CN209780030U - L-shaped column steel framework for foundation and top layer of prefabricated building - Google Patents

L-shaped column steel framework for foundation and top layer of prefabricated building Download PDF

Info

Publication number
CN209780030U
CN209780030U CN201821437085.XU CN201821437085U CN209780030U CN 209780030 U CN209780030 U CN 209780030U CN 201821437085 U CN201821437085 U CN 201821437085U CN 209780030 U CN209780030 U CN 209780030U
Authority
CN
China
Prior art keywords
steel
top layer
concrete
column
shape post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821437085.XU
Other languages
Chinese (zh)
Inventor
杨文奇
杨伯寅
郑芝然
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Huizhou Decoda Construction Engineering Technology Co Ltd
Original Assignee
Huizhou Decoda Construction Engineering Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huizhou Decoda Construction Engineering Technology Co Ltd filed Critical Huizhou Decoda Construction Engineering Technology Co Ltd
Priority to CN201821437085.XU priority Critical patent/CN209780030U/en
Application granted granted Critical
Publication of CN209780030U publication Critical patent/CN209780030U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model relates to a steel knot concrete structure L shape post for assembled building's basic top layer constructs L shape post with this steel knot concrete structure L shape post complex steel node to and construct the assembled building of L shape post including steel node and steel knot concrete. The utility model discloses still relate to the L shape post steel framework of basic top layer steel festival concrete structure L shape post. The L-shaped column of the steel-joint concrete structure comprises a reinforced concrete column body with an L-shaped section, and longitudinal stress steel bars, concrete and steel column heads which are arranged along the circumferential direction of the reinforced concrete column body. The utility model discloses steel-knot concrete constructs L shape post and prefabricates in the mill, at first prepares L shape post steel framework, presss from both sides again and establishes template and concreting, makes steel-knot concrete structure L shape post prefab to be equipped with the assembly. The utility model discloses steel festival concrete constructs L shape post has following advantage: firstly, energy conservation and environmental protection are realized, and the construction period is shortened by at least half; secondly, the quality is improved fundamentally; thirdly, the overall stability of the structure is good; and fourthly, finishing the steel framework of the L-shaped column and the L-shaped column of the steel-joint concrete structure in a factory.

Description

L-shaped column steel framework for foundation and top layer of prefabricated building
Technical Field
The utility model relates to a node that basic top layer steel knot concrete constructs L shape post for assembly type structure constructs L shape post with this node complex basic top layer steel knot concrete and constructs L shape post to and construct the assembly type structure of L shape post including node and basic top layer steel knot concrete. The utility model discloses still relate to the L shape post steel framework of basic top layer steel festival concrete structure L shape post.
Background
Since the little reform is opened, the construction engineering in China continues to develop at a high speed, and the building scale and the investment amount are very huge. In 2017, the construction area of the real estate industry only reaches 78 hundred million square meters. However, most construction projects still adopt the traditional construction site cast-in-place concrete design method and construction technology. Causing serious negative problems in the high-speed development of the building engineering. The problems of land protection, forest ecology protection, dust pollution and air pollution reduction, noise pollution and environment pollution reduction, house heat preservation and energy conservation, engineering quality improvement and the like are the construction technical problems which must be urgently solved by the building industry. In 2016, 9 months, the Like force theory proposes that ' the assembly type building is determined to be developed vigorously ' and the adjustment and the upgrade of the industrial structure are promoted '. The ministry of living construction carries out the guidance opinions of the office of State Council about the vigorous development of the fabricated building, develops the fabricated building for popularizing green buildings and building materials, improves the technical level and the engineering quality of the building, and gives great support and policy preference to the scientific and creative work of the fabricated building. Up to now, the reinforced concrete fabricated building is known as a cast-in-place assembling technology of a factory prefabricated superposition construction site. The technology is not very high in assembly rate in practice, and is high in construction difficulty, high in manufacturing cost and very difficult to popularize.
the utility model provides a steel-knot concrete constructs rectangle post and steel node thereof is a basic component in steel-knot concrete constructs the assembly type building system. Standardized production in factories and assembly into building structures on the construction site. The assembly type building technology abandons the procedures of building a scaffold, supporting a template, binding reinforcing steel bars, pouring concrete and the like in the traditional construction method. The standard of building green, environment-friendly and energy-saving buildings is achieved. It is suitable for high-rise reinforced concrete building. Compared with the traditional building construction method, the technology solves the problem of common quality problems which are not solved for a long time in the building engineering, fundamentally improves the engineering quality and powerfully promotes the progress of building design and construction technology. The shock resistance is more excellent. The cost is suitable, and the economic benefit and the social benefit are good.
SUMMERY OF THE UTILITY MODEL
The utility model provides a can solve the technical scheme of above-mentioned problem. Particularly, the utility model provides an adopt the assembly structure of "steel node + concrete structure" (hereinafter referred to as steel knot concrete structure), thereby make the technical scheme of the utility model can have the advantage that concrete structure is with low costs and steel knot structure intensity/precision is high concurrently. In addition, the structure of the steel-concrete structure is more beneficial to the construction mode of prefabricating structural components in a factory and then assembling on a construction site.
The utility model provides a steel festival concrete structure L shape post for assembled building's basic top layer, include: the steel column head comprises a rectangular steel tube A arranged along the circumferential direction of the steel column head, a base top layer steel column head, a steel column head with an L-shaped section and arranged at the lower end of the reinforced concrete column head, wherein the base top layer steel column head comprises a base top layer rectangular steel tube B arranged along the circumferential direction of the periphery of the base top layer steel column head, the length of the base top layer steel column head in the longitudinal direction is larger than that of the steel column head, and the longitudinal stressed steel bar is connected to the rectangular steel tube A of the steel column head and is connected to the rectangular steel tube B of the base top layer steel column head.
In an alternative embodiment, the reinforced concrete column further comprises one or more angle irons disposed at one or more corners of the reinforced concrete column, and the angle irons are connected to the rectangular steel tube a of the steel column head and the rectangular steel tube B of the base-top steel column head.
in an alternative embodiment, the angle steel extends along the entire longitudinal length of the reinforced concrete column and the one or more longitudinal force-bearing rebars extend along the entire longitudinal length of the steel-reinforced concrete structure L-shaped column.
In an alternative embodiment, the rectangular steel tube a of the steel stud comprises an L-shaped frame and an upper plate a and a lower plate a arranged therein, the one or more longitudinal force-bearing steel bars are passed through holes B in the lower plate a of the steel stud and connected to the upper plate a of the steel stud via bolted connections through holes a in the upper plate a of the steel stud, the rectangular steel tube B of the capital-top layer steel stud comprises an L-shaped frame and an upper plate B and a lower plate B arranged therein, the one or more longitudinal force-bearing steel bars are passed through holes D in the upper plate B of the capital-top layer steel stud and connected to the lower plate B of the capital-top layer steel stud via bolted connections through holes C in the lower plate B of the capital-top layer steel stud.
The utility model discloses still relate to one kind be used for assembled building, and construct L shape post complex basic top layer steel node with aforementioned steel festival concrete, including hollow L shape frame and bottom plate, L shape frame is suitable for to construct basic top layer steel column head of L shape post with aforementioned steel festival concrete and receives wherein and rather than the cooperation and be connected, is provided with a plurality of fixed orificess on the bottom plate, is used for being connected to basic top layer steel node to basic cushion cap.
In an alternative embodiment, the base-top layer steel node comprises a seat extending from one or more surfaces of the frame, the seat being formed in the form of a male seat adapted to receive a female end of a mating beam structure.
In an alternative embodiment, the base-top layer steel node comprises a standoff extending from one or more surfaces of the frame, the standoff being formed in the form of a female standoff adapted to receive a male end of a mating beam structure.
The utility model discloses still relate to a L shape post steel framework that is used for steel festival concrete structure L shape post of assembled building's basic top layer, include: the setting is at the rectangle steel pipe A of L shape post steel skeleton's upper end department, and set up the basic top layer rectangle steel pipe B of L shape post steel skeleton's lower extreme department, one or many vertical atress reinforcing bars along the longitudinal direction extension of L shape post steel skeleton, one or many vertical atress reinforcing bars pass through the ligature with the stirrup and be connected, and arrange the angle steel in the bight of L shape post steel skeleton, wherein, basic top layer rectangle steel pipe B is greater than rectangle steel pipe A's length along the length of longitudinal direction, and vertical atress reinforcing bar and angle steel are connected to rectangle steel pipe A and basic top layer rectangle steel pipe B.
In an alternative embodiment, the rectangular steel duct a comprises an L-shaped frame and upper and lower plates a and a disposed therein, one or more longitudinal force-bearing steel bars pass through holes B in the lower plate a of the rectangular steel duct and are connected to the upper plate a of the rectangular steel duct via bolting through the holes a in the upper plate a of the rectangular steel duct, the base-top rectangular steel duct B comprises an L-shaped frame and upper and lower plates B and B disposed therein, and one or more longitudinal force-bearing steel bars pass through holes D in the upper plate B of the base-top rectangular steel duct and are connected to the lower plate B of the base-top rectangular steel duct via bolting through the holes C in the lower plate B of the base-top rectangular steel duct.
The utility model discloses still relate to an assembly type structure, it includes that aforementioned steel knot concrete constructs L shape post, and aforementioned base top layer steel node, the base top layer steel column head that the steel knot concrete constructs L shape post is received in the hollow part of base top layer steel node to it has high strength joint filling material, constructs L shape post with base top layer steel node fixed to the steel knot concrete in the gap between the internal surface of the surface of L shape post and the frame of base top layer steel node to fill in the steel knot concrete.
The utility model discloses can bring following technical advantage:
(1) The precision of the parts is improved, the assembly difficulty is reduced, the labor consumption is reduced, and the construction efficiency is improved;
(2) The reliable and stable concrete quality is ensured, and the overall design and construction level of the building industry is improved;
(3) The shrinkage cracks generated on the component and the assembled integral structure are avoided, the anti-permeability capability of the building is improved, and the safety degree of the building is improved;
(4) The construction time of a construction site is shortened, and engineering pollution such as dust pollution, noise pollution and the like is reduced;
(5) the problem that outdoor construction cannot be carried out in winter in some areas can be solved, the construction progress is effectively accelerated, the construction quality is improved, and the construction and management cost is reduced;
(6) avoiding damage to the health of the staff (for example due to dust).
drawings
In order to illustrate the technical solutions of the embodiments of the present invention more clearly, the drawings of the embodiments will be briefly described below, and it is obvious that the drawings in the following description only relate to some embodiments of the present invention, and are not intended to limit the present invention.
Fig. 1A shows a side view of a foundation top layer steel-reinforced concrete structural L-shaped column according to one embodiment of the present invention;
3 FIG. 3 1 3B 3 shows 3a 3 cross 3- 3 sectional 3 view 3 taken 3 along 3 section 3 line 3A 3- 3A 3 of 3 the 3 L 3- 3 shaped 3 column 3 of 3 the 3 foundation 3 top 3 layer 3 steel 3- 3 concrete 3 structural 3 in 3 FIG. 3 1 3A 3; 3
FIG. 2 shows a side view of an L-shaped column steel skeleton;
A side view of a rectangular steel tube a of the steel stud is shown in fig. 3A;
FIG. 3B shows a top view of the rectangular steel tube A of FIG. 3A, showing a view of the upper surface of the upper plate A;
FIG. 3C shows a view from above looking down taken along section line B-B, showing a view of the upper surface of lower plate A;
A side view of a rectangular steel tube B of the base-top layer steel stud is shown in fig. 4A;
FIG. 4B shows a view from below looking upwards, taken along section line C-C, showing a view of the lower surface of its upper plate B;
FIG. 5A shows an assembled structure of the foundation top layer steel nodes and the foundation top layer steel node concrete structure L-shaped columns connected together, wherein the outer surfaces of the rectangular steel pipes A of the foundation top layer steel column heads are shown by dotted lines;
FIG. 5B illustrates the skeletal structure of the assembled structure of FIG. 5A to more clearly illustrate the mating relationship of the base top layer steel nodes and the base top layer steel-node concrete structural L-shaped columns;
FIG. 6A shows an elevation view of the base-top layer steel node of FIG. 5A;
FIG. 6B shows a top view of a base top layer steel node;
FIG. 7A shows an elevation view of a base-top layer steel node according to another embodiment;
FIG. 7B shows a top view of the base-top layer steel node of FIG. 7A.
Detailed Description
The following description is provided with reference to the accompanying drawings to assist in a comprehensive understanding of various embodiments of the invention as defined by the claims. It includes various specific details to assist in this understanding, but these details should be construed as merely exemplary. Accordingly, those of ordinary skill in the art will recognize that changes and modifications may be made to the various embodiments described herein without departing from the scope of the present invention, which is defined by the following claims. Moreover, descriptions of well-known functions and constructions may be omitted for clarity and conciseness.
it will be apparent to those skilled in the art that the following descriptions of the various embodiments of the present invention are provided for illustration only and not for the purpose of limiting the invention as defined by the appended claims.
throughout the description and claims of this specification, the words "comprise" and "contain" and variations of the words, for example "comprising" and "comprises", mean "including but not limited to", and are not intended to (and do not) exclude other components, features or steps.
features, components, or characteristics described in connection with a particular aspect, embodiment, or example of the invention are to be understood as being applicable to any other aspect, embodiment, or example described herein unless incompatible therewith.
It is to be understood that the singular forms "a," "an," and "the" include plural referents unless the context clearly dictates otherwise. The expression "comprising" and/or "may comprise" as used in the present invention is intended to indicate the presence of corresponding functions, operations or components, and is not intended to limit the presence of one or more functions, operations and/or components. Furthermore, in the present application, the terms "comprising" and/or "having" are intended to indicate the presence of the features, quantities, operations, elements, and components disclosed in the specification, or combinations thereof. Thus, the terms "comprising" and/or "having" should be understood as presenting additional possibilities for one or more other features, quantities, operations, components and parts, or combinations thereof.
in the present application, the expression "or" encompasses any and all combinations of the words listed together. For example, "a or B" may comprise a or B, or may comprise both a and B.
Although expressions such as "1 st", "2 nd", "first" and "second" may be used to describe various components of the present invention, they are not intended to limit the corresponding components. For example, the above expressions are not intended to limit the order or importance of the corresponding elements. The above description is only intended to distinguish one element from another.
when an element is referred to as being "connected" or "coupled" to another element, it can be directly connected or coupled to the other element, but it is understood that intervening elements may be present. Alternatively, when an element is referred to as being "directly connected" or "directly coupled" to another element, it is to be understood that no intermediate element is present between the two elements.
References herein to "upper", "lower", "left", "right", etc. are merely intended to indicate relative positional relationships, which may change accordingly when the absolute position of the object being described changes.
Unless otherwise defined, all terms (including technical and scientific terms) used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs. It will be further understood that terms, such as those defined in commonly used dictionaries, should be interpreted as having a meaning that is consistent with their meaning in the context of the relevant art and the present specification and will not be interpreted in an idealized or overly formal sense unless expressly so defined herein.
The present invention relates to a concrete structure, and more particularly to a reinforced concrete structure, which is a main part of a member for constituting a building body. The steel joint of the utility model is a steel joint structure, which is used for the connection part of one component and another component. The utility model provides a "steel festival concrete structure" means the building element who adopts concrete (reinforced concrete in particular) as the main part, adopts the steel node as the connecting portion.
The utility model discloses a building site on-site assembly formula's building assembly technique for a plurality of basic components of this on-site assembly formula's building assembly technique to and adopt this a plurality of basic components to build the assembled building that forms. In particular, in order to implement a construction manner of a construction assembly of a construction site assembly type, it is necessary to design a plurality of basic elements of the assembly type construction in advance and manufacture the plurality of basic elements in advance at a factory, then transport the plurality of basic elements to the construction site, and assemble the plurality of basic elements to form a desired construction form at the construction site.
The utility model discloses a basic component includes but is not limited to, the steel festival concrete constructs beam member, steel festival concrete and constructs post component, steel festival concrete structure shear force wall component, steel festival concrete structure elevartor shaft component, steel festival concrete structure basement side wall component, steel festival concrete structure stair component, steel festival concrete structure floor component, steel festival concrete structure infilled wall and so on. These components can be designed in a variety of shapes and sizes, either as single-layer structures or multi-layer structures, assembled in any manner to ultimately form the desired building structure.
In particular, the utility model relates to a basic component of specific steel joint concrete structure, steel joint concrete structure L shape post component promptly, special basic top layer steel joint concrete structure L shape post. The L-shaped column of the steel-joint concrete structure is a component formed by compounding a steel end head and a reinforced concrete column body structure and can be prefabricated in a factory. The reinforced concrete column structure is L-shaped in section and is formed into a vertical supporting column in a building. The steel nodes arranged at the ends of the reinforced concrete column structure are used for connecting the L-shaped column of the reinforced concrete structure with other basic members. For example, a steel node connects the column structure with another column structure in the vertical direction and connects the column structure with a beam structure in the horizontal direction. In particular, the L-shaped column of the steel-reinforced concrete structure for the foundation top layer has its specific structure and requirements due to its location (on the foundation top layer). The foundation top layer steel-knot concrete structural L-shaped column is connected to a foundation cap or a foundation slab at the lower end thereof through a foundation top layer steel node, and optionally transversely connects a foundation beam steel framework, and concrete is poured so that the foundation top layer steel node is embedded in the foundation cap or the foundation slab. The L-shaped column of the top-based steel-concrete structure is positioned at the bottommost layer of the building, and the positioning precision of each component of the whole building structure is directly determined by the precision and the installation precision of the L-shaped column, so that the stress at the position is higher, and the strength requirement and the precision requirement of the L-shaped column are also generally higher.
In particular, the L-shaped column of the steel-reinforced concrete structure on the base top layer can organically combine the flexibility of building beauty and use function with the reasonable stress performance of the building structure, provide ideal living environment for residents, meet the requirement of indoor arrangement, and be well connected with a wall body (such as a filling wall), thereby being popular with developers and residents.
Exemplary embodiments of the present invention are described below with reference to the accompanying drawings. It is to be understood that the drawings and the following description of the drawings are merely exemplary and are not restrictive in any way, and that the scope of the present invention is defined by the appended claims.
fig. 1A shows a side view of a foundation top layer steel-reinforced concrete structural L-shaped column 100 (hereinafter referred to simply as L-shaped column 100) according to an embodiment of the present invention; 3 FIG. 3 1 3B 3 shows 3a 3 cross 3- 3 sectional 3 view 3 taken 3 along 3 section 3 line 3A 3- 3A 3 of 3 the 3 foundation 3 top 3 layer 3 steel 3- 3 reinforced 3 concrete 3 structural 3 L 3- 3 shaped 3 column 3 100 3 of 3 FIG. 3 1 3A 3. 3
referring to fig. 1A, the L-shaped column 100 includes a reinforced concrete column 300, a steel column head 200 located at an upper end of the reinforced concrete column 300, and a basal-top steel column head 400 located at a lower end of the reinforced concrete column 300. The reinforced concrete column 300, the steel column head 200, and the steel column head 400 of the L-shaped column 100 are all L-shaped in cross section.
the internal structure of cylinder 300 is shown in the cross-sectional view of FIG. 1B. Specifically, in the illustrated embodiment, the column 300 includes angle steel 301 at a plurality of corners (6 corners) of the column 300, a plurality of longitudinally stressed rebars 302 arranged along the circumference of the column 300, and concrete 303 filling most of the structure of the column. The angle steel 301 disposed at the corners of the column 300 is connected (e.g., bolted, or welded) to the steel column head 200 and the steel column head 400 of the foundation layer, facilitating the pouring of concrete, and is particularly advantageous in maintaining the dimensional accuracy of the column 300 in the longitudinal direction (i.e., the vertical direction in the view of fig. 1A) during the pouring of concrete. The circumferentially arranged longitudinal force-bearing rebars 302 help to maintain the strength of the column structure. Only a single longitudinal force-receiving rebar 302 is labeled in fig. 2, but it should be understood that in the embodiment shown in fig. 2, 12 longitudinal force-receiving rebars are disposed along the entire circumference of the column 300, particularly circumferentially around the overlapping portions of two mutually perpendicular elongated structures of the L-shaped column 100 (labeled longitudinal force-receiving rebars 302') for reinforcing the overall strength of the column 300. It should be understood by those skilled in the art that although 12 longitudinal force-receiving rebars arranged along the circumference of the column 300 are shown in the embodiment of fig. 1B, those skilled in the art may increase or decrease the number of longitudinal force-receiving rebars or add longitudinal force-receiving rebars to the central portion of the column 300 on the basis of the national standard. In a preferred embodiment, a plurality of longitudinally disposed longitudinally stressed steel bars 302 are secured by stirrups and lashed thereto to help maintain the position and shape of the longitudinally stressed steel bars during the casting of the concrete.
The steel-reinforced concrete structural L-shaped column 100 is prefabricated in a factory. Specifically, the upper steel stud 200, the top-base steel stud 400, the steel diaphragms (not shown), the angle steel 301, the longitudinal load-bearing steel bars 302, and the stirrups are first connected (e.g., by bolting) at the factory into a structurally stable L-shaped stud skeleton 100' (excluding concrete). Fig. 2 shows a side view of the L-shaped column steel skeleton 100' (i.e., the steel-concrete structure L-shaped column 100 in a state where no concrete is poured). As can be seen more particularly in fig. 2, the longitudinal load-bearing rebars 302 extend along the longitudinal direction, along the entire length of the L-shape 100 of the reinforced concrete structure. Subsequently, on the work bench, the L-shaped column steel skeleton 100' is supported by using a standard steel formwork, and concrete is poured to form a steel-reinforced concrete structure L-shaped column 100 as shown in fig. 1A.
fig. 3A shows a side view of a rectangular steel pipe a201 (in a state where concrete is not poured) of the steel stud 200. Fig. 3B shows a top view of the rectangular steel pipe a201 in fig. 3A, showing a view of the upper surface of the upper plate a 202. Fig. 3C shows a view from above looking down, taken along section line B-B, showing a view of the upper surface of lower plate a 204. In the L-shaped column skeleton 100' shown in fig. 2, a longitudinal force-receiving rebar 302 is connected (e.g., bolted) to an upper plate a202 of a rectangular steel pipe a201 through a hole B205 in a lower plate a204 of the rectangular steel pipe a201, through a hole a203 in the upper plate a 202. The upper plate a202 and the lower plate a204 and the holes thereon can effectively fix the position of the longitudinal force-bearing rebar 302. The structure of the upper plate a202 and the lower plate a204 of the rectangular steel tube a201 can realize better fixation of the position of the longitudinal stressed steel bar 302, and particularly avoid deformation at the steel column head, so as to facilitate connection with a matched steel node. In a preferred embodiment, the lower plate a204 is provided to have a hollow portion. The rectangular steel pipe a201 is fixed (e.g., bolted) to the angle iron 301 through a hole provided in the side wall, and is thus connected to a portion of the L-shaped column skeleton 100' corresponding to the column body 300 (fig. 1A).
fig. 4A shows a side view of a rectangular steel tube B401 (in a state where concrete is not poured) of the steel stud 400 of the base-top layer. Fig. 4B shows a view from below looking upwards, taken along section line C-C, showing a view of the lower surface of its upper plate B404. Fig. 4C shows a view from below looking up, taken along section line D-D, showing a view of its lower plate B402. In the L-shaped column skeleton 100' shown in fig. 2, the longitudinal force-receiving rebar 302 is connected (e.g., bolted) to the lower plate B402 of the rectangular steel tube B401 through a hole D405 in the upper plate B404 of the rectangular steel tube B401, through a hole C403 in the lower plate B402. The lower plate B402 and the upper plate B404 and the holes thereon can effectively fix the position of the longitudinal force-bearing steel bars 302. The lower plate B402 and the upper plate B404 of the rectangular steel tube B401 and the holes thereon can achieve better fixation of the position of the longitudinal force-bearing steel bars 302, and particularly avoid deformation at the steel column head of the foundation top layer, so as to facilitate connection with the matched steel node, and particularly facilitate maintaining strength and avoiding deformation during pouring concrete on the steel column head of the foundation top layer and the node of the foundation top layer to be embedded into the foundation cap. In a preferred embodiment, the upper plate B404 is provided to have a hollow portion. The rectangular steel tube B401 is fixed (e.g., bolted) to the angle iron 301 through a hole provided on the side wall, and is thus connected to a portion of the L-shaped column skeleton 100' corresponding to the column body 300 (fig. 1A).
The steel capital-top column head 400 (or rectangular steel tube B401) has substantially the same structure as the steel column head 200 (or rectangular steel tube a201), except that since the steel capital-top column head 400 corresponds to the capital layer and is used to connect to foundation beams through the steel capital-top nodes and cast concrete to embed foundation cap and foundation slab, which are at the bottommost layer of the building, and its own accuracy and installation accuracy directly determine the positioning accuracy of the various elements of the entire building structure, the force at the steel capital-top column head 400 is greater, the strength requirement at the steel capital-top column head 400 is higher, and the accuracy requirement for it is higher, so that the longitudinal length of the steel capital-top column head 400 is chosen to be greater than the longitudinal length of the steel column head 200, as shown in the figures.
Fig. 5A shows an assembled structure of the foundation top layer steel node 500 and the foundation top layer steel-node-concrete structure L-shaped column 100 connected together, in which the outer surface of the rectangular steel tube B401 of the foundation top layer steel stud 400 is shown by a dotted line. Fig. 5B shows the skeletal structure of the assembled structure of fig. 5A to more clearly show the mating relationship of the base top layer steel node 500 and the base top layer steel-node concrete structural L-shaped column 100.
Referring specifically to fig. 5A, the capital-level steel stud 400 of the L-shaped stud 100 is inserted into a capital-level steel node 500. The size of the outer surface of the basic top layer steel node 500 is substantially the same as that of the outer surface of the reinforced concrete column 300, so that a substantially flat outer surface is formed after the basic top layer steel node 500 is assembled with the L-shaped column 100, reducing subsequent adjustment operations. The gap between the outer surface of the capital-level steel stud 400 and the inner surface of the capital-level steel stud 500 is filled with a high-strength caulking material. The high-strength caulking material preferably uses epoxy resin, and more particularly uses a material suitable for connecting steel materials. The high-strength gap filling material can effectively ensure the fixed connection between the rectangular steel pipe B401 of the steel column head 400 on the top base layer and the steel node 500 on the top base layer, and simultaneously fills the gap between the outer surface of the steel column head on the top base layer and the inner surface of the steel node 500 on the top base layer, thereby compensating the machining error possibly generated in the machining process, reducing the machining precision requirement of components and being beneficial to the installation of the components.
fig. 6A shows a front view of the base-top layer steel node 500 of fig. 5A, and fig. 6B shows a top view of the base-top layer steel node 500. Fig. 6A-6B more clearly illustrate the structure of the base-top layer steel node 500. Specifically, the base-top layer steel node 500 includes a hollow L-shaped frame 501, and a bottom plate 502. When the L-shaped column 100 is mounted to the foundation top level steel node 500, the foundation top level steel stud 400 is received in the hollow of the L-shaped frame 501 and is fixedly connected thereto by a high strength caulking material, as described above. A plurality of fastening holes 503 are provided in the bottom plate 502 for attaching the foundation top layer steel node 500 to a foundation cap or foundation bottom plate, e.g. via bolting and/or spot welding, etc. In the illustrated embodiment, a plurality of fixing holes 503 are arranged on the bottom plate 502 at positions corresponding to the outer periphery of the frame 501 in the circumferential direction. In an alternative embodiment, a plurality of fixing holes may be disposed at positions of the bottom plate 502 corresponding to the inside of the frame 501, so that when the foundation top layer steel node 500 is fixed to the foundation cap or the foundation bottom plate, the entire bottom plate is uniformly stressed and can endure a large external force. In other embodiments, the fixing holes 503 are not limited to the arrangement described above, but may be arranged in any pattern as long as it can satisfy the national standards and strength requirements.
In the embodiment shown in fig. 6A-6B, the foundation top layer steel nodes 500 are used only to connect the foundation top layer steel-node concrete structural L-columns 100 to the foundation cap or foundation bedplate, and not to connect the transverse beam structures, such as foundation beams. In an alternative embodiment, the foundation top layer steel node further comprises a brace for connecting the transverse beam structure, such as shown in the embodiment of fig. 7A-7B.
Fig. 7A shows a front view of a base top layer steel node 1500 according to another embodiment, and fig. 7B shows a top view of the base top layer steel node 1500 in fig. 7A. Specifically, the base top layer steel node 1500 includes a hollow L-shaped frame 1501, a bottom plate 1502, and standoffs 1510, 1520 extending from the L-shaped frame 1502. The structure of the L-shaped frame 1501 and the base plate 1502 is similar to the structure of the L-shaped frame 501 and the base plate 502 of the base-top layer steel node 500 shown in fig. 7A-7B. The brackets 1510, 1520 are preferably made of steel material and are used to connect a transverse beam structure, such as a foundation beam.
standoffs 1510, 1520 extend from both surfaces of frame 1501 and are preferably connected to the outer surface of frame 1501 by welding. The brackets 1510, 1520 are used to connect lateral horizontal structures, such as foundation beam structures, and are particularly adapted to receive the steel column heads of beam structures having a steel-to-concrete structure. In the illustrated embodiment, the supports 1510, 1520 have similar structures, and thus, the features described for one support may be similarly applicable to the other supports.
in the embodiment shown in fig. 7A-7B, the supports 1510, 1520 are formed in the form of female supports into which the steel column heads of the mating beam structure are inserted (from above) and connected to the female supports 1510, 1520, preferably by high-strength bolts, for example via holes 1521 (fig. 7A). Similarly, in the preferred embodiment, the gap between the female brace and the steel column head of the beam structure is filled with a high strength caulking material. In a more preferred embodiment, after the steel column heads of the beam structure are fitted to the bearers, the tops of the steel column heads are further fixedly connected to the surface of the frame 1501 by a welded connection. It should be understood by those skilled in the art that while the embodiments of fig. 7A-7B show standoffs extending from both outer surfaces of the frame 1501, a different number of standoffs, and/or different extended positions, may be used depending on the application. Further, in other embodiments, the steel node may include one or more male standoffs extending from its frame such that the steel columns of the mating beam structure are sleeved thereon; and/or the steel node may also include both male and female standoffs extending from different surfaces thereof.
Taking the embodiments of the foundation top layer L-shaped column 100 and the foundation top layer steel node 500 shown in fig. 1-6B as examples, the production and installation of the foundation top layer steel node concrete structure L-shaped column according to the present invention is performed according to the following steps: (1) in a factory, machining a steel node at the top of the foundation, and machining a steel column head, a steel column head at the top of the foundation, a steel diaphragm plate and angle steel, wherein the machined components have higher machining precision; (2) in a factory, connecting (for example, connecting through bolts) a steel column head, a base top layer steel column head, a steel diaphragm plate, angle steel, main steel bars and stirrups into an L-shaped column steel framework 100' with a stable structure; (3) in a factory, on a special workbench, a standard steel template is preferably adopted to support the L-shaped column steel framework 100', concrete is poured, and the base top layer steel joint concrete structure L-shaped column 100 is formed; (4) at the construction site (i.e., worksite), installing the foundation top layer steel nodes, connecting them (e.g., by bolting and/or spot welding, etc.) to the steel skeleton of the foundation cap or the steel skeleton of the foundation bedplate; (5) in a construction site, concrete is poured in situ, so that the steel nodes on the top layer of the foundation are embedded into the foundation bearing platform or the foundation bottom plate; (6) vertically installing a foundation top layer steel-joint concrete structure L-shaped column; (5) and filling special high-strength gap filling materials in gaps between the steel nodes and the steel column heads on the base top layer on a construction site.
In the embodiment where the foundation top layer steel node is also used for connecting the vertical L-shaped columns and the transverse beam structure (e.g. foundation beam), i.e. in the embodiment where the foundation top layer steel node 1500 in fig. 7A-7B is used, the production and installation of the foundation top layer steel node concrete structure L-shaped columns according to the invention proceeds according to the following steps: (1) machining the base top layer steel node, and machining a steel column head, the base top layer steel column head, a steel diaphragm plate and angle steel in a factory, wherein the machined components have high machining precision, and a corresponding support is fixed (for example, welded) to the base top layer steel node; (2) in a factory, connecting (for example, connecting through bolts) a steel column head, a base top layer steel column head, a steel diaphragm plate, angle steel, main steel bars and stirrups into an L-shaped column steel framework 100' with a stable structure; (3) in a factory, on a special workbench, preferably adopting a standard steel template to support the L-shaped column steel framework 100', pouring concrete to form the top-layer steel-concrete structure L-shaped column 100; (4) at a construction site (i.e., a construction site), installing the foundation top layer steel nodes, connecting the steel column heads of the foundation beam steel frameworks to corresponding supports on the foundation top layer steel nodes in a horizontal direction (e.g., through bolting), and connecting the foundation top layer steel nodes to the steel frameworks of the foundation bearing platforms or the steel frameworks of the foundation bottom plates (e.g., through bolting, local welding, etc.); (5) in a construction site, concrete is poured in situ, so that the steel nodes on the foundation top layer are embedded into the foundation bearing platform or the foundation bottom plate, and the foundation beam is formed into a hidden beam and is embedded into the foundation bearing platform and the foundation bottom plate; (6) vertically installing a foundation top layer steel-joint concrete structure L-shaped column; (7) and filling special high-strength gap filling materials in gaps between the steel nodes and the steel column heads on the base top layer on a construction site.
In a preferred embodiment, steel members in the L-shaped column of the base top layer steel-joint concrete structure, such as base top layer steel nodes, base top layer steel column heads, steel diaphragms, angle steels and the like, are preferably machined by adopting standard section steels and special section steels, so that the quality of the members can be improved, and the engineering cost can be reduced.
the utility model provides a basic component for assembly type structure, basic top layer steel festival concrete structure L shape post promptly, it is particularly suitable for assembly type structure's mounting means to following technical advantage has been brought:
(1) because a plurality of components forming the L-shaped column steel framework and steel nodes used for connection are all manufactured in a machining mode, the pouring process of concrete is carried out in a factory, so that the installation precision of the steel bars and the geometric dimension precision of the components are close to the machining precision standard and far higher than the current standard, and the positioning precision of the components is higher than the current standard (far higher than the positioning precision of other current construction paying-off lines), so that higher assembly precision can be ensured, and the corresponding components can be simply connected by adopting high-strength bolts during installation on a construction site without manual adjustment, thereby reducing the assembly difficulty, reducing the labor consumption and improving the construction efficiency;
(2) the pouring process of the concrete is performed in advance in a factory instead of a construction site, so that the requirement of site construction for pumping the concrete on workability is not considered; and the maintenance condition of the factory is good, and the reliable and stable concrete quality can be ensured. The quality of concrete used in construction engineering is improved, and the overall design and construction level of the construction industry can be improved;
(3) Because the pouring process of the concrete is carried out in a factory, the member can be maintained in the factory (for example, the maintenance lasts for 28 days), and the process of concrete shrinkage is carried out in the factory, so that shrinkage cracks generated on the member and the assembled integral structure are avoided, the anti-permeability capability of the building can be improved, and the safety of the building can be improved;
(4) because the L-shaped column member and the corresponding steel node are prefabricated in a factory (particularly, the pouring process of concrete is carried out in the factory), and only simple assembly work is carried out on a construction site, a plurality of complicated procedures such as erecting templates, erecting scaffolds, building walls, plastering, binding reinforcing steel bars and the like on the construction site are avoided, the construction time of the construction site can be greatly shortened, and engineering pollution such as dust pollution, noise pollution and the like is reduced;
(5) In addition, the L-shaped column member and the corresponding steel node are optionally prefabricated in an indoor factory and are not arranged on an outdoor construction site, so that the problem that construction cannot be carried out outdoors in winter in some areas can be solved, the construction progress can be effectively accelerated and the construction quality can be improved by means of producing basic members in winter engineering and installing the basic members on the construction site in warm seasons, and the construction and management cost can be reduced;
(6) Because the higher precision can be realized in the processing of factory basic component and the assembly process at the job site, and need not too much manual adjustment to can improve degree of automation, reduce the manpower demand, avoid causing harm (for example because raise dust) to staff's health, and reduce cost simultaneously.
the above embodiments are only preferred embodiments of the present invention, and the protection scope of the present invention cannot be limited thereby, and any insubstantial changes and substitutions made by those skilled in the art based on the present invention are all within the protection scope of the present invention.

Claims (2)

1. An L-shaped column steel skeleton (100') of an L-shaped column of a steel-joint concrete structure for a base top layer of an assembly type building,
The L-shaped column steel skeleton (100') comprises:
a rectangular steel pipe A (201) arranged at the upper end of the L-shaped column steel framework (100 '), and a base-top layer rectangular steel pipe B (401) arranged at the lower end of the L-shaped column steel framework (100'),
one or more longitudinal load-bearing reinforcing bars (302) extending in the longitudinal direction of the L-shaped column skeleton (100'), which are connected to stirrups by means of ties, and
angle steel (301) arranged at the corner of the L-shaped column steel skeleton (100'),
The length of the base top layer rectangular steel pipe B (401) in the longitudinal direction is larger than that of the rectangular steel pipe A (201), and the longitudinal stress steel bars (302) and the angle steel (301) are connected to the rectangular steel pipe A (201) and the base top layer rectangular steel pipe B (401).
2. The L-shaped column steel skeleton (100') according to claim 1,
the rectangular steel pipe A (201) comprises an L-shaped frame and an upper plate A (202) and a lower plate A (204) arranged therein, the one or more longitudinal force-bearing steel bars (302) are connected to the upper plate A (202) of the rectangular steel pipe via bolting through holes B (205) in the lower plate A (204) of the rectangular steel pipe and through holes A (203) in the upper plate A (202) of the rectangular steel pipe,
The rectangular steel pipe B (401) of the top base layer comprises an L-shaped framework and an upper plate B (404) and a lower plate B (402) which are arranged in the framework, and the one or more longitudinal stress steel bars (302) penetrate through holes D (405) in the upper plate B (404) of the rectangular steel pipe B of the top base layer and penetrate through holes in the lower plate B (402) of the rectangular steel pipe B of the top base layer to be connected to the lower plate B (402) of the rectangular steel pipe B of the top base layer through bolt connection.
CN201821437085.XU 2018-09-03 2018-09-03 L-shaped column steel framework for foundation and top layer of prefabricated building Expired - Fee Related CN209780030U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821437085.XU CN209780030U (en) 2018-09-03 2018-09-03 L-shaped column steel framework for foundation and top layer of prefabricated building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821437085.XU CN209780030U (en) 2018-09-03 2018-09-03 L-shaped column steel framework for foundation and top layer of prefabricated building

Publications (1)

Publication Number Publication Date
CN209780030U true CN209780030U (en) 2019-12-13

Family

ID=68786663

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821437085.XU Expired - Fee Related CN209780030U (en) 2018-09-03 2018-09-03 L-shaped column steel framework for foundation and top layer of prefabricated building

Country Status (1)

Country Link
CN (1) CN209780030U (en)

Similar Documents

Publication Publication Date Title
CN104912190B (en) Dry type joggle frame structure
CN107143034A (en) A kind of assembly concrete frame structure beam column rigid connection node
CN104712089B (en) Open the compound shear attachment structure of net
JP5523179B2 (en) Building construction method and room module
CN203452204U (en) Connecting node of prefabricated hollow steel-reinforced concrete column and steel girder
CN103437425A (en) Connecting joint of prefabricated hollow steel-reinforced concrete column and steel beam and construction method
CN107989228B (en) Prefabricated steel reinforced concrete shear wall structure and preparation and installation methods thereof
CN206903022U (en) A kind of steel bar truss floor support plate
CN108005265A (en) A kind of prefabricated steel reinforced concrete shear wall structure of multilayer and its preparation and construction method
CN110056085A (en) Can quick assembling FRP profile bean column node
CN111962952A (en) Steel tube concrete column-H-shaped steel beam-steel support-pi-shaped connecting piece combined type center pillar bottom node and manufacturing method
CN206873673U (en) A kind of assembling type steel structure out-hung panel node
CN106049754B (en) The assembled section of the standard of assembly concrete combined column and the combined column being made up of assembly section
CN108005264A (en) A kind of steel framework constraint precast reinforced concrete shear wall structure and preparation and installation method
CN207739674U (en) A kind of assembled Residential System of Steel-concrete Composite Structure
CN111962948A (en) Steel tube concrete column-H-shaped steel beam-steel support-pi-shaped connecting piece combined side column bottom node and manufacturing method
CN205875394U (en) Antidetonation concrete beam column that dry process is connected
CN209780036U (en) Rectangular column of foundation layer of prefabricated building and prefabricated building
CN206428805U (en) A kind of concrete prefabricated balcony of assembled steel
CN107119800B (en) A kind of more high-rise assembled modularization Self-resetting steel construction square tube column frame systems
CN209780030U (en) L-shaped column steel framework for foundation and top layer of prefabricated building
CN209780029U (en) A basic top layer steel node for prefabricated building
CN111021630A (en) Section steel concrete column and semi-assembly type construction method thereof
CN208293903U (en) A kind of prefabricated column connected node of inflection point
CN208202224U (en) A kind of prefabricated steel reinforced concrete shear wall structure of multilayer

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191213

Termination date: 20200903

CF01 Termination of patent right due to non-payment of annual fee