CN209728093U - A kind of station operation state of earth wire monitoring device - Google Patents

A kind of station operation state of earth wire monitoring device Download PDF

Info

Publication number
CN209728093U
CN209728093U CN201920350439.5U CN201920350439U CN209728093U CN 209728093 U CN209728093 U CN 209728093U CN 201920350439 U CN201920350439 U CN 201920350439U CN 209728093 U CN209728093 U CN 209728093U
Authority
CN
China
Prior art keywords
stake
line
ground line
module
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920350439.5U
Other languages
Chinese (zh)
Inventor
付渊
田月炜
韦佳钰
邹文强
徐一蝶
杨明波
徐伟杰
鲁守银
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Power Grid Co Ltd
Original Assignee
Guizhou Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Power Grid Co Ltd filed Critical Guizhou Power Grid Co Ltd
Priority to CN201920350439.5U priority Critical patent/CN209728093U/en
Application granted granted Critical
Publication of CN209728093U publication Critical patent/CN209728093U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The utility model provides a kind of station operation state of earth wire monitoring device, it includes RFID electronic label and smart grounding line stake, RFID electronic label is fixed on ground line, RFID electronic label and the stake of smart grounding line are wirelessly connected, the stake of smart grounding line and portable mobile termianl are wirelessly connected, and portable mobile termianl and monitor supervision platform are wirelessly connected;The prior art is solved in interruption maintenance operation process, quantity is more sometimes for the temporary ground wire used, and institute's attaching place disperses, pole is not easy to manage, intensive work is easy to make operator that leakage occurs when removing ground line to tear open, leads to occur the pernicious misoperation faults such as line conjunction breaker with ground, disconnecting switch.

Description

A kind of station operation state of earth wire monitoring device
Technical field
The utility model belongs to station technology more particularly to a kind of monitoring of station operation state of earth wire Device.
Background technique
Temporary ground wire is substation management key points and difficulties, and earth wire standardized management prevents manual operation from making mistakes, Improve transformer substation grounding wire management level.Ground line should complete following functions when electric system carries out line construction and maintenance: Ground line should carry out reliable ground to guarantee the safety of controller switching equipment and construction personnel;Ground line should be connected with determining ground stud It connects, it is ensured that corresponding relationship;Ground line is the safety guard for guaranteeing on-site personnel personal safety, assembly and disassembly ground line operation There are larger risk, if occurring omitting or mistake, may cause to seriously endanger to grid equipment and personal safety.And existing skill Art is in interruption maintenance operation process, and quantity is more sometimes for the temporary ground wire used, and institute's attaching place disperses, and pole is not easy to Management, intensive work are easy to that operator is made, there is a situation where leaking to tear open, to lead to that line with ground occurs when removing ground line Close the pernicious misoperation faults such as breaker, disconnecting switch.
Utility model content
Technical problem to be solved by the utility model is: providing a kind of station operation state of earth wire monitoring dress It sets, to solve the prior art in interruption maintenance operation process, quantity is more sometimes for the temporary ground wire used, and institute's attaching Point dispersion, pole are not easy to manage, and intensive work is easy to lead operator there is a situation where leaking to tear open, when removing ground line Generation line with ground is caused to close the pernicious misoperation faults such as breaker, disconnecting switch.
The technical solution of the utility model is:
A kind of station operation state of earth wire monitoring device, it includes RFID electronic label and smart grounding line Stake, RFID electronic label are fixed on ground line, and RFID electronic label and the stake of smart grounding line are wirelessly connected, smart grounding line Stake is wirelessly connected with portable mobile termianl, and portable mobile termianl and monitor supervision platform are wirelessly connected.
The smart grounding line stake includes ground line stake and controlling terminal, controlling terminal include RFID reader and first ZigBee communication module, RFID reader, the first ZigBee communication module and the first power module connect with first processor respectively It connects;Controlling terminal is fixed in ground line stake.
Portable mobile termianl includes second processor, second processor respectively with the second ZigBee communication module, GPRS Locating module, voice module, display module are connected with second power supply module.
A kind of monitoring method of station operation state of earth wire monitoring device, it includes:
When step 1, mounting ground line, repair apparatus or route are first selected, is selected by portable mobile termianl closest Earth wire pile;
Ground line with electronic tag is installed in smart grounding line stake by step 2, is opened by portable mobile termianl Dynamic RFID reader identifies current ground line number, takes formula mobile terminal and send the information currently read to monitor supervision platform;
If the prompt maintenance of step 3, portable mobile termianl starts, shows that ground line is correct, start upkeep operation;It is no Then, error message is prompted, service personnel answers debug, then this repeats step 2, makees until prompt maintenance starts maintenance after starting Industry;
After step 4, upkeep operation, the ground line to be removed is selected, corresponding ground connection is inquired by ground line number Line stake;
The location information of smart grounding line stake is issued to portable by step 5, monitor supervision platform by ZigBee communication module On mobile terminal;
Step 6, service personnel start the RFID reader of smart grounding line stake, identification ground connection by portable mobile termianl The number information of line is compared with the information of monitor supervision platform;
After the completion of step 7, information comparison, monitor supervision platform is by ZigBee communication module to transmitting under portable mobile termianl Breath shows currently to be grounded, inspection consistent with the ground line to be removed if portable mobile termianl prompt " please remove ground line " It repairs personnel's dismounting to be grounded, otherwise prompt " please check whether ground line is consistent ", shows that currently ground line is not meant to connecing for dismounting Ground wire should check again for, and repeat step 6, carry out dismantling operation again after consistent.
The utility model the utility model has the advantages that
The utility model carries out unified management and running operation to each ground connection point, provides real-time ground connection for staff Current work information is uploaded to monitor supervision platform by line status information, and administrative staff can check each ground line stake and grounding point Working condition, and adjust operation power route and the allotment of personnel in real time according to state of earth wire;It is anti-error to realize earth wire Operation is managed collectively with storage, is solved the long-standing problem of management of ground line, is effectively improved substation's earth wire Control ability and person works' efficiency, reduce the generation of maloperation, mistuning degree accident.
Detailed description of the invention
Fig. 1 is the utility model structure diagram;
Fig. 2 is the utility model monitor supervision platform functional schematic;
Fig. 3 is the utility model monitoring method flow diagram.
Specific embodiment
The utility model is made of monitor supervision platform, portable mobile termianl, the stake of smart grounding line and ground line.
Monitor supervision platform is located at supervisory control of substation center, supervises in monitor supervision platform configured with station operation state of earth wire Survey software, the software central system setting, data management, equipment management, personal management, line information, record are checked and in real time Display function.Software can show temporary ground wire use and situation in place, and show its installing detailed location information.
Station operation state of earth wire monitoring of software main functional modules have system setting, data management, equipment Management, personal management, line information, record is checked and real-time display.System setting includes the time for date-time to be arranged The communication configuration module of configuration module and setting communication IP address information.Data management includes for storing ground line ID data Ground line data module, the line stake data for storing ground line stake ID data are torn open for storing the extension of extension dismounting ground wire data Data module and for storing user's logon data, authority information and the user data module of operation note.Equipment management includes For counting and showing that current ground line stake uses the line stake management module with remaining information, and current ground line to use and remain The ground line management module of remaining information.Personal management includes staff's configuration module for managerial staff member's task With administrative staff's module for personal scheduling.Line information includes for counting and showing current working line letter in substation The working line module of breath, and the maintenance line module for counting display maintenance line information, are additionally integrated with power transformation Power circuit in standing dispatches system, which is only served in the Senior Administrator for possessing power circuit scheduling permission.Record is looked into It sees including being grounded stake usage record for checking for checking the ground line outbound logging modle for being grounded out storage information Line stake usage record module, for checking the staff redeployment logging modle of staff's scheduling information, for checking ground connection The record of examination module of record of examination.Real-time display includes the route operating status for showing substation, road, interior lines operating status Module is currently overhauled for showing the equipment running status module of equipment running status in substation for showing in substation Point position, personal information maintenance point module.
The smart grounding line stake includes ground line stake and controlling terminal, controlling terminal include RFID reader and first ZigBee communication module, RFID reader, the first ZigBee communication module and the first power module connect with first processor respectively It connects;Controlling terminal is fixed in ground line stake.Each electronic tag has the identification number uniquely determined, the RFID when mounting ground line Reader identifies electronic tag, by the first ZigBee communication module transfer to portable mobile termianl, by Portable movable end Monitor supervision platform is issued at end again, and monitor supervision platform retains mark data, again identifies that electronic tag when removing ground line, it is ensured that twice Identification number is consistent.
When removing ground line, the RFID that service personnel can be started on corresponding earth wire pile by portable mobile termianl is read Device identifies current ground line number information, is compared with the mounting information on monitor supervision platform, information is unanimously afterwards by portable Formula mobile terminal notifies service personnel that can remove ground line, otherwise alert.
Portable mobile termianl can be carried by service work personnel, and portable mobile termianl includes second processor, and second Processor connects with the second ZigBee communication module, GPRS locating module, voice module, display module and second power supply module respectively It connects.
Wherein GPRS locating module is used to determine the location information of current service work personnel, and location information is sent to Second ZigBee communication module.Second ZigBee communication module is used to carry out data exchange with monitor supervision platform, keeps the reality of data Shi Gengxin, and the data communication with smart grounding line stake.Voice module is used for the processing of warning message, is grounded removing When, if ground line ID and database in hanging earthing conductor ID mismatch if can alert, remind service personnel should be again Confirm whether the ground line to be removed is currently to be grounded, and warning message is transferred to the second ZigBee communication module, then lead to It crosses the second ZigBee communication module and alert data is uploaded into monitor supervision platform.Display module is made of one piece of liquid crystal display, On can show the notification information etc. that the id information of ground line and monitor supervision platform issue.
Mounting ground line workflow:
(1) selectes repair apparatus or route, and neighbouring earth wire pile is selected by portable mobile termianl.
(2) ground line with electronic tag is installed in smart grounding line stake by, is started by portable mobile termianl RFID reader identifies current ground line number.
(3) if the prompt maintenance of portable mobile termianl starts, show that ground line is correct, upkeep operation can be started;It is no Then, error message is prompted, service personnel answers debug, then this repeats step 2, until prompt maintenance can just overhaul after starting Operation.
Remove ground line workflow:
(1) after the operation of Awaiting Overhaul, the ground line to be removed is selected, corresponding ground connection is inquired by ground line number Line stake.
(2) location information of smart grounding line stake is issued to portable shifting by ZigBee communication module by monitor supervision platform In dynamic terminal, service personnel is notified to go to specific location.
(3) service personnel starts the RFID reader of smart grounding line stake, identification ground line by portable mobile termianl Number information, be compared with the information in database, it is ensured that number the ground line of dismounting correct.
After the completion of comparing, monitor supervision platform by ZigBee communication module to photos and sending messages under portable mobile termianl, If portable mobile termianl prompts " please remove ground line ", show currently to be grounded, maintenance consistent with the ground line to be removed Personnel can remove ground line, otherwise prompt " please check whether ground line is consistent ", show that currently ground line is not meant to dismounting Ground line, should check again for, and repeat step 3, carry out dismantling operation again after consistent.

Claims (3)

1. a kind of station operation state of earth wire monitoring device, it includes RFID electronic label and smart grounding line stake, It is characterized by: RFID electronic label is fixed on ground line, RFID electronic label and the stake of smart grounding line are wirelessly connected, intelligence Stake can be grounded and portable mobile termianl is wirelessly connected, portable mobile termianl and monitor supervision platform are wirelessly connected.
2. a kind of station operation state of earth wire monitoring device according to claim 1, it is characterised in that: described Smart grounding line stake includes ground line stake and controlling terminal, controlling terminal include RFID reader and the first ZigBee communication mould Block, RFID reader, the first ZigBee communication module and the first power module are connect with first processor respectively;Controlling terminal is solid It is scheduled in ground line stake.
3. a kind of station operation state of earth wire monitoring device according to claim 1, it is characterised in that: portable Formula mobile terminal includes second processor, second processor respectively with the second ZigBee communication module, GPRS locating module, voice Module, display module are connected with second power supply module.
CN201920350439.5U 2019-03-19 2019-03-19 A kind of station operation state of earth wire monitoring device Active CN209728093U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920350439.5U CN209728093U (en) 2019-03-19 2019-03-19 A kind of station operation state of earth wire monitoring device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920350439.5U CN209728093U (en) 2019-03-19 2019-03-19 A kind of station operation state of earth wire monitoring device

Publications (1)

Publication Number Publication Date
CN209728093U true CN209728093U (en) 2019-12-03

Family

ID=68687340

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920350439.5U Active CN209728093U (en) 2019-03-19 2019-03-19 A kind of station operation state of earth wire monitoring device

Country Status (1)

Country Link
CN (1) CN209728093U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109813996A (en) * 2019-03-19 2019-05-28 贵州电网有限责任公司 A kind of station operation state of earth wire monitoring device and monitoring method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109813996A (en) * 2019-03-19 2019-05-28 贵州电网有限责任公司 A kind of station operation state of earth wire monitoring device and monitoring method

Similar Documents

Publication Publication Date Title
CN109813996A (en) A kind of station operation state of earth wire monitoring device and monitoring method
CN102509245B (en) Temporary grounding wire management method and system
CN107181319B (en) Intelligent inspection method for state of hard pressing plate of transformer substation
CN102255393B (en) Ground wire hanging anti-error blocking system and method thereof
CN203774866U (en) Intelligent ground wire apparatus and ground wire operation safety monitoring and error-preventing system
CN110336379B (en) Transformer substation online monitoring system based on Internet of things and terminal equipment
CN102332690B (en) Electric power netting safe running temporary ground wire Tracking monitoring system
CN101651293B (en) Real-time monitoring and management system of digital grounding wire
CN110086251B (en) Monitoring method and system for improving operation safety of power grid
CN105242626A (en) Line safety intelligent auxiliary monitoring system
CN108769901B (en) Laboratory equipment management system and method based on UWB technology
CN101826757A (en) Method and device for managing earth wire
CN112598814A (en) Method for checking positions of power distribution network patrolmen
CN111371180B (en) Substation patrol supervision and data analysis system
CN209728093U (en) A kind of station operation state of earth wire monitoring device
CN104237735A (en) Modeling and fault analysis method combining fault indicator and power distribution terminal
CN107480797A (en) A kind of LNG filling machines fault diagnosis removal system and its operating method
CN202150043U (en) Monitoring system for hanging and dismounting ground wire of power line
CN112736760A (en) Power equipment grounding wire operation system
CN205139664U (en) Monitor platform
CN108988481B (en) Power supply's management device
CN207571783U (en) A kind of LNG filling machines fault diagnosis removal system
CN110110868A (en) A kind of ground wire management system of combination ZigBee technology and GPRS global-positioning technology
CN105279537A (en) System and method for detecting hanging of ground wires for transformer station
CN201859341U (en) Remote control device for probe station

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant