CN214725063U - Compaction device is used in production of concrete solid pile - Google Patents

Compaction device is used in production of concrete solid pile Download PDF

Info

Publication number
CN214725063U
CN214725063U CN202023287549.3U CN202023287549U CN214725063U CN 214725063 U CN214725063 U CN 214725063U CN 202023287549 U CN202023287549 U CN 202023287549U CN 214725063 U CN214725063 U CN 214725063U
Authority
CN
China
Prior art keywords
concrete
plate
fixedly connected
fixing bolt
mould
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202023287549.3U
Other languages
Chinese (zh)
Inventor
朱武忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huai'an Guji Pipe Pile Co ltd
Original Assignee
Huai'an Guji Pipe Pile Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huai'an Guji Pipe Pile Co ltd filed Critical Huai'an Guji Pipe Pile Co ltd
Priority to CN202023287549.3U priority Critical patent/CN214725063U/en
Application granted granted Critical
Publication of CN214725063U publication Critical patent/CN214725063U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a compaction device for producing concrete solid piles, which comprises a top plate, wherein both ends of the bottom of the top plate are fixedly connected with fixed rods through screws, the bottom of the top plate is fixedly connected with a cylinder, and a piston rod of the cylinder is fixedly connected with a pressing plate through a fixing mechanism, the utility model compacts the concrete in a mould through the pressing plate, when the pressing plate is blocked to move downwards, the pressing plate is retracted, the descending height of the concrete is observed, and then, continuing to inject concrete into the interior of the mold to a predetermined height, and when the concrete reaches the predetermined height, then the cylinder is opened to drive the pressure plate to compact the concrete, the concrete is injected into the mould after the compaction, the operation is repeated until the height of the compacted concrete reaches the preset height and does not change, thereby with the concrete compaction, solved current concrete solid pile when the preparation, do not pass through the compaction operation, the inside space that exists of concrete solid pile can produce the problem of influence to solid pile's intensity.

Description

Compaction device is used in production of concrete solid pile
Technical Field
The utility model relates to a building correlation technique field specifically is a compaction device is used in production of concrete solid pile.
Background
The prestressed concrete solid pile is a precast pile, the section is generally square, the section of the pile body is generally unchanged along the length of the pile, and the prestressed concrete solid pile has the advantages that: the length and the section can be selected in a certain range according to the actual needs on site, and the prefabricated steel plate is prefabricated on the ground, so that the manufacturing quality is easy to guarantee, the bearing capacity is high, the durability is good, and the engineering application is wide.
When the existing concrete solid pile is manufactured, the compaction operation is not carried out on the concrete inside the mould, so that a gap exists in the middle of the manufactured concrete solid pile, and the gap can influence the strength of the solid pile.
Therefore, the compaction device for producing the concrete solid pile is provided.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a compaction device is used in production of concrete solid pile to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a compaction device is used in concrete solid pile production, includes the roof, the both ends of roof bottom all are through screw rod fixedly connected with dead lever, the bottom fixedly connected with cylinder of roof, the piston rod of cylinder passes through fixed establishment fixedly connected with clamp plate, one side of dead lever is provided with the mould, the mould includes bottom plate, first curb plate, second curb plate, first fixing bolt and second fixing bolt, the both ends of first curb plate one side through first fixing bolt respectively with one side fixed connection of bottom plate and second curb plate, the bottom fixed connection of second fixing bolt and second curb plate is all passed through to the both sides at bottom plate top.
Preferably, the fixing mechanism comprises a fixing plate and a clamping ring, and the bottom of the fixing plate is fixedly connected with the bottom of the clamping ring.
Preferably, the inner ring of the snap ring is fixedly connected with a first sealing ring, and the inner ring of the first sealing ring is fixedly connected with the piston rod of the cylinder.
Preferably, the bottom of the fixed rod is fixedly connected with an installation block, and a pin is arranged in the installation block.
Preferably, a supporting rod is fixedly connected between the two fixing rods, and an overflow hole is formed in the pressing plate.
Preferably, the outer side of the first fixing bolt is sleeved with a second sealing ring, and the outer side of the second fixing bolt is sleeved with a third sealing ring.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses a cylinder drives the clamp plate and removes to the inside of mould, carry out compaction processing to the concrete inside the mould, when the clamp plate moves down and packs up the clamp plate when being obstructed, observe the height that the concrete descends, then continue to pour into the concrete to the predetermined height to the inside of mould, when the concrete reaches the predetermined height, will open the cylinder again and drive the clamp plate and consolidate to the concrete, pour into the concrete into the mould again after the compaction, so reciprocating operation, the concrete height no longer changes until the concrete height reaches the predetermined height after the compaction, thereby consolidate the concrete, when having solved current concrete solid pile and making, do not pass through compaction operation, the space that exists inside the concrete solid pile can produce the problem that influences to the intensity of solid pile;
2. the utility model discloses a through setting up fixed plate and snap ring, convenient to use person to the dismantlement and the installation of clamp plate, through setting up first sealing washer, can seal the junction of snap ring and cylinder, prevent that sewage from causing the damage to the cylinder, through setting up installation piece and pin, convenient to use person fixes this device to the stability that has improved this device;
3. the utility model discloses a set up the bracing piece, make the connection between two dead levers more firm to improved the firmness of whole device, through setting up the spillway hole, in the clamp plate to the pile body pressure real-time, can be with the moisture discharge that extrudes, prevent that moisture from not discharging and make the mould rise to split, through setting up second sealing washer and third sealing washer, can prevent that the inside concrete of mould from leaking.
Drawings
FIG. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural view of the mold of the present invention;
FIG. 3 is a schematic structural view of the pressing plate of the present invention;
fig. 4 is a schematic structural view of the fixing rod of the present invention.
In the figure: 1. a top plate; 2. a screw; 3. fixing the rod; 4. a cylinder; 5. pressing a plate; 6. a mold; 61. a base plate; 62. a first side plate; 63. a second side plate; 64. a first fixing bolt; 65. a second fixing bolt; 7. a fixing mechanism; 8. a fixing plate; 9. a snap ring; 10. a first seal ring; 11. mounting blocks; 12. a pin; 13. a support bar; 14. an overflow hole; 15. a second seal ring; 16. and a third sealing ring.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the technical scheme in the utility model, all other embodiments that ordinary skilled person in the art obtained under the prerequisite of not making the creative work all belong to the scope of the utility model protection.
Referring to fig. 1 to 4, the present invention provides a technical solution: the utility model provides a compaction device is used in concrete solid pile production, including roof 1, 2 fixedly connected with dead levers 3 of screw rod are all passed through at the both ends of 1 bottom of roof, the bottom fixedly connected with cylinder 4 of roof 1, the piston rod of cylinder 4 passes through 7 fixedly connected with clamp plate 5 of fixed establishment, one side of dead lever 3 is provided with mould 6, mould 6 includes bottom plate 61, first curb plate 62, second curb plate 63, first fixing bolt 64 and second fixing bolt 65, the both ends of first curb plate 62 one side pass through first fixing bolt 64 respectively with one side fixed connection of bottom plate 61 and second curb plate 63, the bottom fixed connection of second fixing bolt 65 and second curb plate 63 is all passed through to the both sides at bottom plate 61 top.
Further, the fixing mechanism 7 comprises a fixing plate 8 and a clamping ring 9, the bottom of the fixing plate 8 is fixedly connected with the bottom of the clamping ring 9, and the pressing plate 5 and the air cylinder 4 are connected through the fixing plate 8 and the clamping ring 9, so that the pressing plate 5 can be conveniently detached and installed by a user.
Further, the inner ring of the snap ring 9 is fixedly connected with the first sealing ring 10, the inner ring of the first sealing ring 10 is fixedly connected with the piston rod of the air cylinder 4, the first sealing ring 10 is arranged inside the snap ring 9, the joint of the snap ring 9 and the air cylinder 4 can be sealed, and the air cylinder 4 is prevented from being damaged by sewage.
Further, the bottom fixedly connected with installation piece 11 of dead lever 3, the inside of installation piece 11 is provided with pin 12, sets up installation piece 11 and pin 12 through setting up in the bottom of dead lever 3, and convenient to use person fixes this device to the stability of this device has been improved.
Further, fixedly connected with bracing piece 13 between two dead levers 3, spillway hole 14 has been seted up to the inside of clamp plate 5, through set up bracing piece 13 between dead lever 3, can make the connection between two dead levers 3 more firm to improved the firmness of whole device, through set up spillway hole 14 in the inside of clamp plate 5, in the time of clamp plate 5 is pressed the pile body, can be with the moisture discharge that extrudes, prevent that moisture can not discharge and make mould 6 rise to split.
Further, the outer side of the first fixing bolt 64 is sleeved with the second sealing ring 15, the outer side of the second fixing bolt 65 is sleeved with the third sealing ring 16, and by arranging the second sealing ring 15 and the third sealing ring 16, the concrete inside the mold 6 can be prevented from leaking from the joint of the fixing bolt and the mold 6.
The working principle is as follows: when the device is used, a user firstly assembles a bottom plate 61, a first side plate 62 and a second side plate 63 into a mould 6 through a first fixing bolt 64 and a second fixing bolt 65, then puts a bound reinforcement cage into the mould 6, then pours concrete into the mould 6, in the process of pouring the concrete, constructors observe the pouring condition inside the mould 6 in real time, when the concrete is poured to a preset height, stops pouring the concrete into the mould 6, at the moment, opens a cylinder 4, drives a pressing plate 5 to move towards the inside of the mould 6 through the cylinder 4, carries out compaction treatment on the concrete inside the mould 6, when the pressing plate 5 is blocked to move downwards, packs up the pressing plate 5 to observe the descending height of the concrete, then continues to pour the concrete into the inside of the mould 6 to the preset height, when the concrete reaches the preset height, then opens the cylinder 4 to drive the pressing plate 5 to compact the concrete, after compaction, the concrete is injected into the mould 6, and the operation is repeated until the height of the compacted concrete reaches the preset height and does not change.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (6)

1. The utility model provides a compaction device is used in production of concrete solid pile, includes roof (1), its characterized in that: the utility model discloses a mould, including roof (1), top plate (1), piston rod, mould (6), first curb plate (62), second curb plate (63), first fixing bolt (64) and second fixing bolt (65), the both ends of roof (1) bottom all are through screw rod (2) fixedly connected with dead lever (3), the bottom fixedly connected with cylinder (4) of roof (1), the piston rod of cylinder (4) passes through fixed establishment (7) fixedly connected with clamp plate (5), one side of dead lever (3) is provided with mould (6), mould (6) include bottom plate (61), first curb plate (62), second curb plate (63), first fixing bolt (64) and second fixing bolt (65), the both ends of first curb plate (62) one side pass through first fixing bolt (64) respectively with one side fixed connection of bottom plate (61) and second curb plate (63), the bottom fixed connection of second fixing bolt (65) and second curb plate (63) is all passed through to the both sides at bottom (61) top.
2. The compaction device for producing the concrete solid pile according to claim 1, wherein: the fixing mechanism (7) comprises a fixing plate (8) and a clamping ring (9), and the bottom of the fixing plate (8) is fixedly connected with the bottom of the clamping ring (9).
3. The compaction device for producing the concrete solid pile according to claim 2, wherein: the inner ring of snap ring (9) fixedly connected with first sealing washer (10), the inner circle of first sealing washer (10) and the piston rod fixed connection of cylinder (4).
4. The compaction device for producing the concrete solid pile according to claim 1, wherein: the bottom fixedly connected with installation piece (11) of dead lever (3), the inside of installation piece (11) is provided with pin (12).
5. The compaction device for producing the concrete solid pile according to claim 1, wherein: a supporting rod (13) is fixedly connected between the two fixing rods (3), and an overflow hole (14) is formed in the pressing plate (5).
6. The compaction device for producing the concrete solid pile according to claim 1, wherein: the outside cover of first fixing bolt (64) is equipped with second sealing washer (15), the outside cover of second fixing bolt (65) is equipped with third sealing washer (16).
CN202023287549.3U 2020-12-30 2020-12-30 Compaction device is used in production of concrete solid pile Active CN214725063U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023287549.3U CN214725063U (en) 2020-12-30 2020-12-30 Compaction device is used in production of concrete solid pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023287549.3U CN214725063U (en) 2020-12-30 2020-12-30 Compaction device is used in production of concrete solid pile

Publications (1)

Publication Number Publication Date
CN214725063U true CN214725063U (en) 2021-11-16

Family

ID=78636119

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023287549.3U Active CN214725063U (en) 2020-12-30 2020-12-30 Compaction device is used in production of concrete solid pile

Country Status (1)

Country Link
CN (1) CN214725063U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114589788A (en) * 2022-03-21 2022-06-07 南通理工学院 Automatic preparation facilities of assembled building block

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114589788A (en) * 2022-03-21 2022-06-07 南通理工学院 Automatic preparation facilities of assembled building block

Similar Documents

Publication Publication Date Title
CN206873930U (en) A kind of adjustable assembled composite beam die
CN210308385U (en) Automatic pouring device for cement precast block
CN208343137U (en) A kind of reinforcing bar positioning iterative structure and mold poured for prefabricated components
CN214725063U (en) Compaction device is used in production of concrete solid pile
CN208563525U (en) A kind of gutter construction concreting integral mold plate
CN203160248U (en) Grout enriched vibrated RCC grouting and vibrating device
CN105587050A (en) Sectioned grouting structure and method for fabricated shear wall rebar sleeve connection
CN112873527A (en) Manufacturing mold and method for supporting pile
CN110714462A (en) Precast concrete pile, joint and production method
CN211057781U (en) Precast concrete pile joint
CN213034888U (en) Prefabricated mould of pouring of stair convenient to drawing of patterns
CN210732757U (en) Interior gliding style high leakproofness prefabricated staircase mould
CN107471404A (en) A kind of water channel gool side leads to the production method of prefabricated component
CN107443548A (en) A kind of production method of water channel gool prefabricated component
CN210621403U (en) Concrete placement device for highway construction
CN213563414U (en) Preparation mould of reinforced concrete drain pipe
CN208563314U (en) A kind of high intensity can drain prefabricating composite pile
CN217318455U (en) Forming machine for forming water permeable bricks
CN207310186U (en) A kind of water channel gool side leads to prefabricated-member mould
CN214772759U (en) Solidified soil channel U-shaped groove production equipment
CN101037003B (en) Method and device for forecasting concrete anti-leaking U-shaped groove by using permeability formwork gasket
CN221118494U (en) Water permeable mould box for forming concrete on underwater slope
CN213329480U (en) Be used for windowsill bottom concrete to fill instrument fast
CN110238962A (en) A kind of production method of novel precast concrete interior wall
CN214136534U (en) Shaping main frame of cement prefabricated product punches

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant