CN214459651U - Steel platform construction hanging flower basket on water - Google Patents

Steel platform construction hanging flower basket on water Download PDF

Info

Publication number
CN214459651U
CN214459651U CN202022841761.3U CN202022841761U CN214459651U CN 214459651 U CN214459651 U CN 214459651U CN 202022841761 U CN202022841761 U CN 202022841761U CN 214459651 U CN214459651 U CN 214459651U
Authority
CN
China
Prior art keywords
hanging flower
flower basket
main part
hanging
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022841761.3U
Other languages
Chinese (zh)
Inventor
王振
张会忠
张跃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Construction Port Engineering Group Co Ltd
Original Assignee
China State Construction Port Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China State Construction Port Engineering Group Co Ltd filed Critical China State Construction Port Engineering Group Co Ltd
Priority to CN202022841761.3U priority Critical patent/CN214459651U/en
Application granted granted Critical
Publication of CN214459651U publication Critical patent/CN214459651U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The utility model relates to a steel platform construction hanging flower basket on water, including the hanging flower basket main part, the hanging flower basket main part is open-top's frame construction, the top of hanging flower basket main part is provided with a plurality of rings, one side of hanging flower basket main part is provided with the vaulting pole mount, the vaulting pole mount includes supporting shoe and ties up the rope, the supporting shoe set up in the bottom both ends of hanging flower basket main part, tie up the rope set up in the nearly upper portion of hanging flower basket main part. Utility model's an usage is, with vaulting pole snap-on to the hanging flower basket main part, makes the bottom sprag of vaulting pole to the supporting shoe on, the upper end of vaulting pole is fixed to the hanging flower basket main part through tying up the rope on, directly hangs the hanging flower basket and puts to the position that the vaulting pole needs to be fixed and carry out welding construction. The device has the advantages of simple structure, convenience in use, no need of simultaneous construction and use of multiple cranes, great improvement of construction efficiency, cost reduction, convenience in operation and improvement of safety in the construction process.

