CN212246004U - Crane ship - Google Patents

Crane ship Download PDF

Info

Publication number
CN212246004U
CN212246004U CN202021464474.9U CN202021464474U CN212246004U CN 212246004 U CN212246004 U CN 212246004U CN 202021464474 U CN202021464474 U CN 202021464474U CN 212246004 U CN212246004 U CN 212246004U
Authority
CN
China
Prior art keywords
crane
area
deck
ship
load operation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202021464474.9U
Other languages
Chinese (zh)
Inventor
逯鹏
赵胜国
袁新勇
张清涛
宋云峰
郭小亮
鲁成林
谢锦婷
王怀明
孔德煌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huadian Heavy Industries Co Ltd
Original Assignee
Huadian Heavy Industries Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huadian Heavy Industries Co Ltd filed Critical Huadian Heavy Industries Co Ltd
Priority to CN202021464474.9U priority Critical patent/CN212246004U/en
Application granted granted Critical
Publication of CN212246004U publication Critical patent/CN212246004U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Jib Cranes (AREA)

Abstract

The utility model discloses a crane ship, this crane ship includes: a hull; a deck provided on the hull; the crane is arranged at the middle position of the deck and close to the side of the ship; the deck is divided into a heavy-load operation area and a light-load operation area according to a hoisting weight curve of the crane, and the heavy-load operation area and the light-load operation area are suitable for placing offshore operation materials. According to the arrangement, the crane is arranged at the middle position of the deck and close to the ship board, and then the operation deck can be divided into a heavy-load operation area, a light-load operation area and a chord outer operation area which can be covered, so that the 360-degree full-rotation performance of the crane can be fully utilized during offshore operation, and the areas of the heavy-load operation area and the light-load operation area are increased by more than 80%. In addition, enough offshore operation materials can be stored in the crane ship, and when the offshore operation materials are in short supply, the crane ship does not need to wait at the sea, so that the standby cost is reduced.

Description

Crane ship
Technical Field
The utility model relates to an offshore operation technical field, concretely relates to crane ship.
Background
The offshore wind power industry in China goes through the golden stage from the beginning to the rapid development, and further goes from the shallow and near sea areas of the yellow sea and the east sea to the deep and far sea areas of the south sea. During offshore operations, it is necessary to load and unload offshore operation materials, such as: single piles, steel piles, jacket and the like.
Due to the large weight of the offshore working materials, higher demands are made on the center of gravity and the weight of the required main working crane vessel. In the prior art, as shown in fig. 6, the general arrangement principle of the main working crane ship is: the stern or the bow is arranged with a certain operation area, and the other end of the hull is arranged on a living building.
However, the crane ship itself has the following problems: because the full-rotation crane is arranged at the stern or the bow, the crane ship is easy to have unstable gravity center when the full-rotation crane lifts offshore operation materials for loading and unloading. Further, since the area of the heavy-duty working area of the crane ship is excessively small due to the installation of the full-swing crane at the stern or the bow, the crane ship cannot store marine working materials such as the single piles, the steel piles, and the jacket, and thus the marine working materials need to be transported to the marine working area by other ships. When the shortage of offshore work materials occurs, the crane ship waits at sea, thereby generating standby cost, resulting in a great increase in cost.
SUMMERY OF THE UTILITY MODEL
Therefore, the utility model discloses the heavy load operation district area that the technical problem that solves lies in the crane ship that exists among the prior art is little for the crane ship can not deposit the problem of marine operation materials such as single pile, piling bar and jacket basically. Thereby providing a crane vessel.
In order to achieve the above object, an embodiment of the present invention provides a crane ship, which includes: a hull; a deck provided on the hull; the crane is arranged at the middle position of the deck and close to the side of the ship; the deck is divided into a heavy-load operation area and a light-load operation area according to a hoisting weight curve of the crane, and the heavy-load operation area and the light-load operation area are suitable for placing offshore operation materials.
Optionally, the marine work material comprises steel piles, jackets and mono-piles.
Optionally, when the marine work material is a monopile, the monopile is placed in the direction of the centerline of the hull, and the center of gravity of the monopile is located in the heavy-duty work area.
Optionally, when the marine work material is the steel pile, the steel pile is placed along the centerline direction of the hull, and the center of gravity of the steel pile is located in the light-load work area or the heavy-load work area.
Optionally, when the marine work material is the jacket, the jacket is placed evenly on the deck in the direction of the centerline of the hull.
Optionally, the crane base is 16M-22M in size.
Optionally, the blind area radius of the crane is 15M-20M.
Optionally, the radius of the heavy-load working area of the crane is 20M-40M.
Optionally, the radius of the light load operation area of the crane is 40M-60M.
Optionally, the deck is provided with a tool storage area and a facility storage area on both sides of the crane, respectively.
Compared with the prior art, the utility model, have following advantage:
1. an embodiment of the utility model provides a crane ship, this crane ship includes: a hull; a deck provided on the hull; the crane is arranged at the middle position of the deck and close to the side of the ship; the deck is divided into a heavy-load operation area and a light-load operation area according to the operation range of the crane, and the heavy-load operation area and the light-load operation area are suitable for placing offshore operation materials.
According to the arrangement, the crane is arranged at the middle position of the deck and close to the ship board, and then the operation deck can be divided into a heavy-load operation area, a light-load operation area and a chord outer operation area which can be covered, so that the 360-degree full-rotation performance of the crane can be fully utilized during offshore operation, and the areas of the heavy-load operation area and the light-load operation area are increased by more than 80%. In addition, enough offshore operation materials such as single piles, steel piles and jacket can be stored in the crane ship, and when the offshore operation materials such as the single piles, the steel piles and the jacket are in short supply, the crane ship does not need to wait at the sea, so that the standby cost is reduced. Meanwhile, when the large arm of the crane is in a rest working condition, the crane occupies a small space, and offshore operation materials are stacked in a vertical space.
2. When the offshore operation material is the single pile, the crane can directly rotate the single 1600-plus 1800-t single pile on the transport ship stopped in the extrachord operation area by 360-degree full rotation performance to be refuted onto the deck, the single pile is placed along the center line direction of the ship body, the center of gravity of the single pile is located in the heavy load operation area, and the operation is simple and efficient. Meanwhile, the single pile can be directly turned over after being lifted, and the operation efficiency is improved.
3. When the marine operation material is the piling bar, place on the central line direction of piling bar along the hull, the focus position of piling bar is located the light load operation district or the heavy load operation district, so set up for can directly put on the deck with the pile sinking location equipment of piling bar cooperation operation and do not receive the influence of loop wheel machine davit rest condition, can improve the pile sinking location equipment daily overhaul efficiency simultaneously. And by adopting the placing mode, 12-18 steel piles can be piled on the deck, so that the offshore operation efficiency is improved.
4. When the offshore operation material is the jacket, the jacket stopped on the transport ship in the extrastring operation area can be directly rotated 180 degrees to be refuted to the stacking area of the lifting ship by utilizing the 360-degree full rotation performance, and the jacket is uniformly placed on the deck along the center line direction of the ship body. Meanwhile, the jacket can be directly installed, and the operation is simple and efficient. Meanwhile, the crane ship can be used as a three-in-one ship for jacket transportation, stockpiling and installation, and the applicability of the crane ship is improved.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below, and obviously, the drawings in the following description are some embodiments of the present invention, and for a worker in the field, without creative efforts, other drawings can be obtained according to the drawings.
Fig. 1 is a top view of a crane ship deck according to an embodiment of the present invention;
FIG. 2 is a top view of a deck with single piles in place according to an embodiment of the present invention;
FIG. 3 is a top view of a deck with steel piles according to an embodiment of the present invention;
FIG. 4 is a top view of a deck with jacket positioned according to an embodiment of the present invention;
FIG. 5 is a front view of a deck of an embodiment of the present invention in place of a jacket;
fig. 6 shows the arrangement position of the crane in the prior art.
Reference numerals:
1, a ship body; 11-deck; 111-blind area; 112-heavy load operation area; 113-light load operation area; 114-can cover the working area; 115-extrachord operating area; 116-a tool storage area; 117-facility storage area;
2-hoisting machine; 21-crane base; 3-single pile; 4-steel piles; 5-jacket.
Detailed Description
The technical solution of the present invention will be described clearly and completely with reference to the accompanying drawings, and obviously, the described embodiments are some, but not all embodiments of the present invention. Based on the embodiments in the present invention, all other embodiments obtained by ordinary workers in the field without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; the two elements may be directly connected or indirectly connected through an intermediate medium, or may be communicated with each other inside the two elements, or may be wirelessly connected or wired connected. The specific meaning of the above terms in the present invention can be understood in specific cases for ordinary workers in the art.
Furthermore, the technical features mentioned in the different embodiments of the invention described below can be combined with each other as long as they do not conflict with each other.
The offshore wind power industry in China goes through the golden stage from the beginning to the rapid development, and further goes from the shallow and near sea areas of the yellow sea and the east sea to the deep and far sea areas of the south sea. During offshore operations, it is necessary to load and unload offshore operation materials, such as: single piles, steel piles, jacket and the like. Due to the large weight of the offshore working materials, higher demands are made on the center of gravity and the weight of the required main working crane vessel. In the prior art, the general arrangement principle of a main operation crane ship is as follows: the stern or the bow is arranged with a certain operation area, and the other end of the hull is arranged on a living building. However, the crane ship itself has the following problems: because the full-rotation crane is arranged at the stern or the bow, the crane ship is easy to have unstable gravity center when the full-rotation crane lifts offshore operation materials for loading and unloading. Further, since the area of the heavy-duty working area of the crane ship is excessively small due to the installation of the full-swing crane at the stern or the bow, the crane ship cannot store marine working materials such as the single piles, the steel piles, and the jacket, and thus the marine working materials need to be transported to the marine working area by other ships. When the shortage of offshore work materials occurs, the crane ship waits at sea, thereby generating standby cost, resulting in a great increase in cost. The utility model provides a pair of the heavy load operation district area that the crane ship can solve the crane ship that exists among the prior art is little for the crane ship can not deposit the problem of marine operation materials such as single pile, piling bar and jacket basically.
Example 1
As shown in fig. 1 to 5, an embodiment of the present invention provides a crane ship, including: hull 1, deck 11 and crane 2.
The deck 11 is provided on the hull 1, and the crane 2 is provided at a middle position of the deck 11 and near the side of the ship. According to the hanging weight curve of the crane 2, the deck 11 is divided into a heavy load operation area 112 and a light load operation area 113, and the heavy load operation area 112 and the light load operation area 113 are used for placing offshore operation materials. The marine work material may be steel piles 4, jacket 5, mono-piles 3, etc. The hoisting weight curve reflects the normal load that the hook of the crane 2 can hoist from the center of the crane.
When the ranges of the heavy load operation area 112 and the light load operation area 113 are divided, the radius of the heavy load operation area 112 may be 20M to 40M. The radius of the light load working area 113 may be 40M to 60M. Of course, a person skilled in the art can divide the radius of the heavy load operation area 112 and the radius of the light load operation area 113 according to actual situations, and this embodiment is merely illustrative and not limited, and it is sufficient to ensure the normal operation of the crane 2 and the stability of the crane ship.
As shown in fig. 6, the crane 2 is installed at the bow or stern of the ship in the conventional art, and the area covered by the deck 11 in the heavy load work area 112 and the light load work area 113 in the conventional art is small in accordance with the hoisting curve of the crane 2. The crane 2 is arranged at the middle position of the deck 11 and close to the side of the ship, so that the coverage area of the heavy-load operation area 112 and the light-load operation area 113 on the deck is larger, and through data statistics, the coverage area of the heavy-load operation area 112 and the coverage area of the light-load operation area 113 are correspondingly increased by more than 80%.
With the arrangement, the crane 2 is arranged at the middle position of the deck 11 and close to the ship board, and then the operation deck 11 can be divided into the heavy-load operation area 112, the light-load operation area 113, the coverable operation area 114 and the chord external operation area 115 according to the lifting weight curve of the crane 2, so that the 360-degree full-rotation performance of the crane 2 can be fully utilized during offshore operation, and the areas of the heavy-load operation area 112 and the light-load operation area 113 are increased by more than 80%. In addition, enough construction materials such as the steel piles 4 and the jacket 5 can be stored in the crane ship, and when the steel piles 4 or the jacket 5 are in shortage, the crane ship does not need to wait at sea, so that the standby cost is reduced. Meanwhile, when the large arm of the crane 2 is in a rest working condition, the crane 2 occupies a small space, and the piling of offshore operation materials in a vertical space is facilitated.
The deck 11 may be provided with a tool storage area 116 and a facility storage area 117 on either side of the crane 2 as the case may be. The tool storage area 116 is used for storing tools such as hydraulic hammers, vibratory hammers, rigging tools and the like, and the facility storage area 117 is used for storing facilities such as inner/outer platforms, sailing, climbing stairs and the like. The embodiment is merely an example, and is not limited thereto, and those skilled in the art may divide the remaining area of the deck 11 according to actual situations, and may effectively utilize the area of the deck 11.
This embodiment will explain three cases of the mono-pile 3, the steel pile 4, and the jacket 5.
As shown in fig. 2, when the offshore operation material is the mono-pile 3, the crane 2 can directly rotate the mono-pile 3 of 1600-. Meanwhile, the single pile 3 can be directly turned over after being lifted, and the operation efficiency is improved. A tool storage area 116 and a facility storage area 117 are respectively arranged on two sides of the crane 2, the tool storage area 116 is used for storing tools such as a hydraulic hammer, a vibration hammer and a sling, and the facility storage area 117 is used for storing facilities such as an inner/outer platform, a ship, a ladder and the like. In this way, the area of the deck 11 can be fully utilized.
As shown in fig. 3, when the marine work material is the steel pile 4, the steel pile 4 is placed along the center line direction of the hull 1, and the center of gravity of the steel pile 4 is located in the light load work area 113 or the heavy load work area 112. A tool storage area 116 and a facility storage area 117 are respectively arranged on two sides of the crane 2, the tool storage area 116 is used for storing tools such as a hydraulic hammer, a vibration hammer and a sling, and the facility storage area 117 is used for storing a pile sinking positioning frame. So set up for can directly put on deck 11 and do not receive 2 davit rest condition's of loop wheel machine influence with 4 cooperation operations's of piling bar pile locating rack, can improve the daily maintenance efficiency of pile sinking location equipment simultaneously. And by adopting the placing mode, 12-18 steel piles 4 can be piled on the deck 11, thereby improving the offshore operation efficiency.
As shown in fig. 4 and 5, when the offshore operation material is the jacket 5, the jacket 5 stopped on the transport ship in the extrastring operation area 115 can be directly rotated 180 ° to be refuted to the crane ship stacking area by using the 360 ° full-swing performance, and the jacket 5 is uniformly placed on the deck 11 along the center line direction of the hull 1. Meanwhile, the jacket 5 can be directly installed, and the operation is simple and efficient. Meanwhile, the jacket can be used as a three-in-one ship for transporting, stockpiling and installing the jacket 5, and the applicability of the crane ship is improved.
Of course, the present embodiment is only to illustrate the type of the offshore operation material, and is not limited thereto, and a person skilled in the art may divide the operation area of the deck 11 differently according to different offshore operation materials according to actual situations, so as to ensure the stability of the crane ship during operation. Thus, the arrangement of the deck 11 is more flexible, and the requirements of offshore operation in various basic forms can be met.
Optionally, in some embodiments of the present invention, the size of the crane base 21 is 16M-20M, and the radius of the blind area 111 of the crane 2 is 15M-20M.
A coverable working area 114 is further defined on deck 11, and an extrachord working area 115 is further defined in the offshore area outside the crane ship. The skilled person can divide the working area that can cover the working area 114 and the extrachord working area 115 according to actual conditions, and can ensure the normal operation of the crane 2 and the stability of the crane ship.
It should be understood that the above examples are only for clarity of illustration and are not intended to limit the embodiments. Variations and modifications in other variations may occur to those skilled in the art based upon the foregoing description. And are neither required nor exhaustive of all embodiments. And obvious variations or modifications can be made without departing from the scope of the invention.

Claims (10)

1. A crane vessel, comprising:
a hull (1);
a deck (11) provided to the hull (1);
the crane (2) is arranged at the middle position of the deck (11) and is close to the side of the ship;
the deck (11) is divided into a heavy-load operation area (112) and a light-load operation area (113) according to a hanging weight curve of the crane (2), and the heavy-load operation area (112) and the light-load operation area (113) are suitable for placing offshore operation materials.
2. Crane vessel according to claim 1, wherein the marine work material comprises steel piles (4), jacket (5) and mono-piles (3).
3. Crane vessel according to claim 2, wherein when the offshore construction material is the monopile (3), the monopile (3) is placed in the direction of the centre line of the hull (1), the centre of gravity of the monopile (3) being located in the heavy load working area (112).
4. Crane vessel according to claim 2, wherein when the marine work material is the steel pile (4), the steel pile (4) is placed in the direction of the centre line of the hull (1), and the position of the centre of gravity of the steel pile (4) is located in the light load working area (113) or the heavy load working area (112).
5. Crane vessel according to claim 2, wherein when the marine work material is the jacket (5), the jacket (5) is placed evenly on the deck (11) in the direction of the centre line of the hull (1).
6. Crane vessel according to any one of claims 1 to 5, characterised in that the crane base (21) of the crane (2) has dimensions of 16M-22M.
7. Crane vessel according to any of claims 1 to 5, characterised in that the blind area (111) of the crane (2) has a radius of 15M-20M.
8. Crane vessel according to one of claims 1 to 5, characterised in that the heavy-duty working area (112) has a radius of 20M-40M.
9. Crane vessel according to one of claims 1 to 5, characterised in that the light load working area (113) has a radius of 40M-60M.
10. Crane vessel according to one of claims 1 to 5, characterised in that the deck (11) is provided with a tool storage area (116) and a facility storage area (117) on each side of the crane (2).
CN202021464474.9U 2020-07-22 2020-07-22 Crane ship Active CN212246004U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202021464474.9U CN212246004U (en) 2020-07-22 2020-07-22 Crane ship

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202021464474.9U CN212246004U (en) 2020-07-22 2020-07-22 Crane ship

Publications (1)

Publication Number Publication Date
CN212246004U true CN212246004U (en) 2020-12-29

Family

ID=73979825

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202021464474.9U Active CN212246004U (en) 2020-07-22 2020-07-22 Crane ship

Country Status (1)

Country Link
CN (1) CN212246004U (en)

Similar Documents

Publication Publication Date Title
US10894701B2 (en) Crane, vessel comprising such a crane, and a method for up-ending a longitudinal structure
JP6113832B2 (en) A system for loading and unloading during port operations, comprising a crane and a base installed on the crane body that supports and stacks the hatch cover
JP2004001750A (en) Special working ship and execution method for offshore structure
WO2012066790A1 (en) Ship for installing offshore wind turbines, and method for installing offshore wind turbines using same
CN212246004U (en) Crane ship
CN202169997U (en) Heavy lift vessel with door-shaped trusses
CN111717339A (en) Crane ship
CN206142022U (en) Steel tray is used in submarine cable transportation
CN112455613A (en) Logistics support floating base for open sea oil and gas resource development
CN205365980U (en) Small -size buoy tender bilge distribution structure
CN111017695A (en) Process for hoisting large ship block by matching crawler crane with hoisting system
CN102587340A (en) Installation platform of bottom-supported fan and method for installing fan equipment
CN212890798U (en) Moon pool, ocean engineering ship and ocean engineering platform
CN209816667U (en) Lifting lug structure for integral hoisting of anti-collision steel bushing box
JP5705482B2 (en) Crane and ship
CN203652078U (en) Offshore wind turbine installation vessel having offshore platform service function
CN219906802U (en) Temporary fixing device for offshore hoisting
CN214648893U (en) Floating base for logistics support
CN111337281A (en) Method for heavy-load test of semi-submersible type hoisting and disassembling platform
CN213442970U (en) Assembled crane for container ship
CN219096938U (en) A construction ship for installation of marine photovoltaic module
CN216425153U (en) Formula detritus case can be put to intussusception
CN215361767U (en) Offshore wind power transportation device
CN221235124U (en) Lake mud taking lifting and transporting platform
CN212269279U (en) Crane ship

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant