tension
end plate
hoop
tubular pile
welded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021364672.8U
Other languages
Chinese (zh)
Inventor
吴江斌
王卫东
周建龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East China Architectural Design and Research Institute Co Ltd
Original Assignee
East China Architectural Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East China Architectural Design and Research Institute Co Ltd filed Critical East China Architectural Design and Research Institute Co Ltd
Priority to CN202021364672.8U priority Critical patent/CN212506234U/en
Application granted granted Critical
Publication of CN212506234U publication Critical patent/CN212506234U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model belongs to an enhancement mode resistance to plucking tubular pile welded connection connects in building engineering pile foundation field. The technical scheme is as follows: the end part of the tubular pile is provided with a tension end plate, a longitudinal prestress main rib is arranged in the tubular pile, the prestress main rib is welded with the tension end plate, and a tension hoop is vertically welded with the tension end plate and sleeved on the tube wall of the tubular pile; longitudinal connecting short steel bars are arranged in the tubular pile, the connecting short steel bars and the prestressed main steel bars are arranged in a staggered mode, and one end of each connecting short steel bar is welded with the tension end plate; the tubular pile of the upper section and the tubular pile of the lower section are welded and fixed through respective tension end plates, and the connecting blocks are welded on the tension hoop of the upper section and the tension hoop of the lower section around the joint of the upper tension end plate and the lower tension end plate. The joint has the advantages of reliable quality, reasonable stress, convenience for factory prefabrication and capability of enhancing the connection performance between two sections of pipe piles.

Description

Enhancement mode resistance to plucking tubular pile welded connection connects
Technical Field
The utility model belongs to building engineering pile foundation field especially relates to a tubular pile connects structure.
Background
The prestressed concrete pipe pile has the advantages of high single pile bearing capacity, convenient construction, reliable quality, low cost and the like, and is widely applied to foundation engineering of buildings. When the pipe pile is used as a uplift pile, the quality of the pre-stress of the prestressed reinforcement and the quality of the connecting joint are generally controlled. At present, according to the tubular pile products in the current national standard drawing set 'prestressed concrete tubular pile' 10G409, the prestressed tubular pile only transmits force to concrete through the anchoring holes and the prestressed reinforcements arranged on the end plate, and because the thickness of the end plate at the anchoring holes is small, the phenomenon of stress concentration and shear failure is easily generated at the anchoring holes, even the integral failure of the connecting end plate is possibly caused, and the bearing performance of the pile body is restricted. In addition, the prestressed pipe piles are generally connected by welding joint end plates, the wall thickness of a hoop at the end part of each pipe pile is only 1.5 mm-2.3 mm, the thickness of each pipe pile is small, the pipe piles are only used as structures and cannot play a role in transferring tension, the force borne by the previous pile can be transferred to the next pile only through the end plates, the requirement on the professional technical level of electric welding is very high, and the welding quality of the joint of the end plates often determines the quality of the whole uplift pipe pile. Due to the existence of the two factors, the application of the uplift pipe pile in engineering construction is limited.
SUMMERY OF THE UTILITY MODEL
In order to solve the technical problem, the utility model provides an enhancement mode resistance to plucking tubular pile welded connection connects, it is that a quality is reliable, the atress is reasonable, make things convenient for the mill to prefabricate, can strengthen the joint of the connection performance between two sections tubular piles.
The technical scheme of the utility model is that: a welding connection joint of a reinforced uplift pipe pile is characterized in that a tension end plate is arranged at the end part of the pipe pile, a longitudinal prestress main rib is arranged in the pipe pile, the prestress main rib is welded with the tension end plate, a tension hoop is vertically welded with the tension end plate, and the tension hoop is sleeved on the pipe wall of the pipe pile; longitudinal connecting short steel bars are arranged in the tubular pile, the connecting short steel bars and the prestressed main steel bars are arranged in a staggered mode, and one end of each connecting short steel bar is welded with the tension end plate; the tubular pile of the upper section and the tubular pile of the lower section are welded and fixed through respective tension end plates, and the connecting blocks are welded on the tension hoop of the upper section and the tension hoop of the lower section around the joint of the upper tension end plate and the lower tension end plate.
Based on the technical characteristics: the welding of one end of the connection stub to the tension end plate is replaced with the welding of the connection stub to the inner wall of the tension hoop.
Based on the technical characteristics: the tension hoop is embedded into the tubular pile, and the outer wall of the tension hoop is flush with the outer wall of the tubular pile.
Based on the technical characteristics: the tension end plate, the tension hoop and the connecting short steel bar of the single-section tubular pile are connected through welding, and an integrated structure is prefabricated for a factory.
Based on the technical characteristics: the number of the connecting blocks is 4-6, and the connecting blocks are uniformly arranged and welded on an upper section of tension hoop and a lower section of tension hoop at the periphery of the connection position of the upper tension end plate and the lower tension end plate.
In the technical scheme, the tension end plate and the tension hoop participate in the stress of the tubular pile, the thickness calculation of the tension end plate and the tension hoop considers the tension of the steel pipe, and the specific thickness can be determined according to actual calculation. In the general prior art, as a tubular pile end plate specified in the current national standard drawing set 'prestressed concrete tubular pile' 10G409 is 20mm to 25mm thick, the thickness of the end plate at an anchoring hole is small, and the end plate becomes a weak node of a bearing position and is not beneficial to tension; the pipe pile hoop specified in the current national standard drawing set 'prestressed concrete pipe pile' 10G409 is 1.5 mm-2.3 mm thick and small in thickness, and can not play a role in transferring tension only by being used as a structure. In the technical scheme, the end plate and the hoop need to be thickened to form a system combining the reinforced tension end plate and the tension hoop, the factors such as stress, economic cost and the like are considered, and the thickness of the tension end plate is increased by 3mm to 5mm on the thickness of the end plate of a pipe pile product in 10G409 of the State Standard atlas of prestressed concrete pipe piles; the tension hoops are preferably 10mm to 12mm thick.
The utility model discloses on prior art basis, can form new atress system through pulling the end plate, pulling the hoop, the connecting block of addding and connecting the common atress of short reinforcement, improve the resistance to plucking tubular pile welded connection joint of enhancement mode of the bearing capacity of resistance to plucking tubular pile, have very strong realistic meaning.
Through the above-mentioned technical scheme who conceives, compare with prior art, the utility model discloses effectively strengthened the welded connection joint of resistance to plucking tubular pile, except having considered the tensile performance of end plate in the biography power route, prestressing steel bar, the hoop that draws, connecting block and connection short steel bar also can play irreplaceable effect. The utility model discloses the principle is simple, the atress is reasonable, construction convenience, through the prefabricated processing back field weld of mill can. Can be widely applied to pile foundations adopted by buildings for bearing uplift loads.
Drawings
Fig. 1 is the utility model discloses enhancement mode resistance to plucking tubular pile welded connection connects looks sideways at the schematic diagram.
Fig. 2 is the utility model discloses enhancement mode resistance to plucking tubular pile welded connection connects the schematic view overlooking.
Detailed Description
The following describes the present invention in further detail with reference to the accompanying drawings. These embodiments are provided only for illustrating the present invention and are not intended to limit the present invention.
In the description of the present invention, it should be noted that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", and the like indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, and are only for convenience of description and simplification of the description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; may be a mechanical connection; may be directly connected or indirectly connected through an intermediate. The specific meaning of the above terms in the present invention can be understood according to specific situations by those skilled in the art.
In addition, in the description of the present invention, "a plurality" means two or more unless otherwise specified.
As shown in fig. 1 and 2: the reinforced uplift pipe pile connecting joint comprises a tension end plate 3, a tension hoop 5, a connecting short steel bar 7 and a connecting block 8; the tension hoop 5 is vertically welded with a tension end plate 3 of the tubular pile; longitudinal steel bars are arranged in the tubular pile and comprise a prestressed main bar 6 and a connecting short steel bar 7; the connecting short reinforcing steel bars 7 and the prestressed main reinforcing steel bars 6 are arranged in a staggered mode. The tension hoop 5 is embedded into the pipe pile, and the outer wall of the tension hoop 5 is flush with the outer wall of the pipe pile.
The upper section of tubular pile 1 and the lower section of tubular pile 2 are welded and fixed through respective tension end plates, and the circumferential weld seam 4 at the joint is required to be the same as the weld seam requirement of a common tubular pile in the prior art; the connecting block 8 is welded on the tension hoop 5 around the pipe pile connecting position.
The connecting short bars 7 are connected to the tension end plate 3 and can be welded to the inner wall of the tension hoop 5. The tension end plate 3, the tension hoop 5 and the connecting short steel bar 7 are welded into a whole when being prefabricated in a factory, and the tension end plate, the tension hoop 5 and the connecting short steel bar are used as a part of the prestressed concrete pipe pile and play a role together with the prestressed main steel bar 6.
In construction, an upper section of pipe pile 1 and a lower section of pipe pile 2 are firstly connected through a circumferential weld joint at a tension end plate 3; and then, the additionally arranged connecting blocks 8 are uniformly welded on the tensile hoop 5 at the periphery of the tubular pile connecting position, and the height of the welding seam is more than or equal to 8 mm. The connecting blocks 8 and the tension end plates 3 cooperate together to transmit the pulling resistance from the upper section of tubular pile 1 to the lower section of tubular pile 2, the specific number of the connecting blocks 8 can be determined by calculation according to the pulling resistance bearing capacity of a single pile, and generally 4-6 blocks are uniformly welded on the tension hoop at the periphery of the tubular pile joint, namely the upper section of tension hoop and the lower section of tension hoop at the periphery of the joint of the upper and lower tension end plates.
The above detailed description of the solution provided by the embodiments of the present invention is directed to a person skilled in the art, and according to the idea of the embodiments of the present invention, there are changes in the specific implementation and application range, such as the thickness of the tension hoop, the width of the end plate, or the length of the short steel bar. The connecting short steel bars can be connected with the tension hoop in a welding or overlapping mode. The size of the connecting block can be adjusted during production and processing according to actual conditions.
In summary, the content of the present specification should not be understood as a limitation of the present invention, and any changes made according to the design concept of the present invention are all within the protection scope of the present invention.

Claims (6)

1. A welding connection joint of a reinforced uplift pipe pile is characterized in that a tension end plate (3) is arranged at the end part of the pipe pile, a longitudinal prestress main rib (6) is arranged in the pipe pile, the prestress main rib (6) is welded with the tension end plate (3), a tension hoop (5) is vertically welded with the tension end plate (3) and sleeved on the pipe wall of the pipe pile; longitudinal connecting short steel bars (7) are arranged in the tubular pile, the connecting short steel bars (7) and the prestressed main steel bars (6) are arranged in a staggered mode, and one end of each connecting short steel bar (7) is welded with the tension end plate (3); the upper segment the tubular pile with the lower segment the tubular pile is through respective draw end plate (3) welded fastening, connecting block (8) welding two from top to bottom draw the upper segment all around of end plate (3) junction draw hoop (5) and lower segment draw on the hoop (5).
2. The reinforced uplift pipe pile welding connection joint as claimed in claim 1, wherein: one end of the connecting short steel bar (7) is welded with the tension end plate (3) instead of the connecting short steel bar (7) is welded on the inner wall of the tension hoop (5).
3. The reinforced uplift pipe pile welding connection joint as claimed in claim 1 or 2, wherein: the tension hoop (5) is embedded into the tubular pile, and the outer wall of the tension hoop (5) is flush with the outer wall of the tubular pile.
4. An enhanced uplift pipe pile welding connection joint as claimed in claim 1 or 2, wherein; the single section tubular pile be drawn end plate (3) draw hoop (5) with connect between short reinforcing bar (7) all through welded connection, for the prefabricated integral structure of mill.
5. The reinforced uplift pipe pile welding connection joint as claimed in claim 1 or 2, wherein: the number of the connecting blocks (8) is 4-6, and the connecting blocks are uniformly arranged and welded on the upper section of the tension hoop (5) and the lower section of the tension hoop (5) at the periphery of the connection position of the upper tension end plate and the lower tension end plate (3).
6. The reinforced uplift pipe pile welding connection joint as claimed in claim 1 or 2, wherein: the tension end plate (3) is thickened, and the thickness of the end plate of a tubular pile product specified in the current national standard drawing of prestressed concrete tubular piles (10G 409) is increased by 3mm to 5 mm; the tensile hoop (5) is thickened, and the thickness of the hoop of a tubular pile product specified in the current national standard atlas, prestressed concrete tubular pile (10G 409) is increased to be 10mm to 12mm on the basis that the thickness of the hoop is 1.5mm to 2.3 mm.
CN202021364672.8U 2020-07-13 2020-07-13 Enhancement mode resistance to plucking tubular pile welded connection connects Active CN212506234U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021364672.8U CN212506234U (en) 2020-07-13 2020-07-13 Enhancement mode resistance to plucking tubular pile welded connection connects

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021364672.8U CN212506234U (en) 2020-07-13 2020-07-13 Enhancement mode resistance to plucking tubular pile welded connection connects

Publications (1)

Publication Number Publication Date
CN212506234U true CN212506234U (en) 2021-02-09

Family

ID=74438037

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021364672.8U Active CN212506234U (en) 2020-07-13 2020-07-13 Enhancement mode resistance to plucking tubular pile welded connection connects

Country Status (1)

Country Link
CN (1) CN212506234U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114718059A (en) * 2022-05-05 2022-07-08 广州建筑股份有限公司 Tubular pile connecting structure and pile splicing method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114718059A (en) * 2022-05-05 2022-07-08 广州建筑股份有限公司 Tubular pile connecting structure and pile splicing method thereof
CN114718059B (en) * 2022-05-05 2023-03-21 广州建筑股份有限公司 Tubular pile connecting structure and pile splicing method thereof

Similar Documents

Publication Publication Date Title
CN211037273U (en) Steel joint is connected to assembled concrete structure primary and secondary roof beam
CN111705787A (en) Enhancement mode resistance to plucking tubular pile welded connection connects
CN110106967A (en) A kind of high-performance steel pipe regeneration concrete is put more energy into mixed column-wall construction system
CN208201914U (en) One kind is faced forever in conjunction with covered back-digging structure
CN211572019U (en) Box shaped steel concrete column and concrete beam connected node
CN212506234U (en) Enhancement mode resistance to plucking tubular pile welded connection connects
CN209907570U (en) Assembled frame beam column node that steel sheet and reinforcement are connected
CN110725405A (en) Steel pipe concrete column H-shaped steel beam rigid connection node structure with tie bars and construction method
CN214220084U (en) Row-shaped steel concrete shear wall and assembly type building structure system thereof
CN210947142U (en) Assembled concrete structure post roof beam connecting steel node
CN111021553A (en) Precast concrete post and girder steel connected node of baffle in area
CN213087072U (en) Rigid-joint connection node for superposed beam and thin-wall steel pipe concrete column
CN216276409U (en) End connection reinforcing structure of steel pipe bundle concrete combined shear wall
CN207228398U (en) The house that a kind of shear wall slab being made of steel square tube is assembled
CN212835888U (en) Vertical seam board that draws of assembled autoclaved aerated concrete
CN215330436U (en) Novel concrete-filled steel tube stiffening mixed structure
CN212248224U (en) Prefabricated hollow anti-floating pile is with integration bolt formula anti-floating connection structure
CN108360361A (en) A kind of prestressing force PBL puts more energy into shaped steel case concrete combination beam and its construction method
CN210621920U (en) Steel node is connected with superimposed sheet to assembled concrete structure shear force wall
CN113216380A (en) Steel-concrete composite beam and concrete-filled steel tubular column joint and construction method
CN211774623U (en) Precast concrete post and girder steel connected node of baffle in area
CN206707028U (en) A kind of connecting node of rectangular steel-tube concrete column and girder with rolled steel section en cased in concrete
CN218436994U (en) Butt joint reinforcing structure of concrete pipe pile
CN215106246U (en) Shear wall edge component meets basement outer wall department structure
CN218843486U (en) Quick-connection type variable-rigidity prefabricated floor slab and system thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant