Prior art keywords
groove
limiting
clamping
clamping groove
angle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921824429.7U
Other languages
Chinese (zh)
Inventor
李福荣
纪国庆
闫彦
蒋杰
姜欢笑
吴士俊
邱建兴
卓麟
李洪波
刘希民
李恒轩
李学凯
赵文亮
李鼎甲
杜伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinopec Petroleum Engineering Corp
Sinopec Petroleum Construction Shengli Corp
Original Assignee
Sinopec Petroleum Engineering Corp
Sinopec Petroleum Construction Shengli Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinopec Petroleum Engineering Corp, Sinopec Petroleum Construction Shengli Corp filed Critical Sinopec Petroleum Engineering Corp
Priority to CN201921824429.7U priority Critical patent/CN211690934U/en
Application granted granted Critical
Publication of CN211690934U publication Critical patent/CN211690934U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Roof Covering Using Slabs Or Stiff Sheets (AREA)

Abstract

An assembled module connecting structure of an electronic control integrated cabin comprises a roof, limiting blocks and fixing blocks, wherein the limiting blocks are arranged into four symmetrical right-angle bodies, the four right-angle bodies are symmetrically and vertically arranged on four corners of the cabin, symmetrical convex clamping grooves are formed in the central parts of a first right-angle edge and a second right-angle edge of each limiting block, the convex parts are arranged into sliding grooves, the first right-angle edge clamping grooves are arranged into first clamping grooves, two edges of each first clamping groove are arranged into first limiting plates, and the sliding grooves are first sliding grooves; the second right-angle side clamping groove is arranged as a second clamping groove, two sides of the second clamping groove are arranged as second limiting plates, and the sliding groove is a second sliding groove; the fixed block is in a groove shape, and the upward oriented side of the groove of the fixed block is welded at the upper end of the outer side wall of the limiting block; the first clamping groove and the second clamping groove of the limiting blocks on the four corners are internally provided with a wall plate provided with a window or a door, and the convex edges arranged at the bottom of the roof are arranged in the grooves of the fixing blocks to form the electric control integrated cabin.

Description

Automatically controlled integration cabin assembled module connection structure
Technical Field
The utility model belongs to the technical field of electrical equipment, concretely relates to automatically controlled integration cabin assembled module connection structure.
Background
The electric control integrated cabin is based on the mature manufacturing technology of products of an outdoor box-type substation, combines the requirements of standardized design, integrated assembly and modularized installation, and system equipment such as electric power, automatic control, communication and the like are installed and debugged in a factory and are installed in a movable, sealed, moistureproof and rustproof prefabricated cabin body, so that the construction of a valve chamber equipment room with three types, namely structural integration, power distribution integration and service integration is realized, and the electric control integrated cabin is an innovative quick distribution type room building mode.
The existing electrically-controlled integrated cabin body frameworks are all of a structural steel welded framework structure, when the installing is carried out, the body frameworks are firstly conveyed to an installing place to be installed, four wallboards are fixedly connected in the installing process to be installed, when workers connect and fix the wallboards, the horizontal verticality of the wallboards is guaranteed, the solidity of the fixing between the wallboards is required to be confirmed, the process of installing and fixing is complex, and the installing efficiency is low.
SUMMERY OF THE UTILITY MODEL
The utility model aims at providing an automatically controlled integration cabin assembled module connection structure overcomes the defect that above-mentioned prior art exists. The device has the characteristics of convenience in disassembly, assembly and transportation, improves the labor efficiency and reduces the labor intensity of workers.
In order to achieve the above object, the utility model provides a following technical scheme:
an assembled module connecting structure of an electronic control integrated cabin comprises a roof, limiting blocks, fixing blocks, lengthened bolts and expansion bolts, wherein the limiting blocks are arranged into four symmetrical right-angle bodies which are symmetrically and vertically arranged at four corners of a wall, symmetrical clamping grooves with convex shapes are arranged at the central parts of a first right-angle edge and a second right-angle edge of each limiting block, the convex parts are arranged into sliding grooves, the clamping grooves with the first right-angle edges are arranged into first clamping grooves, two edges of each first clamping groove are arranged into first limiting plates, and the sliding grooves are first sliding grooves; the second right-angle side clamping groove is arranged as a second clamping groove, two sides of the second clamping groove are arranged as second limiting plates, and the sliding groove is a second sliding groove; the fixed block is in a groove shape, and the upward oriented side of the groove of the fixed block is welded at the upper end of the outer side wall of the limiting block; the first clamping groove and the second clamping groove of the limiting block are two clamping grooves for placing a wallboard provided with a window or a door, and the bottom of the edge of the roof (23) is provided with a convex edge matched with the groove of the fixing block.
The roof is arranged to be a rectangular plate, convex ribs matched with the grooves of the fixing block are arranged at the bottoms of the four corners of the roof, and threaded holes concentric with the third threaded holes of the lengthened bolts are formed in the convex ribs.
The middle parts of the two sides of the fixed block correspond to the upper parts of the two first limiting plates and are provided with third threaded holes of concentric lengthened bolts, and the lower parts of the two first limiting plates correspond to the concentric positions and are provided with first threaded holes of expansion bolts.
The limiting block is provided with sealing gaskets on the upper end surface and the lower end surface of the limiting block.
Compared with the prior art, the utility model, the beneficial effects are that:
1. the utility model discloses in have first centre gripping groove between two first limiting plates, second centre gripping groove has between two second limiting plates, when the installation, the staff slides the stopper to between the adjacent wallboard through first spout and second spout, make the wallboard be located between first centre gripping groove and the second centre gripping groove, it is spacing to the wallboard, expansion bolts runs through two first screw holes and second screw hole, and the nut on the locking expansion bolts, it is fixed with wallboard and first limiting plate and second limiting plate, it is fixed with four wallboard connections when guaranteeing wallboard level vertically, it is convenient to provide for the installation of wallboard, after the staff dismantles expansion bolts, through the spout directly with the stopper roll-off, dismantle the wallboard, moreover, the steam generator is simple in structure, it is convenient to use, and the installation efficiency is improved.
2. The utility model discloses well fixed block welding is at stopper upper end lateral wall, and is connecting fixed back with the wallboard, and the roof bottom has the bead, places the bead in the recess of fixed block, and extension bolt runs through the bead and the wallboard is fixed on first limiting plate, makes the roof be connected as an organic wholely with the wallboard, makes wholly more durable, has improved holistic crushing resistance, seals the gap between roof and the connecting piece through sealed the pad simultaneously, has improved the holistic leakproofness of equipment.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention. In the drawings:
FIG. 1 is a schematic structural view of a limiting block and a fixing block of the present invention;
FIG. 2 is a top view of FIG. 1;
fig. 3 is a schematic view of a connection structure of the limiting block, the fixing block and the roof.
In the figure: 1. a limiting block; 101. a first chute; 102. a second chute; 103. a gasket; 11. a first limit plate; 111. a first threaded hole; 12. a second limiting plate; 121. a second threaded hole; 13. a first clamping groove; 14. a second clamping groove; 15. an expansion bolt; 2. a fixed block; 201. a third threaded hole; 21. a card slot; 22. the bolts are lengthened.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-3, the present invention provides the following technical solutions: the assembled module connecting structure of the electric control integrated cabin comprises a roof 23, a limiting block 1, a fixing block 2, a lengthened bolt 22 and an expansion bolt 15, wherein the limiting block is arranged into four symmetrical right-angle bodies, the limiting blocks are symmetrically and vertically arranged on four corners of a wall, symmetrical clamping grooves with convex shapes are arranged at the central parts of a first right-angle edge and a second right-angle edge of each limiting block, the convex parts are arranged into sliding grooves, the clamping grooves with the first right-angle edges are arranged into first clamping grooves 13, two edges of each first clamping groove are arranged into first limiting plates 11, and each sliding groove is a first sliding groove 101; the second right-angle side clamping groove is set as a second clamping groove 14, two sides of the second clamping groove are set as second limiting plates 12, and the sliding groove is a second sliding groove 102; the fixing block 2 is in a groove shape, and one side, which is oriented upwards, of the groove of the fixing block 2 is welded at the upper end of the outer side wall of the limiting block 1; the utility model discloses a building structure, including stopper, window or door, roof (23) limit bottom, first centre gripping groove and second centre gripping groove of stopper are two centre gripping grooves of putting into the wallboard that is equipped with the window or door, roof (23) limit bottom be equipped with fixed block recess assorted bead, with the wallboard that is equipped with the window or door of putting into in the first centre gripping groove and the second centre gripping groove of stopper on four angles, insert the bead that the roof 23 four sides bottom was established in the fixed block recess, constitute the cabin that connects into by automatically controlled integration cabin assembled module connection structure on the sled piece.
In this embodiment, stopper 1 is when the installation, the staff slides stopper 1 to between the adjacent wallboard through first spout 101 and second spout 102, make the wallboard be located between first centre gripping groove 13 and the second centre gripping groove 14, it is spacing to the wallboard, expansion bolt 15 runs through two first screw holes 111 and second screw hole 121, and lock the nut on expansion bolt 15, it is fixed with wallboard and first limiting plate 11 and second limiting plate 12, connect four wallboards when guaranteeing wallboard horizontal vertically and fixedly, it is convenient to provide for the installation of wallboard. During disassembly, after the expansion bolt 15 and the lengthened bolt 22 are disassembled by a worker, the limiting block 1 directly slides out through the sliding groove. Dismantle the wallboard, moreover, the steam generator is simple in structure, high durability and convenient use, the dismouting efficiency is improved, 2 welding of fixed block are at the lateral wall of stopper 1, the intermediate position department of fixed block 2 sets up fluted 21, the left side of fixed block 2 is equipped with extension bolt 22, extension bolt 22 runs through fixed block 2 and 11 threaded connection of first limiting plate, after four wallboard connections are fixed, because the roof bottom has the bead, place the bead in recess 21, extension bolt 22 runs through the bead and the wall body is fixed on first limiting plate 11, make the roof be connected as an organic whole with the wallboard, make wholly more durable, holistic crushing resistance has been improved, simultaneously seal up the gap between roof and the wallboard through sealed pad 103, the holistic leakproofness of equipment has been improved.
The utility model discloses a theory of operation and use flow: the utility model discloses during the installation use, whole connection structure's quantity is four, four connection structure fix the four corners at the four sides wallboard respectively, the staff slides stopper 1 to between the adjacent wallboard through first spout 101 and second spout 102, make the wallboard be located between first centre gripping groove 13 and the second centre gripping groove 14, it is spacing to the wallboard, expansion bolts 15 runs through two first screw hole 111 and second screw hole 121, and lock the nut on expansion bolts 15, it is fixed with wallboard and first limiting plate 11 and second limiting plate 12, it is fixed to connect the wallboard at the four sides when guaranteeing wallboard level vertically, it is convenient to provide for the installation of wallboard. When dismantling, the staff dismantles expansion bolts 15 backs, directly with stopper 1 roll-off through the spout, dismantles the wallboard, simple structure, and it is convenient to use, has improved dismouting efficiency. After the four-side wall boards are fixedly connected, the ribs are arranged at the bottom of the roof and are placed in the grooves 21, the lengthened bolts 22 penetrate through the ribs and the wall and are fixed on the first limiting plate 11, so that the roof and the wall boards are connected into a whole, the whole structure is firmer, the whole pressure resistance is improved, meanwhile, the gap between the roof and the wall boards is sealed through the sealing gaskets 103, and the whole sealing performance of the equipment is improved.

Claims (4)

1. The utility model provides an automatically controlled integration cabin assembled module connection structure, includes roof (23), stopper (1), fixed block (2), extension bolt (22) and expansion bolts (15), its characterized in that: the limiting block is arranged into four symmetrical right-angle bodies, four corners of the cabin are symmetrically and vertically arranged, symmetrical clamping grooves with convex shapes are arranged at the central parts of a first right-angle edge and a second right-angle edge of the limiting block, the convex parts are arranged into sliding grooves, the clamping grooves of the first right-angle edge are arranged into first clamping grooves (13), two edges of each first clamping groove are arranged into first limiting plates (11), and each sliding groove is a first sliding groove (101); the second right-angle side clamping groove is arranged as a second clamping groove (14), two sides of the second clamping groove are arranged as second limiting plates (12), and the sliding groove is a second sliding groove (102); the fixing block (2) is in a groove shape, and one side, which is oriented upwards, of the groove of the fixing block (2) is welded at the upper end of the outer side wall of the limiting block (1); the first clamping groove and the second clamping groove of the limiting block are two clamping grooves of a wallboard provided with a window or a door, and the bottom of the edge of the roof (23) is provided with a convex edge matched with the groove of the fixing block.
2. The assembled module connecting structure of the electric control integrated cabin as claimed in claim 1, wherein: the roof is designed into a rectangular plate, the bottom edge of the roof is provided with a convex edge matched with the groove of the fixing block, and the convex edge is provided with a threaded hole concentric with the third threaded hole (201) of the lengthened bolt.
3. The assembled module connecting structure of the electric control integrated cabin as claimed in claim 1, wherein: the middle parts of the two sides of the fixed block correspond to the upper parts of the two first limiting plates and are provided with third threaded holes of concentric lengthened bolts, and the lower parts of the two first limiting plates are provided with first threaded holes (111) of expansion bolts corresponding to the concentric positions.
4. The assembled module connecting structure of the electric control integrated cabin as claimed in claim 1, wherein: the limiting block is provided with sealing gaskets (103) on the upper end face and the lower end face of the limiting block.
CN201921824429.7U 2019-10-28 2019-10-28 Automatically controlled integration cabin assembled module connection structure Expired - Fee Related CN211690934U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921824429.7U CN211690934U (en) 2019-10-28 2019-10-28 Automatically controlled integration cabin assembled module connection structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921824429.7U CN211690934U (en) 2019-10-28 2019-10-28 Automatically controlled integration cabin assembled module connection structure

Publications (1)

Publication Number Publication Date
CN211690934U true CN211690934U (en) 2020-10-16

Family

ID=72785752

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921824429.7U Expired - Fee Related CN211690934U (en) 2019-10-28 2019-10-28 Automatically controlled integration cabin assembled module connection structure

Country Status (1)

Country Link
CN (1) CN211690934U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113374087A (en) * 2021-06-08 2021-09-10 北京龙鼎源科技股份有限公司 Construction method for skid-mounted integrated valve chamber equipment room

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113374087A (en) * 2021-06-08 2021-09-10 北京龙鼎源科技股份有限公司 Construction method for skid-mounted integrated valve chamber equipment room

Similar Documents

Publication Publication Date Title
CN210529943U (en) Assembled container frame structure
CN211690934U (en) Automatically controlled integration cabin assembled module connection structure
CN103628710B (en) A kind of portable detachable box-type medium-voltage frequency conversion chamber
CN101906818B (en) Assembled earthquake-proof board room
CN212613207U (en) Box-shaped yin-yang staggered special-shaped glass curtain wall
CN205864333U (en) Photovoltaic watt component
CN207194519U (en) Container house with improved supporting structure
CN203339639U (en) Lightning arrester preventing water seepage and leakage of steel plate tile roof
CN201574661U (en) Door window structure convenient in field installation
CN208472979U (en) A kind of modularized house attachment device
CN209665264U (en) One kind taking out tool for nuclear power station self-sealing gate valve self-sealing packing pressure ring
CN203742040U (en) Novel combined curtain wall system
CN203361342U (en) Rapidly-assembled and disassembled and flexibly-combined container type movable house
CN106059454B (en) Photovoltaic watt component
CN204663046U (en) A kind of novel container roofing
CN204407718U (en) Full assembly type GGD low-voltage distribution cabinet
CN216446592U (en) Prevent assembly room of wind husky
CN220521765U (en) Light steel roofing structure for factory building
CN221201715U (en) Plug-in busbar base
CN211396373U (en) Decorative wallboard convenient to installation
CN219492610U (en) Water pump control cabinet
CN204859080U (en) New -type photovoltaic tile
CN203701382U (en) Unit type and component type combined curtain wall system
CN217461867U (en) Row door and window splicing mechanism and row door and window splicing system
CN219458477U (en) Combined box-type transformer substation

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201016