CN214091317U - Construction guardrail - Google Patents

Construction guardrail Download PDF

Info

Publication number
CN214091317U
CN214091317U CN202022783712.9U CN202022783712U CN214091317U CN 214091317 U CN214091317 U CN 214091317U CN 202022783712 U CN202022783712 U CN 202022783712U CN 214091317 U CN214091317 U CN 214091317U
Authority
CN
China
Prior art keywords
base
height
railing
construction guardrail
adjusting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202022783712.9U
Other languages
Chinese (zh)
Inventor
张丁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202022783712.9U priority Critical patent/CN214091317U/en
Application granted granted Critical
Publication of CN214091317U publication Critical patent/CN214091317U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a construction guardrail relates to construction equipment technical field. The utility model discloses a base, the railing is installed at the base top, the guide slot is all installed along its direction of height to two sides that are parallel to each other of railing, two slidable mounting has the lift fence in the guide slot, the regulating plate is installed along its direction of height to the railing side, the spring is installed along its direction of height to the regulating plate bottom, the free end of spring and the fixed of lift fence. The utility model discloses a with lift fence slidable mounting on the railing, utilize adjusting part to adjust the height of lift fence, can improve the protective effect of guardrail, pour into the water source into to the base through the water inlet, make the base more stable, be difficult for being blown down at strong wind weather, compare with traditional construction guardrail, the stability of this device is better and the practicality is high.

Description

Construction guardrail
Technical Field
The utility model relates to a construction equipment technical field, concretely relates to construction guardrail.
Background
The construction is a production movement performed by people to construct various building products in a certain space and time according to a specific design blueprint by using various building materials and mechanical equipment. The method comprises the whole production process from construction preparation, earth breaking and engineering completion acceptance. In the process, construction preparation, construction organization design and management, earthwork engineering, blasting engineering, foundation engineering, reinforcing steel bar engineering, template engineering, scaffold engineering, concrete engineering, prestressed concrete engineering, masonry engineering, steel structure engineering, wood structure engineering, structure installation engineering and the like are carried out.
At construction's in-process, need stick up the guardrail at the construction site, avoid passerby to go into the construction site by mistake and cause accident, traditional construction guardrail poor stability is relatively poor, and the practicality of guardrail has all been reduced to the height of its guardrail can not be adjusted, therefore provides a construction guardrail.
SUMMERY OF THE UTILITY MODEL
The utility model aims to provide a: there is poor stability and the complicated problem of height adjusting mechanism for solving traditional construction guardrail, the utility model provides a construction guardrail.
The utility model discloses a realize above-mentioned purpose and specifically adopt following technical scheme:
the utility model provides a construction guardrail, includes the base, the railing is installed at the base top, the guide slot is all installed along its direction of height to two sides that are parallel to each other of railing, two sliding installation has the lift fence in the guide slot, the regulating plate is installed along its direction of height to the railing side, the spring is installed along its direction of height to the regulating plate bottom, the free end of spring and the fixed of lift fence, the base is inside to be the cavity and has water inlet and the delivery port of taking soft stopper in its top and bottom intercommunication respectively, install between lift fence and the regulating plate and be used for adjusting the adjusting part of lift fence height.
Further, adjusting part includes that a plurality of sets up the spacing groove in adjusting plate side edge along adjusting plate direction of height, adjusting part still including articulating in the fence bottom of going up and down and being on a parallel with the turning handle of fence bottom of going up and down and turning handle rotatable to the spacing inslot portion.
Furthermore, the base bottom is installed the toper thorn, be provided with on the base and accomodate the subassembly with the toper thorn accomodate.
Further, accomodate the subassembly including offering the groove of accomodating in the base bottom, the bottom groove face in accomodating the groove is installed to toper thorn articulated formula.
Furthermore, a reflecting plate is installed on the side surface of the base.
Furthermore, a pipe clamp is installed at the top of the lifting fence, a spray head with a hose is installed on the pipe clamp, and the spray head is communicated with an external water source.
The utility model has the advantages as follows:
the utility model discloses a with lift fence slidable mounting on the railing, utilize adjusting part to adjust the height of lift fence, can improve the protective effect of guardrail, pour into the water source into to the base through the water inlet, make the base more stable, be difficult for being blown down at strong wind weather, compare with traditional construction guardrail, the stability of this device is better and the practicality is high.
Drawings
FIG. 1 is a perspective view of the present invention;
FIG. 2 is a front view structural diagram of the present invention;
fig. 3 is a sectional view taken along the line a-a of fig. 2 according to the present invention;
FIG. 4 is a further perspective view of the present invention;
FIG. 5 is another perspective view of the present invention;
fig. 6 is an enlarged view of fig. 5 according to the present invention;
reference numerals: 1. a base; 2. a railing; 3. a guide groove; 4. a lifting fence; 5. an adjusting plate; 6. a spring; 7. an adjustment assembly; 701. a limiting groove; 702. rotating the handle; 8. a water inlet; 9. a water outlet; 10. conical thorn; 11. a receiving assembly; 1101. a receiving groove; 12. a light reflecting plate; 13. a pipe clamp; 14. and (4) a spray head.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. The components of embodiments of the present invention, as generally described and illustrated in the figures herein, may be arranged and designed in a wide variety of different configurations.
Thus, the following detailed description of the embodiments of the present invention, presented in the accompanying drawings, is not intended to limit the scope of the invention, as claimed, but is merely representative of selected embodiments of the invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
It should be noted that: like reference numbers and letters refer to like items in the following figures, and thus, once an item is defined in one figure, it need not be further defined and explained in subsequent figures. Furthermore, the terms "first," "second," and the like are used merely to distinguish one description from another, and are not to be construed as indicating or implying relative importance.
In the description of the embodiments of the present invention, it should be noted that the terms "inside", "outside", "up", and the like indicate the directions or positional relationships based on the directions or positional relationships shown in the drawings, or the directions or positional relationships that the products of the present invention are conventionally placed when used, and are only for convenience of describing the present invention and simplifying the description, but do not indicate or imply that the device or element to which the term refers must have a specific direction, be constructed and operated in a specific direction, and thus, should not be construed as limiting the present invention.
As shown in fig. 1-6, a building construction guardrail comprises a base 1, the base 1 provides a supporting force for the device, a rail 2 is installed on the top of the base 1, two parallel side surfaces of the rail 2 are both provided with a guide groove 3 along the height direction thereof, a lifting rail 4 is slidably installed in the two guide grooves 3, the lifting rail 4 can slide up and down in the guide groove 3 to adjust the height of the lifting rail 4 according to the requirement of a construction site, a spring 6 is installed at the bottom of an adjusting plate 5 along the height direction thereof, the free end of the spring 6 is fixed with the lifting rail 4, when the lifting rail 4 is positioned in the rail 2 and does not slide up, the spring 6 is in a compressed state, when the spring 6 is extended, the lifting rail 4 can slide up in the guide groove 3 along with the spring, the spring 6 can play a power assisting role, and simultaneously improve the stability of the lifting rail 4 after being fixed in position, base 1 is inside to be the cavity and has water inlet 8 and delivery port 9 of taking soft stopper at its top and bottom intercommunication respectively, after lift fence 4 rises or the job site has scraped the strong wind, pour into the water source in to base 1 through water inlet 8, base 1's weight has been increased, make base 1 more stable, when needs transport the device, open delivery port 9 and pour the water source, base 1's weight alleviates, convenient transportation, it has the poor problem of stability to have solved traditional construction guardrail, install between lift fence 4 and the regulating plate 5 and be used for adjusting the adjusting part 7 of lift fence 4 height, utilize adjusting part 7 to adjust the height of lift fence 4, adjusting spring 6's compression or extension degree promptly, can improve the safeguard effect of guardrail, and the practicality is improved.
As shown in fig. 2 and 3, in order to refine the specific structure of the adjusting assembly 7, the adjusting assembly 7 includes a plurality of limiting grooves 701 formed at the edge of the side surface of the adjusting plate 5 along the height direction of the adjusting plate 5, the adjusting assembly 7 further includes a rotating handle 702 rotatably installed at the bottom of the lifting rail 4 and parallel to the bottom of the lifting rail 4, and the rotating handle 702 can be rotated into the limiting grooves 701, and then the rotating handle 702 is rotated into the limiting grooves 701, so as to control the height of the lifting rail 4 through the adjusting assembly 7, in some embodiments of the present invention, in order to increase the rationality of the device, two methods can be adopted, firstly, a fixing block located in the notch of the limiting groove 701 is installed at the notch, the rotating handle 702 can be installed in the limiting groove 701 in which the fixing block is installed, because the elastic force of the spring 6 will extend and drive the rotating handle 702 to move in the vertical upward direction of the balustrade 2, therefore, when the rotating handle 702 is positioned in the limiting groove 701, the top of the rotating handle 702 is in certain contact with the groove surface on the side, with the horizontal position of the limiting groove 701 being high, of the limiting groove, the fixing block is installed on the groove surface, the rotating handle 702 can be effectively prevented from automatically sliding out of the smooth limiting groove 701, the device is more reasonable, and then the friction force between the top and the bottom of the rotating handle 702 and the parallel groove surface of the limiting groove 701 is increased.
As shown in fig. 4, in some embodiments, in order to increase the applicability of the device, the conical spine 10 is installed at the bottom of the base 1, the accommodating component 11 for accommodating the conical spine 10 is arranged on the base 1, when the road surface of a construction site is hollow soil, the device is directly placed on the base and is unstable, at least two conical spines 10 are inserted into the soil, the stability of the base 1 is increased, when the device needs to be transported, the conical spine 10 is accommodated through the accommodating component 11, accidental injury to a carrier is avoided, and the applicability of the device is increased.
As shown in fig. 4, in order to refine the specific structure of the housing assembly 11, the housing assembly 11 includes a housing groove 1101 formed at the bottom of the base 1, the taper spike 10 is hingedly mounted on the bottom groove surface of the housing groove 1101, the hinge taper spike 10 is rotatably disposed in the housing groove 1101, and since the taper spike 10 is hingedly mounted on the bottom groove surface of the housing groove 1101, the fixed or moving state thereof needs to be manually changed, thereby making the apparatus easier to operate and increasing the safety of the apparatus.
As shown in figure 5, in order to increase the practicability of the device, the reflecting plate 12 is installed on the side surface of the base 1, and the reflecting plate 12 can be seen when a pedestrian or a vehicle approaches to the reflecting plate at night, so that the warning effect is achieved, and the pedestrian or the vehicle is prevented from accidentally breaking into a construction site.
As shown in fig. 6, in order to increase the practicability of the device, the pipe clamp 13 is installed at the top of the lifting fence 4, the spray head 14 with a hose is installed on the pipe clamp 13, the design of the pipe clamp 13 can facilitate the disassembly of the spray head 14, the spray head 14 is communicated with an external water source, when the construction is carried out, a large amount of dust can be generated on the construction site, the long-term dust sucked by a human body can affect the health, the influence of the dust on workers or passersby can be reduced to a certain extent after the spray head 14 communicated with the external water source is opened, and the device is more practical.

Claims (6)

1. The utility model provides a construction guardrail, includes base (1), its characterized in that, railing (2) are installed at base (1) top, railing (2) two sides that are parallel to each other all install guide slot (3), two along its direction of height sliding mounting has lift fence (4) in guide slot (3), regulating plate (5) are installed along its direction of height to railing (2) side, spring (6) are installed along its direction of height to regulating plate (5) bottom, the free end of spring (6) and the fixed of lift fence (4), base (1) is inside to be the cavity and has water inlet (8) and delivery port (9) of taking soft stopper at its top and bottom intercommunication respectively, install between lift fence (4) and regulating plate (5) and be used for adjusting adjustment lift fence (4) height's adjusting part (7).
2. The construction guardrail according to claim 1, wherein the adjusting assembly (7) comprises a plurality of limiting grooves (701) formed at the side edges of the adjusting plate (5) along the height direction of the adjusting plate (5), the adjusting assembly (7) further comprises a rotating handle (702) hinged at the bottom of the lifting rail (4) and parallel to the bottom of the lifting rail (4), and the rotating handle (702) can rotate to the inside of the limiting grooves (701).
3. The construction guardrail according to claim 1, wherein the base (1) is provided with a conical spine (10) at the bottom, and the base (1) is provided with a receiving assembly (11) for receiving the conical spine (10).
4. A construction guardrail according to claim 3, wherein the receiving assembly (11) comprises a receiving groove (1101) formed at the bottom of the base (1), and the tapered spine (10) is hingedly mounted on the bottom groove surface of the receiving groove (1101).
5. The construction guardrail according to claim 1, wherein the base (1) is provided with a reflecting plate (12) on the side.
6. The construction guardrail according to claim 1, wherein a pipe clamp (13) is arranged at the top of the lifting railing (4), a spray head (14) with a hose is arranged on the pipe clamp (13), and the spray head (14) is communicated with an external water source.
CN202022783712.9U 2020-11-26 2020-11-26 Construction guardrail Expired - Fee Related CN214091317U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022783712.9U CN214091317U (en) 2020-11-26 2020-11-26 Construction guardrail

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022783712.9U CN214091317U (en) 2020-11-26 2020-11-26 Construction guardrail

Publications (1)

Publication Number Publication Date
CN214091317U true CN214091317U (en) 2021-08-31

Family

ID=77452898

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022783712.9U Expired - Fee Related CN214091317U (en) 2020-11-26 2020-11-26 Construction guardrail

Country Status (1)

Country Link
CN (1) CN214091317U (en)

Similar Documents

Publication Publication Date Title
CN213898042U (en) Building construction operation supporting mechanism
CN108915273A (en) A kind of plain type structural sheeting fitting machine
CN214091317U (en) Construction guardrail
CN213330351U (en) Rail guard is used in building engineering construction
CN214886147U (en) Building construction safety device
CN213326459U (en) Tower crane anti-climb safety device
CN215167778U (en) But height-adjusting's stable form engineering construction scaffold
CN214246618U (en) Connecting frame for civil engineering
CN215717042U (en) Construction equipment supporting platform for building construction
CN112392210A (en) Adjustable canopy top steel structure
CN218406391U (en) Suspension type work platform
CN220414789U (en) Construction support is built in room
CN221256073U (en) Scaffold for indoor and outdoor decoration engineering
CN211499689U (en) Lifting device for building engineering
CN217400280U (en) Lifting frame with protection function for construction
CN214739743U (en) Connect stable safe type construction scaffolding
CN217650811U (en) Lifting mechanism applied to mechanical engineering installation
CN213597653U (en) A construction rail guard for building transformation
CN216737098U (en) A guard gate for building engineering construction elevator
CN215949115U (en) Construction protective guard for constructional engineering
CN211110757U (en) Automatic lifting tower crane
CN215801293U (en) Architectural decoration rail guard
CN218290366U (en) Scaffold for building construction
CN217079461U (en) Staircase rail guard
CN220100601U (en) Construction frame with anti-drop structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210831