CN211775704U - Building wood formwork - Google Patents

Building wood formwork Download PDF

Info

Publication number
CN211775704U
CN211775704U CN202020186352.1U CN202020186352U CN211775704U CN 211775704 U CN211775704 U CN 211775704U CN 202020186352 U CN202020186352 U CN 202020186352U CN 211775704 U CN211775704 U CN 211775704U
Authority
CN
China
Prior art keywords
template
joint
edge
wood
hanging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202020186352.1U
Other languages
Chinese (zh)
Inventor
史建喜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN202020186352.1U priority Critical patent/CN211775704U/en
Application granted granted Critical
Publication of CN211775704U publication Critical patent/CN211775704U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model provides a building wood formwork, including whole wall formwork, the main stupefied and the inferior stupefied of vertical setting of horizontal setting, whole wall formwork is formed by the concatenation of plank sheathing and seam template, the equidistant peg is established in the seam template outside, sets up the bolt hole according to split bolt design interval on the seam template; the seam template is arranged in a pulling area of the integral wall template; connecting sheets are arranged at the butt joint of the wood template and the joint template, and the connecting sheets are fixed with the wood template and the joint template through bolts; the secondary edge is provided with a groove hanging hole, the lower part of the groove hanging hole is larger than the nail cap of the hanging nail, the upper part of the groove hanging hole is smaller than the nail cap of the hanging nail, the punching area and the template main body are divided into blocks by the template structure, and the template main body (namely a wooden template) is prevented from being cut and punched for many times.

Description

Building wood formwork
Technical Field
The utility model belongs to the technical field of a building templates, specifically a building plank sheathing.
Background
At present, shear walls are adopted in many residential projects, so that the requirements of people on space division are met. During the construction of a conventional shear wall, the wall body formwork is formed by cutting and splicing wooden formworks, secondary ribs are formed by adopting battens, main ribs are formed by adopting steel pipes, formworks on two sides of the wall body are fixed by split bolts, the wooden formworks need to be punched when the split bolts are installed, and the punching distance is generally 400 mm. In the repeated turnover, the template used each time is different in size and punching position, and most of templates need to be cut again and punched again. The random cutting and punching of the template causes the turnover number of the template to be reduced. After the number of times of the general turnover is 5-7 times, a whole template can not be found in the template, and the residual value rate is low.
In addition, in the prior art, sponge strips are mostly adopted for filling the joints between the templates, and the sponge strips are adhered again after each construction is finished, so that the manual efficiency reduction is caused, more pores and gaps exist, and the concrete water loss rate is higher. The supplementary structure of sponge strip also causes the template to demolish the back, and the negative and positive angle is uneven, and the template piece seam has the space, can not satisfy the requirement of present engineering to actual measurement. Therefore, a large amount of defect part repairing work is required after the mould is removed, and the repairing work amount is increased.
SUMMERY OF THE UTILITY MODEL
The invention provides a formwork which can be turned over for many times and is attractive in pouring and forming and a construction method for overcoming the defects in the prior art.
A building wood formwork comprises an integral wall formwork, a main ridge arranged horizontally and a secondary ridge arranged vertically, wherein the integral wall formwork is formed by splicing a wood formwork and a joint formwork, hanging nails are arranged on the outer side of the joint formwork at equal intervals, and bolt holes are arranged on the joint formwork at intervals according to split bolt design; the seam template is arranged in a pulling area of the integral wall template; connecting sheets are arranged at the butt joint of the wood template and the joint template, and the connecting sheets are fixed with the wood template and the joint template through bolts; the secondary edge is provided with a groove hanging hole, the lower part of the groove hanging hole is larger than the nail cap of the hanging nail, and the upper part of the groove hanging hole is smaller than the nail cap of the hanging nail.
The template structure divides the punching area and the template main body into blocks, avoids the template consumption caused by multiple times of cutting and punching of the template main body (namely a wooden template), and improves the service life and turnover times of most template materials. The template all adopts self-adhesion rubber elasticity waterproof sealing material banding, can prevent seam crossing water loss, can prevent simultaneously that the template from sticking up the limit. The hanging nails on the joint template are combined with the secondary ridge hanging holes, so that the construction is convenient to install and disassemble, and the construction progress is accelerated.
Specifically, the seam formworks are arranged at the top, the middle and the lower parts of the integral wall formwork; the connecting piece is arranged at the butt joint position of the joint template and the wood template and the butt joint position of the extension sections of the joint template and the wood template.
The edge of the wooden template is sealed by high-strength resin at the edge of the edge joint and the edge of the hole. The high-strength resin edge sealing thickness is 3 mm. The connecting piece is a galvanized steel plate with the thickness of 3 mm. The connecting sheet is arranged at the joint intersection position of the wood template and the joint template.
Drawings
FIG. 1 is a schematic view of the construction of a wood formwork according to the present invention;
FIG. 2 is a schematic view of a seam template structure;
FIG. 3 is a structural view of an integral wall form with a joint form and a plank form;
FIG. 4 is a joint template and plank sheathing joggle joint fixing structure diagram;
fig. 5 is a sub-corrugation structure of the present invention;
fig. 6 is a basic structure diagram of the main beam of the present invention;
FIG. 7 is a diagram of an external corner main edge node;
FIG. 8 is a diagram of reentrant corner main edge nodes;
FIG. 9 is a diagram of an end main edge node;
FIG. 10 is a schematic view of a main ridge extension structure;
fig. 11(a) is a three-stage water stop bolt;
FIG. 11(b) is an L-shaped split bolt;
FIG. 11(c) shows a conventional split bolt;
FIG. 12 is an overall view of a formwork structure of the present invention;
fig. 13 is a schematic cross-sectional structural view of the formwork structure of the present invention.
Detailed Description
The technical solution of the present invention will be clearly and completely described with reference to the accompanying drawings and a specific embodiment. Obviously, the construction examples provided in the present description are some examples of the present invention, but not all examples, and therefore, the description of the examples should not be taken as a limitation of the technical solution of the present invention.
In the description of the present invention, it should be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "connected," and "connected" are to be construed broadly, e.g., as meaning either a fixed connection, a removable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
The present embodiment is described in detail below with reference to the accompanying fig. 1-13:
a construction method of a building template comprises the following steps:
in the first step, a wooden form 1 as shown in FIG. 1 is fabricated, using a 15mm thick 1830X 915mm plywood flush form. In order to reduce water loss and prevent the template from warping and curling, the edges of the wooden template 1 are sealed by rubber elastic waterproof sealing materials, and the thickness of the self-adhesive rubber edge is 3 mm. The wood template 1 adopts a high-strength film-coated clean water template.
The seam molding board 2 shown in FIG. 2 was manufactured, and the length of the seam molding board 2 of this example was 1830mm as that of the wooden molding board 1. The width of the wooden template 1 is set to be 400mm, and the seam template 2 can be properly widened or reduced according to the height of the wall, namely the seam template is set by referring to the size of the wooden template and the height of the wall, so that the requirement of the pouring height of the wall body after the seam template and the wooden template are spliced is met. The outer side of the seam template 2 is provided with secondary ridge hanging nails 2-1, the length of the secondary ridge hanging nails is 5mm, phi 10, the distance between the secondary ridge hanging nails 2-1 is set according to the expected arrangement distance of the secondary ridges, and the distance in the example is set to be 200 mm; the joint template 2 is provided with bolt holes 2-2 for installing template split bolts, and the bolt holes are phi 20 and have a distance of 600 mm. The seam template 2 can be produced in a factory and customized mode by adopting a high-strength template with the thickness of 15mm, and the turnover use frequency can reach more than 40 times. The inner side and the outer side of the template are both coated with high-strength resin materials. And the edges of the seam template 2 are subjected to edge sealing treatment by rubber elastic waterproof sealing materials, and the thickness of the self-adhesive rubber edge sealing is 3 mm. The gasket is arranged on the periphery of the bolt hole 2-2 and is made of rubber elastic waterproof sealing material with the thickness of 3mm and the diameter of 30mm, and the gasket can effectively prevent water from seeping through the bolt hole.
And secondly, manufacturing secondary ridges 4 as shown in figure 5, namely, adopting a square steel pipe with the diameter of 40 multiplied by 60 multiplied by 3mm, wherein the inner side of the square steel pipe is provided with a groove hanging hole 4-1, and the groove hanging hole 4-1 is matched with the vertical distance of a secondary ridge hanging nail on each joint template. In this embodiment, as shown in fig. 12, three joint templates are respectively disposed at the upper, middle and lower parts of the wall, 3 convenient groove hanging holes 4-1 are also disposed at the inner side of the secondary edge 4 (i.e., the side attached to the template), and the 3 groove hanging holes correspond to the three-layer joint template shown in fig. 12. Of course, the groove hanging holes can be arranged in a plurality of numbers according to a certain interval, and idle groove hanging holes are allowed to exist during use.
And thirdly, manufacturing a main edge 5 as shown in figures 6-9, wherein the main edge adopts 5# U-shaped channel steel 50mm multiplied by 37mm multiplied by 4.5mm, and calculating the bolt hole pitch of the main edge according to the design of the template tie bolt, wherein the bolt hole pitch is generally 600 mm. The end parts of wing plates at two sides of the main ridge are provided with elliptical holes. The oval through nails can be connected with the long main beam and can also be used for installing L-shaped split bolts to connect the main beam of the inner wall with the main beam at the end part; the main beam is transversely arranged and is divided into an inner wall main beam, an end part main beam and a wall corner main beam according to the installation position. When the condition that the length of the main edge is insufficient is found in the construction of the inner wall formwork, the main edge is lapped with the end part of the main edge and is fixed through the oval through nails, so that the main edge is prolonged, as shown in figure 10.
Specifically, the method comprises the following steps: a) manufacturing a 5# U-shaped channel steel external corner shaping main edge: the U-shaped channel steel is adopted, bolt holes are formed in the web plate according to the calculated design pitch, and oval holes are formed in wing plates on two sides of the end portion of the main edge.
b) Manufacturing a 5# U-shaped channel steel internal corner shaping main edge: the U-shaped channel steel is adopted, the inner diameter width of the U-shaped channel steel is 50mm, and the wing plates on one side, facing the end faces of the two U-shaped channel steel, are fixedly connected into an L-shaped right-angle main edge in a full-welding mode.
c) An external corner triangular cushion block 6 is manufactured, the triangular cushion block 6 is shown in figure 7, and is a component which is fixedly connected by three steel plates and has a triangular section, wherein one bottom surface is fixedly connected with a main ridge, and the plate surfaces of two waists are provided with split bolt holes. The triangular cushion blocks 6 are fixed at the end parts of the main ridges of the external corner and tie the ends of the two main ridges 5 in the longitudinal direction and the transverse direction through the split bolts.
And fourthly, preparing a three-section water stop bolt as shown in fig. 11(a) for reinforcing the external wall formwork of the shear wall. The prepared L-shaped split bolts are shown in the attached figure 11(b) and are used for reinforcing the end formwork of the shear wall. Ordinary split bolts are prepared for reinforcing the inner wall as shown in fig. 11(c), or the split bolts are matched with triangular cushion blocks to reinforce the main edge of the external corner. Other components also include: and manufacturing an external corner triangular cushion block for facilitating the pull connection of the split bolt to the main edge end at the external corner position. Manufacturing a U-shaped channel steel clamp for reinforcing a main edge of the U-shaped channel steel; and manufacturing a U-shaped channel steel extension adjusting section shown in figure 10 for adjusting and extending the length of the main edge.
And fifthly, after the wall reinforcing steel bar is concealed and accepted, assembling the shear wall templates, splicing the seam templates manufactured in the first step with the wood templates, reinforcing and fixing the seam templates and the adjacent extension seam templates, the wood templates and the adjacent extension wood templates, and the joint seams of the seam templates and the wood templates by connecting sheets to form a wall surface integral template, and enclosing and reinforcing the periphery of the wall surface template by using a frame to form a whole wall template. The frame is fixed by square steel pipes or battens. The galvanized steel sheet with the thickness of the connecting sheet being 3mm is fixed by 8 screws with the diameter being 8 mm and the length being 12 mm; opposite-pulling bolts (the outer wall adopts three-section water stop bolts, the common bolts of the inner wall are matched with sleeves, and the end parts adopt L-shaped opposite-pulling bolts) are inserted.
And sixthly, inserting split bolts into the bolt holes of the joint template, installing three-section water stop bolts on the outer wall, installing common split bolts on the inner wall, installing L-shaped split bolts at the end part of the wall, and then performing die assembly on the other side template and die assembly on the end template.
And seventhly, vertically hanging the secondary edge manufactured in the second step on the hanging nail of the seam template.
And eighthly, laying main ribs of 5# U-shaped channel steel serving as the shear wall template main ribs, laying main ribs of L-shaped U-shaped channel steel at internal corners for shaping, reinforcing internal corner templates, reinforcing end template L-shaped split bolts, respectively installing the template main ribs manufactured in the third step on the outer sides of the split bolts arranged on the seam templates, and then locking the split bolts.
And ninthly, performing subsequent construction after checking and acceptance.
The shear wall joint template is produced into a high-strength template with the thickness of 15mm in an industrial customized manner. The hole diameter and the distance phi 20@600, the length of the secondary ridge hanging nail of 5mm phi 10@200 is arranged on the template on the outer side, high-strength resin material films are coated on the inner side, the outer side and the hole of the template, the diameter of the rubber elastic waterproof sealing ring with the thickness of 3mm is 30mm on the periphery of the opening of the inner template, and the edges and the peripheries of the wood template and the joint template are subjected to edge sealing treatment by using self-adhesive rubber elastic waterproof sealing materials with the thickness of 3 mm.
The vertical secondary ridges of the invention are square steel pipes with the length of 40mm multiplied by 60mm multiplied by 3mm, the vertical distance is 200mm, the inner side is provided with 3 groove hanging holes, and the distance between the hanging holes is 1150 mm.
The internal diameter of the L-shaped shaping main ridge of the internal corner of the invention adopts a 5# U-shaped channel steel internal corner, the width is 50mm, and the length can be adjusted according to the length of the wall; the length of a 5# U-shaped channel steel main ridge is connected with a length adjusting section, and the length of the adjusting section is 800 mm; the length of a main edge at the end part of the No. 5U-shaped channel steel is +200mm of wall width, generally 400mm, and each side of the main edge extends out of the wall edge by 100 mm;
the L-shaped split bolt is used for reinforcing the end formwork of the shear wall. The U-shaped channel steel clamp is used for reinforcing the main edge of the U-shaped channel steel.
The opposite-pulling bolts at the external corners of the ends of the shear wall adopt common opposite-pulling bolts, and the angles of the opposite-pulling bolts are adjusted by using the triangular cushion blocks so as to reinforce the main edges of the end templates.
The external corner main edge 5# U-shaped channel steel is 50mm multiplied by 37mm multiplied by 4.5mm, the vertical distance is 1150mm, and the hole distance is 600 mm.
The secondary edge of the end template die assembly of the short-limb shear wall adopts a 40mm multiplied by 60mm square steel pipe or a 40mm multiplied by 80mm wood beam, and the main edge is a 5# U-shaped channel steel, and holes are formed in two sides of the U-shaped channel steel and used for enabling L-shaped split bolts to penetrate through.
The formwork supporting method provided by the invention is simple and convenient to construct, avoids punching and cutting of the formwork, has high turnover frequency of main materials of the formwork, reduces the waste of the formwork, can be reused after the formwork is used up, has high residue value rate and good compactness of joints, improves the cast-in-place quality of the wall body, reduces the later maintenance time and improves the working efficiency; the whole quality of the concrete cast-in-place structure is guaranteed, meanwhile, the construction process is simplified, and the construction period is shortened. The invention adopts the rubber elastic waterproof sealing material for edge sealing treatment, has low water loss rate of seams and bolt holes, can prevent the edges of the template from being raised, improves the cast-in-place quality of the wall body, has strong universality and is convenient for large-area construction; the integral quality of the concrete cast-in-place structure is guaranteed, the construction process is simplified, the working efficiency is improved, the construction period is shortened, and good social benefit and economic benefit are achieved.

Claims (6)

1. The utility model provides a building plank sheathing, is stupefied characterized by including whole wall template, the main stupefied and the inferior of vertical setting of horizontal setting: the integral wall template is formed by splicing a wooden template and a joint template, hanging nails with equal intervals are arranged on the outer side of the joint template, and bolt holes are arranged on the joint template according to the design interval of split bolts; the seam template is arranged in a pulling area of the integral wall template; connecting sheets are arranged at the butt joint of the wood template and the joint template, and the connecting sheets are fixed with the wood template and the joint template through bolts; the secondary edge is provided with a groove hanging hole, the lower part of the groove hanging hole is larger than the nail cap of the hanging nail, and the upper part of the groove hanging hole is smaller than the nail cap of the hanging nail.
2. The building plank as defined in claim 1, wherein: the joint formworks are arranged at the top, the middle and the lower parts of the integral wall formwork; the connecting piece is arranged at the butt joint position of the joint template and the wood template and the butt joint position of the extension sections of the joint template and the wood template.
3. The building plank as defined in claim 2, wherein: the edge of the wooden template is sealed by high-strength resin at the edge of the edge joint and the edge of the hole.
4. The building plank as defined in claim 3, wherein: the high-strength resin edge sealing thickness is 3 mm.
5. The building plank sheathing of claim 4, wherein: the connecting piece is a galvanized steel plate with the thickness of 3 mm.
6. The building plank as defined in claim 5, wherein: the connecting sheet is arranged at the joint intersection position of the wood template and the joint template.
CN202020186352.1U 2020-02-19 2020-02-19 Building wood formwork Active CN211775704U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202020186352.1U CN211775704U (en) 2020-02-19 2020-02-19 Building wood formwork

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202020186352.1U CN211775704U (en) 2020-02-19 2020-02-19 Building wood formwork

Publications (1)

Publication Number Publication Date
CN211775704U true CN211775704U (en) 2020-10-27

Family

ID=72908034

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202020186352.1U Active CN211775704U (en) 2020-02-19 2020-02-19 Building wood formwork

Country Status (1)

Country Link
CN (1) CN211775704U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111173256A (en) * 2020-02-19 2020-05-19 中国二十二冶集团有限公司 Building wood formwork and formwork construction method thereof
CN112459462B (en) * 2020-10-30 2022-06-21 晟通科技集团有限公司 Connecting assembly and template frame

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111173256A (en) * 2020-02-19 2020-05-19 中国二十二冶集团有限公司 Building wood formwork and formwork construction method thereof
CN111173256B (en) * 2020-02-19 2024-04-12 中国二十二冶集团有限公司 Building wood formwork and formwork construction method thereof
CN112459462B (en) * 2020-10-30 2022-06-21 晟通科技集团有限公司 Connecting assembly and template frame

Similar Documents

Publication Publication Date Title
CN111173256A (en) Building wood formwork and formwork construction method thereof
CN211775704U (en) Building wood formwork
CN114482375A (en) Integral joint type reinforced concrete laminated slab and construction method
CN210622306U (en) Assembly type floor post-cast strip template splicing structure
CN211817040U (en) Slurry leakage prevention structure at splicing part of assembled laminated slab
CN211200645U (en) Easy-to-detach template for cast-in-place reinforced concrete gutter inlet
CN111877163A (en) Reaming seam construction die pasting process for hollow slab beam
CN213359384U (en) Corner structure post template reinforcing apparatus
CN214220178U (en) Prefabricated disassembly-free side mold and adjustable supporting system for one-step molding of floor water retaining strip
CN211313376U (en) Tool type constructional column template unit and constructional column template structure
CN220953525U (en) Special-shaped retaining wall template
CN111119477A (en) Green fixing device for square steel of vertical template of welded elbow and construction method of green fixing device
CN218479527U (en) Bottom mold sealing structure of double-sided superposed shear wall
CN220909099U (en) Combined double-sided superposed wall bottom mold sealing structure
CN214144269U (en) QX composite heat-preservation external formwork installation structure
CN212562485U (en) Detachable bridge frame reserved hole die
CN113006478B (en) Cast-in-place wall groove mold easy to disassemble and pouring method
CN217896582U (en) Underground works bottom plate post-cast strip template and system
CN214942366U (en) Detachable forming die for one-step forming concrete R angle
CN221321385U (en) Titanium-magnesium fireproof plate assembly type disassembly-free mold construction
CN212201285U (en) Reinforced concrete frame column cross-section control device
CN210659257U (en) Post-cast strip and construction joint position assembled aluminum alloy template
CN117967040B (en) Constructional column formwork structure and special formwork and construction method thereof
CN219973590U (en) Steel plate connecting piece for connecting top of masonry filling wall with profiled steel plate heat-preserving roof
CN219774143U (en) Construction device suitable for subway station wall-separating ditch

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant