CN210999276U - Concrete precast block forming die - Google Patents

Concrete precast block forming die Download PDF

Info

Publication number
CN210999276U
CN210999276U CN201921622048.0U CN201921622048U CN210999276U CN 210999276 U CN210999276 U CN 210999276U CN 201921622048 U CN201921622048 U CN 201921622048U CN 210999276 U CN210999276 U CN 210999276U
Authority
CN
China
Prior art keywords
baffle
precast block
concrete precast
opposite
block forming
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921622048.0U
Other languages
Chinese (zh)
Inventor
王天鹏
蔡志赢
孟阳庆东
吴康
刘滨
刘贝
杨晓磊
陈金龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Construction Engineering Group Co Ltd
Original Assignee
Shenzhen Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Construction Engineering Group Co Ltd filed Critical Shenzhen Construction Engineering Group Co Ltd
Priority to CN201921622048.0U priority Critical patent/CN210999276U/en
Application granted granted Critical
Publication of CN210999276U publication Critical patent/CN210999276U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Moulds, Cores, Or Mandrels (AREA)

Abstract

The utility model relates to a building engineering technical field especially relates to concrete precast block forming die, including relative first baffle subassembly and the second baffle subassembly that sets up, first baffle subassembly with detachably is equipped with a plurality of baffles between the second baffle subassembly, so as to incite somebody to action first baffle subassembly with separate between the second baffle subassembly and form a plurality of molding cavity that link up from top to bottom, the molding cavity is installed and is run through the wall bushing that wears of first baffle subassembly and second baffle subassembly, first baffle subassembly and second baffle subassembly pass through locking mechanism and lock relatively. The application provides a concrete precast block forming die, its preparation is simple and convenient, and the operating feasibility is high, the dismouting turnover is convenient, and the concrete precast block shaping dimension of this concrete precast block forming die preparation of on the other hand is accurate, the preparation is efficient and look feels respond well.

Description

Concrete precast block forming die
[ technical field ] A method for producing a semiconductor device
The application relates to the technical field of constructional engineering, in particular to a concrete precast block forming die.
[ background of the invention ]
In modern building engineering, aiming at the installation of an air conditioner, a wall-through hole of an air conditioner external unit needs to be formed in advance in a wall, the traditional method is to form a hole in a masonry wall by using an electric hammer, then place a reserved pipe, and finally block the space between the reserved pipe and the wall, but because the method is easy to generate dust, the wall is loose, and the problems of hollowing, cracking, water seepage and the like are easy to occur after blocking, a new engineering scheme is developed at present, and the new scheme is to pour a concrete precast block pre-embedded with a sleeve in advance and then build the concrete precast block and a wall building block synchronously.
However, the existing concrete precast block is generally poured through a single wooden template, so that the efficiency is low, and the assembly and disassembly are inconvenient.
[ Utility model ] content
An object of this application is to provide concrete prefabricated section forming die, concrete prefabricated section forming die preparation is simple and convenient, and the operating feasibility is high, the dismouting turnover is convenient, and the concrete prefabricated section shaping size of this concrete prefabricated section forming die preparation of on the other hand is accurate, the preparation is efficient and the impression is respond well.
The application is realized by the following technical scheme:
concrete prefabricated section forming die, including relative first baffle subassembly and the second baffle subassembly that sets up, first baffle subassembly with detachably is equipped with a plurality of baffles between the second baffle subassembly, in order will first baffle subassembly with separate between the second baffle subassembly and form a plurality of molding chamber that link up from top to bottom, the molding intracavity is installed and is run through the wall bushing of wearing of first baffle subassembly and second baffle subassembly, first baffle subassembly and second baffle subassembly pass through locking mechanism and lock relatively.
The concrete precast block forming mould comprises a first base and a plurality of first baffle plates arranged on the first base in the row direction, wherein two sides of each first baffle plate are provided with first clamping grooves;
the second baffle plate assembly comprises a second base and a plurality of second baffle plates arranged on the second base in the row direction, and second clamping grooves are formed in two sides of each second baffle plate;
the first clamping grooves and the second clamping grooves are arranged in a one-to-one opposite mode, the first baffle and the second baffle are arranged in a one-to-one opposite mode, and two opposite sides of each baffle are embedded in the first clamping grooves and the second clamping grooves which are opposite to each other respectively, so that the first baffle and the second baffle which are opposite to each other and the two adjacent baffles are arranged in a surrounding mode to form the forming cavity.
The concrete precast block forming die comprises a first base, a second base and a third base, wherein the first base comprises a plurality of first main ridges and a plurality of first secondary ridges, the two first secondary ridges are transversely arranged and vertically arranged at intervals, the first main ridges are vertically arranged on the inner sides of the first main ridges, every two first main ridges form a group, and the two first main ridges in each group of the first main ridges are arranged side by side at intervals to form a first clamping groove; the second base has the same structure as the first base.
According to the concrete precast block forming die, one end of the wall bushing extends 25-35 mm beyond the first baffle plate.
According to the concrete precast block forming die, the locking mechanism comprises a split screw, a split nut, a clamping head and a clamping column group;
the clamping column groups are provided with two groups of clamping column groups which are respectively vertically arranged at the opposite outer sides of the first baffle plate assembly and the second baffle plate assembly, the opposite-pulling screw rods penetrate through the first baffle plate assembly and the second baffle plate assembly, two ends of each opposite-pulling screw rod respectively extend out of the clamping column groups at two sides, the extending ends of the opposite-pulling screw rods are sleeved with the clamping heads and are in threaded connection with the opposite-pulling nuts, the opposite-pulling nuts at two ends respectively lock the clamping heads inwards from the outermost two ends of the opposite-pulling screw rods, and then the clamping column groups at two opposite sides are forced to tighten the first baffle plate assembly and the second baffle plate assembly;
each group of clamping column group comprises two clamping columns, and clamping notches for clamping the clamping columns are arranged on the clamping heads.
According to the concrete precast block forming die, the counter-pulling screw rod penetrates through the first baffle plate assembly and the second baffle plate assembly from the wall bushing.
The concrete precast block forming mould further comprises a flat plate, and the flat plate is placed at the bottom of the forming cavity.
According to the concrete precast block forming mould, the number of the partition plates is 6, so that 5 forming cavities are formed in a partitioned mode.
According to the concrete precast block forming die, the wall bushing is made of PVC materials.
According to the concrete precast block forming die, the forming cavity is a cube.
Compared with the prior art, the method has the following advantages:
the concrete precast block forming die is simple and convenient to manufacture, high in operation feasibility, convenient to disassemble, assemble and turnover, accurate in forming size of the concrete precast block manufactured by the concrete precast block forming die, high in manufacturing efficiency and good in impression effect.
[ description of the drawings ]
In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings needed to be used in the description of the embodiments are briefly introduced below, and it is obvious that the drawings in the following description are only some embodiments of the present application, and it is obvious for those skilled in the art to obtain other drawings based on these drawings without creative efforts.
Fig. 1 is a schematic perspective view of an embodiment of the present application.
Fig. 2 is a front view of an embodiment of the present application.
Fig. 3 is a top view of an embodiment of the present application.
[ detailed description ] embodiments
In order to make the technical problems, technical solutions and advantageous effects solved by the present application more clear and obvious, the present application is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the present application and are not intended to limit the present application.
As shown in fig. 1 to 3, an embodiment of the present application provides a concrete precast block forming mold, which includes a first baffle assembly 1 and a second baffle assembly 2 that are disposed opposite to each other, a plurality of partition plates 3 are detachably disposed between the first baffle assembly 1 and the second baffle assembly 2 to partition and form a plurality of forming cavities 4 that are through from top to bottom between the first baffle assembly 1 and the second baffle assembly 2, wall penetrating sleeves 5 that penetrate through the first baffle assembly 1 and the second baffle assembly 2 are disposed in the forming cavities 4, and the first baffle assembly 1 and the second baffle assembly 2 are relatively locked by a locking mechanism 6, where the forming cavities 4 are cubes, for example, in a specific implementation, 6 partition plates 3 may be disposed to partition and form 5 forming cavities 4, the size of the forming cavity 4 may be 200 × 200 × 200mm, and PVC wall penetrating sleeves 5 with a diameter of 75mm are cut and then embedded in the forming cavities 4.
The use process of the concrete precast block forming die is as follows: the good concrete prefabricated section forming die of installation locking is arranged in on ground or the flat board, and ground or flat board are arranged in promptly become the die cavity 4 bottom to make die cavity 4 be an upper open-ended cavity, then pour the concrete toward a plurality of die cavities 4 in simultaneously, can adopt C20 pea gravel concreten when pouring, and adopt small-size vibrating rod to vibrate, treat that the concrete solidifies and receive the face maintenance back and loosen locking mechanism 6, with baffle 3, first baffle subassembly 1 and the separation of second baffle subassembly 2, can obtain the concrete prefabricated section of a plurality of standards.
The concrete precast block forming die is simple and convenient to manufacture, high in operation feasibility, convenient to disassemble, assemble and turnover, accurate in forming size of the concrete precast block manufactured by the concrete precast block forming die, high in manufacturing efficiency and good in impression effect.
Specifically, the first baffle plate assembly 1 includes a first base 11 and a plurality of first baffle plates 12 arranged on the first base 11 in a row direction, and first clamping grooves 13 are respectively disposed on two sides of each first baffle plate 12.
The second baffle assembly 2 comprises a second base 21 and a plurality of second baffles 22 arranged on the second base 21 in the row direction, and second clamping grooves 23 are formed in two sides of each second baffle 22.
The first clamping grooves 13 and the second clamping grooves 23 are arranged oppositely one by one, the first baffles 12 and the second baffles 22 are arranged oppositely one by one, and two opposite sides of each baffle 3 are respectively embedded in the first clamping grooves 13 and the second clamping grooves 23 which are opposite to each other, so that the first baffles 12 and the second baffles 22 which are opposite to each other and the two adjacent baffles 3 are surrounded to form the molding cavity 4.
The first baffle plate 12 and the second baffle plate 22 can be welded or adhered to the corresponding bases, and the first baffle plate assembly 1 and the second baffle plate assembly 2 are simple in structure and easy to manufacture.
Wherein, the first baffle 12 and the second baffle 22 which are opposite are provided with mounting holes so that the wall bushing 5 is penetrated and embedded in the molding cavity 4.
More specifically, the first base 11 includes a plurality of first main ridges 111 and a plurality of first secondary ridges 112, two first secondary ridges 112 are transversely disposed and vertically arranged at intervals, the first main ridges 111 are vertically disposed on the inner side of the first main ridges 111, every two first main ridges 111 form a group, and the two first main ridges 111 in each group of first main ridges 111 form the first clamping grooves 13 at intervals in parallel; the second base 21 has the same structure as the first base 11. The first main corrugation 111 and the first secondary corrugation 112 are steel square tube, aluminum square tube or iron square tube coated with anti-rust paint. The first base 11 is simple in structure and easy to manufacture. The first main edge 111 and the first secondary edge 112 are welded or bonded.
In order to ensure that the plastering finish surface of the outer wall is flush with the pipe orifice of the wall bushing 5, one end of the wall bushing 5 extends out of the first baffle 1225 mm-35 mm, preferably 30 mm.
Further, the locking mechanism 6 includes a split screw 61, a split nut 64, a chuck 62, and a clamping column set 63. Wherein the clamping column group 63 is an aluminum square tube or a steel square tube and is welded or bonded on the outer sides of the corresponding first base 11 and the second base 21,
the clamp post group 63 is provided with two sets of and respectively vertically locates first baffle subassembly 1 with the outside that second baffle subassembly 2 is relative, to drawing screw rod 61 runs through first baffle subassembly 1 with second baffle subassembly 2 and both ends stretch out respectively outside the clamp post group 63 of both sides, the pot head that stretches out of drawing screw rod 61 is equipped with dop 62 and threaded connection have to draw nut 64, the nut 64 that draws at both ends is followed draw the outermost both ends of screw rod 61 inwards locking dop 62 respectively, and then force the tensioning of the clamp post group 63 of two offsides first baffle subassembly 1 with second baffle subassembly 2.
Each group of clamping column set 63 comprises two clamping columns 631, and the clamping head 62 is provided with clamping notches for clamping the clamping columns 631.
Further, the counter screw 61 penetrates the first baffle plate assembly 1 and the second baffle plate assembly 2 from the wall bushing 5. This scheme utilization wall bushing 5 need not to reserve the passageway in addition as the passageway of split connection, makes concrete prefabricated section forming die's structure is compacter.
The process of assembling the concrete precast block forming die comprises the following steps: the partition plates 3 are respectively inserted and embedded into the first clamping groove 13 and the second clamping groove 23 which are opposite to each other, the wall bushing 5 is arranged between the first baffle plate 12 and the second baffle plate 22 while the wall bushing is inserted and embedded, then the counter-pull screw 61 penetrates through the wall bushing 5, two ends of the counter-pull screw 61 extend out of the clamping column groups 63 on two sides, then the clamping heads 62 are respectively sleeved at two ends of the counter-pull screw 61, and the counter-pull nuts 64 are screwed in, so that the first baffle plate assembly 1 and the second baffle plate assembly 2 are relatively locked. And in the same way, the concrete precast block forming die can be disassembled on the contrary. The technical scheme has reliable locking, easy manufacture and convenient disassembly and assembly.
It should be understood that the terms "first", "second", etc. are used herein to describe various information, but the information should not be limited to these terms, and these terms are only used to distinguish one type of information from another. For example, "first" information may also be referred to as "second" information, and similarly, "second" information may also be referred to as "first" information, without departing from the scope of the present application. Furthermore, the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience in describing the present application and simplifying the description, but do not indicate or imply that the referred devices or elements must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present application.
The foregoing is illustrative of one or more embodiments provided in connection with the detailed description and is not intended to limit the disclosure to the particular forms disclosed. Similar or identical methods, structures, etc. as used herein, or several technical inferences or substitutions made on the concept of the present application should be considered as the scope of the present application.

Claims (10)

1. Concrete prefabricated section forming die, its characterized in that, including relative first baffle subassembly (1) and the second baffle subassembly (2) that sets up, first baffle subassembly (1) with detachably is equipped with a plurality of baffles (3) between second baffle subassembly (2), in order with first baffle subassembly (1) with separate between second baffle subassembly (2) and form a plurality of shaping chamber (4) that link up from top to bottom, the built-in wall bushing (5) that run through of first baffle subassembly (1) and second baffle subassembly (2) that are equipped with in shaping chamber (4), first baffle subassembly (1) and second baffle subassembly (2) are locked relatively through locking mechanism (6).
2. The concrete precast block forming mould according to the claim 1 is characterized in that the first baffle plate component (1) comprises a first base (11) and a plurality of first baffle plates (12) which are arranged on the first base (11) in a row direction, and both sides of the first baffle plates (12) are provided with first clamping grooves (13);
the second baffle plate assembly (2) comprises a second base (21) and a plurality of second baffle plates (22) which are arranged on the second base (21) in the row direction, and second clamping grooves (23) are formed in two sides of each second baffle plate (22);
the first clamping grooves (13) and the second clamping grooves (23) are arranged oppositely one by one, the first baffle plates (12) and the second baffle plates (22) are arranged oppositely one by one, and two opposite sides of each baffle plate (3) are embedded in the first clamping grooves (13) and the second clamping grooves (23) which are opposite to each other, so that the first baffle plates (12) and the second baffle plates (22) which are opposite to each other and the two adjacent baffle plates (3) are surrounded to form the molding cavity (4).
3. The concrete precast block forming mold according to claim 2, wherein the first base (11) comprises a plurality of first main ridges (111) and a plurality of first secondary ridges (112), two first secondary ridges (112) are transversely arranged and vertically arranged at intervals, the first main ridges (111) are vertically arranged at the inner side of the first main ridges (111), every two first main ridges (111) form a group, and the two first main ridges (111) in each group of the first main ridges (111) are arranged side by side at intervals to form the first clamping grooves (13); the second base (21) has the same structure as the first base (11).
4. The concrete precast block forming die according to claim 2, wherein one end of the wall bushing (5) extends 25-35 mm beyond the first baffle plate (12).
5. The concrete precast block forming mold according to claim 1, wherein the locking mechanism (6) comprises a split screw (61), a split nut (64), a chuck (62) and a clamp column set (63);
the clamp column groups (63) are provided with two groups and are respectively vertically arranged on the outer sides of the first baffle assembly (1) and the second baffle assembly (2) which are opposite, the opposite-pulling screw rods (61) penetrate through the first baffle assembly (1) and the second baffle assembly (2), two ends of each opposite-pulling screw rod respectively extend out of the clamp column groups (63) on two sides, the extending ends of the opposite-pulling screw rods (61) are sleeved with the clamp heads (62) and are in threaded connection with the opposite-pulling nuts (64), the opposite-pulling nuts (64) on two ends respectively lock the clamp heads (62) inwards from the outermost two ends of the opposite-pulling screw rods (61), and then the clamp column groups (63) on two opposite sides are forced to tighten the first baffle assembly (1) and the second baffle assembly (2);
each group of clamping column group (63) comprises two clamping columns (631), and clamping notches for clamping the clamping columns (631) are formed in the clamping heads (62).
6. The concrete precast block forming mold according to claim 5, wherein the counter-pulling screw (61) penetrates the first baffle plate assembly (1) and the second baffle plate assembly (2) from the wall bushing (5).
7. The concrete precast block forming mould according to claim 1, further comprising a flat plate placed at the bottom of the forming cavity (4).
8. The concrete precast block forming mold according to claim 1, wherein the partition plate (3) is provided with 6 to partition 5 forming cavities (4).
9. The concrete precast block forming die according to claim 1, wherein the wall bushing (5) is made of PVC material.
10. The concrete precast block forming mould according to claim 1, wherein the forming cavity (4) is a cube.
CN201921622048.0U 2019-09-26 2019-09-26 Concrete precast block forming die Active CN210999276U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921622048.0U CN210999276U (en) 2019-09-26 2019-09-26 Concrete precast block forming die

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921622048.0U CN210999276U (en) 2019-09-26 2019-09-26 Concrete precast block forming die

Publications (1)

Publication Number Publication Date
CN210999276U true CN210999276U (en) 2020-07-14

Family

ID=71501531

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921622048.0U Active CN210999276U (en) 2019-09-26 2019-09-26 Concrete precast block forming die

Country Status (1)

Country Link
CN (1) CN210999276U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117890283A (en) * 2024-03-15 2024-04-16 四川蜀工公路工程试验检测有限公司 Concrete impermeability appearance

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN117890283A (en) * 2024-03-15 2024-04-16 四川蜀工公路工程试验检测有限公司 Concrete impermeability appearance

Similar Documents

Publication Publication Date Title
CN105888108A (en) Reinforced concrete shear wall with positioning prefabricated member inside and construction method of reinforced concrete shear wall
CN113374245B (en) Construction method for temporary support of post-cast strip of beam plate
KR101010608B1 (en) A mold for channel
CN210999276U (en) Concrete precast block forming die
CN201704946U (en) Shear wall formwork for building
CN107639723A (en) A kind of the production template and production method of concrete prefabricated wallboard with holes
CN108858690B (en) Mold for producing precast concrete member and use method
CN201730317U (en) Floor formwork for buildings
CN107618096B (en) Composite pipeline production mould
CN210308353U (en) Prefabricated coincide floor assembling die of adjustable size
CN217434607U (en) Assembling die of usefulness is pour to prefabricated post
CN217054323U (en) Adjustable post-cast strip temporary support system
CN206053303U (en) It is a kind of to pour auxiliary aluminum diaphragm system
CN110614704A (en) Concrete plate production mold
CN219466475U (en) Equipment for producing multi-specification T/L type corner post and edge member capable of preventing seam from cracking
CN220166979U (en) Pipeline pouring fixing device
CN213476493U (en) Template for construction of CTRS III type ballastless track bed plate
CN210177788U (en) Assembled plane contains post module
CN215331461U (en) Adjustable height difference plate surface partition template
CN212888150U (en) Be used for concrete truss coincide floor combined type mould fixing device
CN219235626U (en) Wallboard mould with adjustable
CN214055733U (en) Cement cushion block prefabricating mould
CN213226781U (en) Mould is used in wallboard production for assembly type structure
CN113524381B (en) Steel-wood combined type prefabricated laminated slab universal mold and manufacturing method of prefabricated laminated slab