN217759526U (en) Unit type GFRC ceiling board installation limiting device
CN205489333U (en) Fixing device of pipeline
CN217811874U (en) Aluminum alloy furred ceiling mounting structure convenient to installation
CN215167104U (en) Ceiling assembled metal keel structure capable of being quickly positioned and installed

Legal Events

Date Code Title Description
GR01 Patent grant