Description

Steel platform construction hanging flower basket on water
Technical Field
The utility model relates to a bridge construction field, more specifically, the utility model relates to a steel platform construction hanging flower basket on water.
Background
In high stake pier and the bridge engineering on water, inevitably will set up work platform on water, all adopt the steel platform structure under the general condition. In order to make the steel platform structure more safe and stable, the platform sets up vertical and horizontal framed bent, uses bridging or stull to connect in adjacent framed bent or the framed bent, ensures its overall stability.
When the construction of steel platform stull and bridging, the operation personnel need be faced the water operation usually, need the crane to hoist the hanging flower basket and put to corresponding position usually, then another crane handling bridging or stull weld behind the corresponding position. The mode is not only low in construction efficiency, but also high in construction risk when multiple cranes are used, and the cost is high.
Therefore, a new construction basket for an overwater steel platform is needed to solve the above problems.
SUMMERY OF THE UTILITY MODEL
The utility model discloses an aim at solve the current steel platform construction hanging flower basket on water and use problem inconvenient, that the efficiency of construction is low.
According to an aspect of the utility model, a steel platform construction hanging flower basket on water is provided, including the hanging flower basket main part, the hanging flower basket main part is open-top's frame construction, the top of hanging flower basket main part is provided with a plurality of rings, one side of hanging flower basket main part is provided with the vaulting pole mount, the vaulting pole mount includes the supporting shoe and ties up the rope, the supporting shoe set up in the bottom both ends of hanging flower basket main part, tie up the rope set up in the nearly upper portion of hanging flower basket main part.
Through this scheme, with vaulting pole (bridging or stull) snap-on to the hanging flower basket main part, make the bottom sprag of vaulting pole to the supporting shoe on, the upper end of vaulting pole is fixed to the hanging flower basket main part through tying up the rope on, directly hangs the hanging flower basket and puts to the vaulting pole and need fixed position and carry out welding construction, after the construction finishes, loosens the vaulting pole again and breaks away from with the fixed of hanging flower basket main part, can accomplish the connection of vaulting pole. The device has the advantages of simple structure, convenience in use, no need of simultaneous construction and use of multiple cranes, great improvement of construction efficiency, cost reduction, convenience in operation and improvement of safety in the construction process.
Preferably, the cross section of the supporting block is L-shaped, the supporting block protrudes outwards from the side surface of the basket body, and the bottom of the support rod is supported to the inner corner of the supporting block.
Through this scheme, the angle steel can be chooseed for use to the supporting shoe of L shape, and the material selection is convenient and the cost is lower, can effectively support the vaulting pole, and convenient fixed and fixed effectual.
Preferably, one side of the hanging basket body is uniformly provided with a plurality of fixing holes, and the binding rope is wound on the fixing holes.
Through this scheme, the vaulting pole that this device was applicable to different length that is provided with of a plurality of fixed orificess is fixed, and a plurality of fixed orificess can also make things convenient for the hanging flower basket main part to utilize to tie up the rope and fix with steel platform, improves security and stability.
Preferably, the fixing device further comprises a support rod which is a polished rod and can be inserted into the fixing hole and connected with the fixing hole in a sliding mode.
Through this scheme, the die-pin supports to the vaulting pole bottom in inserting the fixed orifices, avoids rocking the wearing and tearing that cause tying up the rope, improves the reliability of handling in-process.
Preferably, push rods are arranged at two ends of the bottom of the hanging basket body, the lower middle portion of each push rod is hinged to the hanging basket body, and the bottom ends of the push rods extend into the supporting blocks.
Through this scheme, after the welding is accomplished, pulling push rod top makes the push rod bottom promote the bracing piece and breaks away from the support of supporting shoe to make things convenient for lifting by crane of hanging flower basket.
Preferably, the hanging basket body is provided with a hinge block, the hinge block extends towards the inside of the hanging basket body, and the hinge block is hinged to the hinge block.
Through this scheme, make the push rod wholly be arranged in the hanging flower basket main part, avoid the outside handling that extends the influence this device of push rod.
The utility model discloses a technological effect lies in, this device simple structure, convenient to use only can accomplish the vaulting pole welding construction of steel platform with a loop wheel machine, has improved the efficiency of construction and the security in the work progress greatly to help reducing construction cost.
Other features of the present invention and advantages thereof will become apparent from the following detailed description of exemplary embodiments of the invention, which proceeds with reference to the accompanying drawings.
Drawings
The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments of the invention and together with the description, serve to explain the principles of the invention.
Figure 1 is the utility model discloses structural schematic diagram in steel platform construction hanging flower basket handling process on water.
Fig. 2 is a front view structure schematic diagram of the construction hanging basket of the water steel platform in fig. 1.
Figure 3 is a side view schematic diagram of the overwater steel platform construction basket of figure 2.
Wherein like parts are designated by like reference numerals throughout the several views; the figures are not drawn to scale.
Detailed Description
Various exemplary embodiments of the present invention will now be described in detail with reference to the accompanying drawings. It should be noted that: unless specifically stated otherwise, the relative arrangement of the components and steps, the numerical expressions, and numerical values set forth in these embodiments do not limit the scope of the present invention.
The following description of at least one exemplary embodiment is merely illustrative in nature and is in no way intended to limit the invention, its application, or uses.
Techniques and apparatus known to those of ordinary skill in the relevant art may not be discussed in detail, but are intended to be considered a part of the specification where appropriate.
In all examples shown and discussed herein, any particular value should be construed as merely illustrative, and not limiting. Thus, other examples of the exemplary embodiments may have different values.
It should be noted that: like reference numbers and letters refer to like items in the following figures, and thus, once an item is defined in one figure, further discussion thereof is not required in subsequent figures.
Examples
As shown in fig. 1 to 3, the overwater steel platform construction hanging basket in the embodiment includes a hanging basket body 1100, the hanging basket body 1100 is a frame structure with an open top, a plurality of hanging rings 1110 are disposed on the top of the hanging basket body 1100, a stay fixing frame 1200 is disposed on one side of the hanging basket body 1100, the stay fixing frame 1200 includes a supporting block 1210 and binding ropes (not shown in the drawings), the supporting block 1210 is disposed at two ends of the bottom of the hanging basket body 1100, and the binding ropes are disposed near the upper portion of the hanging basket body 1100 and are used for binding the stay 2000 and the hanging basket body 1100.
According to the scheme of the embodiment, the support rods 2000 (the cross braces or the cross braces) are directly fixed on the basket body 1100, the bottoms of the support rods 2000 are supported on the support blocks 1210, the upper ends of the support rods 2000 are fixed on the basket body 1100 through the binding ropes, the device is directly hoisted to the positions, needing to be fixed, of the support rods 2000 for welding construction, and the binding ropes and the steel platforms can be fixed during welding so as to improve the stability and the safety of the construction process;
after the construction is finished, the support rods 2000 are loosened to be separated from the fixation with the hanging basket body 1100, and the device is lifted, so that the connection of the support rods 2000 can be completed. The device has the advantages of simple structure, convenience in use, no need of simultaneous construction and use of multiple cranes, great improvement of construction efficiency, cost reduction, convenience in operation and improvement of safety in the construction process.
In this or other embodiments, the cross-section of the support block 1210 is "L" shaped, the support block 1210 protrudes outward from the side of the basket body 1100, and the support rods 2000 are supported at the bottom to the inside corners of the support block 1210. The supporting shoe 1210 of L shape can select for use the angle steel, and the material selection is convenient and the cost is lower, can effectively support vaulting pole 2000, and convenient fixed and fixed effectual.
In this embodiment or other embodiments, a plurality of fixing holes 1120 are uniformly formed in one side of the basket body 1100, and the tying rope is wound around the fixing holes 1120 to facilitate the fixing of the tying rope; the arrangement of the fixing holes 1120 helps the device to be suitable for fixing the stay bars 2000 with different lengths, so that the binding ropes can be firmly bound to any place of the hanging basket body 1100 as required, and the fixing holes 1120 can also facilitate the hanging basket body 1100 to be fixed with a steel platform by using the binding ropes, thereby improving the safety and the stability.
In this embodiment or other embodiments, the fixing device further includes a supporting rod 1130, where the supporting rod 1130 is a polished rod, and the supporting rod 1130 can be inserted into the fixing hole 1120 and slidably connected to the fixing hole 1120. The supporting rod 1130 is inserted into the fixing hole 1120 to be supported to the bottom of the supporting rod 2000, so that abrasion of the binding rope caused by shaking is avoided, and the reliability in the hoisting process is improved. After welding is finished, the supporting rod 1130 is directly pulled out, so that the device can be lifted out, and the use is convenient and reliable.
In this embodiment or other embodiments, push rods 1220 are disposed at two ends of the bottom of the basket body 1100, the push rods 1220 are hinged to the basket body 1100 below the middle portion thereof, the bottom ends of the push rods 1220 extend into the support blocks 1210, and after welding is completed, the tops of the push rods 1220 are pulled to make the bottoms of the push rods 1220 push the support rods 2000 to separate from the support of the support blocks 1210, so as to facilitate lifting of the device and avoid interference between the support blocks 1210 and the welded support rods 2000.
In this embodiment or other embodiments, the basket body 1100 is provided with a hinge block 1140, the hinge block 1140 extends towards the inside of the basket body 1100, and the push rod 1220 is hinged to the hinge block 1140. The push rod 1220 is integrally positioned in the basket body 1100, so that the phenomenon that the lifting of the device is influenced by interference between the outward extension of the push rod 1220 and a steel platform is avoided.
The technical effect of this embodiment lies in, this device simple structure, and convenient to use only can accomplish the vaulting pole welding construction of steel platform with a loop wheel machine, has improved the efficiency of construction and the security in the work progress greatly to help reducing construction cost.
Although some specific embodiments of the present invention have been described in detail by way of illustration, it should be understood by those skilled in the art that the above illustration is only for purposes of illustration and is not intended to limit the scope of the invention. It will be appreciated by those skilled in the art that modifications may be made to the above embodiments without departing from the scope and spirit of the invention. The scope of the invention is defined by the appended claims.

Claims (6)

1. The utility model provides a steel platform construction hanging flower basket on water, includes the hanging flower basket main part, the hanging flower basket main part is open-top's frame construction, the top of hanging flower basket main part is provided with a plurality of rings, a serial communication port, one side of hanging flower basket main part is provided with the vaulting pole mount, the vaulting pole mount includes the supporting shoe and ties up the rope, the supporting shoe set up in the bottom both ends of hanging flower basket main part, tie up the rope set up in the nearly upper portion of hanging flower basket main part.
2. The overwater steel platform construction basket according to claim 1, wherein the support blocks are "L" shaped in cross section, the support blocks project outwardly from the sides of the basket body, and strut bottoms are supported to the inside corners of the support blocks.
3. The overwater steel platform construction hanging basket according to claim 2, wherein a plurality of fixing holes are uniformly formed in one side of the hanging basket body, and the binding ropes are wound on the fixing holes.
4. The overwater steel platform construction hanging basket according to claim 3, further comprising a support rod, wherein the support rod is a polished rod, and the support rod can be inserted into the fixing hole and is in sliding connection with the fixing hole.
5. The overwater steel platform construction hanging basket according to claim 2, wherein push rods are arranged at the bottom of the hanging basket body near two ends, the push rods are hinged to the hanging basket body below the middle of the push rods, and the bottom ends of the push rods extend into the supporting blocks.
6. The overwater steel platform construction basket according to claim 5, wherein the basket body is provided with a hinge block extending towards the interior of the basket body, and the push rod is hinged to the hinge block.
CN202022841761.3U 2020-12-01 2020-12-01 Steel platform construction hanging flower basket on water Active CN214459651U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022841761.3U CN214459651U (en) 2020-12-01 2020-12-01 Steel platform construction hanging flower basket on water

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022841761.3U CN214459651U (en) 2020-12-01 2020-12-01 Steel platform construction hanging flower basket on water

Publications (1)

Publication Number Publication Date
CN214459651U true CN214459651U (en) 2021-10-22

Family

ID=78185338

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022841761.3U Active CN214459651U (en) 2020-12-01 2020-12-01 Steel platform construction hanging flower basket on water

Country Status (1)

Country Link
CN (1) CN214459651U (en)

Similar Documents

Publication Publication Date Title
CN204281108U (en) A kind of transfer crane
CN105484503B (en) Inclined shuttle-shaped space truss hoisting method
CN207192616U (en) A kind of gantry crane for preventing that goods from rocking
CN214459651U (en) Steel platform construction hanging flower basket on water
CN211169600U (en) Hoisting accessory for shipbuilding
CN208869199U (en) A kind of overturning Lift-on/Lift-off System for horizontal equipment
CN217128907U (en) Scaffold frame for building engineering construction convenient to material loading
CN215558333U (en) Reusable hanging bar device
CN211895867U (en) Pipeline lifting machine
CN210658016U (en) Trolley for movably dismounting bridge guardrail template
CN213326443U (en) Quick unloading platform
CN203439948U (en) Gantry lifting frame for cableway
CN210163792U (en) High mound pier stud reinforcing bar mounting platform
CN210313118U (en) Suspension cage
CN218090875U (en) Deepwater pile foundation reinforcement cage installation device
CN207792499U (en) A kind of motor stator handling suspender
CN206129292U (en) Novel landing stage platform truck
CN217458499U (en) Movable lifting machine
CN218815131U (en) Hoisting mechanism of scaffold upright rod
CN205668873U (en) Denitrating catalyst lifting helps loop wheel machine structure
CN216512464U (en) Turnover device for prefabricating circular pier stud
CN216583921U (en) Steel reinforcement cage hoisting tool and hoisting device
CN214570025U (en) Auxiliary support for hoisting
CN217126648U (en) Overhead hoist suitable for bridge template and bridge
CN212609328U (en) Big iron bucket hoisting frame for honey

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant