CN214168790U - Steel pipe concrete assembled truss composite beam construction system - Google Patents

Steel pipe concrete assembled truss composite beam construction system Download PDF

Info

Publication number
CN214168790U
CN214168790U CN202023226406.1U CN202023226406U CN214168790U CN 214168790 U CN214168790 U CN 214168790U CN 202023226406 U CN202023226406 U CN 202023226406U CN 214168790 U CN214168790 U CN 214168790U
Authority
CN
China
Prior art keywords
bridge deck
steel
concrete
scaffold
transverse
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202023226406.1U
Other languages
Chinese (zh)
Inventor
卢军球
盛明宏
陈莘
郭永刚
鲍建新
董祥君
王中恩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Road and Bridge Engineering Group Co Ltd
Original Assignee
Anhui Road and Bridge Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Road and Bridge Engineering Group Co Ltd filed Critical Anhui Road and Bridge Engineering Group Co Ltd
Priority to CN202023226406.1U priority Critical patent/CN214168790U/en
Application granted granted Critical
Publication of CN214168790U publication Critical patent/CN214168790U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a steel pipe concrete assembled truss composite beam construction system, which is characterized in that a scaffold supporting system, a finalized temporary support, a bridge deck steel bar binding jig frame and a bridge deck concrete construction platform are arranged; a cast-in-place bearing platform of the scaffold supporting system is embedded into a steep mountain; a vertical rod at one side of the finalized temporary support penetrates through the bridge deck; the bridge deck crossing steel bar binding jig frame is arranged on the circular supporting plates of the two side-shaped temporary supports; the horizontal steel springboard bridge deck of the bridge deck concrete construction platform is arranged on the tie bars of the two side-shaped temporary supports. The utility model discloses adopt steel pipe pile formula scaffold braced system or stepped scaffold braced system respectively to different topography to make full use of regularization temporary support has set up decking reinforcement bed-jig and bridge floor slab concrete construction platform, has still add stretch-draw fixing device and fixed gallows, has the characteristics of the advanced technique, structural stability is good, the efficiency of construction is high and safe.

Description

Steel pipe concrete assembled truss composite beam construction system
Technical Field
The utility model relates to a bridge engineering technical field, concretely relates to concrete filled steel tube pin-connected panel truss composite beam construction system.
Background
The concrete-filled steel tube truss breaks through the traditional application range of the concrete-filled steel tube structure, can give full play to the stress performance of the concrete-filled steel tube, and is an important direction for the development of the concrete-filled steel tube structure. To a certain extent, the characteristics of the steel pipe-concrete truss composite beam structure in design and construction conform to the trend of future bridge design and construction development, namely, on the premise of maintaining the original traffic conveniently, the construction progress is accelerated, the engineering quality is improved, and the engineering construction is developed towards prefabrication, assembly and rapid construction.
However, in actual design and construction, it is found that the traditional truss girder adopting the upper chord member filled with concrete still has disadvantages, firstly, because the concrete is filled in the upper chord member, the integrity of the truss girder is poor, the structural strength and rigidity of the lower chord member and the web pipes are still weak, in order to ensure the reliability of the web pipes, the web pipes are required to be enlarged or thickened, or more web pipes are arranged, so that the construction cost is further increased; on the other hand, the on-site construction efficiency is low, the foundation is mainly limited by the foundation form, the foundation treatment consumes longer construction time, and meanwhile, the whole construction efficiency is further reduced due to the insufficient design of the bridge deck reinforcement and concrete pouring construction platform.
Aiming at the problems, the utility model discloses a concrete filled steel tube assembled truss composite beam construction method which has good construction quality, high construction efficiency and outstanding economic and technical benefits is urgently needed at present.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a concrete filled steel tube pin-connected panel truss composite beam construction system aims at solving the current stage concrete filled steel tube truss construction quality poor, the technical problem that the efficiency of construction is low.
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes:
the steel pipe concrete assembled truss composite beam construction system comprises a scaffold support system, a shaped temporary support, a bridge deck steel bar binding jig frame and a bridge deck concrete construction platform;
the scaffold supporting system comprises a cast-in-place bearing platform, steel pipe stand columns, a lower cross beam, a Bailey truss, a distribution beam and a full hall scaffold which are sequentially arranged from bottom to top; the cast-in-place bearing platform is embedded into a steep mountain;
the shaped temporary support comprises a vertical rod and a connecting rod; wherein, the upright stanchions at one side are arranged through the bridge deck, and are vertically positioned with round supporting plates at equal intervals within the elevation range of the bridge deck slab of the bridge body;
the bridge deck steel bar binding jig frame comprises a transverse jig frame and a longitudinal jig frame; the transverse jig frame is arranged on the circular support plates of the two side sizing temporary supports across the bridge deck, the longitudinal jig frame is parallel to the lower chord and arranged on the circular support plates of the same side sizing temporary supports in a segmented mode and located between the transverse jig frames;
the bridge deck concrete construction platform comprises a transverse steel springboard and a longitudinal steel springboard; the transverse steel springboard bridge-spanning panel is arranged on the tie bars of the two side-shaped temporary supports, and the longitudinal steel springboard is arranged on the transverse steel springboard and is transversely fixed through the limiting plates.
As a further improvement of the utility model, a template is arranged on the top of the scaffold supporting system, and shaped temporary supports are arranged on two sides of the scaffold supporting system; the bridge deck steel bars arranged on the shaped temporary support are bound with a jig frame to perform steel bar operation; the bridge deck concrete construction platform arranged on the finalized temporary support performs concrete operation on the steel truss; the steel strand on the lower chord is tensioned through a tensioning fixing device; the steel truss realizes pouring concrete through the grout pipe on the fixed gallows.
As a further improvement of the present invention, the scaffold support system comprises a steel pipe pile type scaffold support system and a step type scaffold support system; the step type scaffold supporting system comprises a step type support foundation and a full scaffold; the step-type support foundation is formed by excavating undisturbed soil into a step shape and pouring through a stereotyped step-by-step drawknot template.
As a further improvement of the utility model, the shaped step-by-step drawknot template comprises a side plate, a turnable template and a limiting block; the side plates at two sides are vertically embedded into undisturbed soil and are provided with sliding chutes; the turnable template is erected in the sliding grooves of the side plates through central end rods at two ends and is fixed through a limiting block.
As a further improvement, the steel tube stand column is provided with a hoop type connecting piece.
As a further improvement, the top surface of the tensioning and fixing device is arc-shaped, one side of the tensioning and fixing device is provided with a lower edge plate, and the lower edge plate is connected with the side anchoring of the lower chord.
As a further improvement, fixed gallows includes bracing, diaphragm and spacing ring, and one of them bracing passes through tip arc fagging to be supported on the steel truss, and another bracing passes through the tip staple bolt to be fixed on the steel truss, and two bracing other ends are articulated to be connected to be provided with the diaphragm, the spacing ring that vertical setting is used for the grout pipe location to set up on the diaphragm.
As a further improvement of the utility model, the bridge body comprises a lower chord, a bridge deck, an upper chord, an end diagonal, an end cross beam, a middle cross beam and a pier; the upper chord is positioned and arranged on the lower chord through a web plate; the lower chord is positioned on a capping beam of the pier through a permanent support; the bridge deck is arranged between the two lower chords; the end inclined rods are arranged at two ends of the upper chord and are connected with two ends of the lower chord in a positioning way; the end cross beams are arranged at two ends of the bridge deck; the middle cross beam is arranged in the middle of the bridge deck.
As a further improvement of the utility model, an auxiliary upright rod is also arranged; the auxiliary vertical rod is abutted and limited with the upper chord.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model adopts the steel pipe pile type scaffold supporting system or the step type scaffold supporting system respectively aiming at different terrains, and has wide application range; adopt the regularization to draw the template step by step simultaneously and carry out the concrete placement sclerosis to step form original state soil, for traditional step formwork mode, efficiency is higher, only needs once to turn over the mould twice and pours and can accomplish, promotes the site operation efficiency by a wide margin.
2. The utility model discloses required regularization temporary support of make full use of steel truss installation has rationally laid decking reinforcement bed-jig and bridge floor slab concrete construction platform, promotes reinforcing bar operating efficiency and concrete placement construction quality by a wide margin, and technical benefit is obvious.
3. The utility model discloses before lower chord steel strand wires stretch-draw, lay stretch-draw fixing device in advance, effectively prevent unexpected release and lead to jack device skew landing, improved the security of site operation.
4. The utility model discloses set up fixed gallows temporarily on the steel truss, pour into the intraductal concrete of chord on the steel truss through fixed gallows, stability is good, and compares in the support installation more portably.
Of course, it is not necessary for any particular product to achieve all of the above-described advantages at the same time.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, it is obvious that the drawings in the following description are only some embodiments of the present invention, and for those skilled in the art, other drawings can be obtained according to these drawings without creative efforts.
FIG. 1 is a schematic view of a support system of a middle steel pipe pile type scaffold according to the present invention;
fig. 2 is a schematic view of the middle step scaffold support system of the present invention;
FIG. 3 is a schematic view of the installation of the modular form of the present invention;
FIG. 4 is a side view of the modular progressive drawknot template of the present invention;
fig. 5 is a schematic view illustrating the installation of the finalized temporary stand according to the present invention;
FIG. 6 is a sectional view of the modular temporary support of the present invention;
FIG. 7 is a schematic view of a middle tension fixing device according to the present invention;
FIG. 8 is a cross-sectional view taken along line A-A of FIG. 7;
fig. 9 is a schematic view of the installation of the fixed hanger of the present invention;
FIG. 10 is a schematic view of the structure of the middle bridge body of the present invention;
the reference numbers in the figures illustrate:
1. a scaffold support system; 101. casting a bearing platform in situ; 102. a steel pipe upright post; 1021. a hoop type connecting piece; 103. a lower cross beam; 104. a Bailey truss; 105. a distribution beam; 106. a full hall scaffold; 107. a stepped support foundation; 108. setting the step-by-step drawknot template; 1081. a side plate; 10811. a chute; 1082. the template can be turned over; 1083. a limiting block; 2. finalizing the temporary support; 201. erecting a rod; 202. a tie bar; 203. a circular pallet; 3. binding a bed-jig with a bridge deck steel bar; 301. a transverse jig frame; 302. a longitudinal jig frame; 4. a bridge deck concrete construction platform; 401. a transverse steel gangboard; 4011. the limiting plate is horizontal; 402. a longitudinal steel springboard; 403. an auxiliary upright rod; 5. bottom die; 6. a bridge body; 601. a lower chord; 602. a bridge deck; 603. an upper chord; 604. an end diagonal rod; 605. an end cross member; 606. a middle cross beam; 607. a bridge pier; 6071. a capping beam; 608. a permanent support; 7. undisturbed soil; 8. tensioning the fixing device; 9. a jack; 10. steel strand wires; 11. anchoring the bolts; 12. fixing the hanger; 1201. bracing; 1202. a transverse plate; 1203. a limiting ring; 1204. an end arc supporting plate; 1205. an end hoop; 13. and (7) grouting pipes.
Detailed Description
To make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the embodiments of the present invention are combined to clearly and completely describe the technical solution in the embodiments of the present invention, and obviously, the described embodiments are some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
Combine attached figure 1 to figure 10, the utility model provides a concrete filled steel tube pin-connected panel truss composite beam construction system aims at solving the technical problem that the construction quality of current stage concrete filled steel tube truss is poor, and the efficiency of construction is low.
Specifically, the steel pipe concrete assembled truss composite beam construction system comprises a scaffold support system 1, a finalized temporary support 2, a bridge deck steel bar binding jig frame 3 and a bridge deck concrete construction platform 4;
the scaffold supporting system 1 comprises a cast-in-place bearing platform 101, a steel pipe upright post 102, a lower cross beam 103, a Bailey truss 104, a distribution beam 105 and a full hall scaffold 106 which are sequentially arranged from bottom to top; the cast-in-place bearing platform 101 is embedded into a steep mountain;
the regularization temporary support 2 comprises a vertical rod 201 and a connecting rod 202; wherein, the upright stanchions 201 at one side are arranged through the bridge deck, and the circular supporting plates 203 are positioned and arranged vertically at equal intervals in the elevation range of the bridge deck 602 of the bridge body 6;
the bridge deck steel bar binding jig frame 3 comprises a transverse jig frame 301 and a longitudinal jig frame 302; the transverse jig frames 301 are arranged on the circular supporting plates 203 of the two side-shaped temporary supports 2 across the bridge deck 602, the longitudinal jig frames 302 are arranged on the circular supporting plates 203 of the same side-shaped temporary supports 2 in parallel with the lower chords and are arranged between the transverse jig frames 301 in a segmented manner;
the bridge deck concrete construction platform 4 comprises a transverse steel springboard 401 and a longitudinal steel springboard 402; the transverse steel springboard 401 is arranged on the tie bars 202 of the two-side finalized temporary supports 2 across the bridge deck 602, and the longitudinal steel springboard 402 is arranged on the transverse steel springboard 401 and fixed transversely 4011 direction through the limiting plate.
The utility model discloses adopt steel pipe pile formula scaffold braced system or stepped scaffold braced system respectively to different topography to make full use of regularization temporary support has set up decking reinforcement bed-jig and bridge floor slab concrete construction platform, simultaneously, compares in traditional construction mode, has still add stretch-draw fixing device and fixed gallows, has the characteristics of the advanced technique, structural stability is good, the efficiency of construction is high and safe.
A template is arranged at the top of the scaffold supporting system 1, and shaped temporary supports 2 are arranged on two sides of the scaffold supporting system; the reinforcing steel bar binding jig frame 3 of the bridge deck arranged on the shaped temporary support 2 is used for carrying out reinforcing steel bar operation; the bridge deck concrete construction platform 4 arranged on the shaped temporary support 2 carries out concrete operation on the steel truss; the steel strand 10 on the lower chord is tensioned through a tensioning fixing device 8; the steel truss is poured with concrete through a grout pipe 13 on the fixed hanger 12.
Further, the scaffold support system 1 comprises a steel pipe pile type scaffold support system 1 and a stepped scaffold support system 1; the steel pipe pile type scaffold supporting system 1 is used in a steep mountain area; step scaffold braced system 1 is used for the gentle slope topography.
Further, the stepped scaffold support system 1 comprises a stepped support foundation 107 and a full hall scaffold 106; the step-type support foundation 107 is formed by excavating undisturbed soil 7 into steps and pouring through a stereotyped step-by-step drawknot template 108.
Further, the sizing step-by-step pulling template 108 comprises a side plate 1081, a turnable template 1082 and a limiting block 1083; the side plates 1081 at two sides are vertically embedded into undisturbed soil 7 and are provided with sliding grooves 10811; the turnable mold plate 1082 is erected in the slide groove 10811 of the side plate 1081 through the central end rods at both ends, and is fixed by a limit block 1083.
Further, a hoop type connecting piece 1021 is arranged between the steel pipe columns 102.
Further, the top surface of the tensioning and fixing device 8 is arc-shaped, a lower edge plate is arranged on one side of the tensioning and fixing device, and the lower edge plate is connected with the side surface of the lower chord 603 in an anchoring mode.
Further, the fixed hanger 12 comprises inclined struts 1201, transverse plates 1202 and a limit ring 1203, wherein one inclined strut 1201 is supported on the steel truss through an end arc-shaped supporting plate 1204, the other inclined strut 1201 is fixed on the steel truss through an end hoop 1205, the other ends of the two inclined struts 1201 are hinged and connected, the transverse plate 1202 is arranged, and the limit ring 1203 used for positioning and setting the grouting pipe 13 is vertically arranged on the transverse plate 1202.
Further, the bridge body 6 comprises a lower chord 601, a bridge deck 602, an upper chord 603, an end diagonal 604, an end cross beam 605, a middle cross beam 606 and a bridge pier 607; the upper chord 603 is positioned on the lower chord 601 through a web; the lower chord 601 is positioned on a capping 6071 of the pier 607 by a permanent support 608; the bridge deck 602 is arranged between the two lower chords 601; the end inclined rods 604 are arranged at two ends of the upper chord 603 and are connected with two ends of the lower chord 601 in a positioning manner; the end beams 605 are arranged at two ends of the bridge deck 602; the middle cross beam 606 is disposed at a middle position of the bridge deck 602.
Further, an auxiliary upright rod 403 is also arranged; the auxiliary vertical rod 403 is abutted and limited with the upper chord 603.
The construction method of the steel pipe concrete assembled truss composite beam comprises the following steps:
s1, basic processing: for a steep slope, firstly, excavating undisturbed soil 7 into a step shape, mounting a shaped step-by-step drawknot template 108 on the undisturbed soil 7, wherein a reversible template 1082 is arranged at intervals of one step, and pouring a step-type support foundation 107 twice; aiming at an over-steep slope, firstly constructing a cast-in-place bearing platform 101 on the slope surface, erecting a steel pipe upright post 102 on the cast-in-place bearing platform 101, laying a lower cross beam 103 on the basis of the steel pipe upright post to hoist a Bailey truss 104, and installing a distribution beam 105 as the basis of a full-scale scaffold 106; directly filling and leveling treatment aiming at low dam side slopes;
s2, erecting a full scaffold: setting up full framing scaffolds 106 according to a support plane layout drawing and height difference between the ground and the beam bottom, setting one transverse cross brace at intervals of four rows of supports, and setting the cross braces at the edges of the scaffolds longitudinally;
s3, mounting a shaped temporary support: under the working condition of an abrupt slope, the shaped temporary support 2 is directly erected on the distribution beam 105, and under the other working conditions, I-shaped steel is directly arranged on the ground to serve as the foundation of the shaped temporary support 2; erecting upright stanchions 201 firstly when erecting, wherein the upright stanchions 201 at the side close to the bridge need to penetrate through a bridge deck 602 and stand on a distribution beam 105, and welding circular supporting plates 203 in advance at equal vertical intervals in the elevation range of the bridge deck 602 of the bridge body 6, and then welding connecting rods 202 among the upright stanchions 201 for reinforcement;
s4, bottom die installation: the bottom die 5 is mainly installed manually and is constructed in a mechanical matching mode, and the pre-camber is set;
s5, mounting a bridge deck steel bar binding jig: firstly, installing a transverse jig frame 301, crossing a bridge deck 602, installing the transverse jig frame 301 on the circular support plates 203 of the two side-shaped temporary supports 2, then cutting the longitudinal jig frame 302 according to the distance after the transverse jig frame 301 is installed, installing the longitudinal jig frame 302 on the circular support plates 203 of the same side-shaped temporary supports 2 in parallel with the lower chord 601, and arranging the longitudinal jig frame 302 between the transverse jig frames 301 in a segmented manner;
s6, reinforcement binding construction: the steel bar construction sequence is end beam 605, lower chord 601, middle beam 606, bridge deck 602, wherein the steel bar of the bridge deck 602 is constructed layer by using the preset jig, the longitudinal and transverse bridge deck steel bar binding jig 3 is synchronously installed layer by layer on the circular supporting plate 203, and the lifting treatment can also be directly carried out layer by layer;
s7, hoisting a steel truss: each steel truss is manufactured by 11 sections in a factory according to the requirements of a design drawing, is transported to a construction site and then is welded into three sections in a construction site, each hoisting section joint and a corresponding steel piece are welded and installed, and the first supplementary coating is carried out after the welding line is qualified through ultrasonic detection; then hoisting in sections to be in place to the top of the shaped temporary support 2; accurately butting the steel truss joints according to the requirements of the drawing;
s8, mounting of an inner die, an end die and a side die: uniformly adopting a high-strength bamboo plywood, gradually installing an inner die, an end die and a side die, and reasonably arranging a reinforcing cross brace;
s9, mounting the prestressed pipeline: the prestressed pipeline adopts a plastic corrugated pipe for hole forming, the extension of the corrugated pipe adopts a large corrugated pipe for sleeve joint, and the corrugated pipe is accurately positioned by a positioning frame shaped like a Chinese character 'jing';
s10, erecting a concrete construction platform of the bridge deck: firstly, mounting a transverse steel springboard 401 on a bridge spanning panel 602 of the two-side finalized temporary support 2 on the transverse connecting rods 202, and then mounting a longitudinal steel springboard 402 between limiting plates on the transverse steel springboard 401 to finish the erection of a platform;
s11, concrete cast-in-place operation: the bridge deck concrete construction platform 4 is utilized, the concrete pouring is completed by adopting full-height one-step pouring, and the pouring sequence is that the end cross beam 605, the lower chord 601, the middle cross beam 606 and the bridge deck 602 are symmetrically poured in a layered mode;
s12, tensioning, grouting and anchor sealing: a tensioning fixing device 8 is installed in advance before tensioning, so that accidental pressure relief is prevented; performing double control on the tension of the steel strand in the tension process; after the prestress tension is finished, grouting as early as possible, cleaning the periphery of the grouting, and chiseling and sealing the concrete at the beam end through the anchor 11;
s13, pouring steel truss concrete: the concrete in the inclined rod pipe is poured into the grouting pipe 13 firstly, then the fixed hanging bracket 12 is installed on the inclined rod of the steel truss, and the concrete in the upper chord 603 pipe is poured into the grouting pipe 13 on the fixed hanging bracket 12;
s14, dismantling the bracket system: and (3) when the strength of the concrete in the steel truss reaches% of the concrete grade, the support can be disassembled from the beam end to the midspan when the support is disassembled, and the support is correspondingly weighed when the support is disassembled.
It should be noted that the distribution beam 105 is an i-beam structure.
During the concrete construction, take the construction of a certain steel pipe concrete assembled truss composite beam as an example:
before construction, firstly, the undisturbed soil 7 is excavated into a step shape, the step height is 60cm, the step width is 120cm, then a groove is formed in the undisturbed soil 7, a shaped step-by-step pulling formwork 108 is installed, wherein the turnable formworks 1082 are arranged at intervals of one step, the left and the right sides are synchronously performed, a first-time concrete is poured after the turnable formworks 1082 are fixed by using a limiting block 1083, after hardening, the limiting block 1083 is removed, the turnable formworks slide upwards for one step, a second-time concrete is poured after the limiting block 1083 is fixed, and construction of the step-type support foundation 107 is completed; then, full framing 106 is erected according to the support plane layout drawing and the height difference between the ground and the beam bottom, one transverse cross brace is arranged at intervals of four rows on the supports, and the cross braces are arranged at the edges of the framing longitudinally.
Then, measuring and paying off, and paving I-shaped steel on the ground to serve as a foundation of the shaped temporary support 2; when the bridge is erected, the upright rods 201 are erected firstly, wherein the upright rods 201 on the side close to the bridge need to penetrate through the bridge deck 602 to be erected on the distribution beam 105, the circular supporting plates 203 are welded in advance at equal intervals in the vertical direction within the elevation range of the bridge deck 602 of the bridge body 6, and then the connecting rods 202 are welded among the upright rods 201 for reinforcement.
Synchronously installing a bottom die 5, constructing the bottom die 5 in a mode of mainly manual work and mechanical cooperation, and setting pre-camber; after the support and the bottom die 5 are installed, a ballast test is carried out, the ballast test is carried out by taking the grading loading of 1.2 times of the sum of the dead weight of the box girder and the construction load, and the unloading is carried out after the settlement is stable.
Next, the bridge deck steel bar binding jig frame 3 is installed, the transverse jig frame 301 is installed firstly, the bridge deck 602 is installed on the circular support plates 203 of the two side-shaped temporary supports 2 in a crossing mode, then the longitudinal jig frames 302 are cut according to the distance after the transverse jig frame 301 is installed, the longitudinal jig frames 302 are installed on the circular support plates 203 of the same side-shaped temporary supports 2 in a parallel mode with the lower chord 601, and the longitudinal jig frames are arranged between the transverse jig frames 301 in a segmented mode.
The jig frames are utilized to carry out reinforcement binding construction, the reinforcement construction sequence comprises an end cross beam 605, a lower chord 601, a middle cross beam 606 and a bridge deck 602, wherein the reinforcements of the bridge deck 602 are constructed layer by utilizing preset jig frames, and the longitudinal and transverse bridge deck reinforcement jig frames 3 are synchronously installed on the circular supporting plate 203 layer by layer; and after the steel bars are bound, the longitudinal and transverse jig frames 301 are removed in time.
Each steel truss is manufactured in 11 sections in a factory according to the requirements of a design drawing, is transported to a construction site and then is welded into 3 sections in a construction site, each hoisting section joint and the corresponding steel piece are welded and installed, and the first supplementary coating is carried out after the welding line is qualified through ultrasonic detection; then hoisting in sections to be in place to the top of the shaped temporary support 2; and then accurately butting the steel truss joints according to the requirements of the drawing.
Then gradually installing an inner die, an end die and a side die, reasonably arranging a reinforcing cross brace, and uniformly adopting high-strength bamboo plywood for the inner die, the end die and the side die 1; synchronously installing prestressed pipelines: the prestressed pipeline adopts a plastic corrugated pipe for hole forming, the corrugated pipe is lengthened and sleeved by a large corrugated pipe, the sleeved length is 20-30 cm, and the positioning is accurately performed by using a positioning frame shaped like a Chinese character 'jing', and the distance between the positioning frames is 0.5 m.
After the construction is finished, the bridge deck concrete construction platform 4 is erected, the transverse steel springboard 401 is firstly installed on the transverse tie bars 202 of the two side-shaped temporary supports 2 across the bridge deck 602, and then the longitudinal steel springboard 402 is installed between the limiting plates on the transverse steel springboard 401, so that the erection of the platform is finished. The bridge deck concrete construction platform 4 is utilized, the concrete pouring is completed by adopting full-height one-step pouring, and the pouring sequence is that the end cross beam 605, the lower chord 601, the middle cross beam 606 and the bridge deck 602 are symmetrically poured in a layered mode; obliquely layering, longitudinally segmenting, controlling the length of the segmentation to be 4-6m, controlling the layering thickness not to exceed 30cm, and adopting an attaching vibrator and an inserting vibrator to carry out combined vibration.
After concrete curing is finished, the steel strand 10 is symmetrically tensioned at two ends, and a tensioning fixing device 8 is installed in advance before tensioning, so that accidental pressure relief is prevented; performing double control on the tension of the steel strand in the tension process; and after the prestress tension is finished, grouting as early as possible, cleaning the periphery of the grouting, and chiseling and sealing the concrete at the beam end.
And finally, pouring the steel truss concrete, namely pouring the concrete in the inclined rod pipe, mounting the fixed hanging bracket 12 on the steel truss inclined rod, and pouring the concrete in the upper chord 603 pipe by using the fixed hanging bracket 12. And (3) when the strength of the concrete in the steel truss reaches 90% of the strength of the concrete, the support can be disassembled from the beam end to the midspan when the support is disassembled, and the support is correspondingly weighed when the support is disassembled.
The method has the advantages that the process operation is simple, the construction efficiency and the construction precision are improved, the overhead working time is reduced, and special equipment is not required to be input; the investment of equipment and personnel is less, the labor intensity is low, and the occupied area is small; the engineering cost is reduced; the construction method achieves good effects in construction in engineering example projects, has wide popularization and application values under similar equivalent conditions, and has very obvious economic and social benefits.
It should be noted that the detailed description of the present invention is not included in the prior art, or can be obtained directly from the market, and those skilled in the art can obtain the detailed description without creative efforts, and the detailed connection method has a very wide application in the field or daily life, and is not described in detail herein.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", "axial", "radial", "circumferential", and the like, indicate the orientation or positional relationship indicated based on the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present invention.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include at least one such feature. In the description of the present invention, "a plurality" means at least two, e.g., two, three, etc., unless specifically limited otherwise.
In the present invention, unless otherwise expressly stated or limited, the terms "mounted," "connected," and "fixed" are to be construed broadly and may, for example, be fixedly connected, detachably connected, or integrally formed; can be mechanically or electrically connected; they may be directly connected or indirectly connected through intervening media, or they may be connected internally or in any other suitable relationship, unless expressly stated otherwise. The specific meaning of the above terms in the present invention can be understood according to specific situations by those skilled in the art.
In the present application, unless expressly stated or limited otherwise, the first feature may be directly on or directly under the second feature or indirectly via intermediate members. Also, a first feature "on," "over," and "above" a second feature may be directly or diagonally above the second feature, or may simply indicate that the first feature is at a higher level than the second feature. A first feature being "under," "below," and "beneath" a second feature may be directly under or obliquely under the first feature, or may simply mean that the first feature is at a lesser elevation than the second feature.
In the description herein, references to the description of the term "one embodiment," "some embodiments," "an example," "a specific example," or "some examples," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above are not necessarily intended to refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples. Furthermore, various embodiments or examples and features of different embodiments or examples described in this specification can be combined and combined by one skilled in the art without contradiction.
Although embodiments of the present invention have been shown and described, it is understood that the above embodiments are exemplary and should not be construed as limiting the present invention, and that variations, modifications, substitutions and alterations can be made to the above embodiments by those of ordinary skill in the art without departing from the scope of the present invention.

Claims (9)

1. Concrete filled steel tube pin-connected panel truss composite beam construction system, its characterized in that: the construction method comprises a scaffold supporting system, a shaped temporary support, a bridge deck steel bar binding jig frame and a bridge deck concrete construction platform;
the scaffold supporting system comprises a cast-in-place bearing platform, steel pipe stand columns, a lower cross beam, a Bailey truss, a distribution beam and a full hall scaffold which are sequentially arranged from bottom to top; the cast-in-place bearing platform is embedded into a steep mountain;
the shaped temporary support comprises a vertical rod and a connecting rod; wherein, the upright stanchions at one side are arranged through the bridge deck, and are vertically positioned with round supporting plates at equal intervals within the elevation range of the bridge deck slab of the bridge body;
the bridge deck steel bar binding jig frame comprises a transverse jig frame and a longitudinal jig frame; the transverse jig frame is arranged on the circular support plates of the two side sizing temporary supports across the bridge deck, the longitudinal jig frame is parallel to the lower chord and arranged on the circular support plates of the same side sizing temporary supports in a segmented mode and located between the transverse jig frames;
the bridge deck concrete construction platform comprises a transverse steel springboard and a longitudinal steel springboard; the transverse steel springboard bridge-spanning panel is arranged on the tie bars of the two side-shaped temporary supports, and the longitudinal steel springboard is arranged on the transverse steel springboard and is transversely fixed through the limiting plates.
2. The concrete filled steel tube assembled truss composite beam construction system of claim 1, wherein: a template is installed at the top of the scaffold supporting system, and shaped temporary supports are arranged on two sides of the scaffold supporting system; the bridge deck steel bars arranged on the shaped temporary support are bound with a jig frame to perform steel bar operation; the bridge deck concrete construction platform arranged on the finalized temporary support performs concrete operation on the steel truss; the steel strand on the lower chord is tensioned through a tensioning fixing device; the steel truss realizes pouring concrete through the grout pipe on the fixed gallows.
3. The concrete filled steel tube assembled truss composite beam construction system of claim 1, wherein: the scaffold supporting system comprises a steel pipe pile type scaffold supporting system and a step type scaffold supporting system; the step type scaffold supporting system comprises a step type support foundation and a full scaffold; the step-type support foundation is formed by excavating undisturbed soil into a step shape and pouring through a stereotyped step-by-step drawknot template.
4. The concrete filled steel tube assembled truss composite beam construction system of claim 3, wherein: the sizing step-by-step pulling template comprises a side plate, a turnover template and a limiting block; the side plates at two sides are vertically embedded into undisturbed soil and are provided with sliding chutes; the turnable template is erected in the sliding grooves of the side plates through central end rods at two ends and is fixed through a limiting block.
5. The concrete filled steel tube assembled truss composite beam construction system of claim 1, wherein: and hoop type connecting pieces are arranged between the steel pipe columns.
6. The concrete filled steel tube assembled truss composite beam construction system of claim 2, wherein: the top surface of the tensioning and fixing device is arc-shaped, a lower edge plate is arranged on one side of the tensioning and fixing device, and the lower edge plate is connected with the side surface of the lower chord in an anchoring mode.
7. The concrete filled steel tube assembled truss composite beam construction system of claim 2, wherein: the fixed hanging bracket comprises inclined struts, transverse plates and limiting rings, wherein one inclined strut is supported on the steel truss through an end arc supporting plate, the other inclined strut is fixed on the steel truss through an end hoop, the other ends of the two inclined struts are hinged and connected and are provided with the transverse plates, and the limiting rings which are used for positioning and setting the grouting pipes are vertically arranged on the transverse plates.
8. The concrete filled steel tube assembled truss composite beam construction system of claim 1, wherein: the bridge body comprises a lower chord, a bridge deck, an upper chord, an end diagonal rod, an end cross beam, a middle cross beam and a bridge pier; the upper chord is positioned and arranged on the lower chord through a web plate; the lower chord is positioned on a capping beam of the pier through a permanent support; the bridge deck is arranged between the two lower chords; the end inclined rods are arranged at two ends of the upper chord and are connected with two ends of the lower chord in a positioning way; the end cross beams are arranged at two ends of the bridge deck; the middle cross beam is arranged in the middle of the bridge deck.
9. The concrete filled steel tube assembled truss composite beam construction system of claim 8, wherein: an auxiliary upright rod is also arranged; the auxiliary vertical rod is abutted and limited with the upper chord.
CN202023226406.1U 2020-12-28 2020-12-28 Steel pipe concrete assembled truss composite beam construction system Active CN214168790U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202023226406.1U CN214168790U (en) 2020-12-28 2020-12-28 Steel pipe concrete assembled truss composite beam construction system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202023226406.1U CN214168790U (en) 2020-12-28 2020-12-28 Steel pipe concrete assembled truss composite beam construction system

Publications (1)

Publication Number Publication Date
CN214168790U true CN214168790U (en) 2021-09-10

Family

ID=77609971

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202023226406.1U Active CN214168790U (en) 2020-12-28 2020-12-28 Steel pipe concrete assembled truss composite beam construction system

Country Status (1)

Country Link
CN (1) CN214168790U (en)

Similar Documents

Publication Publication Date Title
CN112982181B (en) Construction method for steel-concrete combined section of through-type steel box continuous arch bridge
CN112554077A (en) Steel pipe concrete assembled truss composite beam construction system and construction method
CN105672134A (en) Through concrete-filled steel tube tied-arch bridge erection construction method
CN107476470A (en) Steel pipe built in assembled and GFRP pipe regeneration concrete compound shear walls and its construction method
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN104452597A (en) Supporting system for construction of super-long water pier prestressed cap beam
CN114892552B (en) Box girder type bridge reconstruction construction method
CN112554059B (en) Viaduct ground-crossing parallel bridge pier full combined support and construction method thereof
CN112211113A (en) Cast-in-place construction method for large-span diamond-shaped bent cap of high pier
CN212656384U (en) High-strength concrete connecting piece, high-strength concrete post-cast assembled frame system and support frame
CN109577206B (en) Hollow high pier formwork system and construction method
CN214168790U (en) Steel pipe concrete assembled truss composite beam construction system
CN207109593U (en) A kind of T-shaped high pier Cast-in-place Bent Cap formwork erecting structure
CN216108007U (en) Concrete beam type bridge and cast-in-situ hidden cover beam thereof
CN212742154U (en) Steel reinforced concrete arch bridge
CN104452598A (en) Construction method for water pier super-long pre-stressed cap beam construction supporting system
CN114277672A (en) Large-span prestressed concrete bent cap structure and construction method thereof
CN207484749U (en) Steel pipe built in assembled and GFRP pipe regeneration concrete compound shear walls
CN112726517A (en) Construction method of aqueduct above bridge
CN216129955U (en) Steel-concrete combined section structure of through-type steel box continuous arch bridge
CN218667167U (en) Continuous cantilever beam bracket
CN111305066A (en) Hybrid combination beam steel-concrete combination section and mounting method thereof
CN115506634B (en) Assembled platform canopy and construction method thereof
CN115162165B (en) Construction method for closing middle tower column of highway-railway dual-purpose river-crossing A-type cable-stayed bridge
CN214993140U (en) High headroom cast-in-place box girder staple bolt adds combination support system of steel pipe

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant