CN214214285U - Steel pipe concrete pipe pile processingequipment - Google Patents

Steel pipe concrete pipe pile processingequipment Download PDF

Info

Publication number
CN214214285U
CN214214285U CN202022283286.2U CN202022283286U CN214214285U CN 214214285 U CN214214285 U CN 214214285U CN 202022283286 U CN202022283286 U CN 202022283286U CN 214214285 U CN214214285 U CN 214214285U
Authority
CN
China
Prior art keywords
cylinder
tubular pile
installation
steel tube
fixed mounting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022283286.2U
Other languages
Chinese (zh)
Inventor
徐思强
李军
傅鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Shuotai Construction Technology Co Ltd
Original Assignee
Jiangsu Shuotai Construction Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Shuotai Construction Technology Co Ltd filed Critical Jiangsu Shuotai Construction Technology Co Ltd
Priority to CN202022283286.2U priority Critical patent/CN214214285U/en
Application granted granted Critical
Publication of CN214214285U publication Critical patent/CN214214285U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a steel pipe concrete tubular pile processingequipment, including the processing bottom plate, the rear side rigidity welding of processing bottom plate top left end has the mounting bracket, the left side fixed mounting at mounting bracket top has the third cylinder, the output of third cylinder bottom runs through mounting bracket top and fixed mounting has first installation diaphragm, the right side rigidity mounting at first installation diaphragm top has the second motor, second motor right side output has the cutting wheel through the fixed cover of shaft coupling, the intermediate position department fixed mounting of first installation diaphragm left side lateral wall has the stop gear fixed mutually with the processing bottom plate top. Thereby this tubular concrete filled steel tube tubular pile processingequipment moves to suitable position department about driving second installation diaphragm, lifting roller and tubular concrete filled steel tube tubular pile through starting that first cylinder is flexible, then starts that the third cylinder is flexible and drives first installation diaphragm and slide from top to bottom, thereby starts the second motor and drives the cutting wheel and rotate and cut the tubular concrete filled steel tube tubular pile.

Description

Steel pipe concrete pipe pile processingequipment
Technical Field
The utility model relates to a tubular pile processing equipment technical field specifically is a concrete filled steel tube tubular pile processingequipment.
Background
Concrete filled steel tube tubular pile is the building tubular pile that is formed by steel pipe and concrete combination, and traditional concrete filled steel tube tubular pile processingequipment can satisfy people's user demand basically, but still has certain problem, and concrete problem is as follows:
1. most of steel pipe concrete pipe pile processing devices in the current market are inconvenient for cutting formed pipe piles;
2. most of the concrete filled steel tube tubular pile processingequipment are not convenient for polish to concrete filled steel tube tubular pile's surface in the existing market.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a concrete filled steel tube tubular pile processingequipment to solve the problem that proposes in the above-mentioned background art.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a concrete filled steel tube tubular pile processingequipment, includes the processing bottom plate, the rear side rigidity welding of processing bottom plate top left end has the mounting bracket, the left side fixed mounting at mounting bracket top has the third cylinder, the output of third cylinder bottom runs through mounting bracket top and fixed mounting has first installation diaphragm, the right side rigidity mounting at first installation diaphragm top has the second motor, second motor right side output has the cutting wheel through the fixed cover of shaft coupling, the intermediate position department fixed mounting of first installation diaphragm left side lateral wall has the stop gear who fixes mutually with the processing bottom plate top, stop gear's top is fixed mutually with mounting bracket inner chamber top.
Preferably, among the above-mentioned steel pipe concrete tubular pile processingequipment, stop gear includes spacing vertical pole and spacing standpipe, spacing standpipe fixed mounting is in the intermediate position department of first installation diaphragm left side lateral wall, spacing standpipe inner chamber is provided with runs through spacing standpipe and respectively with the processing bottom plate and the spacing vertical pole that the mounting bracket is connected.
Based on above-mentioned technical characteristics, be convenient for restrict the removal of first installation diaphragm.
Preferably, among the above-mentioned steel pipe concrete pipe pile processingequipment, the right side at processing bottom plate top is provided with the coasting mechanism, the position fixed mounting that coasting mechanism left side and be located the processing bottom plate top has first cylinder, the top fixed mounting of coasting mechanism has second installation diaphragm, the equal fixed mounting in four corners position at second installation diaphragm top has the frame of lifting, controls two sets ofly lift frame inner chamber top is equipped with the installation cross axle that runs through the frame of lifting through the bearing housing, controls two sets of lift between the frame and be located the fixed cover in installation cross axle outer wall position and have connect the roller of lifting.
Based on the technical characteristics, the concrete filled steel tube tubular pile is convenient to polish.
Preferably, among the above-mentioned concrete filled steel tube tubular pile processingequipment, slide mechanism is including sliding groove and slide block, slide groove sets up the right side position at processing bottom plate top, slide groove cavity and set up the slide block of fixing mutually with second installation diaphragm bottom intermediate position department, slide block left side lateral wall is fixed with first cylinder right side output.
Based on the technical characteristics, the concrete filled steel tube tubular pile is convenient to polish.
Preferably, among the above-mentioned steel pipe concrete pipe pile processingequipment, it is two sets of the right side position fixed mounting who just is located second installation diaphragm top between the support frame has first motor, first motor right side output has first connecting wheel, and is two sets of the support frame right side just is located the fixed cover in installation cross axle outside position and has connect the second connecting wheel, the outside cover of second connecting wheel and first connecting wheel is equipped with the connection belt.
Based on the technical characteristics, the concrete filled steel tube tubular pile is convenient to polish.
Preferably, among the above-mentioned steel pipe concrete pipe pile processingequipment, mounting bracket top right side fixed mounting has the second cylinder, second cylinder bottom output runs through mounting bracket top and fixed mounting has the third installation diaphragm, the intermediate position department fixed mounting of third installation diaphragm bottom has the third motor, the output of third motor bottom has the transverse wheel of polishing through the fixed cover of shaft coupling that has connect.
Based on the technical characteristics, the concrete filled steel tube tubular pile is convenient to polish.
Compared with the prior art, the beneficial effects of the utility model are that:
firstly, through the design of the technical scheme, a concrete filled steel tube tubular pile is placed between a front set of lifting rollers and a rear set of lifting rollers, then a first air cylinder is started to stretch and retract so as to drive a second installation transverse plate to move, simultaneously drive the lifting rollers and the concrete filled steel tube tubular pile to move left and right to a proper position, then a third air cylinder is started to stretch and retract so as to drive the first installation transverse plate to slide up and down, and a second motor is started to drive a cutting wheel to rotate so as to cut the concrete filled steel tube tubular pile;
second, through the design of this technical scheme, when starting that first cylinder is flexible to drive the tubular pile and remove about, thereby can start the extension of second cylinder and drive third installation diaphragm and third motor and move down so that polish the upper surface laminating of band pulley bottom and concrete filled steel tube tubular pile, start the third motor and drive the band pulley rotation of polishing and then polish concrete filled steel tube tubular pile.
Drawings
FIG. 1 is a front view of the cross-sectional structure of the present invention;
fig. 2 is the utility model discloses processing bottom plate, lifting roller, second installation diaphragm, second cylinder and mounting bracket right side view structure schematic diagram.
In the figure: 1. a limiting mechanism; 101. limiting the vertical rod; 102. a vertical limiting pipe; 2. a first mounting transverse plate; 3. a cutting wheel; 4. installing a transverse shaft; 5. processing a bottom plate; 6. a first cylinder; 7. a lifting roller; 8. a coasting mechanism; 801. a sliding groove; 802. a sliding block; 9. a second mounting transverse plate; 10. a first motor; 11. a first connecting wheel; 12. connecting a belt; 13. a second fifth wheel; 14. a lifting frame; 15. thirdly, installing a transverse plate; 16. a second cylinder; 17. a mounting frame; 18. a second motor; 19. a third cylinder; 20. a third motor; 21. and (5) polishing the transverse wheel.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-2, the present invention provides an embodiment: a steel pipe concrete pipe pile processing device comprises a processing bottom plate 5, wherein a mounting frame 17 is fixedly welded at the rear side position of the left end of the top of the processing bottom plate 5, a third air cylinder 19 is fixedly installed at the left side of the top of the mounting frame 17, the type of the third air cylinder 19 can be ACQ50X5, a switch button of the third air cylinder 19 is arranged at a proper position, an output end of the bottom of the third air cylinder 19 penetrates through the top of the mounting frame 17 and is fixedly provided with a first mounting transverse plate 2, a right side position of the top of the first mounting transverse plate 2 is fixedly provided with a second motor 18, the type of the second motor 18 can be Y315S-4, the switch button of the second motor 18 is arranged at a proper position, the right side output end of the second motor 18 is fixedly connected with a cutting wheel 3 through a coupler, a limiting mechanism 1 fixed with the top of the processing bottom plate 5 is fixedly arranged at the middle position of the left side wall of the first mounting transverse plate 2, the top of the limiting mechanism 1 is fixed with the top of the inner cavity of the mounting frame 17.
Please refer to fig. 1 in the drawings of the specification: the limiting mechanism 1 comprises a limiting vertical rod 101 and a limiting vertical pipe 102, the limiting vertical pipe 102 is fixedly installed at the middle position of the left side wall of the first installation transverse plate 2, and the limiting vertical rod 101 which penetrates through the limiting vertical pipe 102 and is respectively connected with the processing bottom plate 5 and the installation frame 17 is arranged in the inner cavity of the limiting vertical pipe 102.
Please refer to fig. 1 and 2 in the drawings of the specification: the right side at 5 tops of processing bottom plate is provided with slide mechanism 8, slide mechanism 8 left side and the position fixed mounting that is located 5 tops of processing bottom plate have first cylinder 6, the model of this first cylinder 6 can be SC200-25, and the shift knob setting of this first cylinder 6 is in suitable position department, slide mechanism 8's top fixed mounting has second installation diaphragm 9, the equal fixed mounting in four corners position at second installation diaphragm 9 top has lifting frame 14, it has the installation cross axle 4 that runs through lifting frame 14 to control two sets of lifting frame 14 inner chamber tops through the bearing housing, it has lifting roller 7 to control two sets of lifting frame 14 between and be located 4 outer wall fixed cup joints of installation cross axle.
Please refer to fig. 1 in the drawings of the specification: the sliding mechanism 8 comprises a sliding groove 801 and a sliding block 802, the sliding groove 801 is arranged at the right side position of the top of the processing bottom plate 5, the sliding block 802 fixed with the middle position of the bottom of the second mounting transverse plate 9 is arranged in the inner cavity of the sliding groove 801, and the left side wall of the sliding block 802 is fixed with the right output end of the first air cylinder 6.
Please refer to fig. 1 in the drawings of the specification: a first motor 10 is fixedly installed at the right side position between the two groups of lifting frames 14 and at the top of the second installation transverse plate 9, the type of the first motor 10 can be Y112M-6, a switch button of the first motor 10 is arranged at a proper position, the output end of the right side of the first motor 10 is fixedly connected with a first connecting wheel 11 through a coupler, the right sides of the two groups of lifting frames 14 are fixedly sleeved with a second connecting wheel 13 at the outer position of the installation transverse shaft 4, and a connecting belt 12 is sleeved on the outer portions of the second connecting wheel 13 and the first connecting wheel 11.
Please refer to fig. 1 and 2 in the drawings of the specification: the second cylinder 16 is fixedly mounted on the right side of the top of the mounting frame 17, the type of the second cylinder 16 can be SC160X250, a switch button of the second cylinder 16 is arranged at a proper position, an output end of the bottom of the second cylinder 16 penetrates through the top of the mounting frame 17 and is fixedly mounted with a third mounting transverse plate 15, a third motor 20 is fixedly mounted at the middle position of the bottom of the third mounting transverse plate 15, the type of the third motor 20 can be Y90S-6, the switch button of the third motor 20 is arranged at a proper position, and a polishing transverse wheel 21 is fixedly connected to an output end of the bottom of the third motor 20 through a coupler.
The working principle is as follows: when the device for processing the concrete-filled steel tube tubular pile is used, the device for processing the concrete-filled steel tube tubular pile is placed at a proper position through a processing bottom plate 5, then the concrete-filled steel tube tubular pile is placed between a front lifting roller 7 and a rear lifting roller 7, then an external power supply is switched on, then a first air cylinder 6 is started to stretch and retract so as to drive a sliding block 802 to move left and right in an inner cavity of a sliding groove 801, further the lifting rollers 7 and the concrete-filled steel tube tubular pile are driven to move to the proper position through moving a second installation transverse plate 9, then a third air cylinder 19 is started to stretch so as to drive a first installation transverse plate 2 to slide up and down through a limiting vertical pipe 102 outside a limiting vertical rod 101, a second motor 18 is started to drive a cutting wheel 3 to rotate so as to cut the concrete-filled steel tube tubular pile, when the outer wall of the concrete-filled steel tube tubular pile needs to be polished, the first air cylinder 6 is started to stretch so as to drive the tubular pile to move left and right, thereby can start 16 extensions of second cylinder and drive third installation diaphragm 15 and third motor 20 and remove downwards thereby make the upper surface laminating of 21 bottoms of band pulley and concrete filled steel tube tubular pile of polishing, it drives the band pulley 21 rotation of polishing and then polishes the concrete filled steel tube tubular pile to start third motor 20, thereby start first motor 10 and drive first connecting wheel 11 and rotate and drive second connecting wheel 13 through connecting belt 12 and rotate, thereby second connecting wheel 13 drives installation cross axle 4 pivoted and drives lift roller 7 and rotate and utilize frictional force to drive the concrete filled steel tube and rotate thereby the outer wall of the concrete filled steel tube tubular pile of being convenient for fully polish, when needs cut the concrete filled steel tube tubular pile of big pipe diameter, start third cylinder 19 and second motor 18 and can start first motor 10 and drive lift roller 7 and rotate and then drive the concrete filled steel tube tubular pile and rotate thereby can cut out under the fixed condition of diameter of cutting wheel 3 when cutting the concrete filled steel tube tubular pile of pipe tubular pile Cut the concrete filled steel tube tubular pile of bigger diameter, do above the utility model discloses a whole theory of operation.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (6)

1. The utility model provides a concrete filled steel tube tubular pile processingequipment, includes processing bottom plate (5), its characterized in that: the welding of rear side position of processing bottom plate (5) top left end has mounting bracket (17), the left side fixed mounting at mounting bracket (17) top has third cylinder (19), the output of third cylinder (19) bottom runs through mounting bracket (17) top and fixed mounting has first installation diaphragm (2), the right side position fixed mounting at first installation diaphragm (2) top has second motor (18), second motor (18) right side output has cup jointed cutting wheel (3) through the shaft coupling is fixed, the intermediate position department fixed mounting of first installation diaphragm (2) left side lateral wall has stop gear (1) fixed mutually with processing bottom plate (5) top, the top of stop gear (1) is fixed mutually with mounting bracket (17) inner chamber top.
2. The device for processing the concrete filled steel tube tubular pile according to claim 1, which is characterized in that: the limiting mechanism (1) comprises a limiting vertical rod (101) and a limiting vertical pipe (102), the limiting vertical pipe (102) is fixedly installed at the middle position of the side wall of the left side of the first installation transverse plate (2), and the limiting vertical rod (101) which penetrates through the limiting vertical pipe (102) and is respectively connected with the processing bottom plate (5) and the installation frame (17) is arranged in the inner cavity of the limiting vertical pipe (102).
3. The device for processing the concrete filled steel tube tubular pile according to claim 1, which is characterized in that: the right side at processing bottom plate (5) top is provided with slide mechanism (8), slide mechanism (8) left side and the position fixed mounting that is located processing bottom plate (5) top have first cylinder (6), the top fixed mounting of slide mechanism (8) has second installation diaphragm (9), the equal fixed mounting in four corners position at second installation diaphragm (9) top has lift frame (14), controls two sets ofly lift frame (14) inner chamber top is through the bearing housing and is equipped with installation cross axle (4) that runs through lift frame (14), controls two sets of lift between frame (14) and be located installation cross axle (4) outer wall position fixed cup jointed and lift roller (7).
4. The device for processing the concrete filled steel tube tubular pile as claimed in claim 3, wherein: slide mechanism (8) are including sliding groove (801) and sliding block (802), sliding groove (801) are seted up at the right side position at processing bottom plate (5) top, sliding groove (801) inner chamber sets up sliding block (802) fixed mutually with second installation diaphragm (9) bottom intermediate position department, sliding block (802) left side lateral wall is fixed with first cylinder (6) right side output.
5. The device for processing the concrete filled steel tube tubular pile as claimed in claim 3, wherein: two sets of right side position fixed mounting who just is located second installation diaphragm (9) top between lifting frame (14) has first motor (10), first motor (10) right side output has first connecting wheel (11), two sets of lifting frame (14) right side and be located installation cross axle (4) external position fixed cup joint second connecting wheel (13), second connecting wheel (13) and first connecting wheel (11) outside cover are equipped with and connect belt (12).
6. The device for processing the concrete filled steel tube tubular pile according to claim 1, which is characterized in that: mounting bracket (17) top right side fixed mounting has second cylinder (16), second cylinder (16) bottom output runs through mounting bracket (17) top and fixed mounting has third installation diaphragm (15), the intermediate position department fixed mounting of third installation diaphragm (15) bottom has third motor (20), the output of third motor (20) bottom has cup jointed grinding transverse wheel (21) through the shaft coupling is fixed.
CN202022283286.2U 2020-10-14 2020-10-14 Steel pipe concrete pipe pile processingequipment Active CN214214285U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022283286.2U CN214214285U (en) 2020-10-14 2020-10-14 Steel pipe concrete pipe pile processingequipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022283286.2U CN214214285U (en) 2020-10-14 2020-10-14 Steel pipe concrete pipe pile processingequipment

Publications (1)

Publication Number Publication Date
CN214214285U true CN214214285U (en) 2021-09-17

Family

ID=77694491

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022283286.2U Active CN214214285U (en) 2020-10-14 2020-10-14 Steel pipe concrete pipe pile processingequipment

Country Status (1)

Country Link
CN (1) CN214214285U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114559359A (en) * 2022-04-28 2022-05-31 四川富生电器有限责任公司 Surface polishing device for motor rotor production

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114559359A (en) * 2022-04-28 2022-05-31 四川富生电器有限责任公司 Surface polishing device for motor rotor production
CN114559359B (en) * 2022-04-28 2022-07-22 四川富生电器有限责任公司 Surface polishing device for motor rotor production

Similar Documents

Publication Publication Date Title
CN214214285U (en) Steel pipe concrete pipe pile processingequipment
CN110774124B (en) Fixed-point polishing device for surface nodes of timber piles
CN110814940B (en) Bottom grinding robot for processing bottom of crystal glass cup
CN110722415B (en) Building templates grinding device
CN212957777U (en) Firm type assembled building supporting seat
CN210771029U (en) Convenient to use's portable water pump
CN210342599U (en) Horizontal ground ceramic tile laying device for house construction
CN218504074U (en) Wall grinding equipment
CN112779943A (en) Quick fluting device for construction machinery
CN217260381U (en) All-directional moving mechanism for service robot
CN111227727B (en) Movable indoor drainage equipment
CN214556076U (en) Cleaning device of pneumatic hybrid tower
CN110424646B (en) Automatic laying device of waterproof membrane for outdoor building
CN112496906A (en) Metal product processing sheet metal member surfacing device
CN210060697U (en) Grinding device is used in artificial limb production
CN217942438U (en) Novel automatic pull rod assembling machine
CN214186670U (en) Rostone burnishing machine with adjustable
CN110881939A (en) Efficient and environment-friendly leather shoe sole cleaning equipment
CN213054170U (en) Wood grinding machine convenient to move
CN110900339A (en) Automatic wall grinding device
CN212505448U (en) Grinding device is used in processing of elasticity surface fabric
CN217594803U (en) Novel sand mill of chemical preparation processing usefulness
CN220713801U (en) Dust collector with multifunctional suction head
CN213351918U (en) Grinding wheel leveling mechanism of sharpening machine
CN212351387U (en) Horizontal ground polisher of building engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant