CN211949539U - Building scaffold, construction guardrail mounting - Google Patents

Building scaffold, construction guardrail mounting Download PDF

Info

Publication number
CN211949539U
CN211949539U CN201922290354.5U CN201922290354U CN211949539U CN 211949539 U CN211949539 U CN 211949539U CN 201922290354 U CN201922290354 U CN 201922290354U CN 211949539 U CN211949539 U CN 211949539U
Authority
CN
China
Prior art keywords
connecting piece
steel pipe
scaffold
building
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922290354.5U
Other languages
Chinese (zh)
Inventor
孙红军
周波
刘江
郭峰
薛文光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRSC Engineering Group Co Ltd
Urban Construction Engineering Co Ltd of CRSC Engineering Group Co Ltd
Original Assignee
CRSC Engineering Group Co Ltd
Urban Construction Engineering Co Ltd of CRSC Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CRSC Engineering Group Co Ltd, Urban Construction Engineering Co Ltd of CRSC Engineering Group Co Ltd filed Critical CRSC Engineering Group Co Ltd
Priority to CN201922290354.5U priority Critical patent/CN211949539U/en
Application granted granted Critical
Publication of CN211949539U publication Critical patent/CN211949539U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a building scaffold, construction guardrail mounting, including first connecting piece, second connecting piece and connecting steel pipe, evenly be equipped with four oval bolt holes on four angles of first connecting piece, second connecting piece one end is welded at the middle part of first connecting piece perpendicularly, is equipped with the connecting steel pipe at another tip of second connecting piece, the connecting steel pipe is connected with scaffold horizontal steel pipe drawknot spare; the first connecting piece is fixed on a concrete structure of a building through a bolt. The utility model discloses cancelled and welded, cut the working procedure on the scaffold frame, the batch production preparation is semi-manufactured goods, punches during the use on-the-spot concrete structure and can install, removes finished steel member with the back, but reuse, the efficiency of construction is high, with low costs, and the potential safety hazard that has just significantly reduced.

Description

Building scaffold, construction guardrail mounting
Technical Field
The utility model relates to a scaffold for building, construction guardrail mounting belongs to the building engineering field, especially relates to an old building reforms transform scaffold for building and construction floor face limit safety protection railing temporary fixing spare.
Background
With the rapid development of urban construction, a plurality of old buildings can not be dismantled and rebuilt due to short service life or other reasons, and only the outer walls of the old buildings are renovated and reformed, so that new effects of the old buildings are achieved. When the old building is transformed, the steel pipe external scaffold is normally used in the building, only the external wall is transformed, and the steel pipe external scaffold used in the common building construction must be rigidly connected with the building structure into a whole, so that the safety accidents of collapse and overturn of the scaffold body are avoided. Because the steel pipe can not be installed through the wall for drawknot, the scaffold and the building structure are difficult to drawknot, and great potential safety hazard is caused. The danger that the limit portion position exists the high altitude and falls is faced in the construction floor, often needs the installation to prevent temporarily that the railing from preventing the personnel from falling. The existing technical method is that after an anchoring steel plate is fixed on an outer wall concrete member by using an expansion bolt, a wall connecting tie steel pipe is welded, or a switching steel pipe is welded on the wall anchoring steel plate, the switching steel pipe needs to be perforated, and when a scaffold is dismantled after the wall connecting tie steel pipe is used, the steel pipe at the welding position is cut off by gas cutting. In the prior art, the workload of field welding and dismantling and cutting after use is large, high-altitude electric welding is carried out on a scaffold, the cutting operation efficiency is low, the welding quality is difficult to ensure, and the safety risk is overlarge; but also the steel pipe deckle edge that remains that causes when cutting because of the gas cutting need polish, but steel sheet side reuse, the cost is artifical. The work load of punching the round steel pipe adaptor is large, and the strength of the steel pipe can be influenced. And the other one is, for example, the Chinese patent CN208294057U, the right-angle steel tube of the technology has high processing precision requirement, the manufacturing efficiency is slightly low, the position of the rear fixed steel plate can not be properly adjusted, the material consumption of the steel tube of the welded steel plate section is larger than that of the angle steel of the invention, and the cost is slightly higher.
SUMMERY OF THE UTILITY MODEL
In order to overcome the above-mentioned not enough, the utility model provides a construction scaffolding, construction guardrail mounting adopts prefabricated finished product steel member, and steel member welding quality can be guaranteed in the batch production processing preparation, and on-the-spot expansion bolts is fixed the back and directly links firmly the wall steel pipe with the scaffold fastener tightly, need not carry out high altitude weldment work on the scaffold, and the efficiency of construction is high, and the potential safety hazard that has significantly reduced.
The utility model adopts the technical proposal that: a building scaffold and construction guardrail fixing piece comprises a first connecting piece, a second connecting piece and connecting steel pipes, wherein four oval bolt holes are uniformly formed in four corners of the first connecting piece, one end of the second connecting piece is vertically welded in the middle of the first connecting piece, the other end of the second connecting piece is provided with the connecting steel pipes, and the connecting steel pipes are connected with a horizontal steel pipe tie piece of a scaffold; the first connecting piece is fixed on a concrete structure of a building through a bolt.
Furthermore, the first connecting piece is a square steel plate with the thickness of 150 multiplied by 150mm, the second connecting piece is angle steel with the thickness of 50 multiplied by 5mm, and the second connecting piece is welded at the central position of the first connecting piece.
The oval bolt hole is two-way setting, two promptly for the level setting, two are vertical setting.
The connecting steel pipe is a steel pipe with the diameter of 48 mm multiplied by 3.5mm and the length of 200 mm; the bottom of the connecting steel pipe is welded with the second connecting piece into a whole.
The bolts are four lengthened expansion bolts with the diameter of 12 mm.
The utility model discloses be used in building engineering construction floor face during the limit operation face, directly beat expansion bolts fixed can install the steel pipe railing fast, need not set up the bracing steel pipe, the construction is swift, reduce the material use amount, still can practice thrift the space that the bracing steel pipe occupy. The steel pipe fasteners are fixed on the fixing piece provided by the utility model, and the rigid connection ensures that the scaffold is firmly tied on the concrete structure of the building to form a stable whole, thereby ensuring the safe operation of constructors; after the steel member is used, the finished steel member is loosened and removed without gas cutting, so that the steel member is fast, efficient and safe, and can be recycled.
The utility model provides a building scaffold, construction guardrail mounting, the beneficial effect who brings:
(1) the utility model discloses cancelled and welded, cut the working procedure on the scaffold frame, the batch production preparation is semi-manufactured goods, punches during the use on-the-spot concrete structure and can install, removes finished steel member with the back, but reuse, the efficiency of construction is high, with low costs, and the potential safety hazard that has just significantly reduced.
(2) The high-rise or multi-storey floor construction layer of building engineering faces the limit department and adopts to beat rearmounted anchor slab and weld steel pipe railing or sets up railing and diagonal brace with the fastener and keeps stable, takes a lot of work and wastes material.
(3) Adopt the utility model discloses, the installation or demolish swiftly, firmly stable during the use, but mounting demolishs back reuse.
The present invention will be further explained with reference to the drawings and examples.
Drawings
Figure 1 is the utility model discloses building scaffolding, construction guardrail mounting's structural schematic.
Fig. 2 is a left side view of fig. 1.
Fig. 3 is a top view of fig. 1.
Figure 4 is the utility model discloses building scaffolding, construction guardrail mounting's user state diagram.
In the figure, 1 is a first connecting piece, 2 is a second connecting piece, 3 is a connecting steel pipe, 4 is a scaffold cross fastener, 5 is a scaffold horizontal steel pipe tie piece, 6 is a bolt, 7 is a building concrete structure, and 8 is an oval bolt hole.
Detailed Description
Example (b):
as shown in fig. 1 to 4, a building scaffold and construction guardrail fixing member comprises a first connecting piece 1, a second connecting piece 2 and connecting steel pipes 3, wherein four oval bolt holes 8 are uniformly formed in four corners of the first connecting piece 1, one end of the second connecting piece 2 is vertically welded to the middle of the first connecting piece 1, the other end of the second connecting piece 2 is provided with the connecting steel pipes 3, and the connecting steel pipes 3 are connected with a scaffold horizontal steel pipe tie piece 5; the first connecting member 1 is fixed to a building concrete structure 7 by bolts 6.
The first connecting piece is a square steel plate with the thickness of 150 multiplied by 150mm, the second connecting piece is angle steel with the thickness of less than 50 multiplied by 5mm, and the second connecting piece is welded at the central position of the first connecting piece.
The oval bolt hole is two-way setting, two promptly for the level setting, two are vertical setting.
The connecting steel pipe is a steel pipe with the diameter of 48 mm multiplied by 3.5mm and the length of 200 mm; the bottom of the connecting steel pipe is welded with the second connecting piece into a whole.
The bolts are expansion bolts, preferably four phi 12mm lengthened expansion bolts.
The specific manufacturing method comprises the following steps: the utility model discloses the technique utilizes a 150 x 150 mm's steel sheet (be first connecting piece), 4 oval bolt holes are predetermine to the steel sheet, steel sheet middle part horizontal welding angle less 50 x 5 angle steel (be the second connecting piece), the angle steel is kept away from the phi 48 x 3.5mm steel pipe (be the connecting steel pipe) of the end welding root length 200mm of steel sheet, the preparation is the finished product mounting, set up on the concrete structure of building with 4 phi 12mm extension expansion bolts for the mounting when drawing the knot position with the scaffold frame, two-way oval bolt hole can suitably adjust the displacement that causes because of bolt installation deviation, scaffold frame draws horizontal knot steel pipe with this mounting of cross fastener straining, make scaffold frame and building reliable drawknot.
The using method comprises the following steps: the floor faces limit department during building construction, fixes this drawknot spare on building faces the limit concrete with expansion bolts, notices the installation of the short steel pipe direction perpendicular to railing horizontal steel pipe direction of drawknot spare, and this mounting is fastened with the cross fastener in steel pipe railing pole setting lower part falls to the ground and tightly pushes up ground, can guarantee that it is firm, stable.

Claims (5)

1. The utility model provides a building scaffold, construction guardrail mounting which characterized in that: the scaffold horizontal steel pipe connecting device comprises a first connecting piece, a second connecting piece and connecting steel pipes, wherein four oval bolt holes are uniformly formed in four corners of the first connecting piece, one end of the second connecting piece is vertically welded in the middle of the first connecting piece, the other end of the second connecting piece is provided with the connecting steel pipe, and the connecting steel pipe is connected with a scaffold horizontal steel pipe tie piece; the first connecting piece is fixed on a concrete structure of a building through a bolt.
2. The building scaffold, construction barrier mount of claim 1, wherein: the first connecting piece is a square steel plate with the thickness of 150 multiplied by 150mm, the second connecting piece is angle steel with the thickness of less than 50 multiplied by 5mm, and the second connecting piece is welded at the central position of the first connecting piece.
3. The building scaffold, construction barrier mount of claim 1, wherein: the oval bolt hole is two-way setting, two promptly for the level setting, two are vertical setting.
4. The building scaffold, construction barrier mount of claim 1, wherein: the connecting steel pipe is a steel pipe with the diameter of 48 mm multiplied by 3.5mm and the length of 200 mm; the bottom of the connecting steel pipe is welded with the second connecting piece into a whole.
5. The building scaffold, construction barrier mount of claim 1, wherein: the bolts are four lengthened expansion bolts with the diameter of 12 mm.
CN201922290354.5U 2019-12-19 2019-12-19 Building scaffold, construction guardrail mounting Active CN211949539U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922290354.5U CN211949539U (en) 2019-12-19 2019-12-19 Building scaffold, construction guardrail mounting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922290354.5U CN211949539U (en) 2019-12-19 2019-12-19 Building scaffold, construction guardrail mounting

Publications (1)

Publication Number Publication Date
CN211949539U true CN211949539U (en) 2020-11-17

Family

ID=73175945

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922290354.5U Active CN211949539U (en) 2019-12-19 2019-12-19 Building scaffold, construction guardrail mounting

Country Status (1)

Country Link
CN (1) CN211949539U (en)

Similar Documents

Publication Publication Date Title
CN202139833U (en) Cantilever scaffold for building construction
CN106337555A (en) Method for constructing triangular steel support for cantilever structure of outer wall of building
CN201902010U (en) Instrumental overhanging scaffold hoop
CN203961238U (en) Bolt anchor slab adjustable tool formula builder's jack
CN111764621A (en) Overhanging scaffold and construction method
CN110821159A (en) Steel-structure large-span adjustable floor support plate supporting structure and construction method thereof
CN110005203B (en) Self-adaptive tool type inclined wall formwork supporting system and using method
CN219548348U (en) Novel detachable combined cantilever supporting structure
CN212336672U (en) I-steel overhanging bearing frame of basket pull rod for constructional engineering
CN211949539U (en) Building scaffold, construction guardrail mounting
CN211647306U (en) Floor carrier plate bearing structure with adjustable steel construction large-span
CN211340840U (en) Tower crane foundation of internal climbing tower crane
CN110424601B (en) Concrete pouring anti-floating device for composite floor slab with fabricated structure and implementation method
CN112049415A (en) Construction method of cornice formwork
CN211949540U (en) Building scaffold drawknot spare
CN111236640A (en) Structure of encorbelmenting is shared with outer scaffold to high altitude formwork support
CN115341701B (en) Hanging formwork construction method for high-altitude overhanging steel bar truss floor support plate
CN204343642U (en) Builder's jack corner support frame
CN203603461U (en) Floor aluminum shuttering splicing formwork structure system
CN210002845U (en) Shaped steel overhanging scaffold shaping chemical tool type anchoring structure
CN212773451U (en) Post-cast strip template support system
CN210563352U (en) Wall connecting device for climbing frame
CN109610802B (en) External hanging frame operation platform
CN209228053U (en) Large cantilever combined type anchor curable type steel operation platform
CN220909206U (en) A face limit protection fixture for parapet

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant