CN210802819U - Pipeline construction is with leakproofness on-site measuring device - Google Patents

Pipeline construction is with leakproofness on-site measuring device Download PDF

Info

Publication number
CN210802819U
CN210802819U CN201921707344.0U CN201921707344U CN210802819U CN 210802819 U CN210802819 U CN 210802819U CN 201921707344 U CN201921707344 U CN 201921707344U CN 210802819 U CN210802819 U CN 210802819U
Authority
CN
China
Prior art keywords
supporting shoe
screw
wall
pipeline construction
side outer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201921707344.0U
Other languages
Chinese (zh)
Inventor
乐子燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi North China Tuxingsun Construction Engineering Co ltd
Original Assignee
Hubei Jianyan Kefeng Engineering Quality Detection Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hubei Jianyan Kefeng Engineering Quality Detection Co ltd filed Critical Hubei Jianyan Kefeng Engineering Quality Detection Co ltd
Priority to CN201921707344.0U priority Critical patent/CN210802819U/en
Application granted granted Critical
Publication of CN210802819U publication Critical patent/CN210802819U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Examining Or Testing Airtightness (AREA)
  • Measuring Fluid Pressure (AREA)

Abstract

The utility model discloses a leakproofness witnessed inspections device for pipeline construction, including first supporting shoe, connecting pipe and standing groove, first supporting shoe one side outer wall is provided with the second supporting shoe, the standing groove has all been seted up to first supporting shoe and second supporting shoe inside, first connecting block and second connecting block are installed to the relative one side outer wall of second supporting shoe symmetry respectively, the inside screw of having seted up of second connecting block, the screw is installed to the inside screw thread of screw, first supporting shoe deviates from the grafting of second supporting shoe one side outer wall and installs the connecting pipe. The utility model discloses a set up first supporting shoe, second supporting shoe and manometer, reached the effect of guaranteeing to detect the data accuracy, the staff of being convenient for uses, has guaranteed to detect the accuracy, improves work efficiency, avoids the staff to appear the erroneous judgement.

Description

Pipeline construction is with leakproofness on-site measuring device
Technical Field
The utility model relates to a detection device technical field specifically is a leakproofness on-the-spot detection device is used in pipeline construction.
Background
After the gas pipeline or the water pipe is laid, the worker needs to detect the construction quality, wherein the detection step is important. The pipeline tightness is detected, if the pipeline tightness is not good, internal transportation materials are wasted, if gas leakage occurs, the gas can be burnt immediately when encountering open fire, and economic loss is early.
It should be noted that, a leakproofness field detection device for pipeline construction is the product of selling, and for prior art, a gas pipeline leakproofness detection device has been disclosed in the patent number CN201320825648.3, and its theory of operation and inner structure are known to the technical staff of the technical field that belongs to, the utility model discloses only utilized the function of above-mentioned spare part and do not improve its inner structure, consequently, no longer detailed description here.
The traditional detection mode is low in detection accuracy, error judgment is easily caused, a worker is not convenient to detect and record data at the same time, the accuracy of the detected data is influenced, and the working efficiency is low.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to provide a leakproofness witnessed inspections device is used in pipeline construction possesses the advantage that improves the detection accuracy, has solved the lower problem of detection accuracy.
In order to achieve the above object, the utility model provides a following technical scheme: the utility model provides a leakproofness witnessed inspections device for pipeline construction, includes first supporting shoe, connecting pipe and standing groove, first supporting shoe one side outer wall is provided with the second supporting shoe, the inside standing groove that has all seted up of first supporting shoe and second supporting shoe, first connecting shoe and second connecting block are installed to the relative one side outer wall of first supporting shoe and second supporting shoe symmetry respectively, the inside screw of having seted up of second connecting block, the screw is installed to the inside screw thread of screw, first supporting shoe deviates from second supporting shoe one side outer wall and pegs graft and installs the connecting pipe.
Preferably, the first supporting block and the second supporting block are fixedly provided with sealing gaskets in a manner of being attached to the outer wall of one side of the placing groove.
Preferably, the pipeline body is movably arranged in the placing groove.
Preferably, a movable groove is formed in the first connecting block, and the screw penetrates through the movable groove and is rotatably installed in the screw hole.
Preferably, the outer wall of one side of the connecting pipe is provided with a pressure gauge in an inserting mode, and one end, deviating from the pressure gauge, of the connecting pipe is provided with an air pump.
Preferably, the length of the inner wall of the placing groove is greater than the length of the joint of the pipeline body.
Compared with the prior art, the beneficial effects of the utility model are that: the utility model discloses a set up first supporting shoe, second supporting shoe and manometer, the effect of guaranteeing the detection data accuracy has been reached, the manual first supporting shoe and the second supporting shoe of taking of staff, and place in the pipeline body position that needs detected through the standing groove, the manual spanner rotating screw of taking of staff, screw and screw mesh, drive first supporting shoe and second supporting shoe and contact, and guarantee first supporting shoe through sealed the pad, second supporting shoe and pipeline body connection leakproofness each other, the air pump during operation, pressurize inside giving the standing groove, after the air pump stop work, the staff observes the manometer, if the manometer shows that pressure changes, reach the department of detection and leak gas so, the staff of being convenient for uses, the detection accuracy has been guaranteed, and the work efficiency is improved.
Drawings
Fig. 1 is a schematic structural view of a first support block of the present invention;
fig. 2 is a schematic top view of the first support block structure of the present invention;
fig. 3 is a schematic top view of the structure of the placement groove of the present invention;
fig. 4 is an enlarged schematic view of the structure a in fig. 3 according to the present invention.
In the figure: 1. a first support block; 11. a second support block; 12. a placement groove; 13. a pipe body; 14. a gasket; 15. a first connection block; 16. a movable groove; 17. a screw hole; 18. a screw; 19. a second connecting block; 2. a connecting pipe; 21. a pressure gauge; 22. an air pump.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "both ends", "one end", "the other end" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplification of description, but do not indicate or imply that the device or element to which the reference is made must have a specific orientation, be constructed in a specific orientation, and be operated, and thus, should not be construed as limiting the present invention. Furthermore, the terms "first" and "second" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance.
In the description of the present invention, it is to be noted that, unless otherwise explicitly specified or limited, the terms "mounted," "disposed," "connected," and the like are to be construed broadly, and for example, "connected" may be either fixedly connected or detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1 to 4, the present invention provides an embodiment: the utility model provides a leakproofness witnessed inspections device for pipeline construction, includes first supporting shoe 1, connecting pipe 2 and standing groove 12, and 1 one side outer wall of first supporting shoe is provided with second supporting shoe 11, and standing groove 12 has all been seted up to first supporting shoe 1 and 11 insides of second supporting shoe, and standing groove 12 inside movable mounting has pipeline body 13. The length of the inner wall of the placing groove 12 is larger than that of the joint of the pipeline body 13. The first supporting block 1 and the second supporting block 11 are both separated from the outer wall of one side of the placing groove 12 and are fixedly attached with a sealing gasket 14. When the air pump 22 pressurizes the inside of the placing groove 12, the packing 14 ensures the sealing property of the placing groove 12 and prevents air leakage. First supporting shoe 1 and the relative one side outer wall of second supporting shoe 11 are respectively the symmetry and are installed first connecting block 15 and second connecting block 19, and the inside screw 17 of having seted up of second connecting block 19, and screw 18 is installed to screw 17 internal thread, and the movable groove 16 has been seted up to first connecting block 15 inside, and screw 18 runs through movable groove 16 and rotates and install inside screw 17. The screw 18 engages with the threaded hole 17 to ensure that the second support block 11 is fixedly connected to the first support block 1 and that the pipe body 13 is controllably detached from the placement groove 12. The outer wall of one side of the first supporting block 1, which is far away from the second supporting block 11, is provided with a connecting pipe 2 in an inserting way. The outer wall of one side of the connecting pipe 2 is provided with a pressure gauge 21 in an inserting way. Pressure gauge 21 adopts GU40 type, and this model pressure gauge possesses the advantage of being convenient for maintain, long service life. An air pump 22 is arranged at one end of the connecting pipe 2, which is far away from the pressure gauge 21. The air pump 22 adopts a ZQ520-02 type, the air pump 22 has the advantages of good running performance and economical price, can meet the actual use requirement, can directly purchase on the market by searching the technical personnel through the type, and can directly turn over the searching technical specification to know when needing to know the type, so that the equipment is not repeated. The staff is manual takes first supporting shoe 1 and second supporting shoe 11, and place in the pipeline body 13 position that needs to detect through standing groove 12, the manual spanner that takes of staff rotates screw 18, screw 18 meshes with screw 17 mutually, drive first supporting shoe 1 and second supporting shoe 11 and contact, and guarantee first supporting shoe 1 through sealed pad 14, second supporting shoe 11 and pipeline body 13 connection leakproofness each other, air pump during operation 22, pressurize inside standing groove 12, air pump 22 back of stopping work, staff observes manometer 21, if manometer 21 shows that pressure changes, reach the department of detection and leak gas so, the staff of being convenient for uses, the detection accuracy has been guaranteed, and the work efficiency is improved.
The working principle is as follows: the staff is manual takes first supporting shoe 1 and second supporting shoe 11, and place in the pipeline body 13 position that needs to detect through standing groove 12, the manual spanner that takes of staff rotates screw 18, screw 18 meshes with screw 17 mutually, drive first supporting shoe 1 and second supporting shoe 11 and contact, and guarantee first supporting shoe 1 through sealed pad 14, second supporting shoe 11 and pipeline body 13 connection leakproofness each other, air pump during operation 22, pressurize inside standing groove 12, air pump 22 back of stopping work, staff observes manometer 21, if manometer 21 shows that pressure changes, reach the department of detection and leak gas so, the staff of being convenient for uses, the detection accuracy has been guaranteed, and the work efficiency is improved.
It is obvious to a person skilled in the art that the invention is not restricted to details of the above-described exemplary embodiments, but that it can be implemented in other specific forms without departing from the spirit or essential characteristics of the invention. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (6)

1. The utility model provides a leakproofness witnessed inspections device for pipeline construction, includes first supporting block (1), connecting pipe (2) and standing groove (12), its characterized in that: first supporting shoe (1) one side outer wall is provided with second supporting shoe (11), standing groove (12) have all been seted up to first supporting shoe (1) and second supporting shoe (11) inside, first connecting block (15) and second connecting block (19) are installed to first supporting shoe (1) and the relative one side outer wall of second supporting shoe (11) symmetry respectively, screw (17) have been seted up to second connecting block (19) inside, screw (18) are installed to screw (17) internal thread, first supporting shoe (1) deviates from the grafting of second supporting shoe (11) one side outer wall and installs connecting pipe (2).
2. The field tightness test device for pipeline construction according to claim 1, wherein: the first supporting block (1) and the second supporting block (11) are fixedly attached to a sealing gasket (14) away from the outer wall of one side of the placing groove (12).
3. The field tightness test device for pipeline construction according to claim 1, wherein: the inside movable mounting of standing groove (12) has pipeline body (13).
4. The field tightness test device for pipeline construction according to claim 1, wherein: a movable groove (16) is formed in the first connecting block (15), and the screw (18) penetrates through the movable groove (16) and is rotatably mounted in the screw hole (17).
5. The field tightness test device for pipeline construction according to claim 1, wherein: manometer (21) are installed in the grafting of connecting pipe (2) one side outer wall, connecting pipe (2) deviate from manometer (21) one end and are provided with air pump (22).
6. The field tightness test device for pipeline construction according to claim 1, wherein: the length of the inner wall of the placing groove (12) is greater than that of the joint of the pipeline body (13).
CN201921707344.0U 2019-10-12 2019-10-12 Pipeline construction is with leakproofness on-site measuring device Expired - Fee Related CN210802819U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921707344.0U CN210802819U (en) 2019-10-12 2019-10-12 Pipeline construction is with leakproofness on-site measuring device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921707344.0U CN210802819U (en) 2019-10-12 2019-10-12 Pipeline construction is with leakproofness on-site measuring device

Publications (1)

Publication Number Publication Date
CN210802819U true CN210802819U (en) 2020-06-19

Family

ID=71232122

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921707344.0U Expired - Fee Related CN210802819U (en) 2019-10-12 2019-10-12 Pipeline construction is with leakproofness on-site measuring device

Country Status (1)

Country Link
CN (1) CN210802819U (en)

Similar Documents

Publication Publication Date Title
CN110618087A (en) Corrosion resistance detection device for central heating pipeline
CN210802819U (en) Pipeline construction is with leakproofness on-site measuring device
CN213180586U (en) Pipeline is suppressed and is leaked hunting device
CN108692892A (en) A kind of device for detecting airtightness of corrugated tube and detection method
CN108918040A (en) A kind of detection device of automobile engine cylinder airtightness
CN219102720U (en) Gas leakage detection device for hydrogen-doped natural gas pipeline
CN209783855U (en) Floating ball leak detection device
CN210375577U (en) Engine oil pan water leakage detection device
CN213576796U (en) LNG double-deck metal storage tank wide-angle seam vacuum chamber that leaks hunting
CN213205948U (en) Hydraulic pump performance testing device
CN212180188U (en) Hydraulic cylinder welding seam test structure
CN211042340U (en) Nozzle flowmeter
CN210719571U (en) Novel oil storage tank leakproofness detects device
CN209470827U (en) A kind of device for detecting leak rate for low temperature multilead connector
CN207539489U (en) A kind of gas meter, flow meter pressure measurement connection flexible pipe
CN217304295U (en) Portable detection device for pressure pipeline
CN212903421U (en) Gas flowmeter with good sealing performance
CN216386196U (en) Large-capacity bag body leakage detection device
CN109827719A (en) A kind of device for detecting leak rate for low temperature multilead connector
CN211401589U (en) Detection device for heat exchanger
CN220356612U (en) Pipeline joint sealing detection device
CN209296214U (en) Pipeline pressure detection device
CN217717692U (en) Detection device for natural gas safety management
CN218000466U (en) Natural gas pipeline valve with pressure measurement structure
CN211263021U (en) Flange type valve pressure testing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200629

Address after: No.12, Lane 2, Xinnong North Street, xiliulin village, liujiabao Township, Xiaodian District, Taiyuan City, Shanxi Province

Patentee after: Shanxi Huabei tuxingsun Pipeline Engineering Co.,Ltd.

Address before: No.156 Zhonghang Avenue, Aerospace Industrial Park, Fancheng District, Xiangyang City, Hubei Province

Patentee before: HUBEI JIANYAN KEFENG ENGINEERING QUALITY INSPECTION CO.,LTD.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210512

Address after: 030006 No.12, Lane 2, xinruan North Street, xiliulin village, liujiabao Township, Xiaodian District, Taiyuan City, Shanxi Province

Patentee after: Shanxi North China tuxingsun Construction Engineering Co.,Ltd.

Address before: 030000 No.12, Lane 2, xinruan North Street, xiliulin village, liujiabao Township, Xiaodian District, Taiyuan City, Shanxi Province

Patentee before: Shanxi Huabei tuxingsun Pipeline Engineering Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20200619

Termination date: 20211012