CN214302793U - A hoist and mount scaffold frame for frame post construction - Google Patents

A hoist and mount scaffold frame for frame post construction Download PDF

Info

Publication number
CN214302793U
CN214302793U CN202022927430.1U CN202022927430U CN214302793U CN 214302793 U CN214302793 U CN 214302793U CN 202022927430 U CN202022927430 U CN 202022927430U CN 214302793 U CN214302793 U CN 214302793U
Authority
CN
China
Prior art keywords
frame
plate
frame assembly
screw rod
scaffold according
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022927430.1U
Other languages
Chinese (zh)
Inventor
张大德
徐林则
韩友强
万若萌
陈浩
薛恒岩
李明科
郑颖
侯丽霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Original Assignee
Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd filed Critical Third Construction Engineering Co Ltd of China Construction Second Engineering Bureau Co Ltd
Priority to CN202022927430.1U priority Critical patent/CN214302793U/en
Application granted granted Critical
Publication of CN214302793U publication Critical patent/CN214302793U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The utility model discloses a hoisting scaffold for frame column construction, which comprises a frame component, wherein the frame component comprises a vertical rod and a cross rod which are spliced to form a rectangular frame, and the frame component is integrally covered on the peripheral side of a frame column; the frame assembly also comprises a throwing support rod piece which is obliquely connected between the frame assembly and the ground where the frame column is located; the frame subassembly is still including adjusting the base, its set up in the downside of pole setting, it includes bottom plate, screw rod and regulating plate to adjust the base, the screw rod weld perpendicularly in the bottom plate, regulating plate threaded connection in the screw rod, the screw rod set up in the pole setting and supported by the regulating plate. The utility model provides a pair of a hoist and mount scaffold frame for frame post construction, its is rational in infrastructure, and it is convenient to be under construction, can set up hoist and mount scaffold frame wholly in the periphery side of frame post through the hoist and mount operation, has avoided the loaded down with trivial details that traditional scaffold frame need scene to be assembled, has improved the operating efficiency.

Description

A hoist and mount scaffold frame for frame post construction
Technical Field
The utility model belongs to the technical field of building engineering, a hoist and mount scaffold frame for frame post construction is related to.
Background
In construction work, frame columns are a common structural form. In traditional construction, need build the scaffold temporarily for the structure of frame post, it can use a large amount of steel pipes, extravagant a large amount of manual works. In addition, the temporarily built scaffold cannot be used in a turnover mode, and construction cost is increased invisibly.
Moreover, the temporarily built scaffold is not provided with a leveling function, and various complicated construction sites cannot be used.
Therefore, a hoisting scaffold for frame column construction needs to be designed to solve the technical problems in the prior art.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the partial technical problem that exists among the prior art to a certain extent at least, the hoisting scaffold for frame post construction that provides, its is rational in infrastructure, and the construction is convenient, can set up hoisting scaffold wholly in the periphery side of frame post through the hoist and mount operation, has avoided traditional scaffold to need the loaded down with trivial details of on-the-spot assembly, has improved the operating efficiency.
In order to solve the technical problem, the utility model provides a hoisting scaffold for frame column construction, which comprises a frame component, wherein the frame component comprises a vertical rod and a horizontal rod which are spliced to form a rectangular frame, and the frame component is integrally covered on the peripheral side of the frame column; the frame assembly also comprises a throwing support rod piece which is obliquely connected between the frame assembly and the ground where the frame column is located; the frame subassembly is still including adjusting the base, its set up in the downside of pole setting, it includes bottom plate, screw rod and regulating plate to adjust the base, the screw rod weld perpendicularly in the bottom plate, regulating plate threaded connection in the screw rod, the screw rod set up in the pole setting and supported by the regulating plate.
As a preferred embodiment, the vertical rods are of a pipe structure, the number of the vertical rods is four, and the vertical rods are vertically arranged at four corners of the frame assembly.
As a preferred embodiment, the cross bars are arranged perpendicular to the vertical rods, and the distance between every two adjacent cross bars is not more than 1.5 m.
In a preferred embodiment, the throwing brace is removably attached to the crossbar of the frame assembly.
As a preferred embodiment, an included angle between the throwing brace piece and the ground where the frame column is located is an acute angle.
As a preferred embodiment, the lifting scaffold further comprises a support plate detachably disposed on the cross bar of the frame assembly to form a work plane.
As a preferred embodiment, the supporting plate is a wood plate, and the thickness of the supporting plate is 50 mm.
As a preferred embodiment, the base plate, the screw, and the adjusting plate are made of stainless steel.
As a preferred embodiment, the adjusting base further includes a protection pad disposed at a lower side of the base plate to prevent the base plate from rusting.
As a preferred embodiment, the protective pad is made of polyurethane.
The utility model discloses beneficial effect:
the utility model provides a pair of a hoist and mount scaffold frame for frame post construction, its is rational in infrastructure, and it is convenient to be under construction, can set up hoist and mount scaffold frame wholly in the periphery side of frame post through the hoist and mount operation, has avoided the loaded down with trivial details that traditional scaffold frame need scene to be assembled, has improved the operating efficiency.
Drawings
The above advantages of the present invention will become more apparent and more readily appreciated from the detailed description taken in conjunction with the following drawings, which are given by way of illustration only and do not limit the present invention, and in which:
fig. 1 is a schematic structural diagram of a hoisting scaffold for frame column construction according to the present invention;
fig. 2 is a top view of the corresponding lifting scaffold of fig. 1;
FIG. 3 is a schematic view of the connection between the adjusting base and the stand bar according to the present invention;
fig. 4 is a partially enlarged view of fig. 3.
In the drawings, the reference numerals denote the following components:
10. a frame assembly; 11. erecting a rod; 12. a cross bar; 13. throwing a strut member; 14. adjusting the base; 14a, a base plate; 14b. a screw; 14c, adjusting plate; 14d, a protective pad; 20. a frame column; 30. and a support plate.
Detailed Description
Fig. 1 to 4 are related schematic diagrams of a hoisting scaffold for frame column construction according to the present application, and the present invention will be described in detail below with reference to specific embodiments and accompanying drawings.
The embodiments described herein are specific embodiments of the present invention, and are intended to be illustrative of the concepts of the present invention, which are intended to be illustrative and exemplary, and should not be construed as limiting the scope of the embodiments of the present invention. In addition to the embodiments described herein, those skilled in the art will be able to employ other technical solutions which are obvious based on the disclosure of the claims and the specification of the present application, and these technical solutions include technical solutions which make any obvious replacement or modification for the embodiments described herein.
The drawings in the present specification are schematic views to assist in explaining the concept of the present invention, and schematically show the shapes of the respective portions and the mutual relationships thereof. It should be noted that for the sake of clarity in showing the structures of the various components of the embodiments of the present invention, the drawings are not drawn to the same scale. Like reference numerals are used to denote like parts.
A structure schematic diagram of a hoist and mount scaffold frame for frame post construction, as shown in fig. 1 to fig. 2. The hoisting scaffold for frame column construction comprises a frame assembly 10, wherein the frame assembly 10 comprises upright rods 11 and cross rods 12, the upright rods and the cross rods are spliced to form a rectangular frame, and the frame assembly 10 is integrally covered on the outer peripheral side of a frame column 20; the frame assembly 10 further includes a throwing brace 13 which is connected between the frame assembly 10 and the ground on which the frame post 20 is located at an incline.
The frame assembly 10 further includes an adjusting base 14 disposed at a lower side of the upright 11, the adjusting base 14 includes a bottom plate 14a, a screw 14b and an adjusting plate 14c, as shown in fig. 3, the screw 14b is vertically welded to the bottom plate 14a, the adjusting plate 14c is screwed to the screw 14b, and the screw 14b is disposed in the upright 11 and supported by the adjusting plate 14c. The setting of adjusting base 14 is favorable to the levelness of hoist and mount scaffold frame according to the operating mode adjustment, guarantees the security of operation.
As an embodiment of the present invention, the vertical rods 11 are tube structures, and the number of the vertical rods is four, which are vertically disposed at four corners of the frame assembly 10. The cross bars 12 are perpendicular to the vertical rods 11, and the distance between every two adjacent cross bars 12 is not more than 1.5 m.
In the embodiment shown in fig. 1, the throwing brace 13 is removably attached to the crossbar 12 of the frame assembly 10. The included angle between the throwing brace rod piece 13 and the ground where the frame column 20 is located is an acute angle. In fig. 1, the included angle between the throwing brace 13 and the ground where the frame column 20 is located is 60 degrees, and it is understood that the included angle between the throwing brace 13 and the ground where the frame column 20 is located may be other acute angles. The throwing strut member 13 is installed after the frame assembly 10 formed by the upright rods 11 and the cross rods 12 is lifted to a proper position by using the lifting appliance as a whole.
In fig. 1, the lifting scaffold further comprises a support plate 30 detachably mounted to the ledgers 12 of the frame assembly 10 to form a work plane. In one aspect of this embodiment, the support plate 30 is a wooden plate having a thickness of 50 mm. It will be appreciated that the support plate 30 may also be made of steel plate.
In fig. 3, the base plate 14a, the screw 14b, and the adjusting plate 14c are made of stainless steel. As another embodiment of the present invention, the adjusting base 14 further includes a protection pad 14d, as shown in fig. 4, which is disposed at the lower side of the bottom plate 14a to prevent the bottom plate 14a from rusting.
As an aspect of this embodiment, the protection pad 14d is made of polyurethane to prevent the bottom of the adjustment base 14 from rusting and affecting its normal use.
Compare in prior art's shortcoming and not enough, the utility model provides a pair of a hoist and mount scaffold frame for frame post construction, its is rational in infrastructure, and the construction is convenient, can set up hoist and mount scaffold frame whole in the periphery side of frame post through the hoist and mount operation, has avoided traditional scaffold frame to need the loaded down with trivial details of on-the-spot assembly, has improved the operating efficiency.
The present invention is not limited to the above embodiments, and any person can obtain other products in various forms without departing from the scope of the present invention, but any change in shape or structure is included in the technical solution that is the same as or similar to the present invention.

Claims (10)

1. A hoisting scaffold for frame column construction is characterized by comprising a frame assembly, wherein the frame assembly comprises upright rods and cross rods, the upright rods and the cross rods are spliced to form a rectangular frame, and the frame assembly is integrally covered on the outer peripheral side of a frame column; the frame assembly also comprises a throwing support rod piece which is obliquely connected between the frame assembly and the ground where the frame column is located; the frame subassembly is still including adjusting the base, its set up in the downside of pole setting, it includes bottom plate, screw rod and regulating plate to adjust the base, the screw rod weld perpendicularly in the bottom plate, regulating plate threaded connection in the screw rod, the screw rod set up in the pole setting and supported by the regulating plate.
2. A lifting scaffold according to claim 1, characterized in that the uprights are tubular structures, four in number, arranged vertically at the four corners of the frame assembly.
3. Hoisting scaffold according to claim 1, characterized in that the ledgers are arranged perpendicular to the uprights, the distance between adjacent ledgers being not more than 1.5 m.
4. Hoisting scaffold according to claim 1, characterized in that the cast spreader bar elements are detachably connected to the crossbars of the frame assembly.
5. The hoisting scaffold according to claim 4, wherein the angle between the throwing strut member and the ground on which the frame post is located is acute.
6. The lifting scaffold according to claim 1, further comprising support plates removably attached to the crossbars of the frame assembly to form a work plane.
7. Hoisting scaffold according to claim 6, characterized in that the supporting plate is a wooden plate with a thickness of 50 mm.
8. The lifting scaffold according to claim 1, wherein the base plate, threaded rod and adjustment plate are made of stainless steel.
9. A lifting scaffold according to claim 8, wherein the adjustment base further comprises a protective pad provided on the underside of the base plate to prevent rusting of the base plate.
10. Hoisting scaffold according to claim 9, characterized in that the protective mat is made of polyurethane.
CN202022927430.1U 2020-12-09 2020-12-09 A hoist and mount scaffold frame for frame post construction Active CN214302793U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022927430.1U CN214302793U (en) 2020-12-09 2020-12-09 A hoist and mount scaffold frame for frame post construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022927430.1U CN214302793U (en) 2020-12-09 2020-12-09 A hoist and mount scaffold frame for frame post construction

Publications (1)

Publication Number Publication Date
CN214302793U true CN214302793U (en) 2021-09-28

Family

ID=77852303

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022927430.1U Active CN214302793U (en) 2020-12-09 2020-12-09 A hoist and mount scaffold frame for frame post construction

Country Status (1)

Country Link
CN (1) CN214302793U (en)

Similar Documents

Publication Publication Date Title
CN212773624U (en) Hanging, hanging and pulling supporting device suitable for steel bar truss floor bearing plate
CN108252534B (en) Column top construction device for truss installation
CN110700572A (en) Height-adjustable supporting base and using method thereof
CN213710299U (en) Modular two-layer elevartor shaft integral lifting bracing operation platform
CN210659407U (en) Tool type protective shed for machining of reinforcing steel bars
CN213268605U (en) Steel bar support and raft foundation steel bar structure comprising same
CN113802880A (en) Combined supporting structure for mounting large-span steel beam
CN214302793U (en) A hoist and mount scaffold frame for frame post construction
CN211369597U (en) Construction is with recoverable bearing diagonal structure
CN209741895U (en) Connection structure of assembled elevator steel construction and base
CN206428986U (en) A kind of detachable turnover type support jig
CN214220599U (en) Batter post bearing structure
CN209779457U (en) Supporting device for box girder side template
CN213563427U (en) Precast beam removes stretch-draw rack
CN210002826U (en) detachable welding platform for steel column construction
CN212000638U (en) Overhead cover beam type steel supporting structure
CN210289183U (en) Auxiliary device for mounting beam steel bars
CN219887511U (en) Elevator shaft steel platform
CN211286560U (en) Spherical node suspension adjustable operation platform
CN214423187U (en) Easily carry road and bridge engineering scaffold frame of easy dismouting just equipment
CN214462916U (en) Temporary supporting device for steel net rack
CN214575611U (en) Anti-falling device for steel structure engineering construction and fixing support thereof
CN216713826U (en) Shaping template system
CN215830120U (en) Combined warehouse for construction site
TWI771891B (en) Beam plate structure and external inclined support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant