CN211037001U CN201921772614.6U CN201921772614U CN211037001U CN 211037001 U CN211037001 U CN 211037001U CN 201921772614 U CN201921772614 U CN 201921772614U CN 211037001 U CN211037001 U CN 211037001U
Authority
CN
China
Prior art keywords
crossbeam
clamping plate
fence pole
fixed
pile reinforcing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921772614.6U
Other languages
Chinese (zh)
Inventor
苏鹏冲
袁仕贵
张家昆
刘春云
王朝鲜
杨爱珠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan No2 Railway Engineering Co
Original Assignee
Yunnan No2 Railway Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan No2 Railway Engineering Co filed Critical Yunnan No2 Railway Engineering Co
Priority to CN201921772614.6U priority Critical patent/CN211037001U/en
Application granted granted Critical
Publication of CN211037001U publication Critical patent/CN211037001U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model provides a detachable deep basal pit fender pile reinforcing apparatus relates to the foundation ditch reinforcement field. This detachable deep basal pit fender pile reinforcing apparatus, including first fence pole, the second fence pole, first crossbeam and second crossbeam, first fence pole and second fence pole are to the vertical isolation reinforcement of foundation ditch lateral wall, one side that the second crossbeam is close to the second fence pole is connected with the card post, one side that first crossbeam is close to first fence pole also is connected with the card post, the lateral wall of first fence pole and second fence pole seted up with card post assorted bayonet socket, one side fixedly connected with fixed column that the card post was kept away from to first crossbeam, the inside of second crossbeam seted up with fixed column assorted cavity groove, be provided with locking mechanism between fixed column and the second crossbeam. This detachable deep basal pit fender pile reinforcing apparatus is convenient for install and dismantle, and repeatedly usable can slide first crossbeam according to the width of foundation ditch to adjust the support distance, the person of facilitating the use uses.

Description

Detachable deep basal pit fender pile reinforcing apparatus
Technical Field
The utility model relates to a foundation ditch reinforcing technical field specifically is a detachable deep basal pit fender pile reinforcing apparatus.
Background
In the urban construction process, underground comprehensive pipe galleries, rail transit, deep foundation pits of underground stations and underground engineering projects of partial high-rise building underground garages need to be constructed, and engineering support and reinforcement are carried out on the side walls of the foundation pits in the excavation process of the foundation pits.
The most fixed device that uses of current strutting reinforcing apparatus, inconvenient installation and dismantlement because can not used repeatedly, cause the wasting of resources to the length of crossbeam generally can not just satisfy the width of foundation ditch, causes the user inconvenient, to prior art not enough, the utility model provides a detachable deep basal pit fender pile reinforcing apparatus, with the solution above-mentioned problem.
SUMMERY OF THE UTILITY MODEL
Technical problem to be solved
Not enough to prior art, the utility model provides a detachable deep basal pit fender pile reinforcing apparatus to solve the problem that proposes in the above-mentioned background art.
(II) technical scheme
In order to achieve the above purpose, the utility model discloses a following technical scheme realizes: the utility model provides a detachable deep basal pit fender pile reinforcing apparatus, includes first fence pole, second fence pole, first crossbeam and second crossbeam, first fence pole and second fence pole are to the vertical isolation reinforcement of foundation ditch lateral wall, one side fixedly connected with card post that the second crossbeam is close to the second fence pole, first crossbeam is close to the also fixedly connected with card post in one side of first fence pole, the lateral wall of first fence pole and second fence pole seted up with card post assorted bayonet socket, one side fixedly connected with fixed column that the card post was kept away from to first crossbeam, the inside of second crossbeam seted up with fixed column assorted cavity groove, fixed column sliding connection is in cavity groove, be provided with locking mechanism between fixed column and the second crossbeam.
Preferably, the locking mechanism comprises a fixed clamping plate, the fixed clamping plate is slidably connected to the side wall of the second cross beam, and the side wall of the fixed clamping plate is fixedly connected with a threaded rod.
Preferably, the side walls of the two sides of the second cross beam are provided with sliding grooves matched with the threaded rods, and the side walls of the fixed columns are provided with locking holes.
Preferably, one end, far away from the fixed clamping plate, of the threaded rod penetrates through the sliding groove and the locking hole and is movably sleeved with the movable clamping plate, and the second cross beam is located between the fixed clamping plate and the movable clamping plate.
Preferably, the threaded rod is connected with a bolt in a threaded manner, and the movable clamping plate is fixed on the side wall of the second cross beam through the bolt.
Preferably, the side walls of the two sides of the second cross beam are provided with first racks matched with the sliding grooves, the side wall of the fixed clamping plate is fixedly connected with second racks matched with the first racks, and the side wall of the movable clamping plate is fixed with third racks matched with the first racks.
The utility model provides a detachable deep basal pit fender pile reinforcing apparatus, its beneficial effect who possesses as follows:
1. this detachable deep basal pit fender pile reinforcing apparatus, through setting up first crossbeam, second crossbeam and locking mechanism, the quick joint of first fence pole and second fence pole has been realized, and then carry out vertical isolation to the foundation ditch lateral wall and consolidate, the device is convenient for install and dismantle, repeatedly usable, resources are saved, and the position of first crossbeam and second crossbeam is adjustable, can slide first crossbeam according to the width of foundation ditch, thereby adjust the support distance, the practicality of device has been improved greatly, the person of facilitating the use uses.
2. This detachable deep basal pit fender pile reinforcing apparatus, through setting up first rack, second rack and third rack, realized that fixed cardboard and activity cardboard are pressing from both sides the fastening timing to the second crossbeam, and meshing through the rack can not the pine take off, has strengthened the stability of device for the first bars railing and the second bars railing of both sides can not loosen and take off when bearing great pressure.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic view of the fixing column mechanism of the present invention;
FIG. 3 is a schematic structural view of the locking mechanism of the present invention;
fig. 4 is a schematic view of the structure of the locking hole of the present invention.
In the figure: the first fence rod, the first cross beam, the fixed column 201, the locking hole 202, the second cross beam 3, the hollow groove 301, the sliding groove 302, the first rack 303, the second fence rod 4, the clamping column 5, the fixed clamping plate 6, the second rack 601, the threaded rod 602, the movable clamping plate 603, the third rack 604, the bolt 605 and the bayonet 7.
Detailed Description
The embodiment of the utility model provides a detachable deep basal pit fender pile reinforcing apparatus, as shown in fig. 1-4, including first fence pole 1, second fence pole 4, first crossbeam 2 and second crossbeam 3, first fence pole 1 and second fence pole 4 are to the vertical isolation reinforcement of foundation ditch lateral wall, second crossbeam 3 is close to one side fixedly connected with card post 5 of second fence pole 4, first crossbeam 2 is close to first fence pole 1's one side also fixedly connected with card post 5, first fence pole 1 and second fence pole 4's lateral wall seted up with card post 5 assorted bayonet socket 7, first crossbeam 2 keeps away from card post 5's one side fixedly connected with fixed column 201, second crossbeam 3's inside seted up with fixed column 201 assorted cavity groove 301, fixed column 201 sliding connection is in cavity groove 301, be provided with locking mechanism between fixed column 201 and the second crossbeam 3.
This device is through setting up first crossbeam 2, second crossbeam 3 and locking mechanism, realized the quick joint of first fence pole 1 with second fence pole 4, and then carry out vertical isolation to the foundation ditch lateral wall and consolidate, the device is convenient for install and dismantle, repeatedly usable, resources are saved, and first crossbeam 2 is adjustable with the position of second crossbeam 3, can slide first crossbeam 2 according to the width of foundation ditch, thereby adjust the support distance, the practicality of device has been improved greatly, the person of facilitating the use uses.
Locking mechanism includes fixed cardboard 6, and fixed cardboard 6 sliding connection is at the lateral wall of second crossbeam 3, and the lateral wall fixedly connected with threaded rod 602 of fixed cardboard 6.
The lateral wall of both sides of second crossbeam 3 has seted up the spout 302 with threaded rod 602 assorted, and the lateral wall of fixed column 201 has seted up locking hole 202.
One end of the threaded rod 602, which is far away from the fixed clamping plate 6, penetrates through the sliding groove 302 and the locking hole 202 and is movably sleeved with the movable clamping plate 603, and the second beam 3 is located between the fixed clamping plate 6 and the movable clamping plate 603.
The threaded rod 602 is connected with a bolt 605 through a thread, and the movable clamping plate 603 is fixed on the side wall of the second cross beam 3 through the bolt 605.
The both sides lateral wall of second crossbeam 3 is provided with first rack 303 of spout 302 assorted, the lateral wall fixedly connected with of fixed cardboard 6 and first rack 303 assorted second rack 601, the lateral wall of activity cardboard 603 is fixed with first rack 303 assorted third rack 604, through setting up first rack 303, second rack 601 and third rack 604, it is regularly when clamping the fastening to second crossbeam 3 to have realized fixed cardboard 6 and activity cardboard 603, the meshing through the rack can not loosen and take off, the stability of device has been strengthened, make the first railing 1 and the second railing 4 of both sides when bearing great pressure, can not loosen and take off.
The working principle is as follows: when the user uses, at first arrange first fence pole 1 and second fence pole 4, then rotatory bolt 605, drive bolt 605 along threaded rod 602 helical motion, and then make fixed cardboard 6 and activity cardboard 603 no longer fix the lateral wall at second crossbeam 3, promote first crossbeam 2 this moment, and then make first crossbeam 2 drive fixed column 201 along cavity 301 inwards sliding, fixed column 201 drives threaded rod 602 and slides in spout 302, threaded rod 602 drives fixed cardboard 6, activity cardboard 603 and bolt 605 sliding connection are at the lateral wall of second crossbeam 3, when sliding first crossbeam 2 and second crossbeam 3 and offset, stop sliding.
At the moment, the clamping column 5 on the second cross beam 3 is aligned with the bayonet 7 on the second fence rod 4 and clamped into the bayonet 7, then the first cross beam 2 is pulled to slide towards the first fence rod 1, at the moment, the first cross beam 2 drives the fixed column 201 to slide outwards along the hollow groove 301, the fixed column 201 drives the threaded rod 602 to slide in the sliding groove 302, the threaded rod 602 drives the fixed clamping plate 6, the movable clamping plate 603 and the bolt 605 to slide on the side wall of the second cross beam 3, when the clamping column 5 on the first cross beam 2 is clamped into the bayonet 7 on the first fence rod 1, the bolt 605 is rotated to make the bolt 605 spirally move towards the second cross beam 3 along the threaded rod 602, the bolt 605 pushes the movable clamping plate 603 and makes the movable clamping plate 603 fixed on the side wall of the second cross beam 3, at the moment, the movable clamping plate 603 and the fixed clamping plate 6 clamp the second cross beam 3, and further makes the threaded rod 602, the first cross beam 2 and the second cross beam 3 are supported to tightly support the first grid rail 1 and the second grid rail 4 on two sides.
This device is through setting up first crossbeam 2, second crossbeam 3 and locking mechanism, realized the quick joint of first fence pole 1 with second fence pole 4, and then carry out vertical isolation to the foundation ditch lateral wall and consolidate, the device is convenient for install and dismantle, repeatedly usable, resources are saved, and first crossbeam 2 is adjustable with the position of second crossbeam 3, can slide first crossbeam 2 according to the width of foundation ditch, thereby adjust the support distance, the practicality of device has been improved greatly, the person of facilitating the use uses.
This device has realized fixed cardboard 6 and activity cardboard 603 and is pressing from both sides the fastening timing to second crossbeam 3 through setting up first rack 303, second rack 601 and third rack 604, and the meshing through the rack can not loosen and take off, has strengthened the stability of device for the first railing pole 1 and the second railing pole 4 of both sides can not loosen and take off when bearing great pressure.
The basic principles and the main features of the invention and the advantages of the invention have been shown and described above. It will be understood by those skilled in the art that the present invention is not limited to the above embodiments, and that the foregoing embodiments and descriptions are provided only to illustrate the principles of the present invention without departing from the spirit and scope of the present invention. The scope of the invention is defined by the appended claims and equivalents thereof.

Claims (6)

1. The utility model provides a detachable deep basal pit fender pile reinforcing apparatus, includes first fence pole (1), second fence pole (4), first crossbeam (2) and second crossbeam (3), its characterized in that: first fence pole (1) and second fence pole (4) are to the vertical isolation reinforcement of foundation ditch lateral wall, second crossbeam (3) are close to one side fixedly connected with card post (5) of second fence pole (4), first crossbeam (2) are close to also fixedly connected with card post (5) of one side of first fence pole (1), the lateral wall of first fence pole (1) and second fence pole (4) seted up with card post (5) assorted bayonet socket (7), one side fixedly connected with fixed column (201) of card post (5) are kept away from in first crossbeam (2), the inside of second crossbeam (3) seted up with fixed column (201) assorted cavity groove (301), fixed column (201) sliding connection is in cavity groove (301), be provided with locking mechanism between fixed column (201) and second crossbeam (3).
2. The detachable deep foundation pit support pile reinforcing device of claim 1, characterized in that: the locking mechanism comprises a fixed clamping plate (6), the fixed clamping plate (6) is slidably connected to the side wall of the second cross beam (3), and a threaded rod (602) is fixedly connected to the side wall of the fixed clamping plate (6).
3. The detachable deep foundation pit support pile reinforcing device of claim 1, characterized in that: the side walls of the two sides of the second cross beam (3) are provided with sliding grooves (302) matched with the threaded rods (602), and the side walls of the fixed columns (201) are provided with locking holes (202).
4. The detachable deep foundation pit support pile reinforcing device of claim 2, wherein: one end, far away from the fixed clamping plate (6), of the threaded rod (602) penetrates through the sliding groove (302) and the locking hole (202) and is movably sleeved with the movable clamping plate (603), and the second cross beam (3) is located between the fixed clamping plate (6) and the movable clamping plate (603).
5. The detachable deep foundation pit support pile reinforcing apparatus of claim 4, characterized in that: the threaded rod (602) is connected with a bolt (605) through threads, and the movable clamping plate (603) is fixed on the side wall of the second cross beam (3) through the bolt (605).
6. The detachable deep foundation pit support pile reinforcing device of claim 5, wherein: the side walls of the two sides of the second cross beam (3) are provided with first racks (303) matched with the sliding grooves (302), the side wall of the fixed clamping plate (6) is fixedly connected with second racks (601) matched with the first racks (303), and the side wall of the movable clamping plate (603) is fixed with third racks (604) matched with the first racks (303).
CN201921772614.6U 2019-10-21 2019-10-21 Detachable deep basal pit fender pile reinforcing apparatus Expired - Fee Related CN211037001U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921772614.6U CN211037001U (en) 2019-10-21 2019-10-21 Detachable deep basal pit fender pile reinforcing apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921772614.6U CN211037001U (en) 2019-10-21 2019-10-21 Detachable deep basal pit fender pile reinforcing apparatus

Publications (1)

Publication Number Publication Date
CN211037001U true CN211037001U (en) 2020-07-17

Family

ID=71534587

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921772614.6U Expired - Fee Related CN211037001U (en) 2019-10-21 2019-10-21 Detachable deep basal pit fender pile reinforcing apparatus

Country Status (1)

Country Link
CN (1) CN211037001U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112411562A (en) * 2020-11-04 2021-02-26 河南五建建设集团有限公司 Detachable foundation pit supporting structure and using method thereof
CN113026762A (en) * 2021-03-23 2021-06-25 北京市政建设集团有限责任公司 High-pressure-bearing composite stratum subway foundation pit supporting structure
CN114482065A (en) * 2021-12-09 2022-05-13 中建八局第二建设有限公司 Deep foundation pit construction device for newly-built building, close to subway and connected with subway

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112411562A (en) * 2020-11-04 2021-02-26 河南五建建设集团有限公司 Detachable foundation pit supporting structure and using method thereof
CN113026762A (en) * 2021-03-23 2021-06-25 北京市政建设集团有限责任公司 High-pressure-bearing composite stratum subway foundation pit supporting structure
CN113026762B (en) * 2021-03-23 2022-03-29 北京市政建设集团有限责任公司 High-pressure-bearing composite stratum subway foundation pit supporting structure
CN114482065A (en) * 2021-12-09 2022-05-13 中建八局第二建设有限公司 Deep foundation pit construction device for newly-built building, close to subway and connected with subway
CN114482065B (en) * 2021-12-09 2023-09-12 中建八局第二建设有限公司 Deep foundation pit construction device for newly-built building adjacent to subway and connected with subway

Similar Documents

Publication Publication Date Title
CN211037001U (en) Detachable deep basal pit fender pile reinforcing apparatus
CN208777675U (en) A kind of overhanging scaffold erection structure
CN2799740Y (en) Assembling bis-adjustable multifunctional early-demolishment device
CN204715763U (en) A kind of aluminum alloy mould plate diagonal brace supporting member pre-embedded bolt structure
CN204081485U (en) Beam bottom mother plate bracing frame
CN203701432U (en) Positioning clamp for horizontal steel reinforcements of shearing wall
CN204456936U (en) A kind of combined type faces frontier defense retaining frame body
CN102979458B (en) Rock wall beam oblique surface smooth blasting punching guiding and positioning device
CN215291363U (en) Construction is with novel scaffold frame diagonal draw bar that encorbelments
CN202990855U (en) Guiding and positioning device for light-exposure punching in inclined plane of crane girder
CN211922626U (en) Guide frame for positioning insertion sleeve
CN209369334U (en) A kind of large-span concrete stay in place form support device
CN217252470U (en) Quick ligature device of steel reinforcement cage
CN202658571U (en) Special adjusting device for bi-directional suspension supporting system of steel hoop
CN214831727U (en) Roadbed side ditch template reinforcing apparatus
CN202690091U (en) Fore poling bar type temporary support device used in anchor bolt support roadway construction
CN219840094U (en) Deep foundation pit assembled section steel supporting system
CN213868916U (en) Novel adjustable reinforcing piece for square column template
CN216142397U (en) High-rise wall-attached climbing formwork for building construction
CN217998621U (en) Stainless steel bus shelter stand
CN219027053U (en) Skirtboard processingequipment for concrete pipe pile
CN217840991U (en) A can have enough to meet need formula and enclose fender device for protection of floor adjacent side
CN218562357U (en) Steel construction pretension component with two-way adjustment
CN211499487U (en) Reinforcing steel bar fixing and edge aligning device for municipal building
CN217758792U (en) A instrument that is used for hollow precast pile stake core soil to clear up

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200717

Termination date: 20211021

CF01 Termination of patent right due to non-payment of annual fee