CN210713240U - Building embedded part - Google Patents

Building embedded part Download PDF

Info

Publication number
CN210713240U
CN210713240U CN201921367050.8U CN201921367050U CN210713240U CN 210713240 U CN210713240 U CN 210713240U CN 201921367050 U CN201921367050 U CN 201921367050U CN 210713240 U CN210713240 U CN 210713240U
Authority
CN
China
Prior art keywords
building
embedded
embedded body
wall
buried body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921367050.8U
Other languages
Chinese (zh)
Inventor
金丰程
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201921367050.8U priority Critical patent/CN210713240U/en
Application granted granted Critical
Publication of CN210713240U publication Critical patent/CN210713240U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model belongs to the technical field of building cement pours the body, a building built-in fitting is disclosed, including cylindric or prismatic pre-buried body (1), the one end of pre-buried body (1) is provided with screw hole (2), and is provided with concave-convex structure on pre-buried body (1). Can effectively prevent that the pre-buried body from pulling out in the concrete that cement was pour to, the cylinder part sets up the setting that the protruding edges and corners structure of annular of cutting face, prism form and lug can effectively avoid under the effect of external force, and the rotation takes place for the pre-buried body in the concrete that the building was poured.

Description

Building embedded part
Technical Field
The utility model belongs to the technical field of building cement pours the body, concretely relates to building built-in fitting.
Background
Along with the continuous progress of life, the requirements of people on the building quality are higher and higher, so that a building mode of an industrialized house is generated, namely the traditional house building industry is improved by modern scientific technology, the integral quality level of the house construction is greatly improved through the standardization of the house building design and the industrialization of the house building production, and the use function and the living quality of the house building are improved; the industrial residential construction process mainly comprises the standardization of member prefabrication, field assembly, building products and the like, however, in the construction process of a building wall, some equipment such as an outdoor unit of an air conditioner is often required to be hung on the wall of the building, and the traditional construction mode is that holes are directly drilled in the building wall, and then a bracket of an air conditioner outdoor unit is connected with the building wall through expansion screws; however, with the change of weather and temperature, the weight of the external hanging object is added, so that the connected building external wall is easy to damage, and the expansion screw is easy to pull out, so that the external hanging object falls off.
SUMMERY OF THE UTILITY MODEL
In order to solve the problems existing in the prior art, the utility model aims to provide a building embedded part.
The utility model discloses the technical scheme who adopts does: the utility model provides a building embedded part, includes cylindric or prismatic pre-buried body, and the one end of pre-buried body is provided with the screw hole, and is provided with protruding structure on the pre-buried body.
Further, the protruding structure is an annular protrusion.
Furthermore, the end parts of the embedded bodies are provided with annular bulges.
Furthermore, the middle part of the embedded body is provided with an annular bulge.
Further, the annular protrusion is cylindrical or prismatic.
Furthermore, the protruding structure is a bolt fastener, and the bolt fastener is in threaded connection with the embedded part.
Further, the screw of the bolt fastener comprises a threaded section and a non-threaded section.
Furthermore, the protruding structure is a bump and is arranged on the side wall of the embedded body.
Furthermore, the protruding block is a cylindrical pin, a fixing hole is formed in the embedded body, and the cylindrical pin is installed in the fixing hole.
The utility model has the advantages that: through protruding structure on the embedded body, the prevention embedded body is pulled out in the concrete that the cement was pour under the effect of external force to, the annular of prismatic is protruding and the embedded body that is provided with the lug can effectively avoid under the effect of external force, and the embedded body takes place to rotate in the concrete that the building was poured.
Drawings
Fig. 1 is a schematic structural view of a cylindrical pre-buried body in the first embodiment;
fig. 2 is a schematic structural diagram of a prism-shaped embedded body in the first embodiment;
FIG. 3 is a schematic view of the connection of the embedment member and the connecting plate;
FIG. 4 is a perspective view of an embedment member connected to a single attachment plate;
FIG. 5 is a schematic perspective view of the connection of the embedded part and the connecting pieces distributed in a staggered manner;
fig. 6 is a schematic structural view of a cylindrical embedded body provided with two notches in the first embodiment;
fig. 7 is a schematic structural view of a prismatic embedded body provided with two notches in the first embodiment;
FIG. 8 is a schematic view showing the connection between the bolt fastening member and the embedded body according to the second embodiment;
FIG. 9 is a schematic structural view of an embedment member in the second embodiment;
fig. 10 is a schematic view of connection between the cylindrical embedded body and the cylindrical pin in the third embodiment;
fig. 11 is a schematic connection diagram of a prism-shaped embedded body and a cylindrical pin in the third embodiment;
in the figure: 1-embedded body, 2-threaded hole, 3-notch, 4-bolt fastener, 5-fixing hole, 6-cylindrical pin, 7-screw, 8-connecting piece and 9-flat gasket.
Detailed Description
In order to make the objects, technical solutions and advantages of the embodiments of the present invention clearer, the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are some, but not all, embodiments of the present invention. The components of embodiments of the present invention, as generally described and illustrated in the figures herein, may be arranged and designed in a wide variety of different configurations. Thus, the following detailed description of the embodiments of the present invention, presented in the accompanying drawings, is not intended to limit the scope of the invention, as claimed, but is merely representative of selected embodiments of the invention. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative efforts belong to the protection scope of the present invention.
In the description of the embodiments of the present invention, it should be understood that the terms "upper", "front", "rear", "left", "right", "bottom", "side", and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore, should not be construed as limiting the present embodiments.
In the description of the embodiments of the present invention, it should be further noted that unless otherwise explicitly stated or limited, the terms "disposed," "mounted," "connected," and "connected" are to be construed broadly and may include, for example, a fixed connection, a detachable connection, or an integral connection; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meaning of the above terms in the present invention can be understood as appropriate by those of ordinary skill in the art.
The present invention will be further described with reference to the accompanying drawings and specific embodiments.
Example one
As shown in fig. 1 and 2, the building embedded part comprises a cylindrical or prismatic embedded body 1, and one end of the embedded body 1 is provided with a threaded hole 2. When a concrete wall is constructed, the embedded body 1 is embedded in the wall, after concrete is condensed, the embedded body 1 and the wall are fixed, and the end face threaded hole 2 of the embedded body 1 is located on the wall. As shown in fig. 3-5, a screw 7 penetrates through the connecting piece 8 to be connected with the threaded hole 2 of the embedded body 1, so that the connecting piece 8 is fixed on the wall, and equipment can be hung on the connecting piece 8. A flat gasket 9 is padded between the screw 7 and the connecting piece 8.
As shown in fig. 1 and 2, the embedded body 1 is provided with a protruding structure, the protruding structure is a cylindrical or prismatic annular protrusion 3, and the phenomenon that the embedded body 1 is pulled out under the action of external force to cause the dropping of the hanging device is effectively avoided by the arrangement of the annular protrusion 3. Preferably, the end parts of the embedded bodies 1 are provided with annular protrusions 3. As shown in fig. 6 and 7, the middle of the embedded body 1 is also provided with an annular protrusion 3, so that the embedded body 1 and the wall body are more firmly fixed.
And, adopt prismatic annular protrusion 3, when effectively having avoided rotatory screw 7, pre-buried body 1 rotates in the concrete wall body that the building was pour.
Example two
As shown in fig. 8 and 9, the building embedded part comprises a cylindrical or prismatic embedded body 1, wherein one end of the embedded body 1 is provided with a threaded hole 2, and the other end of the embedded body 1 is in threaded connection with a bolt fastener 4. So that a gap is formed between the head of the bolt fastener 4 and the end of the embedded body 1. The bolt fastener 4 is a threaded fastener, and is composed of a head and a screw. When a concrete wall is constructed, the embedded part is embedded in the wall, after the concrete is condensed, the embedded part and the wall are fixed, and the end face threaded hole 2 of the embedded body 1 is positioned on the wall surface. The same as the first embodiment, the screw 7 penetrates through the connecting piece 8 to be connected with the threaded hole 2 of the embedded body 1, and the connecting piece 8 is fixed on the wall body, so that equipment can be hung on the connecting piece 8. A gap is formed between the head of the bolt fastener 4 and the end part of the embedded body 1, so that the embedded part is effectively prevented from being pulled out under the action of external force. And, the head cross-section of bolt fastener 4 is the polytropic, and when effectively having avoided rotatory screw 7, pre-buried body 1 rotates in the concrete wall body that the building was pour.
As shown in fig. 8, the screw of the bolt fastener 4 includes a threaded section and a non-threaded section, so that the distance between the head of the bolt fastener 4 and the embedded body 1 can be accurately positioned, and the size of the gap can be determined.
EXAMPLE III
As shown in fig. 10 and 11, the building embedded part includes a cylindrical or prismatic embedded body 1, a threaded hole 2 is formed at one end of the embedded body 1, and a protruding structure is arranged on the embedded body 1, the protruding structure is a protruding block, and the protruding block is arranged on a side wall of the embedded body 1. When a concrete wall is constructed, the embedded body 1 is embedded in the wall, after concrete is condensed, the embedded body 1 and the wall are fixed, and the end face threaded hole 2 of the embedded body 1 is located on the wall. The same as the first embodiment, the screw 7 penetrates through the connecting piece 8 to be connected with the threaded hole 2 of the embedded body 1, and the connecting piece 8 is fixed on the wall body, so that equipment can be hung on the connecting piece 8. The arrangement of the convex block effectively avoids the phenomenon that the embedded body 1 is pulled out under the action of external force to cause the dropping of the hanging equipment. Meanwhile, when the rotary screw 7 is effectively avoided by the arrangement of the convex block, the embedded part rotates along with the concrete wall poured by the building.
Preferably, the pre-buried body 1 is provided with a fixing hole 5, a cylindrical pin 6 is installed in the fixing hole 5, a convex block is formed through the cylindrical pin 6, and the processing and the manufacturing are simple and convenient.
Example four
A building embedded part comprises a cylindrical or prismatic embedded body 1, wherein one end of the embedded body 1 is provided with a threaded hole 2, the embedded body 1 is provided with a protruding structure, and the protruding structure can be any combination or all of two of an annular protrusion 3, a bolt fastener 4 and a lug which are mentioned in the embodiment, so that the embedded body 1 and a wall body are fixed more firmly.
The present invention is not limited to the above-mentioned optional embodiments, and any other products in various forms can be obtained by anyone under the teaching of the present invention, and any changes in the shape or structure thereof, all the technical solutions falling within the scope of the present invention, are within the protection scope of the present invention.

Claims (9)

1. A building embedded part is characterized in that: the embedded type steel wire rope.
2. The building embedment of claim 1, wherein: the convex structure is an annular bulge (3).
3. The building embedment of claim 1, wherein: the end parts of the embedded bodies (1) are provided with annular bulges (3).
4. The building embedment of claim 1, wherein: the middle part of the embedded body (1) is provided with an annular bulge (3).
5. The building embedment of claim 2, wherein: the annular bulge (3) is cylindrical or prismatic.
6. The building embedment of claim 1, wherein: the protruding structure is a bolt fastener (4), and the bolt fastener (4) is in threaded connection with the embedded body (1).
7. The building embedment of claim 6, wherein: the screw of the bolt fastener (4) comprises a threaded section and a non-threaded section.
8. The building embedment of claim 1, wherein: the protruding structure is a protruding block and is arranged on the side wall of the embedded body (1).
9. The building embedment of claim 8, wherein: the convex block is a cylindrical pin (6), a fixing hole (5) is formed in the embedded body (1), and the cylindrical pin (6) is installed in the fixing hole (5).
CN201921367050.8U 2019-08-21 2019-08-21 Building embedded part Active CN210713240U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921367050.8U CN210713240U (en) 2019-08-21 2019-08-21 Building embedded part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921367050.8U CN210713240U (en) 2019-08-21 2019-08-21 Building embedded part

Publications (1)

Publication Number Publication Date
CN210713240U true CN210713240U (en) 2020-06-09

Family

ID=70929938

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921367050.8U Active CN210713240U (en) 2019-08-21 2019-08-21 Building embedded part

Country Status (1)

Country Link
CN (1) CN210713240U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112253604A (en) * 2020-11-30 2021-01-22 刘茂生 Ceiling embedded nut piece

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112253604A (en) * 2020-11-30 2021-01-22 刘茂生 Ceiling embedded nut piece

Similar Documents

Publication Publication Date Title
CN210713240U (en) Building embedded part
CN204475593U (en) Support structure installed by a kind of curtain wall
CN201972281U (en) Curtain wall hitching component
CN209457163U (en) A kind of attachment device of assembled superimposed sheet
CN212026701U (en) Prefabricated shear wall horizontal connection structure with W-shaped joint
CN213015417U (en) Template for building construction
CN110439121B (en) Connection structure of external PC wallboard of assembled steel construction building and main part
CN211949113U (en) Assembled floor splicing structure
CN208219909U (en) A kind of construction wall with built-in fitting
CN202809934U (en) Back-buckling locking type stone material curtain wall dry hanging structure installed in close seam
CN203174837U (en) Combination hanging piece and beam-free reinforced ceramic gravel curtain wall system
CN220165604U (en) Hoisting tool for assembled concrete well plate
CN205743455U (en) A kind of Novel civil air defense anchoring hook
CN107060332B (en) Unilateral Screw arbor with nut at both-ends system
CN111350521A (en) Pre-buried sleeve for shield interval
CN215166601U (en) Wall pre-embedding fixing structure
CN213329578U (en) Anti-seismic and anti-falling hanging plate device
KR20090011248U (en) Fixing structure for concrete form
CN214833688U (en) Node is hung futilely to assembly type structure outer wall
CN213174593U (en) Mounting structure of assembled dysmorphism outer wall
CN217325866U (en) Hook type anchor bolt special for connecting steel wire mesh
CN214463504U (en) Self-tapping screw for building door and window
CN219992761U (en) Conveniently-installed external wall insulation board
CN213115467U (en) A novel connecting pin axle for scaffold installation
CN202162728U (en) Bidirectional power transfer positioning device for steel member

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PP01 Preservation of patent right

Effective date of registration: 20210730

Granted publication date: 20200609

PP01 Preservation of patent right