Support bracket for municipal bridge construction Download PDF

Info

Publication number
CN212865604U
CN212865604U CN202020758139.3U CN202020758139U CN212865604U CN 212865604 U CN212865604 U CN 212865604U CN 202020758139 U CN202020758139 U CN 202020758139U CN 212865604 U CN212865604 U CN 212865604U
Authority
CN
China
Prior art keywords
pier
support bracket
fixing base
fixed
bridge construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN202020758139.3U
Other languages
Chinese (zh)
Inventor
何鹏
董婕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202020758139.3U priority Critical patent/CN212865604U/en
Application granted granted Critical
Publication of CN212865604U publication Critical patent/CN212865604U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model belongs to the technical field of support bracket, especially, be a support bracket is used in municipal bridge construction, including the second pier, first pier is installed at the top of second pier, the bridge is installed at the top of first pier, the externally mounted of first pier has first fixing base and second fixing base, the fixed plate is all installed to the tip of first fixing base and second fixing base, the one end fixed mounting of fixed plate has the mount. The utility model discloses can effectively avoid the problem that traditional support bracket continues to punch the installation on the second pier, and first fixing base and second fixing base are under the condition that receives the support of second pier, and stability is better, is difficult for droing, still installs a bracing piece between montant and fixed plate, forms triangle-shaped between bracing piece, fixed plate and the montant, makes the montant more stable not rock, when improving construction safety, uses more stably.

Description

Support bracket for municipal bridge construction
Technical Field
The utility model belongs to the technical field of, concretely relates to support bracket is used in municipal bridge construction.
Background
A bridge construction support bracket is a construction support bracket used for bridge construction and later maintenance, and can realize normal construction of workers and place related construction tools and materials.
The prior art has the following problems:
1. when the support bracket is installed, holes are often needed to be punched on the bridge piers, and the bridge piers are damaged to a certain extent after the bracket is disassembled;
2. poor stability and low safety performance.
SUMMERY OF THE UTILITY MODEL
To solve the problems set forth in the background art described above. The utility model provides a support bracket is used in municipal bridge construction, characteristics that have.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a support bracket is used in municipal bridge construction, includes the second pier, first pier is installed at the top of second pier, the bridge is installed at the top of first pier, the externally mounted of first pier has first fixing base and second fixing base, the fixed plate is all installed to the tip of first fixing base and second fixing base, the one end fixed mounting of fixed plate has the mount.
As the utility model relates to a support bracket is preferred for municipal bridge construction, lies in two with one side pass through the bolt fastening between the fixed plate.
As the utility model relates to a support bracket is preferred for municipal bridge construction, is located two with one side the fixed plate extends into the inside of mount to pass through the bolt fastening with the mount.
As the utility model relates to a support bracket is preferred for municipal bridge construction, the below fixed mounting of mount has the crossbeam, the below fixed mounting of crossbeam has the montant, install the block on the montant.
As the utility model relates to a support bracket is preferred for municipal bridge construction, the support frame is still installed, two to the below of mount install the horizontal pole between the support frame, the outside of horizontal pole installation and second pier.
As the utility model relates to a support bracket is preferred for municipal bridge construction, install the bracing piece between montant and the horizontal pole, the montant passes through the bracing piece with the horizontal pole and fixes.
Compared with the prior art, the beneficial effects of the utility model are that:
1. the utility model discloses during the use, with the outside of first pier of semicircular first fixing base and second fixing base cover, make the fixed plate that first fixing base tip set up and the fixed plate that second fixing base tip set up meet, through tightening up the bolt, will be located two fixed plates of same end and fix, thereby fix first fixing base and second fixing base on the outer wall of first pier, by the diameter little with the second pier with the diameter of first pier, the bottom of first fixing base and second fixing base can receive the support of second pier, can effectively avoid traditional support bracket to continue the problem of the installation of punching on the second pier, and first fixing base and second fixing base are under the condition that receives the support of second pier, and stability is better, difficult for droing.
2. The utility model discloses still install a bracing piece between montant and horizontal pole, form triangle-shaped between bracing piece, horizontal pole and the montant, make the montant stabilize more and do not rock, when improving construction safety, use more stably.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention. In the drawings:
fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural view of the block net of the present invention after installation;
FIG. 3 is a partial top view of the present invention;
in the figure: 1. a bridge; 2. a first bridge pier; 3. a first fixed seat; 4. a fixed mount; 5. a support frame; 6. a cross bar; 7. a second bridge pier; 8. a support bar; 9. a cross beam; 10. a fixing plate; 11. a vertical rod; 12. blocking; 13. a second fixed seat.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Example 1
As shown in fig. 1, 2 and 3;
fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural view of the block net of the present invention after installation;
FIG. 3 is a partial top view of the present invention;
the utility model provides a support bracket is used in municipal bridge construction, includes second pier 7, and first pier 2 is installed at the top of second pier 7, and bridge 1 is installed at the top of first pier 2, and the externally mounted of first pier 2 has first fixing base 3 and second fixing base 13, and fixed plate 10 is all installed to the tip of first fixing base 3 and second fixing base 13, and the one end fixed mounting of fixed plate 10 has mount 4.
In this embodiment: when the support bracket is used, the semicircular first fixed seat 3 and the semicircular second fixed seat 13 are sleeved outside the first pier 2, so that the fixed plate 10 arranged at the end part of the first fixed seat 3 is connected with the fixed plate 10 arranged at the end part of the second fixed seat 13, the two fixed plates 10 positioned at the same end are fixed by screwing the bolts, so that the first fixed seat 3 and the second fixed seat 13 are fixed on the outer wall of the first pier 2, the diameter of the first pier 2 is smaller than that of the second pier 7, the bottoms of the first fixed seat 3 and the second fixed seat 13 are supported by the second pier 7, the problem that the traditional support bracket continuously punches and installs on the second pier 7 can be effectively avoided, and under the condition that the first fixed seat 3 and the second fixed seat 13 are supported by the second pier 7, has better stability and is not easy to fall off.
As shown in fig. 1, 2 and 3;
fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural view of the block net of the present invention after installation;
FIG. 3 is a partial top view of the present invention;
in an alternative embodiment, two fixing plates 10 located on the same side are fixed by bolts.
In this embodiment: through screwing up the bolt, will be located two fixed plates 10 of same end and fix to fix first fixing base 3 and second fixing base 13 on the outer wall of first pier 2.
As shown in fig. 1, 2 and 3;
fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural view of the block net of the present invention after installation;
FIG. 3 is a partial top view of the present invention;
in an alternative embodiment, two fixing plates 10 located on the same side extend into the interior of the fixing frame 4 and are fixed to the fixing frame 4 by bolts.
In this embodiment: the fixing frame 4 is fixed on the fixing plate 10 through bolts, and the cross beam 9 is fixed below the fixing frame 4 through bolts.
As shown in fig. 1, 2 and 3;
fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural view of the block net of the present invention after installation;
FIG. 3 is a partial top view of the present invention;
in an alternative embodiment, a cross beam 9 is fixedly arranged below the fixing frame 4, a vertical rod 11 is fixedly arranged below the cross beam 9, and a barrier net 12 is arranged on the vertical rod 11.
In this embodiment: a vertical rod 11 and a barrier net 12 are arranged below the cross beam 9, and a constructor can stand in the vertical rod 11 for construction and can protect the construction through the barrier net 12.
As shown in fig. 1, 2 and 3;
fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural view of the block net of the present invention after installation;
FIG. 3 is a partial top view of the present invention;
in an alternative embodiment, a support frame 5 is further installed below the fixed frame 4, a cross rod 6 is installed between the two support frames 5, and the cross rod 6 is installed outside the second pier 7.
In this embodiment: a supporting frame 5 is further installed at the bottom of the fixing frame 4 through bolts and fixing blocks, a cross rod 6 is fixedly installed at one end, far away from the fixing frame 4, of the supporting frame 5, the cross rod 6 is sleeved outside the second pier 7, a triangle is formed among the cross rod 6, the supporting frame 5 and the fixing frame 4, and stability is optimal.
As shown in fig. 1, 2 and 3;
fig. 1 is a schematic structural view of the present invention;
fig. 2 is a schematic structural view of the block net of the present invention after installation;
FIG. 3 is a partial top view of the present invention;
in an alternative embodiment, a support bar 8 is installed between the vertical bar 11 and the cross bar 6, and the vertical bar 11 and the cross bar 6 are fixed through the support bar 8.
In this embodiment: for further strengthening the protection work, still install a bracing piece 8 between montant 11 and horizontal pole 6, form triangle-shaped between bracing piece 8, horizontal pole 6 and the montant 11, make montant 11 more stable not rock, when improving the construction security, use more stably.
The utility model discloses a theory of operation and use flow: when the support bracket is used, the semicircular first fixed seat 3 and the semicircular second fixed seat 13 are sleeved outside the first pier 2, so that the fixed plate 10 arranged at the end part of the first fixed seat 3 is connected with the fixed plate 10 arranged at the end part of the second fixed seat 13, the two fixed plates 10 positioned at the same end are fixed by screwing the bolts, so that the first fixed seat 3 and the second fixed seat 13 are fixed on the outer wall of the first pier 2, the diameter of the first pier 2 is smaller than that of the second pier 7, the bottoms of the first fixed seat 3 and the second fixed seat 13 are supported by the second pier 7, the problem that the traditional support bracket continuously punches and installs on the second pier 7 can be effectively avoided, and under the condition that the first fixed seat 3 and the second fixed seat 13 are supported by the second pier 7, the stability is better, and the falling is not easy;
the fixing frame 4 is fixed on the fixing plate 10 through bolts, the cross beam 9 is fixed below the fixing frame 4 through bolts, the vertical rod 11 and the blocking net 12 are installed below the cross beam 9, a constructor can stand in the vertical rod 11 for construction, and protection is performed through the blocking net 12;
in order to further enhance the safety of construction, a support frame 5 is further arranged at the bottom of the fixed frame 4 through bolts and fixed blocks, a cross rod 6 is fixedly arranged at one end of the support frame 5 far away from the fixed frame 4, the cross rod 6 is sleeved outside a second pier 7, and a triangle is formed among the cross rod 6, the support frame 5 and the fixed frame 4, so that the stability is optimal;
for further strengthening the protection work, still install a bracing piece 8 between montant 11 and horizontal pole 6, form triangle-shaped between bracing piece 8, horizontal pole 6 and the montant 11, make montant 11 more stable not rock, when improving the construction security, use more stably.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (6)

1. The utility model provides a support bracket is used in municipal bridge construction, includes second pier (7), its characterized in that: first pier (2) are installed at the top of second pier (7), bridge (1) are installed at the top of first pier (2), the externally mounted of first pier (2) has first fixing base (3) and second fixing base (13), fixed plate (10) are all installed to the tip of first fixing base (3) and second fixing base (13), the one end fixed mounting of fixed plate (10) has mount (4).
2. The support bracket for municipal bridge construction according to claim 1, wherein: two fixing plates (10) positioned on the same side are fixed through bolts.
3. The support bracket for municipal bridge construction according to claim 1, wherein: the two fixing plates (10) positioned on the same side extend into the fixing frame (4) and are fixed with the fixing frame (4) through bolts.
4. The support bracket for municipal bridge construction according to claim 1, wherein: the lower part of the fixing frame (4) is fixedly provided with a cross beam (9), the lower part of the cross beam (9) is fixedly provided with a vertical rod (11), and the vertical rod (11) is provided with a blocking net (12).
5. The support bracket for municipal bridge construction according to claim 1, wherein: support frames (5) are further installed below the fixing frame (4), a cross rod (6) is installed between the support frames (5), and the cross rod (6) is installed outside the second bridge pier (7).
6. The support bracket for municipal bridge construction according to claim 4, wherein: the supporting rod (8) is installed between the vertical rod (11) and the cross rod (6), and the vertical rod (11) and the cross rod (6) are fixed through the supporting rod (8).
CN202020758139.3U 2020-05-10 2020-05-10 Support bracket for municipal bridge construction Expired - Fee Related CN212865604U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020758139.3U CN212865604U (en) 2020-05-10 2020-05-10 Support bracket for municipal bridge construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020758139.3U CN212865604U (en) 2020-05-10 2020-05-10 Support bracket for municipal bridge construction

Publications (1)

Publication Number Publication Date
CN212865604U true CN212865604U (en) 2021-04-02

Family

ID=75204351

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020758139.3U Expired - Fee Related CN212865604U (en) 2020-05-10 2020-05-10 Support bracket for municipal bridge construction

Country Status (1)

Country Link
CN (1) CN212865604U (en)

Similar Documents

Publication Publication Date Title
CN212865604U (en) Support bracket for municipal bridge construction
CN211622727U (en) Intelligent combined mounting frame for building
CN219119274U (en) Height-adjustable support structure for tunnel portal of flood discharge tunnel
CN211899565U (en) Bearing hanging rack for civil engineering construction
CN201473988U (en) Mounting device for suspending and heat radiation system of miniature hydraulic excavator
CN218176563U (en) Steel construction stable in utilization
CN213625278U (en) Bridge reinforcing device for municipal bridge engineering
CN212001590U (en) Steel pipe constructs support with antidumping function
CN214222197U (en) Straight section shock absorption support for cast-in-place surface concrete conveying pipe
CN111236606B (en) Isolation system of overhanging scaffold
CN206829587U (en) A kind of hydraulic climbing formwork wall-attached frame
CN212561191U (en) Hanging flower basket device for bridge construction
CN219509391U (en) Construction is with enclosing fender warning sign
CN214661106U (en) Grid reinforcing structure of corrosion-resistant alloy water pump base
CN205476444U (en) Light -duty support post based on low level jacking die carrier system
CN214403632U (en) Supporting device for underground filling and mining
CN220849085U (en) Anti-collision metal net
CN212926137U (en) Wind power cylinder type foundation closure hanging basket device
CN210002947U (en) Support rod of steel structures
CN215928943U (en) Support for camera
CN214117884U (en) Plate type door and window auxiliary frame capable of effectively resisting earthquake and super-strong typhoon
CN221095940U (en) Construction elevator platform protector
CN210946461U (en) Bridge lateral support convenient to fixed mounting
CN212866045U (en) Iron plate fixing frame
CN217681013U (en) Fender is enclosed in municipal administration

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210402

CF01 Termination of patent right due to non-payment of annual fee