CN212104093U - Pile driving and holding ship on water - Google Patents
Pile driving and holding ship on water Download PDFInfo
- Publication number
- CN212104093U CN212104093U CN202020660041.4U CN202020660041U CN212104093U CN 212104093 U CN212104093 U CN 212104093U CN 202020660041 U CN202020660041 U CN 202020660041U CN 212104093 U CN212104093 U CN 212104093U
- Authority
- CN
- China
- Prior art keywords
- pile
- longkou
- hull
- guide rail
- displacement drive
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
Abstract
The utility model discloses a pile embracing ship of piling on water belongs to construction technical field on water, pile embracing ship on water, including hull and longkou, the longkou sets up on the hull, still includes guide rail, pile embracing device and longkou displacement drive arrangement, guide rail and longkou displacement drive arrangement all set up on the hull, and longkou displacement drive arrangement is connected with the longkou, guide rail one end extends to outside the hull, pile embracing device sets up on the guide rail, longkou displacement drive arrangement's direction of drive is on a parallel with the upper surface of hull, and is perpendicular with the guide rail direction. Two auxiliary positioning devices are arranged on the stern of the ship body, and the two auxiliary positioning devices and the pile embracing device form a triangle. The utility model discloses a pile embracing device and longkou displacement drive device carry out the accurate positioning to precast tubular pile, and the degree of accuracy of location is higher than to fix a position through removing the hull among the prior art far away, and fixes a position simply, and is very convenient, and labour saving and time saving can improve the efficiency of construction, guarantees construction quality.
Description
Technical Field
The utility model relates to a construction technical field on water, concretely relates to pile embracing ship drives piles on water.
Background
With the development of the building industry, the temporary water project and the water project are more and more appeared in the engineering construction, the precast tubular pile is used as a foundation pile, has the advantages of high concrete strength of a pile body, strong penetration capacity, strong bearing capacity of a single pile and the like, and is commonly used for the supporting foundation of the water building.
When the pile is piled on water to the precast tubular pile, in order to find the pile position accurately, often need adjust precast tubular pile's position, before piling, the nozzle is used for fixed mounting to be about to squeeze into submarine precast tubular pile, the pile is also gone on in the nozzle position, at present, the nozzle on the pile driving boat can not remove, during the position of adjustment precast tubular pile, realize through removing whole hull, pile driving hull sum is big, the operation is wasted time and energy, and be difficult to control the displacement of hull, lead to the efficiency of construction low, and the pile driving boat rocks under the effect of stormy waves easily, be difficult to find the pile position more.
SUMMERY OF THE UTILITY MODEL
The utility model aims to solve the technical problem that a pile ship is embraced in pile of piling on water of accurate positioning pile is provided.
The utility model provides a technical scheme that its technical problem adopted is:
pile embracing ship of piling on water, including hull and longkou, the longkou sets up on the hull, still includes guide rail, embracing pile device and longkou displacement drive arrangement, guide rail and longkou displacement drive arrangement all set up on the hull, and longkou displacement drive arrangement is connected with the longkou, guide rail one end extends to outside the hull, embrace the pile device setting on the guide rail, longkou displacement drive arrangement's drive direction is on a parallel with the upper surface of hull, and is perpendicular with the guide rail direction.
Further, still include auxiliary positioning device, the prow device sets up at the hull, auxiliary positioning device sets up the stern at the hull.
Furthermore, the auxiliary positioning device comprises a steel column anchor rod, a sliding rail, a sliding block and a hydraulic rod I, the sliding block is fixed on the steel column anchor rod and arranged on the sliding rail, the sliding rail is perpendicular to the upper surface of the ship body and fixed on the ship body, and the output end of the hydraulic rod I is arranged at the top of the steel column anchor rod.
Furthermore, two auxiliary positioning devices are arranged on the stern of the ship body, and the two auxiliary positioning devices and the pile embracing device form a triangle.
Further, pile embracing device includes mount pad, back staple bolt, preceding staple bolt, motor, transmission shaft and gear, install the rack on the track direction of guide rail, the mount pad sets up on the guide rail, the one end of preceding staple bolt and the one end of back staple bolt all are articulated with the mount pad, and the other end of preceding staple bolt can be dismantled with the other end of back staple bolt and be connected, the motor is fixed at the mount pad, and the output and the transmission shaft of motor are connected, and the cooperation has the gear on the transmission shaft, the gear cooperates with the rack on the guide rail.
Furthermore, the dragon mouth displacement driving device is a hydraulic rod II, and the left end and the right end of the dragon mouth are both provided with the hydraulic rod II.
Furthermore, a notch is formed in the bow of the ship body, and one end of the guide rail extends into the notch of the bow of the ship body.
The utility model has the advantages that:
the utility model discloses a pile embracing device can remove along the guide rail, can increase the stability of hull. During construction, the pile driving boat can be fixed on the water surface, when the pile is driven, the two auxiliary positioning devices and the pile embracing device form a triangle, the position of the pile driving boat is fixed, and the prefabricated pipe pile can be adjusted to the designed pile position only by controlling the upper position and the lower position of the dragon mouth to be adjusted by the dragon mouth displacement driving device, so that the pile driving boat is very convenient, time and labor are saved, the construction efficiency can be improved, and the construction quality is ensured.
Drawings
Fig. 1 is a top view of the hull of the present invention;
FIG. 2 is a schematic structural view of the auxiliary positioning device of the present invention;
fig. 3 is a front view of the pile embracing device of the present invention.
Shown in the figure: 1, a ship body; 2-a guide rail; 3-auxiliary positioning means; 4-steel column anchor rod; 5-a slide rail; 6-a slide block; 7-hydraulic rod I; 8, mounting seats; 9-rear hoop; 10-front hoop; 11-a motor; 12-a rack; 13-a drive shaft; 14-a gear; 15-hydraulic lever II; 16-dragon mouth; and 17-prefabricating the tubular pile.
Detailed Description
The present invention will be further explained with reference to the drawings and examples.
In the description of the present invention, it should be noted that the directions or positional relationships indicated as the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "front", "rear", etc., appear based on the directions or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first," "second," and "third" as appearing herein are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
As shown in fig. 1, the utility model discloses a pile embracing ship of piling on water, including hull 1 and longkou 16, longkou 16 sets up on hull 1, still includes guide rail 2, embracing pile device and longkou displacement drive arrangement, guide rail 2 and longkou displacement drive arrangement all set up on hull 1, and longkou displacement drive arrangement is connected with longkou 16, 2 one end of guide rail extend to outside hull 1, the embracing pile device sets up on guide rail 2, longkou displacement drive arrangement's drive direction is on a parallel with the upper surface of hull 1, and is perpendicular with 2 directions of guide rail. The utility model discloses a pile embracing device is used for embracing the tubular pile that has installed before and fixed in the submarine silt, the position of longkou 16 is used for installing prefabricated tubular pile 17 that has not squeezed into the submarine silt yet, the utility model discloses a pile embracing device carries out rough positioning with hull 1, namely carry out the location of fore-and-aft direction to hull 1 and longkou 16, the fore-and-aft direction corresponds the upper and lower direction of figure 1, then through longkou displacement drive arrangement, adjust hull 1 and the position of longkou 16 about, carry out the location of left and right direction to longkou 16, can adjust prefabricated tubular pile 17 position to the design pile position, reach the purpose of accurate positioning to prefabricated tubular pile 17, among the prior art, the longkou on the pile driving ship can not move, when the prefabricated tubular pile is piled on the water, in order to find the pile position accurately, realize through removing whole pile driving, the hull is bulky and heavy, the operation is time-wasting time, and the moving distance of the ship body is difficult to control, so that the construction efficiency is low, and the pile driving ship easily shakes under the action of wind waves, so that the pile position is more difficult to find. Compared with the prior art, the utility model discloses need not fix a position precast tubular pile 17 through removing whole hull 1, the utility model discloses a carry out the accurate positioning to precast tubular pile 17 through embracing pile device and longkou displacement drive, the degree of accuracy of location is higher than to fix a position through removing the hull among the prior art far away, and fixes a position simply, and it is very convenient, labour saving and time saving can improve the efficiency of construction, guarantees construction quality.
In order to make the hull 1 more stable on the water surface and improve the stability of the hull 1 in the process of pile embracing, the device further comprises an auxiliary positioning device 3, wherein the pile embracing device is arranged at the bow of the hull 1, and the auxiliary positioning device 3 is arranged at the stern of the hull 1.
The auxiliary positioning device 3 may be a series of devices for fixing the ship body 1, such as an anchor chain, an anchor cable or an anchor rod 4, specifically, as shown in fig. 2, the auxiliary positioning device 3 includes a steel column anchor rod 4, a slide rail 5, a slide block 6 and a hydraulic rod i 7, the slide block 6 is fixed on the steel column anchor rod 4, the slide block 6 is arranged on the slide rail 5, the slide rail 5 is perpendicular to the upper surface of the ship body 1 and is fixed on the ship body 1, and an output end of the hydraulic rod i 7 is arranged at the top of the steel column anchor rod 4. During the use, at first will be constructed before through the pile embracing device and the tubular pile that has accomplished is died to lock, also be exactly to embrace the tubular pile of fixing in submarine silt before, then insert the aquatic silt with steel column stock 4 through hydraulic stem I7, can fix hull 1, can be through removing the pile embracing device on guide rail 2 for fixed elasticity obtains control.
In order to further stabilize the hull 1 on the water surface, two auxiliary positioning devices 3 are arranged on the stern of the hull 1, and the two auxiliary positioning devices 3 and the pile-embracing device form a triangle.
Pile embracing device only need before the construction accomplished the tubular pile die lock can, can be chain, clip, a series of connection fixed equipment such as buckle, specific, pile embracing device includes mount pad 8, back staple bolt 9, preceding staple bolt 10, motor 11, transmission shaft 13 and gear 14, install rack 12 on guide rail 2's the track direction, mount pad 8 sets up on guide rail 2, the one end of preceding staple bolt 10 and the one end of back staple bolt 9 all are articulated with mount pad 8, and the other end of preceding staple bolt 10 can be dismantled with the other end of back staple bolt 9 and be connected, motor 11 is fixed at mount pad 8, and the output and the transmission shaft 13 of motor 11 are connected, and the cooperation has gear 14 on the transmission shaft 13, gear 14 and the rack 12 cooperation on the guide rail 2. As shown in fig. 3, the gear 14 is driven by the motor 11 to rotate so as to control the movement of the whole pile embracing device on the guide rail 2, i.e. the movement of the mounting base 8, in this embodiment the direction of the guide rail 2 is from the stern to the bow, i.e. the direction shown in fig. 1, the stern is at the back, the bow is in front, one end of the front hoop 10 and one end of the rear hoop 9 are hinged with the mounting seat 8, can be hinged together through a fastening bolt, the other end of the front hoop 10 and the other end of the rear hoop 9 are connected together after the front hoop 10 and the rear hoop 9 clamp the previously constructed tubular pile by rotating the other end of the front hoop 10 and the other end of the rear hoop 9, accessible bolt, round pin spare, buckle chain etc. link together, still can be through screwing up fastening bolt with preceding staple bolt 10 and back staple bolt 9 dead fix on mount pad 8 for the tubular pile that construction had been accomplished before preceding staple bolt 10 and back staple bolt 9 dead lock.
The dragon mouth displacement driving device is driving equipment for driving the dragon mouth 16 to move left and right, namely left and right in fig. 1, the driving equipment can be driven by a motor and driven by hydraulic pressure, specifically, the dragon mouth displacement driving device is a hydraulic rod II 15, and the left end and the right end of the dragon mouth 16 are both provided with the hydraulic rod II 15. The left and right positions of the faucet 16 are adjusted through the left hydraulic rod II and the right hydraulic rod II 15.
In order to save the volume of the ship body 1 and ensure that the design of the ship body 1 is more reasonable and the pile holding device is better operated, as shown in figure 1, a gap is arranged at the bow of the ship body 1, and one end of the guide rail 2 extends into the gap at the bow of the ship body 1.
Claims (7)
1. Pile driving pilework ship on water, including hull (1) and longkou (16), longkou (16) set up on hull (1), its characterized in that: still include guide rail (2), pile embracing device and longkou displacement drive arrangement, guide rail (2) and longkou displacement drive arrangement all set up on hull (1), and longkou displacement drive arrangement is connected with longkou (16), guide rail (2) one end extends to outside hull (1), pile embracing device sets up on guide rail (2), longkou displacement drive arrangement's drive direction is on a parallel with the upper surface of hull (1), and perpendicular with guide rail (2) direction.
2. The marine pile driving piler according to claim 1, characterized in that: the auxiliary pile-embracing ship is characterized by further comprising an auxiliary positioning device (3), wherein the pile-embracing device is arranged at the bow of the ship body (1), and the auxiliary positioning device (3) is arranged at the stern of the ship body (1).
3. The marine pile driving piler according to claim 2, characterized in that: the auxiliary positioning device (3) comprises a steel column anchor rod (4), a sliding rail (5), a sliding block (6) and a hydraulic rod I (7), the sliding block (6) is fixed on the steel column anchor rod (4), the sliding block (6) is arranged on the sliding rail (5), the sliding rail (5) is perpendicular to the upper surface of the ship body (1) and fixed on the ship body (1), and the output end of the hydraulic rod I (7) is arranged at the top of the steel column anchor rod (4).
4. The marine pile driving piler according to claim 3, wherein: two auxiliary positioning devices (3) are arranged on the stern of the ship body (1), and the two auxiliary positioning devices (3) and the pile embracing device form a triangle.
5. The marine pile driving piler as claimed in claim 1, 2, 3 or 4, wherein: embrace a device and include mount pad (8), back staple bolt (9), preceding staple bolt (10), motor (11), transmission shaft (13) and gear (14), install rack (12) on the track direction of guide rail (2), mount pad (8) set up on guide rail (2), the one end of preceding staple bolt (10) and the one end of back staple bolt (9) all articulate with mount pad (8), and the other end of preceding staple bolt (10) can be dismantled with the other end of back staple bolt (9) and be connected, motor (11) are fixed in mount pad (8), and the output and transmission shaft (13) of motor (11) are connected, and the cooperation has gear (14) on transmission shaft (13), rack (12) cooperation on gear (14) and guide rail (2).
6. The marine pile driving piler according to claim 5, wherein: the dragon mouth displacement driving device is a hydraulic rod II (15), and the left end and the right end of the dragon mouth (16) are both provided with the hydraulic rod II (15).
7. The pile-driving watercraft according to claim 6, characterized in that: the bow of hull (1) department is provided with the breach, guide rail (2) one end extends to in the breach of hull (1) bow.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020660041.4U CN212104093U (en) | 2020-04-27 | 2020-04-27 | Pile driving and holding ship on water |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202020660041.4U CN212104093U (en) | 2020-04-27 | 2020-04-27 | Pile driving and holding ship on water |
Publications (1)
Publication Number | Publication Date |
---|---|
CN212104093U true CN212104093U (en) | 2020-12-08 |
Family
ID=73612597
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202020660041.4U Active CN212104093U (en) | 2020-04-27 | 2020-04-27 | Pile driving and holding ship on water |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN212104093U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116446396A (en) * | 2023-06-16 | 2023-07-18 | 中国建筑第六工程局有限公司 | Self-anchoring device for piling on ship and piling construction method |
CN116605352A (en) * | 2023-05-18 | 2023-08-18 | 建湖宝迪工程机械有限公司 | Piling ship convenient to multidirectional adjustment |
-
2020
- 2020-04-27 CN CN202020660041.4U patent/CN212104093U/en active Active
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116605352A (en) * | 2023-05-18 | 2023-08-18 | 建湖宝迪工程机械有限公司 | Piling ship convenient to multidirectional adjustment |
CN116605352B (en) * | 2023-05-18 | 2023-12-19 | 建湖宝迪工程机械有限公司 | Piling ship convenient to multidirectional adjustment |
CN116446396A (en) * | 2023-06-16 | 2023-07-18 | 中国建筑第六工程局有限公司 | Self-anchoring device for piling on ship and piling construction method |
CN116446396B (en) * | 2023-06-16 | 2023-09-05 | 中国建筑第六工程局有限公司 | Self-anchoring device for piling on ship and piling construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN212104093U (en) | Pile driving and holding ship on water | |
CN102839666B (en) | Bottom-supported floating pile-driving platform | |
CN106759331B (en) | Overwater piling device | |
CN202148526U (en) | Multi-functional piling system, | |
CN207829001U (en) | One kind being used for the steady stake locating platform of offshore wind farm single-pile foundation | |
EP1234978B1 (en) | Off-shore wind turbine | |
CN113152558A (en) | River channel dredging ship capable of adjusting dredging depth | |
CN102556292A (en) | Self-propelled marine wind-power engineering operation boat capable of operating by sitting on sea bed | |
CN102874384B (en) | Simple dredger for gravels in flowing water and method for dredging gravels | |
CN209795746U (en) | novel assembled is tied and is leaned on ship device | |
CN216546599U (en) | A hang and put device that is used for coastal waters geotechnical engineering shipborne reconnaissance to equip | |
CN215669496U (en) | Amphibious hammering tubular pile construction device for mudflat | |
CN109372047A (en) | A kind of three way ropes position system suitable for cutter suction dredger | |
CN201424121Y (en) | Double-crane piling boat for construction of offshore artificial island | |
CN212354310U (en) | Quick group connection device for ship passing through brake | |
CN210887375U (en) | Inland river mud blowing boat | |
CN209099429U (en) | A kind of three way ropes position system applied to cutter suction dredger | |
CN209099415U (en) | A kind of three way ropes position system suitable for cutter suction dredger | |
CN111962543A (en) | Rapid connection and separation process of pile stabilizing platform and mother ship | |
CN115233672B (en) | Construction device and construction method for offshore construction tube plate structure | |
CN110552350A (en) | pile driving ship with pile gripper and overwater construction method thereof | |
CN101628609A (en) | E Horizontal walking positioning pile trolley for engineering vessel | |
CN115258046B (en) | Releasable guarantee platform applicable to hard seabed and mooring method | |
CN219280693U (en) | Underwater piling construction platform | |
CN217782046U (en) | Positioning device applied to pile driving barge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |