CN209686702U CN201920006439.3U CN201920006439U CN209686702U CN 209686702 U CN209686702 U CN 209686702U CN 201920006439 U CN201920006439 U CN 201920006439U CN 209686702 U CN209686702 U CN 209686702U
Authority
CN
China
Prior art keywords
sleeve
support rod
prefabricated lining
convenient
hanged
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920006439.3U
Other languages
Chinese (zh)
Inventor
尤峰
陈瑜
程肖姚
姚建炎
朱少东
丁荣舜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Tuxin Building Technology Co Ltd
Original Assignee
Jiangsu Tuxin Building Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Tuxin Building Technology Co Ltd filed Critical Jiangsu Tuxin Building Technology Co Ltd
Priority to CN201920006439.3U priority Critical patent/CN209686702U/en
Application granted granted Critical
Publication of CN209686702U publication Critical patent/CN209686702U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The utility model discloses a kind of convenient for hanged prefabricated lining, it is related to technical field of prefabricated, aim to solve the problem that the time-consuming and laborious technical problem of the prefabricated lining transfer process for pouring completion, its key points of the technical solution are that including prefabricated lining main body, several preformed holes are offered in the prefabricated lining main body, sleeve is inserted in the preformed hole, the lateral wall of the sleeve is provided with screw thread, support rod is provided in the sleeve, the threaded one end that the support rod stretches out sleeve is connected with hanging ring, operator uses crane, suspension hook on crane is hooked into hanging ring, to which prefabricated lining be lifted, in this way, convenient for carrying out carrying transfer to prefabricated lining, it operates fairly simple.

Description

It is a kind of convenient for hanged prefabricated lining
Technical field
The utility model relates to technical field of prefabricated, more specifically, it relates to it is a kind of convenient for it is hanged it is prefabricated in Wallboard.
Background technique
In today of urbanization high speed development, characterized by design standard, element factoryization manufacture, construction assembling Building trade has become the inexorable trend of era development;Prefabricated lining is important composition portion very important in building trade Point.
Existing Authorization Notice No. provides a kind of prefabricated panel for the Chinese patent of CN207660177U, and prefabricated panel is mixed Solidifying soil pouring structure, side offer lateral opening, lacing wire are provided in opening, and one end of lacing wire is located in concrete, Being bent to form for lacing wire stretching concrete is hook-shaped, is used to form transverse direction in this way convenient for being convenient for taking out after the completion of prefabricated panel pours The template of opening.
But after the completion of prefabricated panel pours, it need to use crane that prefabricated panel is transferred to corresponding storage area, by Heavier in the mass ratio of prefabricated panel, the process shifted to it is more time-consuming, greatly reduces working efficiency, therefore has Wait improve.
Utility model content
In view of the deficienciess of the prior art, the purpose of this utility model is to provide a kind of convenient for hanged prefabricated interior wall Plate has the advantage for capableing of quick hanged prefabricated lining.
To achieve the above object, the utility model provides following technical solution:
It is a kind of convenient for hanged prefabricated lining, including prefabricated lining main body, opened up in the prefabricated lining main body There are several preformed holes, sleeve is inserted in the preformed hole, the lateral wall of the sleeve is provided with screw thread, setting in the sleeve There is support rod, the threaded one end that the support rod stretches out sleeve is connected with hanging ring.
By using above-mentioned technical proposal, operator uses crane, the suspension hook on crane is hooked hanging ring, thus by pre- Lining processed lifts, in this way, operation is fairly simple convenient for carrying out carrying transfer to prefabricated lining, greatly accelerates operation The working efficiency of personnel.
Further, the lateral wall of the support rod offers and offers several fixation holes one along its length, described Fixed link, the fixation hole two that the inner sidewall of the sleeve offers for fixed link insertion are provided in fixation hole one;It is described solid Determine to be provided with spring in hole one, one end of the spring is connected to the bottom wall of fixation hole one, and the other end of the spring is connected to One end of fixed link insertion fixation hole one.
It is fixed under the elastic force effect of spring during support rod is inserted into sleeve by using above-mentioned technical proposal Bar automatic spring from fixation hole one, and be inserted into fixation hole two, realize the rapid abutting joint between sleeve and support rod, significantly Facilitate the operation of staff.
Further, the handle hole communicated with several fixation holes one is offered on the support rod, is set in the handle hole It is equipped with the operating stick that several fixed links are connected.
By using above-mentioned technical proposal, operating stick is stirred, operating stick drives fixed link in fixation hole one and fixation hole two Interior sliding realizes being detachably connected between support rod and sleeve so that fixed link completely disengages fixation hole two, in this way, support Bar is just not necessarily to stay in sleeve, and support rod can be recycled.
Further, one end that the support rod stretches out sleeve is rotatably connected to locking block, the locking block and operating stick It offsets.
By using above-mentioned technical proposal, when locking block and operating stick offset, locking block carries out locking to operating stick, avoids It is shaken during hanged to prefabricated lining main body.
Further, the locking block is provided with magnetic part, the magnetic with one end at support rod rotation connection far from it The lateral wall magnetism of property part and support rod is attracting.
By using above-mentioned technical proposal, when the lateral wall of magnetic part and support rod passes through the magnetic lateral wall with support rod It is connected with each other, locking block is fixed.
Further, one end of the fixed link insertion fixation hole two, which is integrally formed, is provided with guide pad, the guide pad It is tapered.
By using above-mentioned technical proposal, during fixed link is inserted into fixation hole two, guide pad plays guiding role, It avoids fixed link from blocking at the aperture of fixation hole two, realizes the rapid abutting joint between fixed link and fixation hole two.
Further, the lateral wall of the support rod is provided with and the sleeve locating piece that side offsets upward.
By using above-mentioned technical proposal, during support rod is inserted into sleeve, quick positioning support bar is located at vertical Position on direction guarantees that fixed link can be properly inserted in fixation hole two.
Further, the lateral wall of the hanging ring is provided with rubber layer.
By using above-mentioned technical proposal, when the suspension hook on crane hooks hanging ring, rubber layer effectively increases suspension hook and hangs Friction between ring reduces the skidding between suspension hook and hanging ring, to guarantee during hanged to prefabricated lining main body Stablize.
In conclusion the utility model has the following beneficial effects:
1, sleeve is inserted in preformed hole, the lateral wall of sleeve is provided with screw thread, support rod, support rod are provided in sleeve The threaded one end for stretching out sleeve is connected with hanging ring, and operator uses crane, the suspension hook on crane hooked hanging ring, thus by pre- Lining processed lifts, in this way, operation is fairly simple convenient for carrying out carrying transfer to prefabricated lining, greatly accelerates operation The working efficiency of personnel;
2, the handle hole communicated with several fixation holes one is offered on support rod, and several fixed link phases are provided in handle hole The operating stick of connection stirs operating stick, and operating stick drives fixed link to slide in fixation hole one and fixation hole two, so that fixed link Fixation hole two is completely disengaged, being detachably connected between support rod and sleeve is realized, in this way, support rod is just not necessarily to stay in sleeve Interior, support rod can be recycled.
Detailed description of the invention
Fig. 1 is a kind of overall structure diagram convenient for hanged prefabricated lining in embodiment;
Fig. 2 is in embodiment for embodying the dismantling schematic diagram of connection relationship between support rod and sleeve;
Fig. 3 is the enlarged drawing of part A in Fig. 2;
Fig. 4 is the enlarged drawing of part B in Fig. 2.
In figure: 1, prefabricated lining main body;11, preformed hole;2, sleeve;21, screw thread;22, fixation hole two;3, support rod; 31, fixation hole one;311, fixed link;3111, guide pad;312, spring;32, handle hole;321, operating stick;33, locating piece;4, Locking block;41, magnetic part;5, hanging ring;51, rubber layer.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
Embodiment:
It is a kind of convenient for hanged prefabricated lining, referring to Figures 1 and 2 comprising prefabricated lining main body 1, prefabricated interior wall Plate main body 1 is equipped with preformed hole 11, and preformed hole 11 is interior to be connected with sleeve 2 by pouring, and the lateral wall of sleeve 2 is provided with screw thread 21, support rod 3 is provided in sleeve 2;The threaded one end 21 that support rod 3 stretches out sleeve 2 is connected with hanging ring 5, and operator can make Hanging ring 5 is hooked with the suspension hook on crane, prefabricated lining main body 1 is hanged.
Referring to Fig. 2 and Fig. 3, the lateral wall of support rod 3 offers several fixation holes 1, fixation hole one along its length 31 inner sidewall is inserted with fixed link 311, and the inner sidewall of sleeve 2 offers the fixation hole 2 22 being inserted into for fixed link 311, Gu Determine to be provided with spring 312 in hole 1, one end of spring 312 is connected to the bottom wall of fixation hole 1, and the other end of spring 312 supports It is connected to one end that fixed link 311 is inserted into fixation hole 1, under the elastic force effect of spring 312, fixed link 311 is from fixation hole 1 It is inserted into fixation hole 2 22, realizes the fixation between sleeve 2 and support rod 3;
Referring to Fig. 3, one end that support rod 3 stretches out sleeve 2 offers the handle hole 32 communicated with several fixation holes 1, grasps Make to be inserted with the operating stick 321 being connected with several fixed links 311 in hole 32, operating stick 321 passes through with several fixed links 311 Connection is welded and fixed, when inner sidewall sliding of the operating stick 321 along handle hole 32, operating stick 321 drives fixed link 311 in fixation Sliding in hole 1 and fixation hole 2 22.
Referring to Fig. 3, one end that fixed link 311 is inserted into fixation hole 2 22, which is integrally formed, is provided with guide pad 3111, works as fixation Bar 311 is inserted into fixation hole 2 22, and fixed link 311 is avoided to block at the aperture of fixation hole 2 22, realizes fixed link 311 and fixation hole 2 22 rapid abutting joint.
Referring to Fig. 3, the lateral wall of support rod 3 is provided with locating piece 33, the upper surface of locating piece 33 and sleeve 2 by welding It offsets, the position on vertical direction is located at quick positioning support bar 3, guarantee that fixed link 311 can be properly inserted fixation hole two 22。
Referring to Fig. 3 and Fig. 4, one end that support rod 3 stretches out sleeve 2 is connected with locking block 4 by pin rotation, works as fixed link When 311 one end is located in fixation hole 2 22, locking block 4 and the wherein side of operating stick 321 offset, and carry out to operating stick 321 It further fixes, when fixed link 311 is fully located in fixation hole 1, fixed link 311 applies pressure, locking to spring 312 Block 4 and the other side of operating stick 321 offset, and carry out locking to locking block 4, to carry out locking to fixed link 311;Locking block 4 Magnet block is provided with by screw with one end at 3 rotation connection of support rod far from it, magnet block works as magnet as magnetic part 41 The lateral wall of block and support rod 3 is connected with each other by magnetic, is further fixed to locking block 4.
Referring to Fig. 4, the lateral wall of hanging ring 5 is enclosed with rubber layer 51, and when suspension hook hooks hanging ring 5, rubber layer 51 effectively increases Add the friction between suspension hook and hanging ring 5, slows down and skid between suspension hook and hanging ring 5.
Working principle is as follows:
After the completion of prefabricated lining main body 1 pours, it need to be transferred into corresponding storage area, support rod 3 is inserted into Sleeve 2 rotates locking block 4, and locking block 4 is made to be detached from operating stick 321, and under the elastic force effect of spring 312, fixed link 311 is from admittedly Determine automatic spring in hole 1, and be inserted into fixation hole 2 22, fixed link 311 drives operating stick 321 to slide, and rotates locking block 4, so that locking block 4 resists operating stick 321, hanging ring 5 is hooked using the suspension hook on crane, prefabricated lining main body 1 is sling, is turned Corresponding storage area is moved on to, after the completion of transfer, locking block 4 is rotated, so that locking block 4 is detached from operating stick 321, stir operating stick 321, operating stick 321 drives fixed link 311 mobile, so that fixed link 311 is completely disengaged fixation hole 2 22, so that support rod 3 be taken Out, whole operation is completed.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but As long as all by the protection of Patent Law in the scope of the claims of the utility model.

Claims (8)

1. a kind of convenient for hanged prefabricated lining, including prefabricated lining main body (1), it is characterised in that: the prefabricated interior wall It offers in plate main body (1) several preformed holes (11), is inserted with sleeve (2) in the preformed hole (11), outside the sleeve (2) Side wall is provided with screw thread (21), is provided with support rod (3) in the sleeve (2), and the support rod (3) stretches out the one of sleeve (2) End screw thread (21) is connected with hanging ring (5).
2. according to claim 1 a kind of convenient for hanged prefabricated lining, it is characterised in that: the support rod (3) Lateral wall offers and offers several fixation holes one (31) along its length, is provided with fixed link in the fixation hole one (31) (311), the fixation hole two (22) that the inner sidewall of the sleeve (2) offers for fixed link (311) insertion;The fixation hole one (31) it is provided with spring (312) in, one end of the spring (312) is connected to the bottom wall of fixation hole one (31), the spring (312) the other end is connected to one end of fixed link (311) insertion fixation hole one (31).
3. according to claim 2 a kind of convenient for hanged prefabricated lining, it is characterised in that: on the support rod (3) The handle hole (32) communicated with several fixation holes one (31) is offered, is provided with several fixed links in the handle hole (32) (311) operating stick (321) being connected.
4. according to claim 3 a kind of convenient for hanged prefabricated lining, it is characterised in that: the support rod (3) is stretched One end of sleeve (2) is rotatably connected to locking block (4) out, and the locking block (4) offsets with operating stick (321).
5. according to claim 4 a kind of convenient for hanged prefabricated lining, it is characterised in that: the locking block (4) is remote It is provided with magnetic part (41) from it with one end at support rod (3) rotation connection, the magnetic part (41) is outer with support rod (3) Sidewall magnetic is attracting.
6. according to claim 5 a kind of convenient for hanged prefabricated lining, it is characterised in that: the fixed link (311) One end of insertion fixation hole two (22) is integrally formed and is provided with guide pad (3111), and the guide pad (3111) is tapered.
7. according to claim 6 a kind of convenient for hanged prefabricated lining, it is characterised in that: the support rod (3) Lateral wall is provided with and sleeve (2) locating piece (33) that side offsets upward.
8. according to claim 1 a kind of convenient for hanged prefabricated lining, it is characterised in that: outside the hanging ring (5) Side wall is provided with rubber layer (51).
CN201920006439.3U 2019-01-03 2019-01-03 It is a kind of convenient for hanged prefabricated lining Expired - Fee Related CN209686702U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920006439.3U CN209686702U (en) 2019-01-03 2019-01-03 It is a kind of convenient for hanged prefabricated lining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920006439.3U CN209686702U (en) 2019-01-03 2019-01-03 It is a kind of convenient for hanged prefabricated lining

Publications (1)

Publication Number Publication Date
CN209686702U true CN209686702U (en) 2019-11-26

Family

ID=68598078

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920006439.3U Expired - Fee Related CN209686702U (en) 2019-01-03 2019-01-03 It is a kind of convenient for hanged prefabricated lining

Country Status (1)

Country Link
CN (1) CN209686702U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113605686A (en) * 2021-08-24 2021-11-05 无锡市钱桥建筑安装工程有限公司 Special supporting device for building structure deformation joint template

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113605686A (en) * 2021-08-24 2021-11-05 无锡市钱桥建筑安装工程有限公司 Special supporting device for building structure deformation joint template
CN113605686B (en) * 2021-08-24 2023-03-07 无锡市钱桥建筑安装工程有限公司 Building structure movement joint template strutting arrangement

Similar Documents

Publication Publication Date Title
CN209686702U (en) It is a kind of convenient for hanged prefabricated lining
CN108442361B (en) Reinforced cage barb type anti-floating device for bored concrete pile and use method
CN202766247U (en) Cable well lid lifting implement
CN207108307U (en) The portable boom hoisting of urban viaduct construction in later period
CN206570798U (en) A kind of steel reinforcement cage positioner
CN110052649A (en) A kind of adjustable plate drilling equipment with drill bit protection structure
CN103663306A (en) Hoisting device for cable well lid
CN209226456U (en) A kind of height-adjustable air hose sling cart of movable type
CN209668641U (en) A kind of bridge mobile hoisting bracket
CN208866320U (en) A kind of reinforcing bar binding frame
CN109441132A (en) A kind of flooring sewer pipe preformed hole, which is filled up, uses auxiliary device
CN104234643B (en) The automatics of drilling well
CN209501460U (en) A kind of environmental protection and energy saving cake raw material agitator
CN205291265U (en) Single horizontal shaft forced concrete mixer
CN210393398U (en) Rotary lifting appliance for crane
CN209584846U (en) Plate bridge pier column concrete vibrating equipment
CN205820773U (en) A kind of controllable type eminence equipment provision for disengagement
CN206913442U (en) Concrete mixer
CN216042719U (en) Novel practical rebar hook structure
CN207944488U (en) Rectangular municipal administration well lid proposes telephone-moving
CN207877104U (en) A kind of adjustable large-scale steel pipe suspender
CN206769413U (en) A kind of new fixing device that can integrally lift assembling reinforcement
CN209501462U (en) A kind of energy-efficient cake raw material agitator
CN212385701U (en) Mortar flat-end mixer for building
CN117415955A (en) Cement stirring device for indoor construction

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee