CN210898551U - One-time pressure-on synchronous nuclear phase inspection system for electrical system - Google Patents

One-time pressure-on synchronous nuclear phase inspection system for electrical system Download PDF

Info

Publication number
CN210898551U
CN210898551U CN201921879574.5U CN201921879574U CN210898551U CN 210898551 U CN210898551 U CN 210898551U CN 201921879574 U CN201921879574 U CN 201921879574U CN 210898551 U CN210898551 U CN 210898551U
Authority
CN
China
Prior art keywords
voltage
power supply
transformer
incoming line
phase
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921879574.5U
Other languages
Chinese (zh)
Inventor
徐金兵
王慧军
项俨锋
王良峰
段江涛
潘海波
楼天雄
赵维国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East China Power Test and Research Institute Co Ltd
Original Assignee
East China Power Test and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East China Power Test and Research Institute Co Ltd filed Critical East China Power Test and Research Institute Co Ltd
Priority to CN201921879574.5U priority Critical patent/CN210898551U/en
Application granted granted Critical
Publication of CN210898551U publication Critical patent/CN210898551U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Stand-By Power Supply Arrangements (AREA)

Abstract

The utility model discloses an once logical pressure of electric system is with nuclear phase test system in phase. The system is used for carrying out primary voltage-passing and synchronous phase-checking before the power is supplied to the electric system, and ensures that the electric system is in synchronous phase-checking with a power supply and operates normally. The output end of the generator and one end of the high-voltage plant transformer are respectively connected to the input end of the main transformer; the knife switch end of the working power supply incoming line switch DL1 and the detection end of the working power supply incoming line voltage transformer PT1 are respectively connected to the other end of the high-voltage plant transformer; two ends of a low-voltage plant transformer are respectively connected to the three-phase voltage regulator and one end of the feeder switch DL3, and a three-phase experimental power supply is connected with the three-phase voltage regulator; the switch end of the standby power supply incoming line switch DL2 and the detection end of the standby power supply incoming line voltage transformer PT2 are respectively connected to one end of the high-voltage standby transformer.

Description

One-time pressure-on synchronous nuclear phase inspection system for electrical system
Technical Field
The utility model relates to an once lead to and press in the same phase nuclear phase inspection technical field of electric system, concretely relates to once lead to and press in the same phase nuclear phase inspection system of electric system.
Background
One of the characteristics of the large-capacity thermal power generating set is that a centralized control mode of a machine, a furnace and an electric unit is adopted, the safety and the reliability of a station service electric system have quite important influence on the operation of the whole generating set and even the whole power plant, and the station service switching is an important link of the whole station service electric system.
The large-capacity thermal power generating set has the other characteristics of large number of motors and large capacity, so that voltage attenuation is slow after a station-service bus is powered off. The generator set has the basic requirements of safety and reliability on service power switching. The safety of the device is realized in that the device can not be damaged in the switching process, the reliability is embodied in that the switching success rate is improved, and the accidents that the boiler steam turbine stops running due to standby transformer overcurrent or tripping of important auxiliary machines are reduced.
The service power switching mode determines the operation mode of the service load, affects the operation safety of equipment and greatly affects the operation economy of the generator set. In the past, the industrial power system widely adopts an SN type oil-less breaker, the tripping and closing time is long, and slow switching is generally adopted. With the wide application of vacuum and SF6 circuit breakers, factory power supplies are rapidly switched in a new generation.
At present, the auxiliary contact of a working switch is generally adopted for switching the service power, so that the standby power is directly started to be switched on, or the low-voltage relay is used for delaying the switching on of the standby power of the relay, if the phase angle difference between the feedback voltage of the service bus and the voltage of the standby power is large or is possibly close to 180 degrees at the moment of switching on, the motor is subjected to great switching-on impact, and the switching-on mode with fixed delay cannot reliably avoid the switching-on of a reverse phase point due to the influence of factors such as the service load fault type of the operation mode of an electric system during switching. If the standby power supply is put into use after the residual voltage is attenuated to a certain amplitude, the voltage of the bus and the rotating speed of the motor are greatly reduced due to overlong power-off time, so that the operation condition of the boiler is seriously influenced. Therefore, the current widely used auxiliary power rapid switching device adopts rapid switching with synchronous function, and the device is classified according to the switching speed: fast switching, short delay switching, contemporaneous capture switching, residual voltage switching, and the like. Because the rapid switching device with the synchronous function is adopted for the station service, strict requirements are provided for the polarity led out by each voltage transformer of the station service power section.
After the generator set is connected to the grid and is loaded, under the operating condition of the main transformer, the high-voltage plant transformer and the high-voltage backup transformer are operated in a charged mode, and the power supply is provided for the plant working section by the high-voltage backup transformer. In this case, the electrical system does not have a condition for performing a system synchronization power source phase check once to perform a service switching device voltage circuit synchronization check, and cannot perform the voltage circuit synchronization phase check. If the primary nuclear phase is adopted for synchronous inspection, the operation amount of the field operation state is large, the inspection operation risk is high, and the correctness of the voltage loop of the station service power switching device can be indirectly inspected and confirmed only through the primary nuclear phase and the secondary nuclear phase. Therefore, the primary voltage-passing synchronous phase checking system for the electrical system is designed, primary voltage-passing and synchronous phase checking is carried out before the electrical system is powered on, and the fact that the electrical system is in synchronous phase checking with a power supply and normal operation is ensured is very necessary.
SUMMERY OF THE UTILITY MODEL
The utility model provides a system for checking the same-period nuclear phase of an electrical system, which is to carry out the same-period nuclear phase check of the voltage conduction test before the electrical system is powered on, to ensure the same-period nuclear phase and normal operation of the electrical system, and to carry out the linkage test of the service power quick switching device after the check of the same-period nuclear phase of the electrical system is correct, to obtain the final test result, to execute the service power switching test without confirming the same-period nuclear phase of the quick switching voltage loop again after the grid connection of the generator set, to ensure the correct checking of the same-period nuclear phase of the service power supply against the service power supply incoming line voltage transformer PT1, the standby power supply incoming line voltage transformer 2 voltage, the service bus voltage transformer PT3 voltage before the service power switching test, the service power switching test is qualified, the situations that the electric system fails and the electric equipment is damaged due to non-synchronous switching of the electric system are prevented, and safe and stable operation of the electric system is guaranteed.
The technical problem is solved by the following technical scheme:
a primary voltage-passing synchronous nuclear phase inspection system of an electrical system is characterized by comprising a generator, a main transformer, a high-voltage plant transformer, a working power supply incoming line switch DL1, a working power supply incoming line voltage transformer PT1, a service working section bus voltage transformer PT3, a feeder switch DL3, a low-voltage plant transformer, a standby power supply incoming line switch DL2, a standby power supply incoming line voltage transformer PT2, a high-voltage standby transformer, a service quick switching device and a service working section bus; the output end of the generator and one end of the high-voltage plant transformer are respectively connected to the input end of the main transformer; the knife switch end of the working power supply incoming line switch DL1 and the detection end of the working power supply incoming line voltage transformer PT1 are respectively connected to the other end of the high-voltage plant transformer; two ends of the low-voltage plant transformer are respectively connected to the three-phase voltage regulator and one end of the feeder switch DL 3; the knife switch end of the standby power supply inlet wire switch DL2 and the detection end of the standby power supply inlet wire voltage transformer PT2 are respectively connected to one end of a high-voltage standby transformer; the control end of a working power supply incoming line switch DL1, the signal uploading end of a working power supply incoming line voltage transformer PT1, the signal uploading end of a station-service working section bus voltage transformer PT3, the signal uploading end of a standby power supply incoming line voltage transformer PT2 and the control end of a standby power supply incoming line switch DL2 are respectively connected with a station-service power rapid switching device; the tool receiving end of the working power supply incoming line switch DL1, the detection end of the station-service working section bus voltage transformer PT3, the other end of the feeder switch DL3 and the tool receiving end of the standby power supply incoming line switch DL2 are respectively connected with the station-service working section bus.
The detection method of the primary voltage-passing synchronous nuclear phase detection system of the electrical system comprises the steps that when an auxiliary power rapid switching test is carried out, an auxiliary power rapid switching device compares the amplitude and the phase of incoming line voltage of a working power supply, incoming line voltage of a standby power supply and busbar voltage of an auxiliary working section, and synchronous detection and capture are carried out; the service power rapid switching device carries out synchronous nuclear phase check when receiving a starting rapid switching instruction, and sends a switching action instruction to correspondingly switch on and off the working power supply incoming line switch DL1 and the standby power supply incoming line switch DL2 under the synchronous condition of meeting the amplitude and the phase so as to complete the switching of service power supply.
The scheme is that one-time voltage-passing and synchronous phase-checking is carried out before the electric system is powered on, so that the synchronous phase-checking and normal operation of the electric system with the same power supply are ensured, and after the one-time power-on test of the electrical system and the check of the synchronous nuclear phase are correct, the linkage test of the auxiliary power rapid switching device is carried out to obtain the final test result, the method has the advantages that the service power switching test can be executed without confirming the phase of the synchronous power supply of the quick-switching voltage loop again after the generator set is connected to the grid, the correct phase check of the synchronous power supply can be carried out aiming at the voltages of the working power supply incoming line voltage transformer PT1, the standby power supply incoming line voltage transformer PT2 and the service bus voltage transformer PT3 before the service power switching test, the qualification of the service power switching test is ensured, the situations that the electric system fails and the electric equipment is damaged due to the asynchronous switching of the electric system are prevented, and the safe and stable operation of the electric system is ensured.
Preferably, the system further comprises a three-phase experimental power supply, and the three-phase experimental power supply is connected with the three-phase voltage regulator. The three-phase experimental power supply increases the reliability of the low-voltage power supply.
The utility model discloses can reach following effect:
before an industrial power switching test, the synchronous power supply phase checking is carried out on the voltages of a working power supply incoming line voltage transformer PT1, a standby power supply incoming line voltage transformer PT2 and an industrial bus voltage transformer PT3, an industrial power quick switching device linkage test is carried out, and the difficulty that one-time power-on test and synchronous phase checking of an electrical system cannot be carried out due to the limitation of test equipment is overcome; after the primary power-on test and the synchronous phase checking of the electrical system are correct, the service power switching test can be executed without confirming the synchronous power supply phase of the quick-switching voltage loop again after the generator set is connected to the grid, so that the construction benefit is improved; the new method is not limited by voltage grades, so that the method has reference significance for one-time power-on tests and synchronous phase check of the factory bus electrical systems with various voltage grades, and has general popularization. Simple structure, good safety and high reliability.
Drawings
Fig. 1 is a schematic diagram of a circuit principle connection structure of the present invention.
Detailed Description
The present invention will be further described with reference to the accompanying drawings and examples.
Example (b): a one-time pressure-passing synchronous nuclear phase inspection system for an electrical system is shown in figure 1. The system comprises a generator, a main transformer, a high-voltage substation, a working power supply incoming line switch DL1, a working power supply incoming line voltage transformer PT1, a station-used working section bus voltage transformer PT3, a feeder switch DL3, a low-voltage substation, a three-phase experimental power supply, a standby power supply incoming line switch DL2, a standby power supply incoming line voltage transformer PT2, a high-voltage standby substation, a station-used rapid switching device and a station-used working section bus;
the output end of the generator and one end of the high-voltage plant transformer are respectively connected to the input end of the main transformer;
the knife switch end of the working power supply incoming line switch DL1 and the detection end of the working power supply incoming line voltage transformer PT1 are respectively connected to the other end of the high-voltage plant transformer;
two ends of a low-voltage plant transformer are respectively connected to the three-phase voltage regulator and one end of the feeder switch DL3, and a three-phase experimental power supply is connected with the three-phase voltage regulator;
the knife switch end of the standby power supply inlet wire switch DL2 and the detection end of the standby power supply inlet wire voltage transformer PT2 are respectively connected to one end of a high-voltage standby transformer;
the control end of a working power supply incoming line switch DL1, the signal uploading end of a working power supply incoming line voltage transformer PT1, the signal uploading end of a station-service working section bus voltage transformer PT3, the signal uploading end of a standby power supply incoming line voltage transformer PT2 and the control end of a standby power supply incoming line switch DL2 are respectively connected with a station-service power rapid switching device;
the tool receiving end of the working power supply incoming line switch DL1, the detection end of the station-service working section bus voltage transformer PT3, the other end of the feeder switch DL3 and the tool receiving end of the standby power supply incoming line switch DL2 are respectively connected with the station-service working section bus.
The detection method of the one-time voltage-on synchronous nuclear phase detection system of the electrical system comprises the following steps:
when an auxiliary power rapid switching test is carried out, the auxiliary power rapid switching device compares the amplitude and the phase of the incoming line voltage of the working power supply, the incoming line voltage of the standby power supply and the busbar voltage of the auxiliary working section, and carries out synchronous inspection and capture; the service power rapid switching device carries out synchronous nuclear phase check when receiving a starting rapid switching instruction, and sends a switching action instruction to correspondingly switch on and off the working power supply incoming line switch DL1 and the standby power supply incoming line switch DL2 under the synchronous condition of meeting the amplitude and the phase so as to complete the switching of service power supply.
Changing a feeder switch DL3 on the high-voltage side of the low-voltage plant transformer into a switching-on position, so that the high-voltage side of the low-voltage plant transformer is communicated with a plant working section bus;
changing a working power supply inlet wire voltage transformer PT1, a standby power supply inlet wire voltage transformer PT2 and a station-service working section bus voltage transformer PT3 into operation positions on a bus; the low-voltage transformer low-voltage side of a low-voltage factory is connected with a three-phase voltage regulator with the capacity of 10kVA, the input end of the three-phase voltage regulator is connected with a 400V three-phase experimental power supply, the output voltage amplitude of the three-phase voltage regulator is manually adjusted, high voltage can be generated at the high-voltage side of the low-voltage factory and is transmitted to a factory working section bus through a feeder switch DL3, and a working power supply inlet wire voltage transformer PT1, a standby power supply inlet wire voltage transformer PT2 and a factory working section bus voltage transformer PT3 are simultaneously provided with the same power supply; when the amplitude of the output voltage of the three-phase voltage regulator is manually adjusted to be 400V rated in a low-voltage factory, corresponding secondary voltage is collected to the working power supply incoming line voltage, the standby power supply incoming line voltage and the input channel of the factory working section bus voltage to simultaneously sense the secondary voltage of the voltage transformer provided by the same power supply, namely the secondary winding voltage of the working power supply incoming line voltage transformer PT1, the standby power supply incoming line voltage transformer PT2 and the factory working section bus voltage transformer PT3 can be measured, amplitude and phase comparison is carried out, and the synchronous comparison result of the working power supply incoming line voltage, the standby power supply incoming line voltage and the factory working section bus voltage of the factory quick switching device is checked.
The method comprises the following steps that a working power supply incoming line voltage transformer PT1, a standby power supply incoming line voltage transformer PT2 and a plant-service working section bus voltage transformer PT3 are simultaneously provided with the same power supply, corresponding secondary voltages are collected to input channels of the working power supply incoming line voltage, the standby power supply incoming line voltage and the plant-service working section bus voltage of a plant-service quick switching device, the secondary voltages of the voltage transformers provided by the same power supply are simultaneously sensed, amplitude and phase comparison is carried out on the voltages of the working power supply incoming line voltage transformer PT1, the standby power supply incoming line voltage transformer PT2 and the secondary winding voltage of the plant-service working section bus voltage transformer PT3, and the results of the simultaneous comparison of the working power supply incoming line voltage, the standby power supply incoming line voltage and the plant-service working section bus voltage detected by the plant-service quick switching device are; the method is characterized in that amplitude and phase comparison is carried out on working power supply incoming line voltage, standby power supply incoming line voltage and station service working section bus voltage of the station service quick switching device, and after synchronous normality of the working power supply incoming line voltage, the standby power supply incoming line voltage and the station service working section bus voltage of the station service quick switching device is checked, conditions for carrying out linkage test of the station service quick switching device are provided.
Firstly, a working power supply inlet wire switch DL1 is changed into a bus running state, a standby power supply inlet wire switch DL2 is changed into a bus hot standby state, a knife switch of a working power supply inlet wire switch DL1 and a knife switch of a standby power supply inlet wire switch DL2 are switched to a remote control position, an auxiliary power supply quick switching device is manually started to carry out working power supply → standby power supply switching, the auxiliary power supply quick switching device carries out synchronous phase checking when receiving a starting quick switching instruction, the auxiliary power supply quick switching device sends a standby power supply inlet wire switch DL2 switching-on instruction under the condition that the synchronous conditions of amplitude and phase are met, the auxiliary power supply quick switching device sends a working power supply inlet wire switch DL1 switching-off instruction after confirming that the standby power supply inlet wire switch DL2 is switched on and after a set fixed delay, and the working power supply → standby power supply switching process is completed;
secondly, the standby power supply inlet wire switch DL2 is changed into a bus running state, the working power supply inlet wire switch DL1 is changed into a bus hot standby state, the switch control handle is switched to a remote control position, the service rapid switching device is manually started to carry out standby power supply → working power supply switching, the service rapid switching device carries out synchronous check when receiving a starting rapid switching instruction, the service rapid switching device sends a working power supply inlet wire switch DL1 switching-on instruction under the synchronous condition that amplitude and phase are met, and after the working power supply inlet wire switch DL1 is confirmed to be switched on and is subjected to a set fixed delay, the service rapid switching device sends a standby power supply inlet wire switch DL2 switching-off instruction, and the standby power supply → working power supply switching process is completed.
Before the service power is supplied with power, the voltages of a working power supply incoming line voltage transformer PT1, a standby power supply incoming line voltage transformer PT2 and a service working section bus voltage transformer PT3 are subjected to synchronous power supply phase checking, a linkage test of the service power quick switching device is carried out, and after the linkage test is correct, the service power switching test can be executed without confirming the synchronous power supply phase checking of a quick switching voltage loop again after the generator set is connected with the power grid;
before the generator set is electrified in a factory, the voltage of a working power supply incoming line voltage transformer PT1, the voltage of a standby power supply incoming line voltage transformer PT2 and the voltage of a factory working section bus voltage transformer PT3 are simultaneously in an operating working position through the adjustment of equipment states, and the primary voltage electrification and the synchronous check of the electrical system are realized by adopting primary voltage electrification of the electrical system;
by adopting a test method of applying voltage to the low-voltage side of a low-voltage plant to perform reverse boosting, the voltages of a working power supply incoming line voltage transformer PT1, a standby power supply incoming line voltage transformer PT2 and a plant working section bus voltage transformer PT3 are electrified with a power supply;
and carrying out comparative analysis on the checking data of the nuclear phase in the same period, and carrying out linkage test on the rapid service switching device to obtain a final test result.
Taking 2 × 1000MW project of a third period of a power plant as an example, the service power supply is provided with 4 sections, and each section is provided with a set of service power quick switching device which is used for switching a working power supply and a standby power supply of the service section;
after the generator set is operated in a grid-connected mode, the auxiliary power rapid switching device switches the load on the auxiliary power section to the working power supply by controlling the tripping and closing of the working power supply incoming line switch DL1 and the tripping and closing of the standby power supply incoming line switch DL2, and therefore the auxiliary power switching is achieved.
The signals that need gather of auxiliary power quick switching device have: the auxiliary power supply voltage transformer comprises a position auxiliary contact of a working power supply incoming line switch DL1, a position auxiliary contact of a standby power supply incoming line switch DL2, the voltage of a working power supply incoming line voltage transformer PT1, the voltage of a standby power supply incoming line voltage transformer PT2 and the voltage of a service bus voltage transformer PT 3.
Because the service power fast switching device has the synchronization function, before the service power switching action is performed, the service power fast switching device needs to perform synchronization check on the voltage of the working power supply inlet line voltage transformer PT1, the voltage of the standby power supply inlet line voltage transformer PT2 and the voltage of the service bus voltage transformer PT3, and the synchronization check is the synchronization check of the service power supply.
After the generator set is connected to the grid and is loaded, under the condition that the generator transformer unit system wiring is operated, the high-voltage plant transformer and the high-voltage backup transformer are operated in a live-line mode, and the plant working section is powered by the high-voltage backup transformer.
In this case, the electrical system does not have a condition for performing a voltage circuit synchronization check of the utility power switching device by performing a system synchronization power supply phase check once, and the voltage circuit synchronization check cannot be performed.
If the primary nuclear phase is adopted for synchronous inspection, the operation amount of the field operation state is large, the risk of inspection operation is high, whether the voltage loop of the station power switching device is correct or not can be indirectly inspected and confirmed only through the primary nuclear phase and the secondary nuclear phase, and the construction benefit is not high.
Before the station load of the generator set is powered on, the voltage of a working power supply inlet line voltage transformer PT1, the voltage of a standby power supply inlet line voltage transformer PT2 and the voltage of a station bus voltage transformer PT3 are enabled to simultaneously run at a working position through the adjustment of the state of equipment, and the primary voltage electrification and the synchronous check of the electrical system can be better realized by adopting the primary voltage electrification of the electrical system.
The method comprises the following steps of directly and slowly boosting voltage on a medium-voltage bus by adopting alternating-current voltage-withstanding equipment to check the installation and wiring conditions of the medium-voltage bus equipment;
the conventional primary voltage electrifying test method has the characteristics that: the device is simple and reliable, can boost the pressure slowly, and is beneficial to controlling the whole boosting process;
generally, alternating-current voltage-withstanding equipment is single-phase, so that the boosting is divided into three phases, and the test needs to be carried out by dividing the three phases A, B and C into three times; due to single-phase boosting, the voltage of the secondary side of the TV can only be checked for one phase each time, the phase sequence cannot be measured, and meanwhile, a bus low-voltage tripping loop cannot be simulated actually.
When a three-phase primary power-on test is carried out by adopting 400V low voltage, the amplitude of the secondary voltage of the voltage transformer is small, and the leading-out polarity and the phase sequence of the voltage transformer cannot be well checked.
Through the analysis, the polarity and the synchronous nuclear phase led out by the voltage transformer cannot be well verified by adopting the conventional one-time voltage electrifying test method. The main reasons are: the transformer for the instrument has larger transformation ratio, and the amplitude of the voltage signal after transmission is smaller, so that the phase analysis of the voltage signal measured and recorded by the instrument is difficult to perform on site; the high-voltage test equipment is limited by test equipment, the high-voltage test equipment can only be used for conducting power-on in a split-phase mode, the phase sequence cannot be well checked, and the like, and the working efficiency is low.
Therefore, a method for verifying the leading-out polarity of the voltage transformer and making up the limitation of a test instrument is needed to be designed for one-time voltage connection and synchronous phase checking of the electrical system.
The test method for applying voltage to the low-voltage side of the low-voltage plant to perform reverse boosting can conveniently solve the problem of the deficiency of the conventional primary voltage electrifying test method, and can better perform primary voltage electrifying and synchronous phase checking of an electrical system.
According to the practical situation of a concrete project, the following method is adopted to implement a reverse boost test to verify the leading-out polarity of the voltage transformer.
Firstly, before the service power receiving switching, the connection between a working power supply incoming line switch DL1 and the low-voltage side of a high-voltage service is checked and confirmed to be in the disconnection position, and the connection between a standby power supply incoming line switch DL2 and the low-voltage side of a high-voltage standby is checked and confirmed to be in the disconnection position;
secondly, the working power supply incoming line switch DL1 and the standby power supply incoming line switch DL2 are changed into the switching-on positions; changing the operation positions of a working power supply inlet line voltage transformer PT1, a standby power supply inlet line voltage transformer PT2 and a station service bus voltage transformer PT 3;
changing a feeder switch DL3 on a high-voltage side (6.3 kV) of a low-voltage substation into a switching-on position, so that the high-voltage side of the low-voltage substation is communicated with a service bus (6.3 kV) on the high-voltage side;
then, the output voltage is slowly regulated by a three-phase voltage regulator on a bus section of a low-voltage side (400V) of a low-voltage plant until the regulated output voltage is 400V, and the voltage on a 6.3kV plant bus is raised to a rated value.
Then, the following items are checked and confirmed:
respectively checking the voltage amplitude and the phase sequence of a working power supply incoming line voltage transformer PT1, a standby power supply incoming line voltage transformer PT2 and a station service bus voltage transformer PT 3;
performing synchronous power supply phase checking on secondary voltages of a working power supply incoming line voltage transformer PT1, a standby power supply incoming line voltage transformer PT2 and a station bus voltage transformer PT3 respectively;
checking the voltage amplitude and the phase sequence of the 400V bus section of the low-voltage plant transformer, and simultaneously checking the voltage amplitude, the phase sequence and a secondary loop of the 400V bus voltage transformer;
checking the indication correctness of the live displays of all the disk cabinets connected to the 6.3kV factory bus;
the low-voltage protection of a station bus voltage transformer PT3 and the low-voltage jump circuit of each feeder line are checked;
recording the input current of the three-phase voltage regulator, and calculating the no-load loss of the low-voltage plant transformer;
and finally, carrying out comparative analysis on data of the phase checking of the synchronous power supply to obtain a final test result, and ending.
The embodiment can perform synchronous power supply phase checking on the voltages of the working power supply incoming line voltage transformer PT1, the standby power supply incoming line voltage transformer PT2 and the station bus voltage transformer PT3 before the station power switching test, and breaks through the difficulty that one-time power-on test and synchronous phase checking of an electrical system cannot be performed due to the limitation of test equipment; after the primary power-on test and the synchronous phase check of the electrical system are correct, a linkage test of the service quick switching device is carried out, after the primary power-on test and the synchronous phase check of the electrical system and the linkage test of the service quick switching device are correct, the service switching test can be executed without confirming the synchronous power supply phase of the quick switching voltage loop again after the generator set is connected to the grid, and the construction benefit is improved; the new method is not limited by voltage grades, so that the method has reference significance for one-time power-on tests and synchronous phase check of the factory bus electrical systems with various voltage grades, and has general popularization. Simple structure, good safety and high reliability.
The embodiments of the present invention have been described above with reference to the accompanying drawings, but the present invention is not limited to the above embodiments, and those skilled in the art can make various changes or modifications within the scope of the appended claims.

Claims (2)

1. A primary voltage-passing synchronous nuclear phase inspection system of an electrical system is characterized by comprising a generator, a main transformer, a high-voltage plant transformer, a working power supply incoming line switch DL1, a working power supply incoming line voltage transformer PT1, a service working section bus voltage transformer PT3, a feeder switch DL3, a low-voltage plant transformer, a standby power supply incoming line switch DL2, a standby power supply incoming line voltage transformer PT2, a high-voltage standby transformer, a service quick switching device and a service working section bus;
the output end of the generator and one end of the high-voltage plant transformer are respectively connected to the input end of the main transformer;
the knife switch end of the working power supply incoming line switch DL1 and the detection end of the working power supply incoming line voltage transformer PT1 are respectively connected to the other end of the high-voltage plant transformer;
two ends of the low-voltage plant transformer are respectively connected to the three-phase voltage regulator and one end of the feeder switch DL 3;
the knife switch end of the standby power supply inlet wire switch DL2 and the detection end of the standby power supply inlet wire voltage transformer PT2 are respectively connected to one end of a high-voltage standby transformer;
the control end of a working power supply incoming line switch DL1, the signal uploading end of a working power supply incoming line voltage transformer PT1, the signal uploading end of a station-service working section bus voltage transformer PT3, the signal uploading end of a standby power supply incoming line voltage transformer PT2 and the control end of a standby power supply incoming line switch DL2 are respectively connected with a station-service power rapid switching device;
the tool receiving end of the working power supply incoming line switch DL1, the detection end of the station-service working section bus voltage transformer PT3, the other end of the feeder switch DL3 and the tool receiving end of the standby power supply incoming line switch DL2 are respectively connected with the station-service working section bus.
2. The system for one-time voltage-on synchronous nuclear phase inspection of an electrical system according to claim 1, further comprising a three-phase experimental power supply connected to the three-phase voltage regulator.
CN201921879574.5U 2019-11-04 2019-11-04 One-time pressure-on synchronous nuclear phase inspection system for electrical system Active CN210898551U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921879574.5U CN210898551U (en) 2019-11-04 2019-11-04 One-time pressure-on synchronous nuclear phase inspection system for electrical system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921879574.5U CN210898551U (en) 2019-11-04 2019-11-04 One-time pressure-on synchronous nuclear phase inspection system for electrical system

Publications (1)

Publication Number Publication Date
CN210898551U true CN210898551U (en) 2020-06-30

Family

ID=71320732

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921879574.5U Active CN210898551U (en) 2019-11-04 2019-11-04 One-time pressure-on synchronous nuclear phase inspection system for electrical system

Country Status (1)

Country Link
CN (1) CN210898551U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110854925A (en) * 2019-11-04 2020-02-28 中国能源建设集团华东电力试验研究院有限公司 One-time voltage-on synchronous nuclear phase inspection system and inspection method for electrical system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110854925A (en) * 2019-11-04 2020-02-28 中国能源建设集团华东电力试验研究院有限公司 One-time voltage-on synchronous nuclear phase inspection system and inspection method for electrical system
CN110854925B (en) * 2019-11-04 2021-06-08 中国能源建设集团华东电力试验研究院有限公司 One-time voltage-on synchronous nuclear phase inspection system and inspection method for electrical system

Similar Documents

Publication Publication Date Title
CN110854925B (en) One-time voltage-on synchronous nuclear phase inspection system and inspection method for electrical system
CN110854924B (en) One-time voltage-on synchronous phase-checking linkage switching inspection system and inspection method for electrical system
CN203881875U (en) Low-voltage three-phase line fault generator
CN111478370A (en) Multi-parallel-machine grid-connected method and system based on non-stop of low-voltage power supply vehicle
CN110880792B (en) One-time voltage-on synchronous nuclear phase fast switching inspection system and inspection method for electrical system
CN210898551U (en) One-time pressure-on synchronous nuclear phase inspection system for electrical system
CN113595227B (en) Low-voltage transformer area load uninterrupted switching system and working method thereof
CN106684927A (en) Grid-connected system for large generator sets in isolated grid system and grid-connected method
CN109683106B (en) Short circuit test system for different-capacity impact generator grid-connected power supply
CN103532444A (en) Large-scale impact power generation device group frequency conversion starting device
CN211456713U (en) One-time pressure-on synchronous nuclear phase linkage switching and testing system for electrical system
CN107546778B (en) Hydropower station intelligent in-situ control system and method based on IEC61850 standard
CN114441896B (en) Distribution network automatic simulation platform and FTU detection method
CN211402556U (en) One-time voltage-on synchronous nuclear phase fast switching inspection system for electrical system
CN204481493U (en) Transformer unit synchronous device closing circuit system
CN108279345B (en) Power substation power transmission testing device
CN118017575B (en) Debugging circuit and method of cascade high-voltage direct-hanging energy storage system
CN205665584U (en) Extra -high voltage station circuit breaker controlling means's in same term calibration equipment
CN114252710B (en) Method for unit grid-connected synchronous system homologous nuclear phase
Tang et al. Synchrophasor based transmission system anti-islanding scheme
CN111190358B (en) 10kV closing angle control system and accurate control method
CN212726900U (en) Nuclear power plant excitation system, excitation regulator working power supply and power supply output circuit
CN216016755U (en) Starting current suppression device of steam residual pressure utilization asynchronous generator of thermal power plant
CN116068361B (en) Alternating current test system
CN219738027U (en) Electromagnetic-electromechanical transient semi-physical simulation test system of multi-source power generation system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant