CN211006617U - Install level standard core structure on basement rock - Google Patents

Install level standard core structure on basement rock Download PDF

Info

Publication number
CN211006617U
CN211006617U CN201921241261.7U CN201921241261U CN211006617U CN 211006617 U CN211006617 U CN 211006617U CN 201921241261 U CN201921241261 U CN 201921241261U CN 211006617 U CN211006617 U CN 211006617U
Authority
CN
China
Prior art keywords
mound
core
mark core
basement rock
bedrock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921241261.7U
Other languages
Chinese (zh)
Inventor
胡升伟
胡明秀
彭巨为
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Chengdu Engineering Co Ltd
Original Assignee
PowerChina Chengdu Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Chengdu Engineering Co Ltd filed Critical PowerChina Chengdu Engineering Co Ltd
Priority to CN201921241261.7U priority Critical patent/CN211006617U/en
Application granted granted Critical
Publication of CN211006617U publication Critical patent/CN211006617U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Testing Or Calibration Of Command Recording Devices (AREA)

Abstract

The utility model discloses a water conservancy water and electricity safety monitoring field install level mark core structure on basement rock, including setting up the observation mound on the basement rock, the level mark core has been buried underground at the top of observing the mound, the top of level mark core is equipped with standard core cover board and covers the level mark core cover on observing the mound. The utility model has the advantages that: through set up an observation mound on the basement rock, set up level mark core and mark core apron on observing the mound, utilize and observe the mound and come firm level mark core, utilize mark core apron to come to cover the protection to level mark core, overall structure has characteristics such as simple and easy, durable reliable, pleasing to the eye practicality, can avoid level mark core to damage and lose to improve basement rock settlement monitoring's reliability.

Description

Install level standard core structure on basement rock
Technical Field
The utility model relates to a water conservancy water and electricity safety monitoring field especially relates to an install level standard core structure on basement rock.
Background
Monitoring the settlement of building and side slope is more and more important in water and electricity engineering, in order to timely accurate gain monitoring data, need bury some level punctuations underground on being monitored the thing, judges the settlement condition of being monitored the thing through the detection to the level punctuation. Different level mark points need to be buried aiming at different topographic and geological conditions, when facing bedrock, the traditional installation method is to directly drill holes on the bedrock and bury a level mark core as a mark of a monitored object, but the level mark core is not easily protected by the method, and is easily lost after a long time, so that a novel level mark core structure mounted on the bedrock needs to be designed.
SUMMERY OF THE UTILITY MODEL
For overcoming the current not enough such as damage or loss of burying the water standard core on the basement rock underground, the utility model aims to solve the technical problem that: the utility model provides a can play the water standard core structure of installing on the basement rock of good guard action to the water standard core on the basement rock.
The utility model provides a technical scheme that its technical problem adopted is:
the utility model provides an install water mark core structure on basement rock, is including setting up the observation mound on the basement rock, the top of observing the mound has buried the water mark core underground, the top of water mark core is equipped with mark core cover board and covers the water mark core cover on observing the mound.
Furthermore, the observation pier is of a reinforced concrete structure penetrating into the bedrock, and a rammed sandstone layer is arranged around the observation pier.
Furthermore, the observation pier is integrally of a frustum-shaped structure with a smaller upper end and a larger lower end.
Further, the observation pier penetrates into the bedrock and accounts for 40-45% of the height of the whole observation pier.
Further, a concrete base is arranged at the top of the gravel layer, the concrete base surrounds the top of the observation pier, and a concrete cover plate is arranged at the top of the concrete base.
Further, a handle is arranged at the top of the concrete cover plate.
The utility model has the advantages that: through set up an observation mound on the basement rock, set up level mark core and mark core apron on observing the mound, utilize and observe the mound and come firm level mark core, utilize mark core apron to come to cover the protection to level mark core, overall structure has characteristics such as simple and easy, durable reliable, pleasing to the eye practicality, can avoid level mark core to damage and lose to improve basement rock settlement monitoring's reliability.
Drawings
Fig. 1 is a schematic structural diagram of the present invention.
Marked in the figure as 1-bedrock, 2-observation pier, 3-level mark core, 4-mark core cover plate, 5-gravel layer, 6-concrete base, 7-concrete cover plate and 8-handle.
Detailed Description
The present invention will be further explained with reference to the accompanying drawings.
As shown in fig. 1, the utility model discloses an install water mark core structure on basement rock, including setting up observation mound 2 on basement rock 1, the top of observing mound 2 has buried water mark core 3 underground, the top of water mark core 3 is equipped with standard core apron 4 and covers the cover with water mark core 3 on observing mound 2. The traditional mounting mode is that directly drill hole on the basement rock, then lay the level mark core downthehole, because the rock mass steadiness is relatively poor to there is not the safeguard measure, the easy not hard up damage or the loss of level mark core laid. The utility model discloses a set up and observe mound 2 and mark core apron 4 back, can play fine fixed and guard action to level mark core 3, examine time measuring when needs, only need open mark core apron 4 can, convenient and fast.
When setting up and observing mound 2, clear away the overburden soil body on the basement rock 1 earlier, until seeing fresh rock mass, observe the bottom basis of mound 2 and go deep into basement rock 1, pour with 8 diameter 12 reinforced concrete, the upper portion is poured into reinforced concrete structure with 4 diameter 12 reinforcing bars as the support, fills and tamps with grit layer 5 afterwards all around, guarantees to contact well, improves the steadiness of observing mound 2.
Because it has the take the altitude to observe mound 2, for the stability of guaranteeing the structure, observe mound 2 global design for the upper end less, the great frustum shape structure of lower extreme, this structural shape is favorable to gravel layer 5 to the firm effect of observing mound 2 simultaneously. In order to further ensure the connection reliability of the observation pier 2 and the bedrock 1, the size of the observation pier 2 penetrating into the bedrock 1 accounts for 40-45% of the height of the whole observation pier 2.
Because rock rolling, wood falling and the like easily occur around the bedrock 1 and the leveling marker core 3 cannot be completely protected only by the marker core cover 4, a concrete base 6 can be arranged at the top of the gravel layer 5, the concrete base 6 surrounds the top of the observation pier 2, and a concrete cover plate 7 is arranged at the top of the concrete base 6. To ensure stability, the concrete base 6 and the concrete cover plate 7 are preferably cast by reinforced concrete, and the concrete base 6 can be inserted into the sandstone layer 5 to a certain depth. In order to facilitate the opening, a handle 8 can be arranged above the concrete cover plate 7.
The utility model discloses a set up an observation mound on the basement rock, set up level mark core and mark core apron on observing the mound, utilize and observe the mound and come firm level mark core, utilize mark core apron to come to cover the protection to level mark core, whole structure has characteristics such as simple and easy, durable reliable, pleasing to the eye practicality, can avoid level mark core to damage and lose to improve the reliability that the basement rock subsides the monitoring, fine practicality and application prospect have.

Claims (6)

1. The utility model provides an install water standard core structure on basement rock which characterized by: including setting up observation mound (2) on basement rock (1), the top of observing mound (2) has buried the water mark core (3) underground, the top of water mark core (3) is equipped with mark core apron (4) and covers the water mark core (3) cover on observing mound (2).
2. A bedrock-mounted water standard core structure as defined in claim 1, wherein: the observation pier (2) is a reinforced concrete structure penetrating into the bedrock (1), and a rammed sandstone layer (5) is arranged around the observation pier (2).
3. A bedrock-mounted water standard core structure as defined in claim 2, wherein: the observation pier (2) is integrally of a frustum-shaped structure with a smaller upper end and a larger lower end.
4. A bedrock-mounted water standard core structure as defined in claim 2, wherein: the observation pier (2) penetrates into the bedrock (1) and the size of the observation pier (2) accounts for 40-45% of the height of the whole observation pier (2).
5. A bedrock-mounted level gauge core structure as claimed in any one of claims 2 to 4, wherein: the top of gravel layer (5) is equipped with concrete base (6), and concrete base (6) will observe the top of mound (2) and surround including, the top of concrete base (6) is equipped with concrete apron (7).
6. A bedrock-mounted water standard core structure as defined in claim 5, wherein: the top of the concrete cover plate (7) is provided with a handle (8).
CN201921241261.7U 2019-07-30 2019-07-30 Install level standard core structure on basement rock Active CN211006617U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921241261.7U CN211006617U (en) 2019-07-30 2019-07-30 Install level standard core structure on basement rock

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921241261.7U CN211006617U (en) 2019-07-30 2019-07-30 Install level standard core structure on basement rock

Publications (1)

Publication Number Publication Date
CN211006617U true CN211006617U (en) 2020-07-14

Family

ID=71468546

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921241261.7U Active CN211006617U (en) 2019-07-30 2019-07-30 Install level standard core structure on basement rock

Country Status (1)

Country Link
CN (1) CN211006617U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112229383A (en) * 2020-09-29 2021-01-15 上海铁大建设工程质量检测有限公司 Observation pier

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112229383A (en) * 2020-09-29 2021-01-15 上海铁大建设工程质量检测有限公司 Observation pier

Similar Documents

Publication Publication Date Title
CN105040667B (en) High roadbed deforms wireless remote comprehensive monitor system and installs monitoring method
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN102644275A (en) Rotary excavation combined pile-forming construction method under complex geological condition
CN101818505A (en) Soil pressure testing method for a cutting edge of caisson
CN211006617U (en) Install level standard core structure on basement rock
CN102304915B (en) New method for controlling top quality of drilled pile
CN104532853A (en) Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning
CN112281868A (en) Support system and method combining temporary foundation pit support and permanent slope support
CN106088115A (en) The method increasing Stability of Soil of High Side Slopes
CN203284786U (en) Side slope anti-slide and pre-warning system with underground water collection and utilization function
CN101768960B (en) Bored concrete pile construction method of permafrost layer
CN113846618A (en) Dynamic compaction replacement reinforcing method for foundation treatment
CN203498860U (en) Anchor rod foundation structure with concrete blocks for photovoltaic module brackets
CN201347559Y (en) Supporting structure of suspending pile for foundation pit
CN101481913A (en) Construction method of rock-socketed underground continuous wall punching slot section
CN205975646U (en) Shallow water territory steel pipe pile holder fortifield village weir structure
CN108625368A (en) A kind of Deep Thick Soft Ground Area Rigid Long-Short-Pile Composite Foundation construction method
CN216664149U (en) Good strutting arrangement of stability for foundation ditch
CN207423212U (en) Inclinometer pipe datum mark school geodesic structure
CN202745027U (en) Settlement observation marker for hydraulic fill field
CN104420479A (en) Anchor rod base structure with concrete block of photovoltaic module bracket and setting method
CN203160222U (en) Ground settlement monitoring point device
CN107246010B (en) Karst area Percussion Piles construction
CN114993248A (en) Ground settlement monitoring method
CN101718095B (en) Minimal invasion healing management method for landslide

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant