CN213330082U - Hoisting system for mounting assembled metal curtain wall ceiling board - Google Patents

Hoisting system for mounting assembled metal curtain wall ceiling board Download PDF

Info

Publication number
CN213330082U
CN213330082U CN202021446223.8U CN202021446223U CN213330082U CN 213330082 U CN213330082 U CN 213330082U CN 202021446223 U CN202021446223 U CN 202021446223U CN 213330082 U CN213330082 U CN 213330082U
Authority
CN
China
Prior art keywords
main body
bracket
hoisting
vertical edge
curtain wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021446223.8U
Other languages
Chinese (zh)
Inventor
张桂旺
陈少阳
王金鑫
吴波
武建乐
郭宁
张辉
朱天送
李奇志
黄�俊
陈之
张利雪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
China Construction Second Bureau Decoration Engineering Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
China Construction Second Bureau Decoration Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd, China Construction Second Bureau Decoration Engineering Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN202021446223.8U priority Critical patent/CN213330082U/en
Application granted granted Critical
Publication of CN213330082U publication Critical patent/CN213330082U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Bearing And Curtain Walls (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A hoisting system for mounting a ceiling plate of an assembled metal curtain wall comprises a hoisting component; the hoisting components are symmetrically arranged on two sides of the suspended ceiling plate to be hoisted; the hoisting assembly comprises a steel wire rope, a bracket and a fixed pulley; the bracket comprises a bracket main body and a connecting piece; the bracket main body is in an inverted L shape and comprises a first transverse edge and a first vertical edge; the connecting piece is in an inverted L shape and comprises a second transverse edge and a second vertical edge; the connecting piece is connected to the outer side of the lower part of the first vertical edge, and a clamping groove is formed between the connecting piece and the first vertical edge; the clamping groove is clamped on the steel structure main body, and the bracket is detachably connected with the steel structure main body; the fixed pulley is correspondingly connected to the first transverse edge of the bracket main body; the steel wire rope is arranged on the fixed pulleys in a penetrating mode, one end of the steel wire rope penetrates through the fixed pulleys to be connected with the ceiling plate, and the other end of the steel wire rope extends to a position close to the ground. The utility model provides an adopt traditional construction method when construction measure expense high, the big technical problem with the construction cycle length of cross construction volume.

Description

Hoisting system for mounting assembled metal curtain wall ceiling board
Technical Field
The utility model belongs to the technical field of the building engineering construction, especially a hoist and mount system for installation of assembled metal curtain wall furred ceiling board.
Background
Aiming at the construction of the suspended ceiling of the ultra-large span and the ultra-high metal curtain wall, the conventional technical scheme needs to set up construction measures such as full framing scaffold, weld the steel skeleton on site and install the metal panel on site, and the construction mode has high measure cost, large cross construction amount and long construction period. The problem that how to save construction cost, install fast and avoid alternately constructing to occupy the place is how to guarantee construction quality and safe prerequisite at present need solve urgently.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing a hoist and mount system for installation of assembled metal curtain wall furred ceiling board will solve and adopt traditional construction method to construct the time measure expense high, the big and construction cycle long technical problem of cross construction volume.
In order to achieve the above purpose, the utility model adopts the following technical scheme.
A hoisting system for mounting a ceiling plate of an assembled metal curtain wall comprises a hoisting component; the two hoisting assemblies are symmetrically arranged on two sides of the ceiling board to be hoisted, and each hoisting assembly comprises a steel wire rope, a bracket and a fixed pulley; the brackets are arranged in a group and are arranged at the top of the steel structure main body at intervals; the bracket comprises a bracket main body and a connecting piece; the bracket main body is in an inverted L shape and comprises a first transverse edge and a first vertical edge arranged on one side of the bottom of the first transverse edge; the connecting piece is in an inverted L shape and comprises a second transverse edge and a second vertical edge arranged on one side of the bottom of the second transverse edge; the connecting piece is connected to the outer side of the lower part of the first vertical edge, and the connecting piece and the first vertical edge form a clamping groove; the clamping groove is clamped on the steel structure main body, and the bracket is detachably connected with the steel structure main body; the fixed pulleys are provided with a group and correspondingly connected to the first transverse edge of the bracket main body; the steel wire rope penetrates through the fixed pulleys, one end of the steel wire rope penetrates through the fixed pulleys to be connected with the ceiling board, and the other end of the steel wire rope extends to a position close to the ground.
Preferably, the ceiling board for the assembled metal curtain wall comprises a panel and a ceiling keel connected to the back surface of the panel.
Preferably, the hoisting assembly further comprises a hand-operated hoist; the hook of hand block one end articulates on the furred ceiling board, and the hook of hand block other end articulates on steel construction main part.
Preferably, the first transverse edge and the first vertical edge of the bracket main body are provided with inclined struts at corners.
Preferably, the distance between the adjacent brackets is 6 m-8 m.
Preferably, the lower part of the first vertical edge is provided with a first through hole; a second through hole is formed in the lower portion of the second vertical edge, and the second through hole and the first through hole are arranged correspondingly; and a connecting bolt penetrates through the second through hole and the first through hole.
Compared with the prior art, the utility model has the following characteristics and beneficial effect.
1. The utility model discloses an theory of assembled installation: namely, the drawing is optimized and deeply designed, the hoisting system of the utility model is adopted to carry out assembled hoisting on the suspended ceiling plate of the metal curtain wall, and then the manual hoist is adopted to carry out plate adjustment on the suspended ceiling plate, so that the full scaffold is avoided being erected, and the construction measure cost is reduced; has the advantages of small cross construction amount and short construction period.
2. The utility model discloses installing support in the steel construction main part to adopt wire rope and fixed pulley to hoist the furred ceiling board, it is high to have solved the measure expense when adopting traditional construction method to be under construction, and the cross construction volume is big and the technical problem of construction cycle length.
Drawings
The present invention will be described in further detail with reference to the accompanying drawings.
Fig. 1 is a schematic structural diagram of the hoisting system of the present invention.
Fig. 2 is a schematic structural view of the bracket of the present invention mounted on the steel structure body.
Fig. 3 is a schematic structural diagram of the middle support of the present invention.
Reference numerals: the steel structure comprises a steel structure body, 1-a suspended ceiling plate, 1.1-a panel, 1.2-a suspended ceiling keel, 2-a steel wire rope, 3-a support, 3.1-a support body, 3.1.1-a first transverse edge, 3.1.2-a first vertical edge, 3.1.3-an inclined strut, 3.2-a connecting piece, 3.2.1-a second transverse edge, 3.2.2-a second vertical edge, 4-a fixed pulley, 5-a steel structure body, 6-a clamping groove, 7-a winch, 8-a connecting bolt, 9-a manual hoist, 10-a first perforation and 11-a second perforation.
Detailed Description
As shown in fig. 1-3, the hoisting system for mounting the assembled metal curtain wall ceiling comprises a hoisting component; the two hoisting assemblies are symmetrically arranged on two sides of the ceiling board 1 to be hoisted, and each hoisting assembly comprises a steel wire rope 2, a bracket 3 and a fixed pulley 4; the brackets 3 are arranged in a group and are arranged at the top of the steel structure main body 5 at intervals; the bracket 3 comprises a bracket main body 3.1 and a connecting piece 3.2; the bracket main body 3.1 is in an inverted L shape and comprises a first transverse edge 3.1.1 and a first vertical edge 3.1.2 arranged at one side of the bottom of the first transverse edge 3.1.1; the connecting piece 3.2 is in an inverted L shape and comprises a second transverse edge 3.2.1 and a second vertical edge 3.2.2 arranged on one side of the bottom of the second transverse edge 3.2.1; the connecting piece 3.2 is connected to the outer side of the lower part of the first vertical edge 3.1.2, and the connecting piece 3.2 and the first vertical edge 3.1.2 form a clamping groove 6; the clamping groove 6 is clamped on the steel structure main body 5, and the bracket 3 is detachably connected with the steel structure main body 5; the fixed pulleys 4 are provided with a group and correspondingly connected to the first transverse edge 3.1.1 of the bracket main body 3.1; the steel wire rope 2 penetrates through the fixed pulleys 4, one end of the steel wire rope 2 penetrates through the fixed pulleys 4 to be connected with the ceiling board 1, and the other end of the steel wire rope 2 extends to a position close to the ground.
In this embodiment, the ceiling board for the assembled metal curtain wall comprises a panel 1.1 and a ceiling keel 1.2 connected to the back surface of the panel 1.1.
In this embodiment, the hoisting assembly further comprises a hand-operated hoist 9; the hook at one end of the manual hoist 9 is hung on the ceiling plate 1, and the hook at the other end of the manual hoist 9 is hung on the steel structure main body 5; the position of the ceiling plate 1 is finely adjusted by the constructor adjusting the free end of the manual hoist 9.
In this embodiment, the first transverse side 3.1.1 and the first vertical side 3.1.2 of the bracket main body 3.1 are provided with inclined struts 3.1.3 at the corners.
In the embodiment, the distance between the adjacent brackets 3 is 6 m-8 m.
In this embodiment, the lower portion of the first vertical edge 3.1.2 is provided with a first through hole 10; a second through hole 11 is formed in the lower portion of the second vertical edge 3.2.2, and the second through hole 11 corresponds to the first through hole 10; the second through hole 11 and the first through hole 10 are provided with a connecting bolt 8.
In this embodiment, one end of the steel wire rope 2 close to the ground is connected with the winch 7.
The above embodiments are not exhaustive of the specific embodiments, and other embodiments are possible, and the above embodiments are intended to illustrate, but not limit the scope of the present invention, and all applications coming from the simple changes of the present invention fall within the scope of the present invention.

Claims (6)

1. The utility model provides a hoist and mount system for installation of assembled metal curtain wall furred ceiling board which characterized in that: comprises a hoisting component; the two hoisting assemblies are symmetrically arranged on two sides of the ceiling plate (1) to be hoisted, and each hoisting assembly comprises a steel wire rope (2), a bracket (3) and a fixed pulley (4); the brackets (3) are arranged in a group and are arranged at the top of the steel structure main body (5) at intervals; the bracket (3) comprises a bracket main body (3.1) and a connecting piece (3.2); the bracket main body (3.1) is in an inverted L shape and comprises a first transverse edge (3.1.1) and a first vertical edge (3.1.2) arranged on one side of the bottom of the first transverse edge (3.1.1); the connecting piece (3.2) is in an inverted L shape and comprises a second transverse edge (3.2.1) and a second vertical edge (3.2.2) arranged on one side of the bottom of the second transverse edge (3.2.1); the connecting piece (3.2) is connected to the outer side of the lower part of the first vertical edge (3.1.2), and the connecting piece (3.2) and the first vertical edge (3.1.2)) form a clamping groove (6); the clamping groove (6) is clamped on the steel structure main body (5), and the bracket (3) is detachably connected with the steel structure main body (5); the fixed pulleys (4) are provided with a group and correspondingly connected to the first transverse edge (3.1.1) of the bracket main body (3.1); the steel wire rope (2) penetrates through the fixed pulleys (4), one end of the steel wire rope (2) penetrates through the fixed pulleys (4) to be connected with the ceiling plate (1), and the other end of the steel wire rope (2) extends to a position close to the ground.
2. The hoisting system for the installation of the assembled metal curtain wall ceiling tile according to claim 1, wherein: the ceiling board for the assembled metal curtain wall comprises a panel (1.1) and a ceiling keel (1.2) connected to the back of the panel (1.1).
3. The hoisting system for the installation of the assembled metal curtain wall ceiling tile according to claim 1, wherein: the hoisting component also comprises a manual hoist (9); the hook at one end of the manual hoist (9) is hung on the ceiling plate (1), and the hook at the other end of the manual hoist (9) is hung on the steel structure main body (5).
4. The hoisting system for the installation of the assembled metal curtain wall ceiling tile according to claim 1, wherein: and inclined struts (3.1.3) are arranged at corners of the first transverse edge (3.1.1) and the first vertical edge (3.1.2)) of the bracket main body (3.1).
5. The hoisting system for the installation of the assembled metal curtain wall ceiling tile according to claim 1, wherein: the distance between the adjacent brackets (3) is 6-8 m.
6. The hoisting system for the installation of the assembled metal curtain wall ceiling tile according to claim 1, wherein: the lower part of the first vertical edge (3.1.2)) is provided with a first through hole (10); a second through hole (11) is formed in the lower portion of the second vertical edge (3.2.2), and the second through hole (11) is arranged corresponding to the first through hole (10); and a connecting bolt (8) penetrates through the second through hole (11) and the first through hole (10).
CN202021446223.8U 2020-07-21 2020-07-21 Hoisting system for mounting assembled metal curtain wall ceiling board Active CN213330082U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021446223.8U CN213330082U (en) 2020-07-21 2020-07-21 Hoisting system for mounting assembled metal curtain wall ceiling board

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021446223.8U CN213330082U (en) 2020-07-21 2020-07-21 Hoisting system for mounting assembled metal curtain wall ceiling board

Publications (1)

Publication Number Publication Date
CN213330082U true CN213330082U (en) 2021-06-01

Family

ID=76089868

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021446223.8U Active CN213330082U (en) 2020-07-21 2020-07-21 Hoisting system for mounting assembled metal curtain wall ceiling board

Country Status (1)

Country Link
CN (1) CN213330082U (en)

Similar Documents

Publication Publication Date Title
CN205577327U (en) Metal clad sheet system is hung futilely to wall body
CN211923473U (en) Hanging basket suspension mechanism
CN213330082U (en) Hoisting system for mounting assembled metal curtain wall ceiling board
CN209744005U (en) Hanging type vibration damping mounting structure of total heat exchanger
CN210064895U (en) Installation hoist of prefabricated unit in space
CN209702096U (en) A kind of means for correcting when hanging column installation
CN214169619U (en) Reverse installation aluminum honeycomb panel furred ceiling system
CN217128708U (en) Lifting point dislocation adjustment structure of keel
CN211447587U (en) Assembled frame construction cladding construction node
CN109850740B (en) Curtain wall unit body hoisting system and hoisting method thereof
CN221216935U (en) Assembled curtain wall unit body lifting device for super high-rise building reconstruction
CN219429514U (en) Climbing frame dismantling support
CN210086725U (en) Assembled for building externally-hung wallboard fossil fragments convenient to installation
CN216042530U (en) Heightening hanging basket system
CN210685129U (en) Conveniently-hoisted modeling honeycomb aluminum plate
CN212984292U (en) Structure platform unit body articulates structure
CN216471692U (en) Safety device
CN216641228U (en) Simple grid suspension supporting structure
CN212053696U (en) Steel beam wall high altitude welding safety protection operation platform
CN218492298U (en) Hanging basket with adjustable supporting legs for bridge construction
CN216974142U (en) Non-standard hanging basket mounting structure
CN220889405U (en) Concrete vertical member hanging basket
CN215626237U (en) Hanging crane rail mounting mechanism for net rack roof
CN218715070U (en) Upper frame body main frame structure of hydraulic creeping formwork
CN210084734U (en) Detachable lifting appliance for square steel pipe column

Legal Events

Date Code Title Description
GR01 Patent grant