CN213505736U - High-tension transmission line iron tower device in high-altitude area - Google Patents

High-tension transmission line iron tower device in high-altitude area Download PDF

Info

Publication number
CN213505736U
CN213505736U CN202022549895.8U CN202022549895U CN213505736U CN 213505736 U CN213505736 U CN 213505736U CN 202022549895 U CN202022549895 U CN 202022549895U CN 213505736 U CN213505736 U CN 213505736U
Authority
CN
China
Prior art keywords
mounting bracket
support frame
iron tower
threaded rod
transmission line
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202022549895.8U
Other languages
Chinese (zh)
Inventor
雍云川
赵松
戴绍钧
白永帅
李宽
李进江
应柳
刘和松
吕昌会
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Energy Construction Group Yunnan Thermal Power Construction Co ltd
Original Assignee
China Energy Construction Group Yunnan Thermal Power Construction Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Energy Construction Group Yunnan Thermal Power Construction Co ltd filed Critical China Energy Construction Group Yunnan Thermal Power Construction Co ltd
Priority to CN202022549895.8U priority Critical patent/CN213505736U/en
Application granted granted Critical
Publication of CN213505736U publication Critical patent/CN213505736U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Suspension Of Electric Lines Or Cables (AREA)

Abstract

The utility model discloses a high altitude area high tension transmission line iron tower device, the loach carrying platform comprises a supporting fram, one side of support frame is provided with first mounting bracket, the opposite side of support frame is provided with the second mounting bracket, the utility model relates to a power equipment technical field. This high altitude area high tension transmission line iron tower device, reached and installed first mounting bracket on the support frame, second mounting bracket and support frame are installed simultaneously, the kelly is installed with first mounting bracket, and carry out the joint with the draw-in groove on support frame surface, improve the installation effectiveness, set up first layer board, the second layer board, the jack of being convenient for supports, improve stability, set up first threaded rod, the second threaded rod, make first mounting bracket, the second mounting bracket cup joints each other, and utilize the nut to consolidate, further improve overall installation stability, make things convenient for the staff to install, and the work efficiency is improved, the purpose of user demand is satisfied.

Description

High-tension transmission line iron tower device in high-altitude area
Technical Field
The utility model relates to a power equipment field, more specifically say, relate to a high altitude area high tension transmission line iron tower device.
Background
The high-voltage transmission line iron tower is an important supporting structure for completing electric power transmission wires and is arranged along the electric power transmission direction according to design requirements. In the construction process of a power line, the iron tower needs to be moved away from the original installed position due to design reasons or construction reasons, the iron tower is dismantled and installed again on the basis of a new position according to the conventional method, and the construction by adopting the method has the following problems: the construction method is characterized in that the construction method comprises the following steps of dismantling an iron tower, installing the iron tower, and designing a construction technology for translation of the iron tower of the high-voltage transmission line, wherein the construction technology is long in construction period, the dismantling difficulty of the iron tower is high relative to the installation difficulty of the iron tower, and the unforeseen factors in the dismantling process of the iron tower are more than one, so that the damage to tower materials can be caused, the safety risk is high, certain difficulty is brought to the installation quality control of the iron tower, and the construction technology is. On the basis of the completion of the construction of a new foundation of the iron tower, the time for disassembling and assembling the original foundation iron tower is 15 days, and the time for only 1 day is required by adopting the iron tower translation technology, so that the safe, quality and on-time and efficient completion of the construction of the iron tower is ensured. The staff need install the backing plate additional at four support frames of iron tower, utilize the jack, the backing plate to the support frame supports, four corners simultaneous working, with iron tower jack-up, the below of the staff of being convenient for love the support frame installs the guide rail additional, again with wholly on the guide rail, utilize the calabash to pull whole, make the integral movement to new mounted position, reuse the jack with whole jack-up, carry out the dismantlement of guide rail, then will wholly descend, can install the tower body in new position, and the work efficiency is improved, but this operation, at the in-process of using, need install the backing plate additional to the support frame, be convenient for wholly support. At present, current high altitude area high tension transmission line iron tower device, backing plate single structure is not convenient for the staff and installs fast, and overall stability is poor, can't satisfy the user demand.
SUMMERY OF THE UTILITY MODEL
1. Technical problem to be solved
To current high altitude area high tension transmission line iron tower device that exists among the prior art, backing plate structure is single, is not convenient for the staff to install fast, and overall stability is poor, can't satisfy the problem of user demand, the utility model aims to provide a high altitude area high tension transmission line iron tower device, it can realize that support frame, first mounting bracket, second mounting bracket, kelly, draw-in groove, first layer board and second layer board constitute a whole, install first mounting bracket on the support frame, second mounting bracket and support frame are installed simultaneously, and the kelly is installed with first mounting bracket to carry out the joint with the draw-in groove on support frame surface, improve the installation effectiveness, set up first layer board, second layer board, the jack of being convenient for supports, improves stability, sets up first threaded rod, second threaded rod for first mounting bracket, make first mounting bracket, The second mounting bracket cup joints each other to utilize the nut to consolidate, further improve the overall installation stability, set up stop device, be convenient for further consolidate second mounting bracket and support frame, improve overall stability, make things convenient for the staff to install, improve work efficiency, satisfy the user demand.
2. Technical scheme
In order to solve the above problems, the utility model adopts the following technical proposal.
The utility model provides a high altitude area high tension transmission line iron tower device, includes the support frame, one side of support frame is provided with first mounting bracket, the opposite side of support frame is provided with the second mounting bracket, the lateral wall fixedly connected with kelly of second mounting bracket, the kelly runs through and sliding connection with first mounting bracket, the inside of support frame is provided with the draw-in groove, kelly and draw-in groove joint, the first layer board of lateral wall fixedly connected with of first mounting bracket, the lateral wall fixedly connected with second layer board of second mounting bracket.
Preferably, the lateral wall fixedly connected with first threaded rod of second mounting bracket, first threaded rod runs through and sliding connection with first mounting bracket, the end screw thread of first threaded rod is connected with first mounting nut, the fixed surface of first mounting bracket is connected with the second threaded rod, the second threaded rod runs through and sliding connection with the second mounting bracket, the end screw thread of second threaded rod is connected with second mounting nut.
Preferably, the side wall of the second mounting frame is provided with a limiting device, and the second mounting frame is clamped with the support frame through the limiting device.
Preferably, stop device includes the link, link and second mounting bracket fixed connection, the tip fixedly connected with fixed block of link, fixed block threaded connection has the rotation lead screw, the tip fixedly connected with turning block of rotation lead screw, the one end fixedly connected with dog that the turning block was kept away from to the rotation lead screw, the fixed surface of dog is connected with the gag lever post, the gag lever post runs through and sliding connection with the second mounting bracket, the surface of support frame is provided with the spacing groove, gag lever post and spacing groove joint.
Preferably, the surface of the first supporting plate is provided with a first supporting groove, the surface of the second supporting plate is provided with a second supporting groove, and the first supporting groove and the second supporting groove correspond to the end part of the jack.
3. Advantageous effects
Compared with the prior art, the utility model has the advantages of: the first mounting frame is arranged on the supporting frame, the second mounting frame is arranged on the supporting frame, the clamping rod is arranged with the first mounting frame and is clamped with the clamping groove on the surface of the supporting frame, the mounting efficiency is improved, the first supporting plate and the second supporting plate are arranged, a jack can be conveniently supported, the stability is improved, when the second mounting frame is arranged with the first mounting frame, a first threaded rod arranged on the second mounting frame is sleeved with the first mounting frame, a second threaded rod arranged on the first mounting frame is sleeved with the second mounting frame, the first threaded rod and the second mounting frame are mutually limited and are reinforced by nuts, the overall stability is improved, a limiting device is arranged, the second mounting frame and the supporting frame can be further reinforced conveniently, and the overall stability is improved, the rotating block is rotated to drive the rotating lead screw to rotate and drive the stop block to move and drive the limiting rod to move, so that the limiting rod is clamped with the limiting groove, the installation stability of the second mounting frame and the supporting frame is improved, the surfaces of the first supporting plate and the second supporting plate are respectively provided with the supporting groove, the end part of the jack is conveniently supported, the end part of the jack is embedded into the supporting groove, the overall stability is improved, the construction is convenient for workers, the supporting frame, the first mounting frame, the second mounting frame, the clamping rod, the clamping groove, the first supporting plate and the second supporting plate form an integral body, the first mounting frame is mounted on the supporting frame, the second mounting frame is mounted with the supporting frame, the clamping rod is mounted with the first mounting frame and clamped with the clamping groove on the surface of the supporting frame, the mounting efficiency is improved, the first supporting plate and the second supporting plate are arranged, the supporting of the jack, set up first threaded rod, second threaded rod for first mounting bracket, second mounting bracket cup joint each other, and utilize the nut to consolidate, further improve the overall installation stability, set up stop device, be convenient for further consolidate second mounting bracket and support frame, improve the overall stability, make things convenient for the staff to install, improve work efficiency, satisfy the purpose of user demand.
Drawings
Fig. 1 is a schematic view of the overall external structure of the present invention;
FIG. 2 is a schematic view of the overall internal structure of the present invention;
fig. 3 is a schematic view of a part of an enlarged structure of fig. 2 according to the present invention.
The reference numbers in the figures illustrate:
1. a support frame; 2. a first mounting bracket; 3. a second mounting bracket; 4. a clamping rod; 5. a card slot; 6. a first threaded rod; 7. a first mounting nut; 8. a second threaded rod; 9. a second mounting nut; 10. a limiting device; 101. a connecting frame; 102. a fixed block; 103. rotating the screw rod; 104. rotating the block; 105. a stopper; 106. a limiting rod; 107. a limiting groove; 11. a first pallet; 12. a first support groove; 13. a second pallet; 14. a second support groove.
Detailed Description
The drawings in the embodiments of the present invention will be combined; the technical scheme in the embodiment of the utility model is clearly and completely described; obviously; the described embodiments are only some of the embodiments of the present invention; rather than all embodiments. Based on the embodiment of the utility model; all other embodiments obtained by a person skilled in the art without making any inventive step; all belong to the protection scope of the utility model.
Example 1:
referring to fig. 1-3, the present invention provides a technical solution: the utility model provides a high altitude area high tension transmission line iron tower device, including support frame 1, one side of support frame 1 is provided with first mounting bracket 2, the opposite side of support frame 1 is provided with second mounting bracket 3, the lateral wall fixedly connected with kelly 4 of second mounting bracket 3, kelly 4 runs through and sliding connection with first mounting bracket 2, the inside of support frame 1 is provided with draw-in groove 5, kelly 4 and draw-in groove 5 joint, the first layer board 11 of lateral wall fixedly connected with of first mounting bracket 2, the lateral wall fixedly connected with second layer board 13 of second mounting bracket 3. Support frame 1, first mounting bracket 2, second mounting bracket 3, kelly 4, draw-in groove 5, a whole is constituteed with second layer board 13 to first layer board 11, install first mounting bracket 2 on support frame 1, second mounting bracket 3 is installed with support frame 1 simultaneously, kelly 3 is installed with first mounting bracket 2, and carry out the joint with draw-in groove 5 on 1 surface of support frame, improve the installation effectiveness, set up first layer board 11, second layer board 13, the jack of being convenient for supports, and stability is improved.
Example 2:
referring to fig. 2, a high-voltage transmission line iron tower device in a high-altitude area is basically the same as that in embodiment 1, further, a first threaded rod 6 is fixedly connected to a side wall of the second mounting frame 3, the first threaded rod 6 penetrates through and is slidably connected with the first mounting frame 2, a first mounting nut 7 is connected to an end portion of the first threaded rod 6 in a threaded manner, a second threaded rod 8 is fixedly connected to a surface of the first mounting frame 2, the second threaded rod 8 penetrates through and is slidably connected with the second mounting frame 3, and a second mounting nut 9 is connected to an end portion of the second threaded rod 8 in a threaded manner. When second mounting bracket 3 and first mounting bracket 1 were installed, the first threaded rod 6 that second mounting bracket 3 set up cup jointed with first mounting bracket 2, and the second threaded rod 8 that first mounting bracket 2 set up cup joints with second mounting bracket 3, and both restrict each other to utilize the nut to consolidate, improve overall stability.
Example 3:
referring to fig. 2, a high-voltage transmission line iron tower device in a high altitude area is substantially the same as that in embodiment 1, and further, a limiting device 10 is disposed on a side wall of the second mounting frame 3, and the second mounting frame 3 is clamped to the support frame 1 through the limiting device 10. Set up stop device 10, be convenient for further consolidate second mounting bracket 3 and support frame 1, improve overall stability.
Example 4:
referring to fig. 3, a high-voltage transmission line iron tower device in a high altitude area is substantially the same as that in embodiment 3, and further, the limiting device 10 includes a connecting frame 101, the connecting frame 101 is fixedly connected to the second mounting frame 3, an end portion of the connecting frame 101 is fixedly connected to a fixing block 102, the fixing block 102 is in threaded connection with a rotating lead screw 103, an end portion of the rotating lead screw 103 is fixedly connected to a rotating block 104, one end of the rotating lead screw 103, which is far away from the rotating block 104, is fixedly connected to a stop block 105, a surface of the stop block 105 is fixedly connected to a limiting rod 106, the limiting rod 106 is in sliding connection with the second mounting frame 3 in a penetrating manner, a limiting groove 107 is formed in the surface of the support. The rotating block 104 is rotated to drive the rotating screw rod 103 to rotate, the stop block 105 is driven to move, and the limiting rod 106 is driven to move, so that the limiting rod 106 is clamped with the limiting groove 107, and the installation stability of the second installation frame 3 and the support frame 1 is improved.
Example 5:
referring to fig. 2, a high-voltage transmission line iron tower device in a high-altitude area is substantially the same as that in embodiment 1, further, a first supporting groove 12 is formed on a surface of a first supporting plate 11, a second supporting groove 14 is formed on a surface of a second supporting plate 13, and both the first supporting groove 12 and the second supporting groove 14 correspond to an end of a jack. The surfaces of the first supporting plate 11 and the second supporting plate 13 are provided with supporting grooves, so that the end parts of the jacks are conveniently supported, the end parts of the jacks are embedded into the supporting grooves, the overall stability is improved, and workers can construct the jacks conveniently.
The above; is only a preferred embodiment of the present invention; however, the scope of protection of the present invention is not limited thereto; any person skilled in the art is within the technical scope of the present disclosure; according to the technical scheme of the utility model and the improvement conception, equivalent substitution or change is carried out; are all covered by the protection scope of the utility model.

Claims (5)

1. The utility model provides a high altitude area high tension transmission line iron tower device, includes support frame (1), its characterized in that: one side of support frame (1) is provided with first mounting bracket (2), the opposite side of support frame (1) is provided with second mounting bracket (3), lateral wall fixedly connected with kelly (4) of second mounting bracket (3), kelly (4) run through and sliding connection with first mounting bracket (2), the inside of support frame (1) is provided with draw-in groove (5), kelly (4) and draw-in groove (5) joint, the first layer board of lateral wall fixedly connected with (11) of first mounting bracket (2), the lateral wall fixedly connected with second layer board (13) of second mounting bracket (3).
2. The high-tension transmission line iron tower device of claim 1, characterized in that: the utility model discloses a mounting structure, including lateral wall fixedly connected with first threaded rod (6) of second mounting bracket (3), first threaded rod (6) run through and sliding connection with first mounting bracket (2), the tip threaded connection of first threaded rod (6) has first mounting nut (7), the fixed surface of first mounting bracket (2) is connected with second threaded rod (8), second threaded rod (8) run through and sliding connection with second mounting bracket (3), the tip threaded connection of second threaded rod (8) has second mounting nut (9).
3. The high-tension transmission line iron tower device of claim 1, characterized in that: the side wall of the second mounting rack (3) is provided with a limiting device (10), and the second mounting rack (3) is connected with the support frame (1) in a clamping mode through the limiting device (10).
4. The high-tension transmission line iron tower device of claim 3, characterized in that: stop device (10) are including link (101), link (101) and second mounting bracket (3) fixed connection, the tip fixedly connected with fixed block (102) of link (101), fixed block (102) threaded connection has rotation lead screw (103), the tip fixedly connected with turning block (104) of rotation lead screw (103), the one end fixedly connected with dog (105) of turning block (104) are kept away from in rotation lead screw (103), the fixed surface of dog (105) is connected with gag lever post (106), gag lever post (106) run through and sliding connection with second mounting bracket (3), the surface of support frame (1) is provided with spacing groove (107), gag lever post (106) and spacing groove (107) joint.
5. The high-tension transmission line iron tower device of claim 1, characterized in that: the surface of the first supporting plate (11) is provided with a first supporting groove (12), the surface of the second supporting plate (13) is provided with a second supporting groove (14), and the first supporting groove (12) and the second supporting groove (14) correspond to the end part of the jack.
CN202022549895.8U 2020-11-06 2020-11-06 High-tension transmission line iron tower device in high-altitude area Active CN213505736U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202022549895.8U CN213505736U (en) 2020-11-06 2020-11-06 High-tension transmission line iron tower device in high-altitude area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202022549895.8U CN213505736U (en) 2020-11-06 2020-11-06 High-tension transmission line iron tower device in high-altitude area

Publications (1)

Publication Number Publication Date
CN213505736U true CN213505736U (en) 2021-06-22

Family

ID=76421404

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202022549895.8U Active CN213505736U (en) 2020-11-06 2020-11-06 High-tension transmission line iron tower device in high-altitude area

Country Status (1)

Country Link
CN (1) CN213505736U (en)

Similar Documents

Publication Publication Date Title
CN206598032U (en) A kind of workpiece feeding and cutting agency applied to spot welding robot
JP2012051732A (en) Assembling auxiliary lifting unit on mobile crane
CN201302897Y (en) Replacement device of transformer oil pump
CN213505736U (en) High-tension transmission line iron tower device in high-altitude area
CN205051219U (en) Supplementary device of installing and removing of high pressure substation equipment ground connection
CN106862842A (en) It is multi-functional without code pin mounting tool
CN211232163U (en) Remove concatenation screen support
CN219098578U (en) Nickel ingot transfer device
CN204893538U (en) Flexible positioner
CN214162879U (en) General type hydraulic turbine servomotor fast overhaul platform
CN205046848U (en) Gate -type steel sheet mould holder
CN218623613U (en) Adjustable electric power steel pole
CN205146684U (en) Automatic trade screen cloth device
CN216760880U (en) Solidification heating device for outdoor maintenance of wind power blade
CN219886812U (en) Ground anchor dismantling device for power engineering
CN215186339U (en) Connecting mechanism convenient to disassemble and assemble and used for fixed motor
CN221141076U (en) Power equipment hoisting device
CN203761008U (en) Installation base of lightning arrester
CN212887462U (en) Automotive interior ceiling processing support
CN218202089U (en) Flange splicing platform for wind power generation tower cylinder
CN219261694U (en) Intelligent lifting climbing frame protection platform
CN219991090U (en) Mobile electric power overhauling high-altitude hanging basket
CN216587719U (en) Template support auxiliary structure for building engineering
CN207043920U (en) Water conservancy construction pipe built-in grooving mechanism
CN220710979U (en) Power station construction site overhauls device