CN210963634U - Safety belt fixing device for electric power overhaul - Google Patents

Safety belt fixing device for electric power overhaul Download PDF

Info

Publication number
CN210963634U
CN210963634U CN201921812228.5U CN201921812228U CN210963634U CN 210963634 U CN210963634 U CN 210963634U CN 201921812228 U CN201921812228 U CN 201921812228U CN 210963634 U CN210963634 U CN 210963634U
Authority
CN
China
Prior art keywords
locking
rod
safety
electric power
locking block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921812228.5U
Other languages
Chinese (zh)
Inventor
颜筱宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Petroleum University
Original Assignee
Southwest Petroleum University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Petroleum University filed Critical Southwest Petroleum University
Priority to CN201921812228.5U priority Critical patent/CN210963634U/en
Application granted granted Critical
Publication of CN210963634U publication Critical patent/CN210963634U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Emergency Lowering Means (AREA)

Abstract

The utility model discloses a safety belt fixing device for electric power overhaul, which comprises a base, a safety rod and two clamp assemblies; the base is a rectangular frame consisting of two long rods and two short rods, and the middle part of one long rod is provided with a fixed sleeve; the safety rod is arranged on the fixing sleeve and is provided with a safety hook; the two clamp assemblies are respectively positioned on the base and on two sides of the fixing sleeve, each clamp assembly comprises a pressing plate, a locking block and a locking screw, through holes are formed in the middle parts of the pressing plate and the locking block, the locking screw vertically penetrates through the through holes of the pressing plate and the locking block, and a locking nut is mounted at the lower end of the locking screw; the locking device comprises a locking block and is characterized in that connecting rods extend from two sides of the locking block along the length direction of the locking block respectively, a U-shaped clamping plate is arranged at the tail end of each connecting rod, a clamping groove is formed in each U-shaped clamping plate, and a push rod is arranged on the outer side of each U-shaped clamping plate. The utility model discloses a high-speed joint between safety belt and the electric power framework, and easy and simple to handle.

Description

Safety belt fixing device for electric power overhaul
Technical Field
The utility model relates to a safety guarantee instrument when field high altitude construction such as power equipment installation, maintenance specifically is a safety belt fixing device for electric power overhaul.
Background
The regulation of electric power safety work regulations: the hook or rope of the safety belt should be hung on a firm and firm framework and should be hung on a movable or insecure object in a high-hanging and low-using mode. In the process of maintenance work, because the electric power framework has no place to fix or cannot fix the safety belt quickly, the high-altitude operation personnel often put the safety belt on the underfoot framework or on the lightning arrester post insulator body, and the safety work regulation is seriously violated, which is not allowed by the electric power safety work. When working, the high-altitude working personnel are easy to fatigue due to the lack of proper standing positions, and have potential safety hazards. In order to ensure the safety of the high-altitude operation personnel and reduce the danger degree of the high-altitude operation personnel, an effective method must be adopted to improve the working efficiency.
SUMMERY OF THE UTILITY MODEL
The to-be-solved technical problem of the utility model is: in order to overcome the problems, the safety belt fixing device for electric power overhaul is provided.
The technical proposal of the utility model for solving the technical problem is that:
a safety belt fixing device for electric power overhaul comprises a base, a safety rod and two clamp assemblies; the base is a rectangular frame consisting of two long rods and two short rods, and the middle part of one long rod is provided with a fixed sleeve; the safety rod is arranged on the fixing sleeve and is provided with a safety hook;
the two clamp assemblies are respectively positioned on the base and on two sides of the fixing sleeve, each clamp assembly comprises a pressing plate, a locking block and a locking screw, through holes are formed in the middle parts of the pressing plate and the locking block, the locking screw vertically penetrates through the through holes of the pressing plate and the locking block, and a locking nut is mounted at the lower end of the locking screw; the locking block extends along two sides of the length direction of the locking block to form a connecting rod, a U-shaped clamping plate is arranged at the tail end of the connecting rod, a clamping groove is formed in the U-shaped clamping plate, an ejector rod is arranged on the outer side of the U-shaped clamping plate, and the ejector rod and the clamping groove are located at the same height.
Preferably, a pedal is fixed on the upper surface of the base.
Preferably, the fixing sleeve is a hollow cylinder, a C-shaped locking ring is arranged at the upper part of the cylinder, and fasteners are arranged on two sides of the locking ring.
Preferably, a handle is arranged at the upper end of the locking screw rod.
The utility model has the advantages that:
1. the problem that the safety belt is fixed in a non-position or cannot be fixed quickly is effectively solved;
2. the problem that the operators are inconvenient to stand during overhead operation is effectively solved;
3. the utility model discloses simple structure, but quick assembly disassembly improves work efficiency.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic structural view of the base portion of the present invention;
FIG. 3 is a schematic structural view of the clamp assembly of the present invention;
fig. 4 is a use state diagram of the middle clamp assembly of the present invention when connecting the power frame.
Detailed Description
The present invention will now be described in further detail with reference to the accompanying drawings. These drawings are simplified schematic drawings and illustrate the basic structure of the present invention only in a schematic manner, and thus show only the components related to the present invention.
As shown in fig. 1-3: the utility model discloses a safety belt fixing device for electric power overhaul, which comprises a base 1, a safety rod 6 and two clamp assemblies 3; the base 1 is a rectangular frame consisting of two long rods 101 and two short rods 102, wherein the middle part of one long rod 101 is provided with a fixed sleeve 2 which is a hollow cylinder, the upper part of the fixed sleeve is provided with a C-shaped locking ring (not shown in the figure), and two sides of the locking ring are provided with fasteners 5; the safety rod 6 is arranged on the fixed sleeve 2 and is provided with a safety hook 7.
The two clamp assemblies 3 are both positioned on the base 1 and are respectively positioned at two sides of the fixed sleeve 2, each clamp assembly 3 comprises a pressure plate 301, a locking block 304 and a locking screw 302, through holes are formed in the middles of the pressure plate 301 and the locking block 304, the locking screw 302 vertically penetrates through the through holes of the pressure plate 301 and the locking block 304, and a fastening nut 307 is arranged at the lower end of the locking screw 302; the locking block 304 is provided with connecting rods 308 respectively extending along two sides of the length direction thereof, the tail end of each connecting rod 308 is provided with a U-shaped clamping plate 305, the U-shaped clamping plates 305 are provided with clamping grooves 309, the outer sides of the U-shaped clamping plates 305 are provided with push rods 306, and the push rods 306 and the clamping grooves 309 are located at the same height. The ejector rod 306 can be used for ejecting the lower surface of the long rod 1 and matching with the pressing plate 301. The entire clamping assembly 3 is fixed with the base 1 by the locking screw 302.
In a further scheme, a pedal 4 is fixed on the upper surface of the base. The standing position is provided for the operating personnel during the aloft work, and convenience is provided for the work.
As shown in fig. 4: the utility model discloses well anchor clamps subassembly 3 is connected with the electric power framework through the U type groove on the U type cardboard 305.
When the clamp is used, firstly, the safety rod 6 with the safety hook 7 is fixed in the fixing sleeve 2, the base 1 is lapped on the surface of the electric power frame at the working position, the pressing plate 301 of the clamp assembly 3 is placed on the upper surface of the base, the position of the clamp assembly 3 is moved, the U-shaped clamping plate 305 of the clamp assembly 3 clamps the upper end surface of the electric power frame, and then the base 1 is firmly fastened with the clamp assembly 3 and the electric power frame by twisting the handle 303 and the fastening nut 307 on the locking screw 302.
The utility model discloses a fixed cover 2 will have safety hook 7 safety pole 6 fixed with fastener 5, and the staff hangs self safety belt on safety hook 7 like this, has just realized being connected between safety belt and the electric power framework.
The staff hangs own safety belt on safety hook 7, has just so realized the connection between safety belt and the electric power framework to can stand on footboard 4 according to the work needs and carry out the operation.
To sum up, the utility model discloses can realize the high-speed joint between safety belt and the electric power framework, can provide the footboard of standing for the operation personnel again, easy and simple to handle moreover.
In light of the above, it is intended that the present invention cover modifications and variations of this invention provided they fall within the scope of the following claims and their equivalents. The technical scope of the present invention is not limited to the contents of the specification, and must be determined according to the required scope.

Claims (4)

1. The utility model provides an electric power overhauls uses safety belt fixing device which characterized in that: comprises a base, a safety rod and two clamp assemblies; the base is a rectangular frame consisting of two long rods and two short rods, and the middle part of one long rod is provided with a fixed sleeve; the safety rod is arranged on the fixing sleeve and is provided with a safety hook;
the two clamp assemblies are respectively positioned on the base and on two sides of the fixing sleeve, each clamp assembly comprises a pressing plate, a locking block and a locking screw, through holes are formed in the middle parts of the pressing plate and the locking block, the locking screw vertically penetrates through the through holes of the pressing plate and the locking block, and a locking nut is mounted at the lower end of the locking screw; the locking device comprises a locking block and is characterized in that connecting rods extend along two sides of the locking block in the length direction respectively, a U-shaped clamping plate is arranged at the tail end of each connecting rod, a clamping groove is formed in each U-shaped clamping plate, an ejector rod is arranged on the outer side of each U-shaped clamping plate, and the ejector rods and the clamping grooves are located at the same height.
2. A safety belt fixing device for electric power overhaul as claimed in claim 1, wherein: a pedal is fixed on the upper surface of the base.
3. A safety belt fixing device for electric power overhaul as claimed in claim 1, wherein: the fixed sleeve is a hollow cylinder, a C-shaped locking ring is arranged at the upper part of the fixed sleeve, and fasteners are arranged on two sides of the locking ring.
4. A safety belt fixing device for electric power overhaul as claimed in claim 1, wherein: and a handle is arranged at the upper end of the locking screw rod.
CN201921812228.5U 2019-10-26 2019-10-26 Safety belt fixing device for electric power overhaul Expired - Fee Related CN210963634U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921812228.5U CN210963634U (en) 2019-10-26 2019-10-26 Safety belt fixing device for electric power overhaul

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921812228.5U CN210963634U (en) 2019-10-26 2019-10-26 Safety belt fixing device for electric power overhaul

Publications (1)

Publication Number Publication Date
CN210963634U true CN210963634U (en) 2020-07-10

Family

ID=71446039

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921812228.5U Expired - Fee Related CN210963634U (en) 2019-10-26 2019-10-26 Safety belt fixing device for electric power overhaul

Country Status (1)

Country Link
CN (1) CN210963634U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113546346A (en) * 2021-06-16 2021-10-26 国网河南省电力公司安阳供电公司 Telescopic 110 KV isolating switch safety belt hanging device

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113546346A (en) * 2021-06-16 2021-10-26 国网河南省电力公司安阳供电公司 Telescopic 110 KV isolating switch safety belt hanging device
CN113546346B (en) * 2021-06-16 2024-01-09 国网河南省电力公司安阳供电公司 Telescopic 110 KV isolating switch safety belt suspension device

Similar Documents

Publication Publication Date Title
CN201904568U (en) Overhead ground wire lifting device
CN210963634U (en) Safety belt fixing device for electric power overhaul
CN105688378A (en) Pneumatic rod-climbing robot
CN112271632B (en) Standing type high-voltage cable operation device
CN205429607U (en) Cable straightener
CN207253594U (en) A kind of safety belt aids in hanger
CN202940488U (en) Circuit breaker energy storage cylinder maintenance tool
CN206045223U (en) The fixing device of safety belt suspension device
CN204050726U (en) Fixed connector between framework and safety belt during work high above the ground
CN104009416A (en) Large-span telescopic universal tower head fixture
CN103520852A (en) Spacing-adjustable safety belt hanging device for disconnecting switch overhaul
CN110499951B (en) Iron tower cross arm rope ladder hanging point extension device and application
CN111162478A (en) Suspension clamp gasket supplementing device
CN209322393U (en) Chimney titanium alloy inner tube installation special equipment
CN206180544U (en) Conductor spacer gyration tile
CN203216951U (en) Junction pole used for lightning arrester
CN202333524U (en) Hoisting support for overhaul of isolating switch
CN209993996U (en) Suspension clamp gasket supplementing device
CN206471748U (en) Universal 500kV straight lines wineglass tower line maintenance cross-arm hanging point device
CN103437698A (en) Retractable insulating ladder for overhaul at high altitude
CN111162389A (en) Special earth connection of transformer substation's generating line bridge
CN211508417U (en) Auxiliary supporting mechanism for mounting cross arm and corresponding supporting device
CN205608037U (en) Novel insulating safety tool prophylactic test device
CN221130778U (en) GW5B-72.5 type self-supporting knife switch overhaul waist rope hanger
CN205489268U (en) Installation tool for bird repelling device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200710