CN212248295U - Combined anti-sliding structure with prestressed anchor cables additionally arranged on existing piles - Google Patents

Combined anti-sliding structure with prestressed anchor cables additionally arranged on existing piles Download PDF

Info

Publication number
CN212248295U
CN212248295U CN202021670336.6U CN202021670336U CN212248295U CN 212248295 U CN212248295 U CN 212248295U CN 202021670336 U CN202021670336 U CN 202021670336U CN 212248295 U CN212248295 U CN 212248295U
Authority
CN
China
Prior art keywords
anchor cable
pile
pile body
section
prestressed anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021670336.6U
Other languages
Chinese (zh)
Inventor
吴兵
梁瑶
吴晓春
唐晓波
彭友松
陈兵
李为
王同俊
贠志强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Communication Surveying and Design Institute Co Ltd
Original Assignee
Sichuan Communication Surveying and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Communication Surveying and Design Institute Co Ltd filed Critical Sichuan Communication Surveying and Design Institute Co Ltd
Priority to CN202021670336.6U priority Critical patent/CN212248295U/en
Application granted granted Critical
Publication of CN212248295U publication Critical patent/CN212248295U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The utility model discloses a combined anti-sliding structure with prestressed anchor cables added to an existing pile, which is a novel combined anti-sliding structure that the cantilever section of the existing anti-sliding pile is drilled, and a vertical prestressed anchor cable A and a plurality of rows of diagonal prestressed anchor cables B are added to strengthen, improve and optimize the structural stress of the existing anti-sliding pile; the method aims to optimize the pile body internal force distribution of the existing pile, provide enough anchoring force for the existing pile, and share a part of landslide thrust so as to reinforce and manage the engineering instability caused by slope toe excavation.

Description

Combined anti-sliding structure with prestressed anchor cables additionally arranged on existing piles
Technical Field
The utility model relates to an excavation supporting technology field, concretely relates to existing stake is add combination cling compound structure of prestressed anchorage cable.
Background
Landslide control is a disaster-resistant project with huge investment, complex technology and dangerous and difficult construction. China is a country with serious landslide disasters, and for years, in order to ensure the safety of lives and properties of people and ensure the smooth progress of economic construction, the country consumes a large amount of manpower, material resources and financial resources on landslide prevention and control work.
In the later stage of the 20 th century and the 60 s, the anti-slide pile is used as a novel geotechnical engineering reinforcing technology, has the advantages of being smaller than an excavation surface of a retaining wall, small in masonry volume, high in anti-slide strength, high in construction speed and the like, is quickly popularized and applied in China, and is still used in the fields of highways, railways and the like in a large scale. Because the anti-slide piles in the existing highway landslide control are arranged at positions which are thinner in landslide, smaller in thrust, higher in foundation strength of the anchoring section and beneficial to anti-slide. In this case, the embedded type slide resistant piles outside a certain distance (later extension range) from the outside of the road are widely used in the management of the landslide along the line.
With the development of social economy, projects such as highway capacity expansion, trunk line upgrading and reconstruction and the like emerge in large quantity; in the road excavation and extension scheme, existing landslides along the line cannot be avoided, the rock-soil mass at the front slope foot of the embedded type anti-slide pile needs to be excavated, and at the moment, safe excavation and retreatment of the existing side slope become one of the control projects (difficult problems) in engineering construction. After a resistance-providing soil body is excavated before the embedded type anti-slide pile, the existing anti-slide pile may have the phenomenon that an upper pile body is exposed to form a cantilever section or the front edge width of the pile body is insufficient, and compared with the increased landslide thrust, enough anchoring force and anti-slide force cannot be provided, so that the landslide body is damaged by instability due to excavation of a road extension slope foot.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide an existing pile adds combination cling compound structure of prestressed anchorage cable, it aims at solving and can't provide sufficient anchor power and cling compound power among the prior art to lead to the landslide body to produce the technical problem of unstability destruction because of road enlargement slope foot excavation.
The utility model discloses a following technical scheme realizes:
a combined anti-sliding structure with an existing pile additionally provided with a prestressed anchor cable comprises an existing anti-sliding pile body, wherein the pile body is divided into a cantilever section and an embedded section, and the embedded section is embedded in a stable rock-soil body below a sliding surface;
the top of the cantilever section of the pile body is provided with a vertical prestressed anchor cable A, the upper end of the vertical prestressed anchor cable A is connected with the top of the cantilever section of the pile body, and the lower end of the vertical prestressed anchor cable A vertically penetrates through the bottom of the embedded section of the pile body from the top of the cantilever section of the pile body downwards and extends along the direction of the embedded section;
and a cable-stayed prestressed anchor cable B is also arranged on the cantilever section of the pile body, the lower end of the cable-stayed prestressed anchor cable B is anchored in the stable rock-soil body behind the sliding surface, the upper end of the cable-stayed prestressed anchor cable B is connected with the cantilever section of the pile body, and an included angle theta is formed between the cable-stayed prestressed anchor cable B and the horizontal plane.
Furthermore, distribution ribs and stirrups are arranged in the pile body, and bending-resistant reinforcing steel bars are arranged on the tension side of the pile body;
and drilling an anchor rope preformed hole A for placing the vertical prestressed anchor rope A at the symmetrical position of the A-A central axis of the cantilever section of the pile body outside the protective layer of the bending-resistant reinforcing steel bar at the tension side of the pile body.
Furthermore, one or more anchor cable preformed holes A are formed in the top of the cantilever section of the pile body;
the vertical prestressed anchor cable A consists of a fastening head, a free section and an anchoring section, wherein the fastening head consists of a cement anchor pier, a steel base plate and an anchorage device;
and a plastic gasket is arranged between the cement anchor pier and the pile body.
And further, drilling a cable-stayed anchor cable preformed hole B for placing the cable-stayed prestressed anchor cable B at the central axis of the front side of the pile body at the position, which is not smaller than 300mm from the top of the pile top, of the cantilever section of the pile body.
Furthermore, one or more anchor cable preformed holes B are formed in the central axis of the front side of the pile body, which is located at the position, with the distance from the cantilever section of the pile body to the top of the pile top being not less than 300 mm;
the cable-stayed prestressed anchor cable B consists of a fastening head, a free section and an anchoring section, wherein the fastening head consists of a cement anchor pier, a steel backing plate and an anchorage device;
and a plastic gasket is arranged between the cement anchor pier and the pile body.
Further, the plastic gasket is a rubber gasket or a nylon gasket with the layer thickness of 30mm, and the boundary size of the plastic gasket is 50mm larger than that of the cement anchor pier.
Furthermore, the prestressed anchor cable A and the prestressed anchor cable B are both made of 4-8 strands of steel stranded wires;
the prestressed anchor cable A is divided into an anchoring section A and a free section A; the anchoring section A is an anchoring section anchored in a stable rock-soil body below the pile body, and the free section A is the distance length from the top of the prestressed anchor cable A to the pile bottom of the pile body plus 500 mm;
the prestressed anchor cable B is divided into an anchoring section B and a free section B, the anchoring section B is an anchoring section anchored in a stable rock-soil body behind the sliding surface, and the free section B is the distance length from the top of the prestressed anchor cable B to the sliding surface plus 1000 mm.
Compared with the prior art, the utility model, following advantage and beneficial effect have:
1. the utility model provides a combined anti-sliding structure with prestressed anchor cables added on the existing pile, which effectively solves the problems that the anchoring depth of the existing anti-sliding pile is not enough after the pile body front slope foot of the existing anti-sliding pile is excavated and the bending strength and the anti-sliding force of the existing anti-sliding pile are not enough; meanwhile, anchor cables are additionally arranged on the existing anti-slide piles for construction, so that the disturbance on the existing landslide is small, and the danger of secondary sliding in the construction period can be effectively reduced.
2. The utility model provides a combination cling compound structure of prestressed anchorage cable is add to existing stake, other structures relatively full play the cling compound effect of existing cling compound stake, reduced the step of slope foot expand the interim support measure of digging, practice thrift the engineering investment greatly, and this novel combination cling compound structure has that the construction is simple, safe swift, to existing road operation guarantor's characteristics such as disturb little, has wide popularization application prospect.
Drawings
The accompanying drawings, which are included to provide a further understanding of the embodiments of the invention and are incorporated in and constitute a part of this application, illustrate embodiment(s) of the invention and together with the description serve to explain the principles of the invention. In the drawings:
FIG. 1 is a schematic view of the cross section of the landslide along the road of the utility model treated by the embedded anti-slide pile.
Fig. 2 is the utility model discloses the road adopts because of the extension excavation the utility model discloses administer landslide cross section schematic diagram.
Fig. 3 is a top view of the pre-stressed anchor cable added to the existing pile of the present invention.
Fig. 4 is a front view of the pre-stressed anchor cable added to the existing pile of the present invention.
Fig. 5 is a schematic view of the novel fastening head of the prestressed anchor cable added to the existing pile of the present invention.
Reference numbers and corresponding part names:
10-existing slide-resistant pile body; 11-distribution ribs; 12-a stirrup; 13-bending-resistant reinforcing steel bars; 14-tension side (pile body back side); 15a-a central axis; 15B-B-B central axis; 16-central axis of front side of pile body; 17 a-anchor cable preformed hole A; 17 b-anchor cable preformed hole A; 18 a-anchor cable preformed hole B; 18B-anchor cable preformed holes B; 19 a-pile body cantilever section; 19 b-pile body embedding and fixing section; 20 a-a prestressed anchor cable A; 20 b-a prestressed anchor cable A; 21 a-free segment a; 22 a-anchor segment a; 21 b-free segment a; 22 b-anchor segment a; l1-spacing A; l2-eccentricity A; 30 a-a prestressed anchor cable B; 30B-a prestressed anchor cable B; 31 a-free segment B; 32 a-anchor segment B; 31B-free segment B; 32B-anchor segment B; l3-spacing B; 40-an anchor device; 41-steel strand wires; 42-a catheter; 43-steel backing plate; 44-cement anchor piers; 45-plastic gaskets; 50-excavating a protective measure on an empty surface; 60-a sliding surface; 70-horizontal plane; thetaa-an anchoring angle; thetab-an anchoring angle.
Detailed Description
To make the objects, technical solutions and advantages of the present invention more apparent, the present invention is further described in detail below with reference to the following examples and drawings, and the exemplary embodiments and descriptions thereof of the present invention are only used for explaining the present invention, and are not intended as limitations of the present invention.
In the following description, numerous specific details are set forth in order to provide a thorough understanding of the present invention. However, it will be apparent to one of ordinary skill in the art that: it is not necessary to employ these specific details to practice the invention. In other instances, well-known structures, circuits, materials, or methods have not been described in detail so as not to obscure the present invention.
Throughout the specification, reference to "one embodiment," "an embodiment," "one example," or "an example" means: the particular features, structures, or characteristics described in connection with the embodiment or example are included in at least one embodiment of the present invention. Thus, the appearances of the phrases "one embodiment," "an embodiment," "one example" or "an example" in various places throughout this specification are not necessarily all referring to the same embodiment or example. Furthermore, the particular features, structures, or characteristics may be combined in any suitable combination and/or sub-combination in one or more embodiments or examples. Further, those of ordinary skill in the art will appreciate that the illustrations provided herein are for illustrative purposes and are not necessarily drawn to scale. As used herein, the term "and/or" includes any and all combinations of one or more of the associated listed items.
[ examples ] A method for producing a compound
As shown in fig. 1, the utility model discloses be applied to and solve and adopt existing friction pile to administer landslide engineering back, when the stake before (base of slope) the ground body excavate once more because of later stage engineering construction (like road enlargement, upgrading transformation etc.), and then cause the landslide thrust increase that existing friction pile bore, self anchor length reduce and bending strength (anti-sliding force) not enough and the engineering unstability problem that leads to.
As shown in FIG. 2, the scheme is a novel combined anti-slide structure which is used for reinforcing and improving the existing anti-slide pile and optimizing the structural stress by drilling the cantilever section of the existing anti-slide pile and additionally arranging a vertical prestressed anchor cable A and a plurality of rows of diagonal prestressed anchor cables B; the method aims to optimize the pile body internal force distribution of the existing pile, provide enough anchoring force for the existing pile, and share a part of landslide thrust so as to reinforce and manage the engineering instability caused by slope toe excavation.
As shown in fig. 2, 3, 4 and 5, a combined anti-sliding structure with an existing pile additionally provided with a prestressed anchor cable comprises an existing anti-sliding pile body 10, wherein the pile body 10 is divided into an embedded section 19b and a cantilever section 19a, and the embedded section 19b is embedded in a stable rock-soil body below a sliding surface 60; a vertical prestressed anchor cable A20a is arranged on the top of the cantilever section 19a of the pile body 10, the upper end of the vertical prestressed anchor cable A20a is connected with the top of the cantilever section 19a of the pile body 10, and the lower end of the vertical prestressed anchor cable A20 is vertically penetrated downwards from the top of the cantilever section 19a of the pile body 10 through the bottom of the embedded section 19b of the pile body 10 and extends along the direction of the embedded section 19 b; in the embodiment, two prestressed anchor cables a are provided, namely a prestressed anchor cable a20a and a prestressed anchor cable a20b, and a plurality of prestressed anchor cables a can be provided and uniformly distributed in the scheme; the prestress applied by the prestressed anchor cable a20a provides enough anchoring force for the existing slide-resistant pile body 10, and improves the stress mode of the existing slide-resistant pile body 10.
The setting position of the prestressed anchor cable A20a is as follows: according to the structural stress of the pile body 10 after the soil body before the pile of the existing slide-resistant pile body 10 is excavated, the landslide thrust, the pile length (the cantilever section 19a and the embedded section 19b), the pile section size, the pile body steel bar arrangement, the anchoring force of the existing slide-resistant pile body 10 and the like are considered; meanwhile, the eccentricity AL2 of the prestressed anchor cable A, namely the distance between the hole distribution position 17a and the central axis 15b, the distance AL1 of the prestressed anchor cable A, namely the hole distribution positions (17a and 17b), the length of the free section 21a of the anchor cable, the length of the anchoring section 22a, the number of the steel strands 41, the designed prestress value of the anchor cable and the like are reasonably set.
The cantilever section 19a of the pile body 10 is also provided with a cable-stayed prestressed anchor cable B30a, the lower end of the cable-stayed prestressed anchor cable B30a is anchored in the stable rock-soil body behind the sliding surface 60, the upper end of the cable-stayed prestressed anchor cable B30 is connected with the cantilever section 19a of the pile body 10, and the cable-stayed prestressed anchor cable B30a forms an included angle horizontal plane with the horizontal plane 70; in the embodiment, two prestressed anchor cables B are provided, namely a prestressed anchor cable B30a and a prestressed anchor cable B30B, and a plurality of prestressed anchor cables B can be provided, and the space and the anchoring angle of the prestressed anchor cables B are reasonably set; the maximum stress bending moment of the existing slide-resistant pile body 10 is reduced by applying prestress to the prestressed anchor cable B18a, and the internal force distribution of the pile body 10 is optimized.
The setting position of the prestressed anchor cable B18a is as follows: according to the structural stress of the pile body 10 after the excavation of the soil body in front of the pile of the existing slide-resistant pile body 10, the landslide thrust, the pile length (the cantilever section 19a and the embedded section 19b), the pile section size, the pile body steel bar arrangement, the anchoring force of a pre-stressed anchor cable A20a and the like are considered; meanwhile, the distance BL3 between the prestressed anchor cable B18a and the prestressed anchor cable B30B, namely the hole distribution positions (18a and 18B) and the anchor angle B (theta) are reasonably seta、θa) The length of the free section 31a of the prestressed anchor rope B18a, the length of the anchor section 32a, the number of the strands 41, the designed prestress value of the prestressed anchor rope B18a, and the like.
Furthermore, distribution ribs 11 and stirrups 12 are arranged in the pile body 10, and bending-resistant reinforcing steel bars 13 are arranged on the tension side of the pile body 10;
drilling anchor rope preformed holes A17a for placing vertical prestressed anchor ropes A20a at symmetrical positions of an A-A central axis 15a of a cantilever section 19a of the pile body 10 outside a protective layer of a bending-resistant reinforcing steel bar 13 at the tension side of the pile body 10; the distance A between the prestressed anchor cable A20a and the prestressed anchor cable A20b is L1, and the eccentricity A between the prestressed anchor cable A20a and the prestressed anchor cable A20b and the central axis 15b is L2; vertical prestress can be applied through the prestressed anchor cable A20a, the vertical anchoring force of the existing slide-resistant pile body 10 is effectively enhanced, and the stress mode of the existing slide-resistant pile body 10 is improved.
Further, in the pile body 10A stayed anchor cable preformed hole B18a for placing a stayed prestressed anchor cable B30a is drilled at the central axis 16 of the front side of the pile body, which is at a position of the cantilever section 19a not smaller than 300mm away from the top of the pile top; wherein the prestressed anchorage cable B30a forms an included angle theta with the horizontal plane 70aIs an anchoring angle; the angle theta formed by the prestressed anchor cable B30B and the horizontal plane 70bIs an anchoring angle; by applying oblique prestress to the pre-stressed anchor cable B30a and the pre-stressed anchor cable B30B, the bending strength of the existing slide-resistant pile body 10 is effectively enhanced, and the internal force distribution of the existing slide-resistant pile body 10 is optimized; meanwhile, the prestressed anchor cable A20a and the prestressed anchor cable B30a are additionally arranged on the existing slide-resistant pile body 10, so that the existing slide-resistant pile body 10 can be enhanced, improved and optimized in structural stress, the slide-resistant effect of the existing slide-resistant pile body 10 is fully exerted, temporary support measures for slope toe expanding excavation are reduced, and the engineering investment is greatly saved.
Further, one or more anchor cable preformed holes a17a are arranged on the top of the cantilever section 19a of the pile body 10; the vertical prestressed anchor cable A20a consists of a fastening head, a free section and an anchoring section, wherein the fastening head consists of a cement anchor pier 44, a steel backing plate 43 and an anchorage device 40; and a plastic gasket 45 is arranged between the cement anchor pier 44 and the pile body 10.
Further, one or more anchor cable preformed holes B18a are arranged on the central axis 16 of the front side of the pile body at the position, which is not smaller than 300mm away from the top of the pile top, of the cantilever section 19a of the pile body 10; the cable-stayed prestressed anchor cable B30a consists of a fastening head, a free section and an anchoring section, wherein the fastening head consists of a cement anchor pier 44, a steel backing plate 43 and an anchorage device 40; and a plastic gasket 45 is arranged between the cement anchor pier 44 and the pile body 10.
Further, the plastic gasket 45 is a rubber gasket or a nylon gasket with the thickness of 30mm, and the boundary size of the plastic gasket 45 is 50mm larger than that of the cement anchor block 44.
In the existing prestressed anchor cable construction, because the existing anti-slide pile body 10 is constructed for years, the concrete on the surface layer part of the pile body 10 may be corroded, aged and uneven, when the prestressed anchor cable is added in the later period, in order to prevent the cement anchor pier 44 from generating rigid contact with the pile body 10, the surface concrete is cracked after the prestress of the prestressed anchor cable A20a or the prestressed anchor cable B30a is applied, so that the anchor cable generates prestress loss and the structure safety is influenced; therefore, in the scheme, a rubber gasket or a nylon gasket with the thickness of 30mm is independently arranged between the pile body 10 of the existing slide-resistant pile and the cement anchor pier 44, and the boundary size of the rubber gasket or the nylon gasket is 50mm larger than that of the cement anchor pier 44; the structure can provide enough deformation space for the concrete contact surface of the existing slide-resistant pile body 10 when being pressed, so that the slide-resistant pile body 10 is stressed uniformly and deforms and is coordinated, the surface concrete of the existing slide-resistant pile body 10 is protected from cracking and damage, a steel bar protective layer of the slide-resistant pile body 10 is protected, the prestress loss of an anchor rope is reduced, and the structural safety degree is improved.
Furthermore, the prestressed anchor cable A20a and the prestressed anchor cable B30a both adopt 4-8 strands of steel stranded wires 41, and the same anchoring tension is designed; the prestressed anchor cable A20a is divided into an anchoring section A22 a and a free section A21 a; the anchoring section A22 a is an anchoring section anchored in a stable rock-soil body below the sliding surface 60, the free section A21 a is the distance length from the top of the prestressed anchor cable A20a to the pile bottom of the existing slide-resistant pile body 10, which is plus 500mm, namely the free section A21 a of the prestressed anchor cable A20a extends into the pile bottom of the existing slide-resistant pile body 10 and is not less than 500 mm; the prestressed anchor cable B30a is divided into an anchoring section B32 a and a free section B31a, wherein the anchoring section B32 a is an anchoring section anchored in a stable rock-soil body behind the sliding surface 60; the free section B31a is the distance length +1000mm from the top of the prestressed anchor cable B30a to the sliding surface 60, namely the distance that the free section B31a of the prestressed anchor cable B30a extends into the sliding surface 60 is not less than 1000 mm; the prestressed anchor cable B30a and the prestressed anchor cable B30B keep a certain distance BL3 and an anchor angle thetaaAnd an anchor angle thetabHolding thetaa≤θbTo reduce the group anchor effect.
Wherein, the distance between L3 is preferably 3-6 m, and the minimum distance is not less than 1.5 m. The included angle between the prestressed anchor cable B30a and the horizontal plane 70 is preferably lower, should not be greater than 45 degrees, and is preferably 15-30 degrees.
The utility model discloses a theory of operation, including following step:
s1: collecting a structural design drawing and a completion drawing of an existing slide-resistant pile body 10 in a construction stage, wherein the two structural design drawings and the completion drawing in the construction stage include but are not limited to collection of drawings of a pile body structure, design reinforcement, steel bar arrangement and the like; detecting the structure and the steel bars of the existing slide-resistant pile body 10 by using a steel bar detector through an electromagnetic induction method, wherein the positions of the steel bars, the thickness of a protective layer and the diameter of the steel bars in a concrete structure or a component are detected, or the number, the trend, the distribution and the like of the detected steel bars are detected;
s2: according to the detection result of the steel bar detector, outside the protective layer of the bending-resistant steel bar 13 on the tension side 14 of the pile body 10, drilling an anchor rope preformed hole A17a for embedding the prestressed anchor rope A20a by using a concrete drilling and core-taking machine according to the symmetrical position of an A-A central axis 15a at the top of a cantilever section 19b of the pile body 10, wherein the drilling position should avoid the steel bar position (including the concrete protective layer), and the drilling position needs to be symmetrical and reasonably set the drilling eccentricity, the spacing, the aperture size and the like; after the anchor cable preformed hole A17a is drilled, the guide pipe 42 is adopted to follow up to complete the subsequent drilling in rock and soil mass;
s3: when the prestressed anchor cable A20a is buried, in order to enable the pile body 10 structure of the existing slide-resistant pile to be stressed reasonably, total tension is respectively and alternately applied to the prestressed anchor cable A20a (the total tension is design tension and anchor cable prestress loss over-tension), wherein the total tension is respectively and alternately applied to the prestressed anchor cable A20a according to 50%, 70% and 100% (a free section is positioned in the pile body, and prestress loss over-tension is considered to be 10% -15%);
s4: finally, cutting off the steel strand 41 outside the anchorage device 40, reserving the exposed length of 120mm, and sealing the prestressed anchor cable A20a by using C30 concrete with the thickness of 200mm as a cement anchor pier 44;
s5: according to the detection result of the steel bar detector, drilling and placing an anchor rope preformed hole B18a drilled by a concrete drilling and core-taking machine and used for embedding the prestressed anchor rope B30a at the central axis 16 of the front side of the pile body at the position, not smaller than 300mm away from the top of the pile top, of the cantilever section 19a of the pile body 10, wherein the drilling position should avoid the position of the steel bar (including a concrete protective layer), and the drilling interval, the anchoring angle, the aperture size and the like are reasonably set;
s6: similarly, when the prestressed anchor cable B30a is buried, in order to enable the pile body 10 structure of the existing slide-resistant pile to be stressed reasonably, total tension is applied to the prestressed anchor cable B30a in turn, wherein the total tension is applied to the prestressed anchor cable B30a in turn according to 50%, 70% and 100% respectively, (when the free section is a rock stratum, the prestressed loss is considered to be over-tensioned by 10% -15%, and when the free section is a soil stratum, the prestressed loss is considered to be over-tensioned by 10% -20%);
s7: finally, cutting off the steel strand 41 outside the anchorage device 40, reserving the exposed length of 120mm, and sealing the prestressed anchor cable B30a by using C30 concrete with the thickness of 200mm as a cement anchor pier 44;
s8: after the construction of adding the prestressed anchor cable A20a and the prestressed anchor cable B30a on the existing slide-resistant pile body 10 is completed, the residual soil body in front of the pile body is excavated according to the road extension requirement, and the pre-pile or inter-pile empty face protection body 50 is made in time.
Further, the pre-pile or inter-pile face shield 50 includes a retaining wall, an inter-pile retaining plate, or an inter-pile soil nailing wall provided in front of or between the piles.
The above-mentioned embodiments, further detailed description of the objects, technical solutions and advantages of the present invention, it should be understood that the above description is only the embodiments of the present invention, and is not intended to limit the scope of the present invention, and any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the scope of the present invention.

Claims (7)

1. A combined anti-sliding structure with an existing pile additionally provided with a prestressed anchor cable comprises an existing anti-sliding pile body (10), wherein the pile body (10) is divided into a cantilever section (19a) and an embedded section (19b), and the embedded section (19b) is embedded and fixed in a stable rock-soil body below a sliding surface (60);
the pile is characterized in that a vertical prestressed anchor cable A (20a) is arranged on the top of the cantilever section (19a) of the pile body (10), the upper end of the vertical prestressed anchor cable A (20a) is connected with the top of the cantilever section (19a) of the pile body (10), and the lower end of the vertical prestressed anchor cable A (20a) vertically penetrates through the bottom of the embedded section (19b) of the pile body (10) from the top of the cantilever section (19a) of the pile body (10) downwards and extends along the direction of the embedded section (19 b);
and a cable-stayed prestressed anchor cable B (30a) is also arranged on the cantilever section (19a) of the pile body (10), the lower end of the cable-stayed prestressed anchor cable B (30a) is anchored in the stable rock-soil body behind the sliding surface (60), the upper end of the cable-stayed prestressed anchor cable B (30a) is connected with the cantilever section (19a) of the pile body (10), and an included angle theta is formed between the cable-stayed prestressed anchor cable B (30a) and the horizontal plane (70).
2. The combined anti-sliding structure of the existing pile added with the prestressed anchor cable according to claim 1, characterized in that a distribution rib (11) and a stirrup (12) are arranged in the pile body (10), and a bending-resistant reinforcing steel bar (13) is arranged on the tension side (14) of the pile body (10);
and drilling anchor rope preformed holes A (17a) for placing the vertical prestressed anchor ropes A (20a) at the symmetrical positions of the central axis (15a) of the cantilever section (19a) of the pile body (10) outside the protective layer of the bending-resistant reinforcing steel bars (13) at the tension side (14) of the pile body (10).
3. The combined structure of an existing pile with an additional prestressed anchor cable of claim 2 is characterized in that one or more anchor cable preformed holes A (17a) are arranged on the top of the cantilever section (19a) of the pile body (10);
the vertical prestressed anchor cable A (20a) consists of a fastening head, a free section and an anchoring section, wherein the fastening head consists of a cement anchor pier (44), a steel base plate (43) and an anchorage device (40);
and a plastic gasket (45) is arranged between the cement anchor pier (44) and the pile body (10).
4. The combined anti-sliding structure of the existing pile added with the prestressed anchor cable according to claim 1, wherein a stay anchor cable reserved hole B (18a) for placing the stay prestressed anchor cable B (30a) is drilled at the central axis (16) of the front side of the pile body at the position where the distance between the cantilever section (19a) of the pile body (10) and the top of the pile top is not less than 300 mm.
5. The combined anti-sliding structure of the existing pile with the additional pre-stressed anchor cables according to claim 4, characterized in that one or more anchor cable reserved holes B (18a) are arranged at the central axis (16) of the front side of the pile body, which is located at a position where the distance between the cantilever section (19a) of the pile body (10) and the top of the pile top is not less than 300 mm;
the cable-stayed prestressed anchor cable B (30a) consists of a fastening head, a free section and an anchoring section, wherein the fastening head consists of a cement anchor pier (44), a steel backing plate (43) and an anchorage device (40);
and a plastic gasket (45) is arranged between the cement anchor pier (44) and the pile body (10).
6. The combined antiskid structure of the prestressed anchor cable added to the existing pile according to any one of claims 3 or 5, wherein the plastic gasket (45) is a rubber gasket or a nylon gasket with a layer thickness of 30mm, and the boundary size of the plastic gasket (45) is 50mm larger than that of the cement anchor block (44).
7. The combined anti-sliding structure of the pre-stressed anchor cable added to the existing pile according to claim 1, wherein the pre-stressed anchor cable A (20a) and the pre-stressed anchor cable B (30a) are each 4-8 strands of steel strands (41);
the prestressed anchor cable A (20a) is divided into an anchoring section A (22a) and a free section A (21 a); the anchoring section A (22a) is an anchoring section anchored in a stable rock-soil body below the pile body (10), and the free section A (21a) is the distance length from the top of a prestressed anchor cable A (20a) to the pile bottom of the pile body (10) plus 500 mm;
the prestressed anchor cable B (30a) is divided into an anchoring section B (32a) and a free section B (31a), wherein the anchoring section B (32a) is an anchoring section anchored in a stable rock-soil body behind the sliding surface (60), and the free section B (31a) is the distance length +1000mm from the top of the prestressed anchor cable B (30a) to the sliding surface (60).
CN202021670336.6U 2020-08-12 2020-08-12 Combined anti-sliding structure with prestressed anchor cables additionally arranged on existing piles Active CN212248295U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021670336.6U CN212248295U (en) 2020-08-12 2020-08-12 Combined anti-sliding structure with prestressed anchor cables additionally arranged on existing piles

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021670336.6U CN212248295U (en) 2020-08-12 2020-08-12 Combined anti-sliding structure with prestressed anchor cables additionally arranged on existing piles

Publications (1)

Publication Number Publication Date
CN212248295U true CN212248295U (en) 2020-12-29

Family

ID=73981556

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021670336.6U Active CN212248295U (en) 2020-08-12 2020-08-12 Combined anti-sliding structure with prestressed anchor cables additionally arranged on existing piles

Country Status (1)

Country Link
CN (1) CN212248295U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113605411A (en) * 2021-07-20 2021-11-05 重庆交通大学 Slope combined reinforcing structure and slope reinforcing construction method
CN114922017A (en) * 2022-01-17 2022-08-19 兰州交通大学 Newly-built cantilever type retaining wall-existing pile sheet wall roadbed slope wide integrated configuration

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113605411A (en) * 2021-07-20 2021-11-05 重庆交通大学 Slope combined reinforcing structure and slope reinforcing construction method
CN114922017A (en) * 2022-01-17 2022-08-19 兰州交通大学 Newly-built cantilever type retaining wall-existing pile sheet wall roadbed slope wide integrated configuration
CN114922017B (en) * 2022-01-17 2024-02-06 兰州交通大学 Newly-built cantilever type retaining wall-existing stake board wall roadbed group wide integrated configuration

Similar Documents

Publication Publication Date Title
CN203741868U (en) Reinforced concrete retaining wall structure with combined anchor wire
CN212248295U (en) Combined anti-sliding structure with prestressed anchor cables additionally arranged on existing piles
CN105274922B (en) A kind of antiskid key steel-pipe pile composite construction and method for repairing landslide roadbed
CN110820763A (en) Truss type cast-in-situ bored pile supporting method for mucky soil deep foundation pit
CN109930609A (en) A kind of campshed composite supporting construction and its construction method for upper-soft lower-hard ground
CN106702840A (en) Anchored pile reinforced earth retaining wall embankment for treating shoreside soft soil roadbed
CN106968245A (en) The uplift pile of prestress anchorage cable manually digging hole and its construction method
CN112301887A (en) Suspension bridge main cable anchoring system under bedrock deep-buried condition and construction method
CN105887948B (en) A kind of friction pile, which is tilted, resets correction and reinforcement means
CN109898521A (en) A kind of anchored pile supporting and construction method for foundation pit external corner
CN111827316A (en) Combined anti-sliding structure with prestressed anchor cables additionally arranged on existing pile and construction method
CN212129160U (en) Oblique-pulling foundation pit supporting structure for pile top
CN211816193U (en) Anchor draws formula steel sheet pile supporting construction
CN205954636U (en) Prestressing force steel sheet pile supporting construction
CN213773384U (en) Deep basal pit side slope protection reinforcing bar net fixing device
CN206477204U (en) Punish the soft soil roadbed pull-type pile reinforced earth barricade embankment of anchor in bank
CN105256809B (en) A kind of utilization prestressing force H profile steel supporting construction carries out the construction method of supporting
CN210288408U (en) Foundation pit supporting structure
CN108951618B (en) Pile anchor supporting device
CN109056717B (en) Support-free supporting device and construction method thereof
CN213539004U (en) Novel structure for preventing and treating landslide
CN220565238U (en) Pile anchor and inner support combined supporting system suitable for large-height-difference deep foundation pit
CN115094922B (en) Slope foundation integrated foundation and construction process thereof
CN205954635U (en) Prestressing force H shaped steel supporting construction
CN213925867U (en) Suspension bridge main cable anchoring system under bedrock deep-buried condition

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant