CN211164518U CN201921715787.4U CN201921715787U CN211164518U CN 211164518 U CN211164518 U CN 211164518U CN 201921715787 U CN201921715787 U CN 201921715787U CN 211164518 U CN211164518 U CN 211164518U
Authority
CN
China
Prior art keywords
hole
precast concrete
pipe body
concrete block
air conditioner
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921715787.4U
Other languages
Chinese (zh)
Inventor
姚文京
李香薇
李宪
赵阳
刘有帅
安枫
高美丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Kegong Construction Group Co., Ltd
Original Assignee
Hebei Science And Engineering Construction Engineering Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Science And Engineering Construction Engineering Group Co ltd filed Critical Hebei Science And Engineering Construction Engineering Group Co ltd
Priority to CN201921715787.4U priority Critical patent/CN211164518U/en
Application granted granted Critical
Publication of CN211164518U publication Critical patent/CN211164518U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses an air conditioner hole precast concrete piece mould, constitute the casing of pouring the chamber including two mutual locks, in each two opposite sides of casing are constructed respectively first half pipe and second half pipe, in the upper end of casing is constructed half and is pour the mouth, and two halves sprue gate, two first half pipes and two second half pipes form complete sprue gate, first body and second body along with the mutual lock of two casings respectively, the axis coincidence of first body and second body is the tilt state, and sprue gate, first body and second body all with pour the chamber intercommunication, still disclose the air conditioner hole precast concrete piece of making by above-mentioned mould. The utility model provides a rainwater seepage, outer facade air conditioner hole position are unified and plastering layer, heat preservation, decorative layer receive the disturbance problem around the infilled wall brickwork air conditioner hole, are applicable to precast concrete mould technical field in the civil construction.

Description

Air conditioner hole precast concrete piece mould and air conditioner hole precast concrete piece
Technical Field
The utility model belongs to the technical field of precast concrete mould among the civil construction, specifically speaking relates to an air conditioner hole precast concrete piece mould and air conditioner hole precast concrete piece.
Background
In residential building engineering, an air conditioner hole is reserved on an outer wall surface, and for a masonry outer wall, a traditional construction method comprises the steps of drilling holes by a water drill after masonry is completed, and then embedding a sleeve into the holes. In the construction method, the sleeve and the drill hole cannot be tightly bonded, so that rainwater leakage around the air conditioner hole is easily caused, and meanwhile, the drill hole cannot ensure the gradient and the position accuracy of the hole, so that unsmooth drainage can be caused, the upper position and the lower position of a floor are not uniform, and the appearance quality of an outer vertical surface is influenced. Meanwhile, the impact force of the rhinestone can disturb a plastering layer, a heat insulation layer, a decorative layer and surrounding masonry, and the engineering quality is affected.
SUMMERY OF THE UTILITY MODEL
The utility model provides a solve rainwater seepage, outer facade air conditioner hole position non-unity around infilled wall brickwork air conditioner hole and plastering layer, heat preservation, decorative layer receive the air conditioner hole precast concrete piece mould of disturbance problem.
In order to achieve the above object, the utility model adopts the following technical scheme:
the utility model provides an air conditioner hole precast concrete piece mould, includes that two mutual locks constitute the casing of pouring the chamber, in each two opposite sides of casing structure respectively have first half pipe and second half pipe, in the upper end of casing structure has half pouring the mouth, and two halves pouring gate, two first half pipes and two second half pipes form complete pouring gate, first body and second body along with the mutual lock of two casings respectively, the axis coincidence of first body and second body is the tilt state, and pouring gate, first body and second body all with pour the chamber intercommunication.
Further, one end, far away from the second pipe body, of the first pipe body is lower than any end of the second pipe body.
Furthermore, a flange extending inwards along the radial direction is formed at the end part of one end of the first pipe body, which is far away from the second pipe body, and the flange is formed by buckling two half flanges respectively formed on the two first half pipes with the two shells.
Furthermore, a first annular clamping groove extending inwards along the radial direction of the first pipe body is formed in the outer peripheral surface of the first pipe body, and the two first half pipes are connected through a clamping hoop tightened on the first annular clamping groove.
Furthermore, a second annular clamping groove extending inwards in the radial direction is formed in the outer peripheral surface of the second pipe body, and the two second half pipes are connected through a clamping hoop tightened on the second annular clamping groove.
Furthermore, a first rubber layer is adhered to the inner wall of the first half pipe.
Furthermore, a second rubber layer is adhered to the inner wall of the second half pipe.
Furthermore, a first half hole and a second half hole are formed in the buckling position of the shell body, the first half hole and the second half hole are respectively formed in the lower portion and the upper portion of the shell body and are communicated with the pouring cavity, the two first half holes and the two second half holes respectively form a complete first through hole and a complete second through hole when the two shell bodies are buckled, and the first through hole and the second through hole are respectively detachably connected with a plug.
The embodiment also discloses an air conditioner hole precast concrete piece made through above-mentioned air conditioner hole precast concrete piece mould, including the concrete piece body, the shape of concrete piece body with it is corresponding to pour the chamber, it has the sleeve pipe to run through on the concrete piece body, the axis of sheathed tube coincides with the axis of first body, and the inner wall looks adaptation of sheathed tube outer wall and first body and second body.
Further, the sleeve is of a tubular structure made of PVC materials.
The utility model discloses owing to adopted foretell structure, it compares with prior art, and the technical progress who gains lies in: the two first half pipes and the two second half pipes are respectively buckled with the two shells to form a complete pouring gate, a first pipe body and a second pipe body, two ends of the sleeve are clamped by the first pipe body and the second pipe body, the sleeve penetrates through the pouring cavity, concrete is poured into the pouring cavity from the pouring gate, the axes of the first pipe body and the second pipe body are overlapped and in an inclined state, so that the sleeve is ensured to keep a required inclination angle in the pouring process and after pouring forming, after the pouring forming, the two shells are disassembled to obtain an air-conditioning hole precast concrete block, then, before the outer wall masonry is built, the position of an air-conditioning reserved hole is accurately positioned according to a positioning line and an elevation control point, bricks are reasonably arranged, building blocks at the air-conditioning hole are replaced by the air-conditioning hole precast concrete block by adjusting the size of the surrounding masonry, and when an inner decorative layer and an outer decorative layer are built, the inner decorative layer and the outer decorative layer are flush with the, to sum up, the utility model provides a rainwater seepage, outer facade air conditioner hole position are unified and plastering layer, heat preservation, decorative layer receive the problem of disturbance around the infilled wall brickwork air conditioner hole, have guaranteed engineering entity quality and have perceived the quality.
Drawings
The accompanying drawings are included to provide a further understanding of the invention, and are incorporated in and constitute a part of this specification, illustrate embodiments of the invention, and together with the description serve to explain the invention and not to limit the invention.
In the drawings:
fig. 1 is a schematic structural diagram of an embodiment of the present invention;
fig. 2 is a schematic structural view of another angle according to the embodiment of the present invention;
fig. 3 is a schematic structural diagram of a housing according to an embodiment of the present invention;
fig. 4 is a schematic structural view of a plug according to an embodiment of the present invention;
fig. 5 is the utility model discloses the structure schematic diagram of air conditioner hole precast concrete piece.
Labeling components: 1-shell, 2-half sprue gate, 3-second half pipe, 4-second annular clamping groove, 5-first half pipe, 6-half flange, 7-first annular clamping groove, 8-first half hole, 9-second half hole, 10-plug, 1001-plug part, 1002-limit table, 11-concrete block body and 12-sleeve.
Detailed Description
The preferred embodiments of the present invention will be described below with reference to the accompanying drawings. It should be understood that the preferred embodiments described herein are for purposes of illustration and explanation only and are not intended to limit the invention.
Embodiment 1 an air conditioner hole precast concrete piece mould
The embodiment discloses an air conditioner hole precast concrete piece mould, as shown in fig. 1, fig. 3, constitute the casing 1 of pouring the chamber including two mutual locks, two opposite sides at every casing 1 are constructed respectively with first half pipe 5 and second half pipe 3, be constructed at the upper end of casing 1 and half pour the mouth, two half sprue gates 2, two first half pipe 5 and two second half pipe 3 form complete sprue gate along with two casing 1's mutual locks respectively, first body and second body, the axis coincidence of first body and second body is the tilt state, and the sprue gate, first body and second body all with pour the chamber intercommunication.
In the embodiment, one end of the first pipe body, which is far away from the second pipe body, is lower than any end of the second pipe body, that is, the whole height of the first pipe body is lower than the second pipe body, and in order to prevent the sleeve 12 from being fixed between the two shells 1 and from axial displacement during casting, a flange extending radially inward is formed at one end of the first pipe body, which is far away from the second pipe body, and the flange is formed by buckling two half flanges 6 respectively formed on two first half pipes 5 along the two shells 1, and because the sleeve 12 moves downward along the axial line of the first pipe body under the impact force of gravity and cast concrete during casting, the flange hinders the movement of the sleeve 12. In this embodiment, another flange is also formed at the end of the second tube body away from the first tube body, and the shape and structure of the flange are consistent with those of the flange on the first tube body, so that the displacement of the sleeve 12 is further limited.
In order to facilitate clamping of the sleeve 12 and to make the connection between the two housings 1 more stable, the first pipe body is formed with a first annular clamping groove 7 extending radially inward along the outer peripheral surface thereof, and the two first half pipes 5 are connected by a clamp tightened on the first annular clamping groove 7. A second annular groove 4 is formed on the outer peripheral surface of the second pipe body so as to extend radially inward, and the two second pipe halves 3 are connected by a band tightened in the second annular groove 4. In this embodiment, a first rubber layer (not shown) is adhered to the inner wall of the first half pipe 5, and a second rubber layer (not shown) is adhered to the inner wall of the second half pipe 3, so that the tightening ability of the first and second pipe bodies to the sleeve 12 is improved, slipping is prevented, and the sleeve 12 is not easily constrained to be deformed.
In order to ensure that the pouring is sufficient, the incomplete pouring is avoided, as shown in fig. 2, a first half hole 8 and a second half hole 9 are formed in the buckling position of the shell 1, the first half hole 8 and the second half hole 9 are respectively formed in the lower portion and the upper portion of the shell 1 and are communicated with the pouring cavity, when the two shells 1 are buckled, the two first half holes 8 and the two second half holes 9 respectively form a complete first through hole and a complete second through hole, the first through hole and the second through hole are respectively detachably connected with a plug 10, whether the concrete flows out from the first through hole or the second through hole is observed, whether the pouring is sufficient at the position and below the position is determined, and the corresponding first through hole or the second through hole is plugged by the plug 10 after the pouring is sufficient. The plug 10 of this embodiment preferably has a structure, as shown in fig. 4, including a cylindrical plug portion 1001 fitted to the first through hole or the second through hole, a limit stop 1002 integrally formed at an end of the plug portion 1001 away from the casting cavity, and when the limit stop 1002 is attached to the outer surface of the housing 1, an end of the plug portion 1001 away from the limit stop 1002 is flush with the inner wall of the housing 1.
The embodiment of the utility model provides an operation process as follows:
two first half pipes 5 and two second half pipes 3 form complete sprue gates, first body and second body along with the mutual lock of two casings 1 respectively, the both ends of sleeve pipe 12 are by first body and second body centre gripping this moment, and sleeve pipe 12 runs through and pours the chamber, the intracavity is pour into by the sprue gate to the concrete, because the axis coincidence of first body and second body is the tilt state, guarantee like this that sleeve pipe 12 keeps required inclination after pouring process and pouring shaping, after pouring shaping, demolish two casings 1 and can obtain the precast concrete piece in air conditioning hole.
Embodiment 2 an air conditioning hole precast concrete piece
The embodiment discloses an air-conditioning hole precast concrete block, which is made by the air-conditioning hole precast concrete block mould described in embodiment 1, and comprises a concrete block body 11, wherein the shape of the concrete block body 11 corresponds to that of a pouring cavity, a sleeve 12 penetrates through the concrete block body 11, the axis of the sleeve 12 coincides with the axis of a first pipe body, and the outer wall of the sleeve 12 is matched with the inner walls of the first pipe body and a second pipe body. The sleeve 12 is a tubular structure made of PVC material. This concrete block body 11 is preferred for the square, and the length of a side is 250mm, and the slope of sleeve 12 is 5, and the diameter of sleeve 12 is 75mm, and concrete block body 11 is C15 pea gravel concrete, and sleeve 12 length is: the sum of the thickness of the masonry, the thickness of the decorative surface layer on the indoor side, the thickness of the heat-insulating layer on the outdoor side and the thickness of the decorative surface layer.
The utility model discloses the work progress as follows:
before the outer wall brickwork was built by laying bricks or stones, go out the position in air conditioner reservation hole according to the accurate location of line of location and elevation control point, rationally arrange the brick, through brickwork size around the adjustment, replace the building block of air conditioner hole department with air conditioner hole precast concrete piece, when treating inside and outside decorative layer construction, inside and outside decorative surface layer and reservation sleeve 12 parallel and level, rainwater seepage around the infilled wall brickwork air conditioner hole has been solved to this embodiment, outer facade air conditioner hole position is non-uniform and the layer of plastering, the heat preservation, the problem that the decorative layer received the disturbance, engineering entity quality and impression quality have been guaranteed.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments described in the foregoing embodiments, or equivalents may be substituted for elements thereof. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the scope of the protection of the claims of the present invention.

Claims (10)

1. The utility model provides an air conditioner hole precast concrete piece mould which characterized in that: the casting device comprises two shells which are mutually buckled to form a casting cavity, wherein a first half pipe and a second half pipe are respectively constructed on two opposite sides of each shell, a half casting opening is constructed at the upper end of each shell, the two half casting openings, the two first half pipes and the two second half pipes are respectively buckled with the two shells to form a complete casting opening, a first pipe body and a second pipe body, the axes of the first pipe body and the second pipe body are overlapped and are in an inclined state, and the casting opening, the first pipe body and the second pipe body are communicated with the casting cavity.
2. An air conditioning hole precast concrete block mould according to claim 1, characterized in that: one end of the first pipe body, which is far away from the second pipe body, is lower than any end of the second pipe body.
3. An air conditioning hole precast concrete block mould according to claim 2, characterized in that: and a flange which extends inwards along the radial direction of the first pipe body is formed at the end part of one end of the first pipe body, which is far away from the second pipe body, and the flange is formed by buckling two half flanges which are respectively formed on two first half pipes with the two shells.
4. An air conditioning hole precast concrete block mould according to claim 1, characterized in that: the first pipe body is provided with a first annular clamping groove which extends inwards along the radial direction, and the two first half pipes are connected through a hoop tightly tied on the first annular clamping groove.
5. An air conditioning hole precast concrete block mould according to claim 1, characterized in that: and a second annular clamping groove extending inwards along the radial direction is formed on the outer peripheral surface of the second pipe body, and the two second half pipes are connected through a clamping hoop tightly tightened on the second annular clamping groove.
6. An air conditioning hole precast concrete block mould according to claim 1, characterized in that: and a first rubber layer is adhered to the inner wall of the first half pipe.
7. An air conditioning hole precast concrete block mould according to claim 1, characterized in that: and a second rubber layer is adhered to the inner wall of the second half pipe.
8. An air conditioning hole precast concrete block mould according to claim 1, characterized in that: the shell body buckling position is provided with a first half hole and a second half hole, the first half hole and the second half hole are respectively arranged at the lower part and the upper part of the shell body and are communicated with the pouring cavity, when the two shell bodies are buckled, the two first half holes and the two second half holes respectively form a complete first through hole and a complete second through hole, and the first through hole and the second through hole are respectively detachably connected with a plug.
9. An air conditioning hole precast concrete block manufactured by the air conditioning hole precast concrete block mold according to any one of claims 1 to 8, characterized in that: the concrete block comprises a concrete block body, wherein the shape of the concrete block body corresponds to the pouring cavity, a sleeve penetrates through the concrete block body, the axis of the sleeve coincides with the axis of the first pipe body, and the outer wall of the sleeve is matched with the inner walls of the first pipe body and the second pipe body.
10. An air conditioning hole precast concrete block according to claim 9, characterized in that: the sleeve is of a tubular structure made of PVC materials.
CN201921715787.4U 2019-10-14 2019-10-14 Air conditioner hole precast concrete piece mould and air conditioner hole precast concrete piece Active CN211164518U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921715787.4U CN211164518U (en) 2019-10-14 2019-10-14 Air conditioner hole precast concrete piece mould and air conditioner hole precast concrete piece

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921715787.4U CN211164518U (en) 2019-10-14 2019-10-14 Air conditioner hole precast concrete piece mould and air conditioner hole precast concrete piece

Publications (1)

Publication Number Publication Date
CN211164518U true CN211164518U (en) 2020-08-04

Family

ID=71818730

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921715787.4U Active CN211164518U (en) 2019-10-14 2019-10-14 Air conditioner hole precast concrete piece mould and air conditioner hole precast concrete piece

Country Status (1)

Country Link
CN (1) CN211164518U (en)

Similar Documents

Publication Publication Date Title
CN207177063U (en) Pre-buried air conditioner comdenstion water drain pipe sheathed tube prefabricated building block
CN107460981B (en) Template-free cast-in-place heat-insulation decorative molding wall and construction method
CN108755972B (en) Foot pad for prefabricated part and using method thereof
CN216131506U (en) Hydraulic engineering prefabricated inspection shaft and drain pipe connection structure
WO2015076680A1 (en) Method and device for providing pipe joint in concrete wall
CN211164518U (en) Air conditioner hole precast concrete piece mould and air conditioner hole precast concrete piece
CN202164698U (en) Steel die for sewage inspection well
CN111779159A (en) Concrete block wrapping process for wall bushing
CN111136763A (en) Manufacturing method of air conditioner hole and exhaust hole concrete precast block
CN211172673U (en) Brickwork and mold processing thereof
CN113373985B (en) Basement waterproof construction method
KR100805622B1 (en) Mold device for manufacturing multi-divided segments of sectional manhole
KR200393504Y1 (en) Bit piping protection sleeve of building
CN206667305U (en) Basement seepage point gradually leak stopping structure
TWI702330B (en) Reinforcement connector and precast construction structure having the same
CN113445609B (en) Well chamber prefabricated by municipal rainwater and sewage and well chamber pipe orifice plugging construction method
CN205617787U (en) Positioning device free from opening reserved bolt hole of climbing frame on aluminum alloy template
CN208009731U (en) A kind of prefabricated components bearing diagonal bottom embedded part and its pre-buried structure
CN207469533U (en) A kind of exterior finish modeling structure of two-sided prefabricated overlapping wall
CN217501049U (en) A can have enough to meet need design mould for building wall body air conditioner hole
CN110616848A (en) Pipeline wall-penetrating prefabricated unit and manufacturing tool
KR101783246B1 (en) Construction methode of waterway
CN220318582U (en) Well wall construction template of municipal administration tube well
CN216239260U (en) Water supply and drainage embedded part for building
CN220468930U (en) Cover digs vertical structure post and pours construction structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 050000 Xinhua Road 917, Qiaoxi District, Shijiazhuang, Hebei

Patentee after: Hebei Kegong Construction Group Co., Ltd

Address before: 050000 Xinhua Road 917, Qiaoxi District, Shijiazhuang, Hebei

Patentee before: HEBEI SCIENCE AND ENGINEERING CONSTRUCTION ENGINEERING GROUP Co.,Ltd.

CP01 Change in the name or title of a patent holder