CN212053178U - Energy-conserving ready-package steel construction for building - Google Patents

Energy-conserving ready-package steel construction for building Download PDF

Info

Publication number
CN212053178U
CN212053178U CN201922440170.2U CN201922440170U CN212053178U CN 212053178 U CN212053178 U CN 212053178U CN 201922440170 U CN201922440170 U CN 201922440170U CN 212053178 U CN212053178 U CN 212053178U
Authority
CN
China
Prior art keywords
wall
fixed
word form
energy
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201922440170.2U
Other languages
Chinese (zh)
Inventor
汪殿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Shenghuabo Parts Co ltd
Original Assignee
Wuhan Baisrun Construction Steel Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Baisrun Construction Steel Technology Co ltd filed Critical Wuhan Baisrun Construction Steel Technology Co ltd
Priority to CN201922440170.2U priority Critical patent/CN212053178U/en
Application granted granted Critical
Publication of CN212053178U publication Critical patent/CN212053178U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses an energy-conserving ready-package steel construction for building, including bottom plate, fixed column, roof and steel sheet body, the fixed column is fixed in bottom plate top outer wall middle part, and the roof is fixed in the fixed column top, bottom plate, fixed column and roof combination form an I word form connecting piece, and I word form connecting piece both sides outer wall has all seted up C word form draw-in groove, C word form draw-in groove one side inner wall is fixed with first C word form fixed plate, and C word form draw-in groove inner wall sliding connection has second C word form fixed plate, one side outer wall that first C word form fixed plate was kept away from to the roof is seted up the first screw hole of two sets of symmetric distributions. The utility model discloses in going into the C word form draw-in groove on the I word form connecting piece with the steel sheet card, make on the steel sheet a plurality of constant head tanks and the second C word form the reference column on the fixed plate form the joint cooperation, then screw up a plurality of screw rods and can fix the steel sheet, whole process is simple and convenient, realizes the effect of quick installation and dismantlement.

Description

Energy-conserving ready-package steel construction for building
Technical Field
The utility model relates to an energy-conserving building technical field especially relates to an energy-conserving ready-package steel construction for building.
Background
Energy-saving building definition: designing and constructing buildings that employ energy-efficient structures, materials, appliances, and products; in the buildings, part or all of renewable energy sources are utilized, and most of the steel plates are connected in a welding mode or are fixed together through bolts at openings when being used and connected at present, so that the operation is troublesome, and the working efficiency is reduced.
SUMMERY OF THE UTILITY MODEL
The utility model aims at solving the defects existing in the prior art and providing a quick-mounting steel structure for energy-saving buildings.
In order to achieve the above purpose, the utility model adopts the following technical scheme:
a quick-assembly steel structure for an energy-saving building comprises a bottom plate, a fixing column, a top plate and a steel plate body, wherein the fixing column is fixed in the middle of the outer wall of the top of the bottom plate, the top plate is fixed at the top end of the fixing column, the bottom plate, the fixing column and the top plate are combined to form an I-shaped connecting piece, C-shaped clamping grooves are formed in the outer walls of the two sides of the I-shaped connecting piece, a first C-shaped fixing plate is fixed on the inner wall of one side of each C-shaped clamping groove, a second C-shaped fixing plate is connected to the inner wall of the C-shaped clamping groove in a sliding mode, two groups of first threaded holes which are symmetrically distributed are formed in the outer wall of one side, away from the first C-shaped fixing plate, of the top plate, two groups of second threaded holes which are symmetrically distributed are formed in the, and the first threaded hole, the second threaded hole and the third threaded hole are communicated with the C-shaped clamping groove, a screw rod is screwed on the inner wall of the first threaded hole, the inner wall of the second threaded hole and the inner wall of the third threaded hole, one end of the screw rod, which is close to the second C-shaped fixing plate, is fixedly connected with the second C-shaped fixing plate through a bearing, a first non-slip mat and a second non-slip mat are respectively fixed on the outer wall of one side, opposite to the first C-shaped fixing plate and the second C-shaped fixing plate, of the second non-slip mat, two first openings which are symmetrically distributed are respectively formed in the outer wall of the top and the outer wall of the bottom of the second non-slip mat, a second opening is formed in the outer wall of the middle of the second non-slip mat, positioning columns are fixed on the inner walls of the first opening and the second opening, the positioning columns are fixedly connected with the.
Preferably, the outer wall of the bottom plate is provided with a polygonal slot, and the middle part of the outer wall of the top plate is fixed with a polygonal inserting block.
Preferably, the outer walls of the two sides of the bottom plate are provided with first limiting openings, and the two first limiting openings are communicated with the polygonal slots.
Preferably, the middle part of the polygonal inserting block is provided with a second limiting through opening, and the inner diameter of the first limiting through opening is the same as that of the second limiting through opening.
Preferably, the polygonal slot and the polygonal inserting block form a splicing fit, and the inner walls of the two first limiting through holes and the inner wall of the second limiting through hole are spliced to form the same bolt.
Preferably, the number of each group in the two groups of first threaded holes is two, and the number of each group in the two groups of second threaded holes is two.
Preferably, the screw rod is connected with the I-shaped connecting piece in a threaded manner, and the locking nut is in contact with the I-shaped connecting piece.
The utility model has the advantages that:
1. this ready-package steel construction for energy-conserving building, in the C word form draw-in groove on I word form connecting piece is gone into to the steel sheet card, make on the steel sheet reference column on a plurality of constant head tanks and the second C word form fixed plate form the joint cooperation, then screw up a plurality of screw rods and can fix the steel sheet, whole process is simple and convenient, realize quick installation and the effect of dismantling, and second C word form fixed plate can slide regulation in C word form draw-in groove, but the steel sheet of the different thickness of adaptation is fixed.
2. This ready-package steel construction for energy-conserving building, but external I word form connecting piece, only need form the grafting cooperation with the polygon inserted block of external I word form connecting piece and the polygon slot by external I word form connecting piece, then will be inserted same root bolt and can realize the fixed connection of two I word form connecting pieces by two first spacing opening inner walls on external I word form is connected and the spacing opening inner wall of second on the external I word form connecting piece, satisfy the effect of fixed a plurality of steel sheets.
Drawings
Fig. 1 is a schematic side view of a side-view vertical cross-section structure of a quick-mounting steel structure for an energy-saving building provided by the utility model;
fig. 2 is a schematic view of a front view structure of a quick-mounting steel structure for energy-saving buildings provided by the utility model;
fig. 3 is a schematic structural view of a steel plate body of a quick-mounting steel structure for an energy-saving building provided by the utility model;
fig. 4 is a schematic structural view of a second C-shaped fixing plate of the quick-mounting steel structure for energy-saving buildings provided by the utility model;
fig. 5 is the utility model provides a polygon slot and polygon inserted block connection structure sketch map of ready-package steel construction for energy-conserving building.
In the figure: the anti-skid device comprises a base plate 1, fixing columns 2, a top plate 3, a clamping groove 4C-shaped, a fixing plate 5 first C-shaped, a first anti-skid pad 6, a fixing plate 7 second C-shaped, a second anti-skid pad 8, a positioning column 9, a screw rod 10, a locking nut 11, a steel plate body 12, a polygonal slot 13, a first limiting opening 14, a polygonal inserting block 15, a second limiting opening 16, a positioning groove 17 and a bolt 18.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments.
Referring to fig. 1-5, a ready-package steel structure for energy-saving buildings comprises a bottom plate 1, a fixing column 2, a top plate 3 and a steel plate body 12, wherein the fixing column 2 is fixed in the middle of the outer wall of the top of the bottom plate 1, the top plate 3 is fixed at the top end of the fixing column 2, the bottom plate 1, the fixing column 2 and the top plate 3 are combined to form an I-shaped connecting piece, the outer walls of two sides of the I-shaped connecting piece are respectively provided with a C-shaped clamping groove 4, the inner wall of one side of the C-shaped clamping groove 4 is fixed with a first C-shaped fixing plate 5, the inner wall of the C-shaped clamping groove 4 is connected with a second C-shaped fixing plate 7 in a sliding manner, the outer wall of one side of the top plate 3 away from the first C-shaped fixing plate 5 is provided with two groups of first threaded holes which are symmetrically distributed, the middle of the outer wall of one side of the fixing, the first threaded hole, the second threaded hole and the third threaded hole are communicated with the C-shaped clamping groove 4, the inner wall of the first threaded hole, the inner wall of the second threaded hole and the inner wall of the third threaded hole are all in threaded connection with a screw rod 10, one end of the screw rod 10 close to the second C-shaped fixing plate 7 is fixedly connected with the second C-shaped fixing plate 7 through a bearing, the outer wall of one side, opposite to the first C-shaped fixing plate 5 and the second C-shaped fixing plate 7, of the first anti-skid pad 6 and the second anti-skid pad 8 are respectively fixed on the outer wall of the first C-shaped fixing plate and the outer wall of the second anti-skid pad 8, the outer wall of the top and the outer wall of the bottom of the second anti-skid pad 8 are respectively provided with two first openings which are symmetrically distributed, the outer wall of the middle part of the second anti-skid pad 8 is provided with a second opening, positioning columns 9 are fixed on the inner walls of, polygonal slot 13 has been seted up to 1 bottom outer wall of bottom plate, and 3 top outer walls middle parts of roof are fixed with polygon inserted block 15, first spacing opening 14 has all been seted up to 1 both sides outer wall of bottom plate, and two first spacing openings 14 are linked together with polygon slot 13, the spacing opening 16 of second has been seted up at polygon inserted block 15 middle part, and the internal diameter of first spacing opening 14 is the same with the 16 internal diameters of the spacing opening of second, polygon slot 13 forms the cooperation of pegging graft with polygon inserted block 15, and two first spacing opening 14's inner wall all pegs graft with the inner wall of the spacing opening 16 of second has same root bolt 18, every quantity is two in two sets of first screw holes, and every quantity is two in two sets of second screw holes, screw rod 10 has lock nut 11 with I style of calligraphy connecting piece junction spiro union, and lock nut 11 contacts with I style of calligraphy connecting piece.
The working principle is as follows: when the connecting piece is used, the steel plate body 12 is clamped into the C-shaped clamping groove 4 on the I-shaped connecting piece consisting of the bottom plate 1, the fixing plate 2 and the top plate 3, then the steel plate body 12 is adjusted, a plurality of positioning grooves 17 on the steel plate body 12 and positioning columns 9 on the second C-shaped fixing plate 7 form clamping fit, the screw rods 10 are fixedly connected with the second C-shaped fixing plate 7 through bearings, a plurality of screw rods 10 can be screwed, the second C-shaped fixing plate 7 is pushed, the second anti-skid pads 8 continuously extrude the steel plate body 12, the positioning columns 9 are tightly connected with the positioning grooves 17, and then the fixing work of the steel plate body 12 is completed, when the external I-shaped connecting piece is needed, only the polygonal inserting blocks 15 of the external I-shaped connecting piece and the polygonal inserting slots 13 of the external I-shaped connecting piece are required to form inserting fit, and then the inner walls of two first limiting through holes 14 connected by the external I-shaped connecting piece and the second limiting through holes 16 on the external I-shaped connecting piece The walls are connected together, so that the fixed connection of the two I-shaped connecting pieces can be realized, and the steel plate body 12 which can be used for next step is fixed.
The above, only be the concrete implementation of the preferred embodiment of the present invention, but the protection scope of the present invention is not limited thereto, and any person skilled in the art is in the technical scope of the present invention, according to the technical solution of the present invention and the utility model, the concept of which is equivalent to replace or change, should be covered within the protection scope of the present invention.

Claims (7)

1. The utility model provides an energy-conserving ready-package steel construction for building, includes bottom plate (1), fixed column (2), roof (3) and steel sheet body (12), its characterized in that, fixed column (2) are fixed in bottom plate (1) top outer wall middle part, and roof (3) are fixed in fixed column (2) top, bottom plate (1), fixed column (2) and roof (3) combination form an I word form connecting piece, and I word form connecting piece both sides outer wall has all seted up C word form draw-in groove (4), C word form draw-in groove (4) one side inner wall is fixed with first C word form fixed plate (5), and C word form draw-in groove (4) inner wall sliding connection has second C word form fixed plate (7), the first screw hole of two sets of symmetric distributions is seted up to the one side outer wall that first C word form fixed plate (5) was kept away from in roof (3), and two symmetric distributions's second screw hole is seted up in the middle part of the outer wall of one side that first C word form fixed The outer wall of one side of the bottom plate (1) far away from the first C-shaped fixing plate (5) is provided with two groups of symmetrically distributed third threaded holes, the first threaded hole, the second threaded hole and the third threaded hole are communicated with the C-shaped clamping groove (4), the inner wall of the first threaded hole, the inner wall of the second threaded hole and the inner wall of the third threaded hole are respectively screwed with a screw rod (10), one end of the screw rod (10) close to the second C-shaped fixing plate (7) is fixedly connected with the second C-shaped fixing plate (7) through a bearing, the outer walls of one side of the first C-shaped fixing plate (5) opposite to the second C-shaped fixing plate (7) are respectively fixed with a first anti-skid pad (6) and a second anti-skid pad (8), the outer wall of the top and the outer wall of the bottom of the second anti-skid pad (8) are respectively provided with two symmetrically distributed first openings, and the outer wall of the middle part of the second anti-skid pad, and first opening and second opening inner wall all are fixed with reference column (9), reference column (9) and second C word form fixed plate (7) fixed connection, constant head tank (17) with reference column (9) looks adaptation are all seted up to steel sheet body (12) both sides.
2. The quick-assembly steel structure for the energy-saving building as claimed in claim 1 is characterized in that the bottom outer wall of the bottom plate (1) is provided with a polygonal slot (13), and the middle part of the top outer wall of the top plate (3) is fixed with a polygonal insert block (15).
3. The quick-assembly steel structure for the energy-saving building as claimed in claim 1 is characterized in that the outer walls of the two sides of the bottom plate (1) are respectively provided with a first limiting through hole (14), and the two first limiting through holes (14) are communicated with the polygonal slot (13).
4. The quick-assembly steel structure for the energy-saving building according to claim 2, wherein a second limiting through opening (16) is formed in the middle of the polygonal inserting block (15), and the inner diameter of the first limiting through opening (14) is the same as that of the second limiting through opening (16).
5. The quick-assembly steel structure for the energy-saving building as claimed in claim 2, wherein the polygonal slots (13) are in insertion fit with the polygonal insertion blocks (15), and the inner walls of the two first limiting through holes (14) and the inner wall of the second limiting through hole (16) are inserted with the same plug pin (18).
6. The quick-assembly steel structure for energy-saving buildings according to claim 1, characterized in that the number of each of the two first threaded holes is two, and the number of each of the two second threaded holes is two.
7. The quick-assembly steel structure for the energy-saving building as claimed in claim 1, wherein a lock nut (11) is screwed at the joint of the screw (10) and the I-shaped connecting member, and the lock nut (11) is in contact with the I-shaped connecting member.
CN201922440170.2U 2019-12-30 2019-12-30 Energy-conserving ready-package steel construction for building Expired - Fee Related CN212053178U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922440170.2U CN212053178U (en) 2019-12-30 2019-12-30 Energy-conserving ready-package steel construction for building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922440170.2U CN212053178U (en) 2019-12-30 2019-12-30 Energy-conserving ready-package steel construction for building

Publications (1)

Publication Number Publication Date
CN212053178U true CN212053178U (en) 2020-12-01

Family

ID=73535068

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922440170.2U Expired - Fee Related CN212053178U (en) 2019-12-30 2019-12-30 Energy-conserving ready-package steel construction for building

Country Status (1)

Country Link
CN (1) CN212053178U (en)

Similar Documents

Publication Publication Date Title
CN217480405U (en) Assembled steel construction building
CN211735945U (en) Steel construction building assembled heat preservation wallboard
CN212053178U (en) Energy-conserving ready-package steel construction for building
CN209780216U (en) Scaffold node connection structure
CN214657789U (en) Lap joint assembly type energy-saving building
CN210857492U (en) Fabricated building structure system
CN210563000U (en) Net rack board convenient to installation
CN209817127U (en) Clip type node connection structure
CN209723359U (en) A kind of lightgage steel joist right angle fast joint structure
CN112982956A (en) Connecting piece for aluminum alloy template steel back edge
CN217950333U (en) Installation part and petroleum perforator
CN210380144U (en) Row type elevator
CN219431092U (en) Socket type assembled partition keel
CN215252259U (en) A connect stopper that is used for bailey roof beam and I-steel to be connected
CN215054432U (en) Can diversified assembled building steel construction roof truss
CN205265169U (en) Cable drags and makes system and cable fixing device
CN218204919U (en) Connecting piece for steel structure assembly
CN219732286U (en) Novel combination component for houses
CN219954944U (en) Frame
CN205224273U (en) It constructs girder construction that links up to do benefit to steel between roof beam
CN104874693B (en) Rectangular thin-wall steel pipe corrugation forming clamp and using method thereof
CN216740481U (en) House stand column decoration aluminum pinch plate convenient to install
CN219240852U (en) Light steel supporting structure
CN214532341U (en) Reversing structure for stand column
CN220204284U (en) Connecting piece convenient to installation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210506

Address after: 430000 d236, Jingkai Zhizao 2045 innovation Valley intelligent manufacturing innovation center, No.101, second Minli Road, Wuhan Economic and Technological Development Zone, Hubei Province

Patentee after: Wuhan Shenghuabo Parts Co.,Ltd.

Address before: 430000 Changfu Industrial Demonstration Park, Caidian District, Wuhan City, Hubei Province

Patentee before: Wuhan baisrun Construction Steel Technology Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201201

Termination date: 20211230