CN209760793U CN201822138181.0U CN201822138181U CN209760793U CN 209760793 U CN209760793 U CN 209760793U CN 201822138181 U CN201822138181 U CN 201822138181U CN 209760793 U CN209760793 U CN 209760793U
Authority
CN
China
Prior art keywords
template
pair
pull rods
hinge
square column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201822138181.0U
Other languages
Chinese (zh)
Inventor
魏振伟
***
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HEFEI WANZHONG TRAFFIC ENGINEERING Co Ltd
Original Assignee
HEFEI WANZHONG TRAFFIC ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HEFEI WANZHONG TRAFFIC ENGINEERING Co Ltd filed Critical HEFEI WANZHONG TRAFFIC ENGINEERING Co Ltd
Priority to CN201822138181.0U priority Critical patent/CN209760793U/en
Application granted granted Critical
Publication of CN209760793U publication Critical patent/CN209760793U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a special cement square column mould for construction sites, which comprises a first template, a fourth template and a first hoop, wherein a first hinge is arranged on the first template through an inner screw angle, the first template and the second template are arranged together through the first hinge, the first template and the third template are fixed through a first pair of pull rods, the upper sides of the first pair of pull rods and the first template are fixed through first bolts, and a first gasket is arranged at the lower side of each first bolt; a second pair of pull rods are arranged on the right side of the fourth template, and the first template, the second template, the third template and the fourth template enclose a mold cavity; the first anchor ear is installed on the second template through the second bolt and the second gasket. This dedicated cement square column mould of building site, simple structure, convenient to use easily dismantles and saves the transportation, has the reduction construction degree of difficulty simultaneously, raises the efficiency, practices thrift construction cost's purpose.

Description

Dedicated cement square column mould of building site
Technical Field
The utility model relates to a square column mould equipment technical field specifically is a dedicated cement square column mould of building site.
Background
at present, in building construction, particularly when square concrete columns are poured on site, steel templates or wood templates are generally spliced into square column templates, the steel templates are firm in structure and can be repeatedly used for many times, but the steel templates are heavy, inconvenient to operate, easy to rust and high in price, construction cost is increased, and the steel templates are easily bonded with concrete when in use, difficult to demould and inconvenient to construct; the wooden template is light in weight, but is easy to rot due to water erosion when in use, the problems that the existing square column mould is not uniform in stress, bulges appear, the sizes of the square columns are inconsistent, construction difficulty is large and the like are caused, the quality and the attractiveness of the square columns are directly influenced, meanwhile, the construction period is prolonged, and the construction cost is increased.
In order to solve the disadvantages existing in the current market, there is an urgent need for improving the technology of the square column mold device.
SUMMERY OF THE UTILITY MODEL
The utility model provides a technical problem lie in overcoming prior art's existence mould atress inequality and appear protruding, and the square column size nonconformity causes the big scheduling problem of the construction degree of difficulty, directly influences the quality of square column and defect such as pleasing to the eye degree, provides a dedicated cement square column mould of building site. The first pair of pull rods, the second pair of pull rods, the first hoop and the second hoop have the advantages that the problems of concrete expansion, deformation of the appearance of the cement square column and damage of a template cannot occur, the use is convenient, and the disassembly, storage and transportation are easy.
In order to achieve the above object, the utility model provides a following technical scheme: a special cement square column die for a construction site comprises a first die plate, a fourth die plate and a first hoop, wherein a first hinge is arranged on the first die plate through an inner screw corner, the first die plate and the second die plate are arranged together through the first hinge, the first die plate and the third die plate are fixed through a first pair of pull rods, the upper sides of the first pair of pull rods and the first die plate are fixed through first bolts, and meanwhile, first gaskets are arranged on the lower sides of the first bolts; a second pair of pull rods are arranged on the right side of the fourth template, and the first template, the second template, the third template and the fourth template enclose a mold cavity; first staple bolt passes through the second bolt and installs on the second template with the second gasket, and the second staple bolt is installed to first staple bolt downside, and the tip at first staple bolt is cup jointed to the stationary blade simultaneously, second template surface mounting has the strengthening rib, and installs the second hinge on the second template, circular through-hole has been seted up on first template surface, and the square through-hole has been seted up to circular through-hole downside.
Preferably, the first pair of pull rods and the second pair of pull rods are screw rods, the first pair of pull rods and the second pair of pull rods are matched with the circular through holes in size, the first pair of pull rods 5 penetrate through the circular through holes 19 in the first formwork 2 and the third formwork 7, the first pair of pull rods 5 are fixed on the left sides of the first formwork 2 and the third formwork 7 by using the first bolt 1, and the second pair of pull rods 10 are fixed on the right sides of the first formwork 2 and the third formwork 7 by using the same method, so that concrete in the mold cavity 9 is prevented from expanding, damage is caused to the mold, and the appearance of the cement square column is influenced.
Preferably, the second template is hinged to the first template through the first hinge and the second hinge, the fourth template is hinged to the first template through the first hinge and the second hinge, the third template is taken down, and the second template and the fourth template are separated from the surface of the square column, so that the demolding speed is accelerated.
Preferably, the fourth template, the second template, the third template and the first template are made of polytetrafluoroethylene, the mold cavity is square, the weight is light, the disassembly is convenient, the corrosion is prevented, the service life is long, the polytetrafluoroethylene cannot be adhered to cement, and the disassembly of the device is convenient.
Preferably, the first anchor ear is matched with the square through hole in size, and penetrates through the square through hole to be screwed with the second bolt.
Preferably, the first hoop and the second hoop are the same in size, the first hoop and the second hoop are square in shape, the middle of the mold is reinforced by the first hoop 12 and the second hoop 13, concrete expansion is prevented, and the mold is protected.
Preferably, the first anchor ear and the second anchor ear are both made of 304 stainless steel materials, and the sizes of the first anchor ear and the second anchor ear are matched with the size of the second template.
Compared with the prior art, the beneficial effects of the utility model are that: this dedicated cement square column mould in building site, first staple bolt 12 is strengthened the position at mould middle part with second staple bolt 13, prevent the concrete inflation simultaneously, protect the mould, four template surface mounting strengthening ribs, and intensity is high, can not take place the problem that the concrete inflation caused cement square column appearance to lose shape and template to damage, simple structure, and convenient to use easily dismantles and the storage transportation, has the reduction construction degree of difficulty simultaneously, raises the efficiency, practices thrift construction cost's purpose.
Drawings
FIG. 1 is a top view of the present invention;
FIG. 2 is a front view of the structure of the present invention;
FIG. 3 is a schematic view of the circular through hole and the square through hole of the present invention;
Fig. 4 is a schematic view of the first hoop of the structure of the present invention.
Reference numbers in the figures: 1. the first bolt, 2, the first template, 3, first hinge, 4, internal spiral angle, 5, first pair of pull rods, 6, the second template, 7, the third template, 8, the first gasket, 9, die cavity, 10, the second pair of pull rods, 11, the fourth template, 12, the first staple bolt, 13, the second staple bolt, 14, strengthening rib, 15, the second hinge, 16, the second gasket, 17, the second bolt, 18, stationary blade, 19, circular through hole, 20, square through hole.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without creative work belong to the protection scope of the present invention.
Referring to fig. 1-4, the present invention provides a technical solution: a special cement square column die for a construction site comprises a first die plate 2, a fourth die plate 11 and a first hoop 12, wherein a first hinge 3 is installed on the first die plate 2 through an inner screw angle 4, the first die plate 2 and a second die plate 6 are installed together through the first hinge 3, a second pair of pull rods 10 are installed on the right side of the fourth die plate 11, and a die cavity 9 is defined by the first die plate 2, the second die plate 6, a third die plate 7 and the fourth die plate 11; fourth template 11, second template 6, the material of third template 7 and first template 2 is polytetrafluoroethylene, and die cavity 9 is square, first staple bolt 12 is 304 stainless steel material with second staple bolt 13, and the size looks adaptation of first staple bolt 12 and second staple bolt 13 and second template 6, second template 6 articulates on first template 2 through first hinge 3 and second hinge 15, and fourth template 11 articulates on first template 2 through first hinge 3 and second hinge 15, 6 surface mounting of second template has strengthening rib 14, and install second hinge 15 on the second template 6, circular through-hole 19 has been seted up on first template 2 surface, and square through-hole 20 has been seted up to circular through-hole 19 downside.
As shown in fig. 1-3: the first template 2 and the third template 7 are fixed through a first pair of pull rods 5, the upper sides of the first pair of pull rods 5 are fixed with the first template 2 through first bolts 1, and meanwhile, first gaskets 8 are installed on the lower sides of the first bolts 1; the first pair of pull rods 5 and the second pair of pull rods 10 are screw rods, the first pair of pull rods 5 and the second pair of pull rods 10 are matched with the circular through holes 19 in size, the first bolt 1 fixes the first pair of pull rods 5 on the left sides of the first template 2 and the third template 7, the second pair of pull rods 10 are fixed on the right sides of the first template 2 and the third template 7 by using the same method, and the second pair of pull rods 10 and the first pair of pull rods 5 are respectively provided with two groups to fix the upper position and the lower position of the mold, so that the concrete in the mold cavity 9 is prevented from expanding, the mold is prevented from being damaged, and the appearance of the cement square column is influenced.
As shown in fig. 1-4: the first anchor ear 12 is arranged on the second template 6 through a second bolt 17 and a second gasket 16, the second anchor ear 13 is arranged at the lower side of the first anchor ear 12, meanwhile, the fixing piece 18 is sleeved at the end part of the first anchor ear 12, the first anchor ear 12 is matched with the square through hole 20 in size, and the first anchor ear 12 penetrates through the square through hole 20 and is in threaded connection with the second bolt 17; first staple bolt 12 passes behind the square through hole 20 on first template 2 and the third template 7, cup joint stationary blade 18 behind the both ends of first staple bolt 12, use second bolt 17 to fix first staple bolt 12 on third template 7, the mounting means of second staple bolt 13 is unanimous with the mounting means of first staple bolt 12, first staple bolt 12 is strengthened the position at mould middle part with second staple bolt 13, prevent the concrete inflation simultaneously, protect the mould, moreover, the steam generator is simple in structure, high durability and convenient use, easily dismantle and store the transportation, the while has the reduction construction degree of difficulty, high efficiency, practice thrift construction cost's purpose.
The working principle is as follows: when the cement square column mould special for the construction site is used, a second template 6 and a fourth template 11 are hinged on a first template 2 through a first hinge 3 and a second hinge 15, then an opening is sealed by using a third template 7, a first pair of pull rods 5 are used for penetrating through circular through holes 19 on the first template 2 and the third template 7, the first pair of pull rods 5 are fixed on the left sides of the first template 2 and the third template 7 by using first bolts 1, a second pair of pull rods 10 are fixed on the right sides of the first template 2 and the third template 7 by using the same method, the second pair of pull rods 10 and the first pair of pull rods 5 are respectively provided with two groups, the upper position and the lower position of the mould are fixed, the concrete inside a mould cavity 9 is prevented from expanding, the mould is prevented from being damaged, the appearance of the cement square column is influenced, after a first hoop 12 penetrates through square through holes 20 on the first template 2 and the third template 7, after the fixing pieces 18 are sleeved at two ends of the first hoop 12, the first hoop 12 is fixed on the third formwork 7 by using the second bolts 17, the installation mode of the second hoop 13 is consistent with that of the first hoop 12, the middle position of the mould is reinforced by the first hoop 12 and the second hoop 13, simultaneously, the concrete expansion is prevented, the mould is protected, the third formwork 7 is taken down, the second formwork 6 and the fourth formwork 11 are separated from the surface of the square column under the action of the first hinges 3 and the second hinges 15, the demoulding speed is accelerated, the four formworks are made of polytetrafluoroethylene materials, the weight is light, the disassembly is convenient, the corrosion is prevented, the service life is long, the polytetrafluoroethylene cannot be adhered to cement, the disassembly of the device is convenient, reinforcing ribs 14 are arranged on the surfaces of the four formworks, the strength is high, the problems of appearance deformation of the cement square column and damage of the formworks caused by concrete expansion can be avoided, simple structure, convenient to use easily dismantles and the storage transportation, has the reduction construction degree of difficulty simultaneously, raises the efficiency, practices thrift construction cost's purpose, and this is the whole process of this dedicated cement square column mould work of building site.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (7)

1. the utility model provides a dedicated cement square column mould of building site, includes first template (2), fourth template (11) and first staple bolt (12), its characterized in that: a first hinge (3) is installed on the first template (2) through an inner screw corner (4), the first template (2) and the second template (6) are installed together through the first hinge (3), the first template (2) and the third template (7) are fixed through a first pair of pull rods (5), the upper sides of the first pair of pull rods (5) are fixed with the first template (2) through a first bolt (1), and meanwhile, a first gasket (8) is installed on the lower side of the first bolt (1); a second pair of pull rods (10) are arranged on the right side of the fourth template (11), and the first template (2), the second template (6), the third template (7) and the fourth template (11) enclose a mold cavity (9); first staple bolt (12) are installed on second template (6) through second bolt (17) and second gasket (16), and second staple bolt (13) are installed to first staple bolt (12) downside, and stationary blade (18) cup joint the tip at first staple bolt (12) simultaneously, second template (6) surface mounting has strengthening rib (14), and installs second hinge (15) on second template (6), circular through-hole (19) have been seted up on first template (2) surface, and square through-hole (20) have been seted up to circular through-hole (19) downside.
2. The cement square column mould special for the construction site as claimed in claim 1, wherein: the first pair of pull rods (5) and the second pair of pull rods (10) are screw rods, and the first pair of pull rods (5) and the second pair of pull rods (10) are matched with the circular through holes (19) in size.
3. The cement square column mould special for the construction site as claimed in claim 1, wherein: the second template (6) is hinged to the first template (2) through a first hinge (3) and a second hinge (15), and the fourth template (11) is hinged to the first template (2) through the first hinge (3) and the second hinge (15).
4. The cement square column mould special for the construction site as claimed in claim 1, wherein: the fourth template (11), the second template (6), the third template (7) and the first template (2) are made of polytetrafluoroethylene, and the mold cavity (9) is square.
5. The cement square column mould special for the construction site as claimed in claim 1, wherein: the first anchor ear (12) is matched with the square through hole (20) in size, and the first anchor ear (12) penetrates through the square through hole (20) and is in threaded connection with the second bolt (17).
6. The cement square column mould special for the construction site as claimed in claim 1, wherein: the first anchor ear (12) and the second anchor ear (13) are consistent in size, and the first anchor ear (12) and the second anchor ear (13) are square in shape.
7. The cement square column mould special for the construction site as claimed in claim 1, wherein: the first anchor ear (12) and the second anchor ear (13) are both made of 304 stainless steel, and the size of the first anchor ear (12) and the size of the second anchor ear (13) are matched with the size of the second template (6).
CN201822138181.0U 2018-12-20 2018-12-20 Dedicated cement square column mould of building site Expired - Fee Related CN209760793U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822138181.0U CN209760793U (en) 2018-12-20 2018-12-20 Dedicated cement square column mould of building site

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822138181.0U CN209760793U (en) 2018-12-20 2018-12-20 Dedicated cement square column mould of building site

Publications (1)

Publication Number Publication Date
CN209760793U true CN209760793U (en) 2019-12-10

Family

ID=68746948

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822138181.0U Expired - Fee Related CN209760793U (en) 2018-12-20 2018-12-20 Dedicated cement square column mould of building site

Country Status (1)

Country Link
CN (1) CN209760793U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114018663A (en) * 2021-10-25 2022-02-08 中冶武汉冶金建筑研究院有限公司 Thermoplastic ramming material forming equipment and forming method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114018663A (en) * 2021-10-25 2022-02-08 中冶武汉冶金建筑研究院有限公司 Thermoplastic ramming material forming equipment and forming method

Similar Documents

Publication Publication Date Title
CN105569331A (en) Simple supporting method for cylindrical concrete formwork
CN201125529Y (en) Large template corner chucking appliance for building
CN106917505B (en) A kind of transparent plastic template for building and preparation method thereof
CN209760793U (en) Dedicated cement square column mould of building site
CN102296812A (en) Building template molding structure, fastening piece and building template construction method
CN204983646U (en) Device is assembled to reinforced concrete structure post -cast strip template
CN204626966U (en) A kind of deformation joint formwork erection device
CN213477626U (en) Combined plastic formwork
CN204676885U (en) A kind of steel concrete column template fast pacifies the system of tearing open
CN2368912Y (en) Assembled steel-plastic formwork
CN208009896U (en) A kind of construction column template and the fixed attachment device of wall
CN203097290U (en) Assembled type split bolt
CN212613727U (en) Be applied to mould shell of close rib structure superstructure building
CN216476335U (en) Inclined frame concrete cylindrical formwork reinforcing system
CN204040457U (en) Wood frame plastic formwork system
CN204212417U (en) A kind of bracing means of shear wall aluminum alloy mould plate
CN210622270U (en) Scaffold suitable for shear force wall
CN110284705B (en) Sectional type formwork system for reinforcing concrete cylinder
CN210315625U (en) Anti reinforcement structure that floats of sump pit template
CN202148687U (en) Building template forming structure and fastening piece
CN113958120A (en) Inclined frame concrete cylindrical formwork reinforcing system
CN207934069U (en) A kind of precast inspection well reserved opening circular apparatus
CN202391092U (en) U-shaped anchor bolt fixing device of overhanging steel beam
CN218990250U (en) Fixing structure of steel template
CN214117050U (en) Prefabricated steel mesh heat-insulation plate for built-in heat-insulation composite wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191210

CF01 Termination of patent right due to non-payment of annual fee