CN214423947U - CL-1 type all-steel attached lifting scaffold rail - Google Patents
CL-1 type all-steel attached lifting scaffold rail Download PDFInfo
- Publication number
- CN214423947U CN214423947U CN202120186742.3U CN202120186742U CN214423947U CN 214423947 U CN214423947 U CN 214423947U CN 202120186742 U CN202120186742 U CN 202120186742U CN 214423947 U CN214423947 U CN 214423947U
- Authority
- CN
- China
- Prior art keywords
- steel
- track
- scaffold
- mounting bracket
- mounting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 57
- 239000010959 steel Substances 0.000 title claims abstract description 57
- 238000009434 installation Methods 0.000 claims abstract description 36
- 229910000746 Structural steel Inorganic materials 0.000 claims description 17
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims description 4
- 238000010276 construction Methods 0.000 abstract description 2
- 238000000034 method Methods 0.000 description 11
- 230000003014 reinforcing effect Effects 0.000 description 8
- 230000008569 process Effects 0.000 description 4
- 239000011435 rock Substances 0.000 description 4
- 238000005096 rolling process Methods 0.000 description 4
- 230000009471 action Effects 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- OKTJSMMVPCPJKN-UHFFFAOYSA-N Carbon Chemical compound [C] OKTJSMMVPCPJKN-UHFFFAOYSA-N 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 229910052799 carbon Inorganic materials 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 230000009194 climbing Effects 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 230000007246 mechanism Effects 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
Images
Landscapes
- Movable Scaffolding (AREA)
Abstract
The utility model relates to a construction equipment technical field just discloses CL-1 type all steel adheres to and promotes scaffold rail, which comprises a mounting bracket, the top fixedly connected with of mounting bracket one side connects the channel-section steel, the bottom fixedly connected with support frame of mounting bracket one side, connect the one end of channel-section steel bottom and the other end fixed connection of support frame, connect the other end fixedly connected with installation angle bar of channel-section steel, there is the track one side of installation angle bar through bolt fixed mounting, both ends fixed mounting has the pivot about the track, the pivot is rotated and is connected with the leading wheel. The utility model provides a current inserted lift scaffold's track simple to use's channel-section steel or guide post as the track, security and structural strength are high problem inadequately during the use, and the track is installed through the mounting hole with the installation angle bar for the track setting makes things convenient for the scaffold frame to go up and down on the outer facade of building, and strengthens the structural strength of connecting channel-section steel and mounting bracket.
Description
Technical Field
The utility model relates to a building construction equipment technical field specifically is CL-1 type all steel adheres to and promotes scaffold rail.
Background
The attached lifting scaffold equipment is a novel scaffold technology which is rapidly developed in the early century, and has important influence on the progress of construction technology in China. It becomes the low place operation with the eminence operation, becomes the inside operation of support body with unsettled operation, has apparent low carbon nature, high-tech content and characteristics such as more economic, safer, more convenient. The attached lifting scaffold is an outer scaffold which is erected at a certain height, attached to an engineering structure, capable of climbing or descending layer by layer along with the engineering structure by virtue of self lifting equipment and devices and provided with an anti-overturning and anti-falling device; the attached lifting scaffold mainly comprises an attached lifting scaffold frame body structure, an attached support, an anti-tilting device, an anti-falling device, a lifting mechanism, a control device and the like. The main building body with the attached lifting scaffold of more than 45 meters is suitable. The higher the floor is, the more obvious the economic efficiency is, each building can comprehensively save 30-60% of cost, can be applied to building main bodies of various structures, adopts a full-automatic synchronous control system and a remote control system, can actively prevent unsafe states, adopts a multi-set star wheel anti-falling device to prevent failures such as failure of a reset device and the like, can ensure that a protection frame body is always in a safe state and effectively prevents falling.
The track of current inserted lift scaffold frame generally only uses simple channel-section steel or guide post as the track, and when using, security and structural strength are all high inadequately.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide CL-1 type all steel adheres to and promotes scaffold rail, reaches reinforcing track structural strength, prevents the purpose of scaffold slope.
In order to achieve the above object, the utility model provides a following technical scheme:
CL-1 type all steel adheres to and promotes scaffold rail way, including the mounting bracket, the top fixedly connected with of mounting bracket one side connects the channel-section steel, the bottom fixedly connected with support frame of mounting bracket one side, the one end of connecting the channel-section steel bottom and the other end fixed connection of support frame, the other end fixedly connected with installation angle bar of connecting the channel-section steel, there is the track one side of installation angle bar through bolt fixed mounting, both ends fixed mounting has the pivot about the track, the pivot is rotated and is connected with the leading wheel.
Preferably, the mounting frames are two parallel channel steel, and the two mounting frames are fixedly connected through a reinforcing steel plate.
Preferably, the number of the connecting channel steels is two, and the two connecting channel steels are parallel to each other.
Preferably, the top and the bottom of the installation angle iron are fixedly connected with reinforcing triangular plates, and the thickness of each reinforcing triangular plate is six millimeters.
Preferably, the rail is made of angle iron, and mounting holes corresponding to each other are formed in the rail and the mounting angle iron.
Preferably, the rotating shaft is arranged at the upper end and the lower end of the track, and the guide wheels arranged on the rotating shaft are arranged oppositely.
The utility model provides a CL-1 type all steel adheres to and promotes scaffold rail. The method has the following beneficial effects:
(1) the utility model discloses a mounting bracket carries out fixed mounting with the outer wall of building, will install angle bar and mounting bracket fixed connection through connecting the channel-section steel, carries out fixed mounting with track and installation angle bar through the mounting hole that corresponds again for the track setting makes things convenient for the scaffold frame to go up and down on the outer facade of building, and sets up and provides the support for connecting the channel-section steel at the support frame of connecting the channel-section steel bottom, and strengthens the structural strength who connects channel-section steel and mounting bracket.
(2) The utility model discloses a set up the pivot in orbital side, through rotating in the pivot and connecting the leading wheel, carry out the joint through the lifter with leading wheel and scaffold, prevent that the scaffold from taking place to rock at the in-process that goes up and down, the leading wheel also can become rolling friction with the sliding friction when the scaffold goes up and down for the friction greatly reduced between promotion scaffold track and the scaffold, improve the life of scaffold, the scaffold can be held to leading wheel and scaffold joint when the scaffold emptys.
Drawings
FIG. 1 is a schematic view of the present invention;
fig. 2 is a top view of the present invention;
fig. 3 is a side view of the rail of the present invention.
In the figure: 1. a mounting frame; 2. connecting channel steel; 3. a support frame; 4. mounting angle iron; 5. reinforcing the triangular plate; 6. a track; 7. a rotating shaft; 8. reinforcing the steel plate; 9. a guide wheel; 10. and (7) installing holes.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
As shown in fig. 1-3, the utility model provides a technical solution:
CL-1 type all-steel adheres to and promotes scaffold rail, including mounting bracket 1, mounting bracket 1 is two channel steels parallel to each other, pass through the reinforcing steel plate 8 fixed connection between two mounting brackets 1, two mounting brackets 1 can strengthen the installation intensity, and set up reinforcing steel plate 8 between two mounting brackets 1, can strengthen the structural strength of scaffold rail even more, the top of one side of mounting bracket 1 is fixedly connected with connecting channel steel 2, the quantity of connecting channel steel 2 is two, two connecting channel steels 2 are parallel to each other, through two parallel installing channel steels 2 fixed mounting two tracks 6, the bottom of one side of mounting bracket 1 is fixedly connected with support frame 3, one end of the bottom of connecting channel steel 2 is fixedly connected with the other end of support frame 3, the other end of connecting channel steel 2 is fixedly connected with installation angle bar 4, the top and the bottom of installation angle bar 4 are fixedly connected with reinforcing set-square 5, the thickness of the reinforcing triangular plate 5 is six millimeters, the reinforcing triangular plate 5 is arranged at the top and the bottom of the installation angle iron 4 to prevent the deformation of the installation angle iron 4, the installation angle iron 4 is fixedly installed on the outer wall of a building through the installation frame 1, the installation angle iron 4 is fixedly connected with the installation frame 1 through the connecting channel steel 2, then the track 6 and the installation angle iron 4 are fixedly installed through the corresponding installation holes 10, the track 6 is arranged on the outer vertical surface of the building to facilitate the lifting of a scaffold, the support frame 3 arranged at the bottom of the connecting channel steel 2 provides support for the connecting channel steel 2 and enhances the structural strength of the connecting channel steel 2 and the installation frame 1, one side of the installation angle iron 4 is fixedly provided with the track 6 through bolts, the track 6 is made of angle iron, the corresponding installation holes 10 are formed in the track 6 and the installation angle iron 4, the track 6 and the installation angle iron 4 are fixedly installed through the installation holes 10, both ends fixed mounting has pivot 7 about track 6, pivot 7 sets up the upper and lower both ends at track 6, and the leading wheel 9 of installation sets up relatively on pivot 7, carry out the joint through the lifter with leading wheel 9 and scaffold, prevent that scaffold from taking place to rock at the in-process of going up and down, pivot 7 rotates and is connected with leading wheel 9, through setting up pivot 7 in the side at track 6, through rotating at pivot 7 and connecting leading wheel 9, carry out the joint through the lifter with leading wheel 9 and scaffold, prevent that scaffold from taking place to rock at the in-process of going up and down, leading wheel 9 also can become rolling friction with the sliding friction when scaffold goes up and down, make the friction between promotion scaffold track 6 and the scaffold descend greatly, improve the life of scaffold, the scaffold can be pulled with the scaffold joint to leading wheel 9 when the scaffold topples.
When the scaffold is used, the scaffold is fixedly installed on the outer wall of a building through the installation frame 1, the installation angle iron 4 is fixedly connected with the installation frame 1 through the connecting channel steel 2, the track 6 and the installation angle iron 4 are fixedly installed through the corresponding installation holes 10, the track 6 is arranged on the outer vertical surface of the building to facilitate the lifting of the scaffold, the support frame 3 arranged at the bottom of the connecting channel steel 2 supports the connecting channel steel 2 and strengthens the structural strength of the connecting channel steel 2 and the installation frame 1, the rotating shaft 7 is arranged on the side surface of the track 6, the guide wheel 9 is connected through rotating the rotating shaft 7, the guide wheel 9 is connected with a lifting rod of the scaffold in a clamping mode, the scaffold is prevented from shaking in the lifting process, the guide wheel 9 can also change the sliding friction of the scaffold in the lifting process into the rolling friction, and the friction between the lifting scaffold track 6 and the scaffold is greatly reduced, improve the life of scaffold, the scaffold can be held to leading wheel 9 and scaffold joint when the scaffold is emptyd.
To sum up, the utility model discloses a mounting bracket 1 and the outer wall of building carry out fixed mounting, through connecting channel-section steel 2 with installation angle bar 4 and mounting bracket 1 fixed connection, again with track 6 and installation angle bar 4 through corresponding mounting hole 10 fixed mounting, make track 6 and building set up on the facade, make things convenient for the scaffold frame to go up and down, and set up the support frame 3 in the bottom of connecting channel-section steel 2 and provide the support for connecting channel-section steel 2, and strengthen the structural strength of connecting channel-section steel 2 and mounting bracket 1; set up pivot 7 through the side at track 6, through rotating at pivot 7 and connecting leading wheel 9, carry out the joint through the lifter with leading wheel 9 and scaffold, prevent that scaffold from taking place to rock at the in-process that goes up and down, leading wheel 9 also can become rolling friction with the sliding friction when scaffold goes up and down, make the friction between promotion scaffold track 6 and the scaffold decline greatly, improve the life of scaffold, the scaffold can be held to leading wheel 9 and scaffold joint when the scaffold is emptyd.
It is noted that, herein, relational terms such as first and second, and the like may be used solely to distinguish one entity or action from another entity or action without necessarily requiring or implying any actual such relationship or order between such entities or actions. Also, the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims (6)
- CL-1 type all steel adheres to and promotes scaffold rail, including mounting bracket (1), its characterized in that: the utility model discloses a mounting bracket, including mounting bracket (1), the top fixedly connected with of mounting bracket (1) one side connects channel-section steel (2), bottom fixedly connected with support frame (3) of mounting bracket (1) one side, the one end of connecting channel-section steel (2) bottom and the other end fixed connection of support frame (3), the other end fixedly connected with installation angle bar (4) of connecting channel-section steel (2), there is track (6) one side of installation angle bar (4) through bolt fixed mounting, both ends fixed mounting has pivot (7) about track (6), pivot (7) are rotated and are connected with leading wheel (9).
- 2. The CL-1 type all-steel attachment lifting scaffold rail of claim 1, characterized in that: the mounting rack (1) is two channel steel which are parallel to each other, and the two mounting racks (1) are fixedly connected through a reinforcing steel plate (8).
- 3. The CL-1 type all-steel attachment lifting scaffold rail of claim 1, characterized in that: the number of the connecting channel steel (2) is two, and the two connecting channel steel (2) are parallel to each other.
- 4. The CL-1 type all-steel attachment lifting scaffold rail of claim 1, characterized in that: the top and the bottom of installation angle bar (4) are fixedly connected with and consolidate set square (5), and the thickness of consolidating set square (5) is six millimeters.
- 5. The CL-1 type all-steel attachment lifting scaffold rail of claim 1, characterized in that: the rail (6) is made of angle iron, and mounting holes (10) corresponding to each other are formed in the rail (6) and the mounting angle iron (4).
- 6. The CL-1 type all-steel attachment lifting scaffold rail of claim 1, characterized in that: the rotating shaft (7) is arranged at the upper end and the lower end of the track (6), and guide wheels (9) arranged on the rotating shaft (7) are arranged oppositely.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120186742.3U CN214423947U (en) | 2021-01-23 | 2021-01-23 | CL-1 type all-steel attached lifting scaffold rail |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202120186742.3U CN214423947U (en) | 2021-01-23 | 2021-01-23 | CL-1 type all-steel attached lifting scaffold rail |
Publications (1)
Publication Number | Publication Date |
---|---|
CN214423947U true CN214423947U (en) | 2021-10-19 |
Family
ID=78056902
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202120186742.3U Expired - Fee Related CN214423947U (en) | 2021-01-23 | 2021-01-23 | CL-1 type all-steel attached lifting scaffold rail |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN214423947U (en) |
-
2021
- 2021-01-23 CN CN202120186742.3U patent/CN214423947U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2018232720A1 (en) | Attached vertically moving aluminum alloy scaffold | |
CN211286566U (en) | Wall-attached support of attached lifting scaffold | |
CN108487624A (en) | Attachment type raise scaffold | |
CN214423947U (en) | CL-1 type all-steel attached lifting scaffold rail | |
CN114150857A (en) | Construction method of attached type automatic climbing elevator shaft safety protection platform | |
CN110185247A (en) | Mobile outrigger platform | |
CN105152052B (en) | Glass curtain wall component installing method | |
CN205908031U (en) | A rail mounted lifting device for high -rise building curtain wall construction | |
CN107355069A (en) | A kind of climbing frame falling proof mechanism and the climbing frame falling proof seat in the plane lock based on the mechanism | |
CN214942219U (en) | Swing block type falling protector for CL-1 type all-steel attached lifting scaffold | |
CN207375586U (en) | A kind of hanging apparatus of prefabricated assembled concrete Side fascia | |
CN216446489U (en) | Wall-attached support of attached lifting scaffold | |
CN214246547U (en) | Attached lifting scaffold | |
CN212154108U (en) | Wall-attached type anti-tilting and anti-falling support | |
CN112609950B (en) | Be used for convenient movable handling frame of outer facade construction | |
CN107447931B (en) | The closed factory building roof skylight frame installation method of overlarge area | |
CN211974267U (en) | Attached lifting scaffold structure | |
CN212127307U (en) | Adjustable hoisting support applied to maintenance on bridge crane trolley steel rail | |
CN114215339A (en) | Tool type ultrahigh-structure hanging basket suspension mechanism installation method | |
CN208981152U (en) | A kind of fast-type high-speed rail Bridge Pier Construction hanging basket mounting platform | |
CN207377096U (en) | Overlength large girder scaffold building structure | |
CN107269014B (en) | Hydraulic climbing formwork angle-variable protective net system | |
CN211817863U (en) | Novel attached lifting scaffold | |
CN216007769U (en) | Collect and prevent inclining, prevent weighing down, guide in wall attached support of an organic whole | |
CN215558540U (en) | Movable hanging basket |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20211019 |
|
CF01 | Termination of patent right due to non-payment of annual fee |