CN209671140U - A kind of prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system - Google Patents

A kind of prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system Download PDF

Info

Publication number
CN209671140U
CN209671140U CN201821824642.3U CN201821824642U CN209671140U CN 209671140 U CN209671140 U CN 209671140U CN 201821824642 U CN201821824642 U CN 201821824642U CN 209671140 U CN209671140 U CN 209671140U
Authority
CN
China
Prior art keywords
concrete
steel tube
double skin
filled double
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821824642.3U
Other languages
Chinese (zh)
Inventor
周绪红
王宇航
王姝琪
谭继可
邓然
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chongqing University
Original Assignee
Chongqing University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chongqing University filed Critical Chongqing University
Priority to CN201821824642.3U priority Critical patent/CN209671140U/en
Application granted granted Critical
Publication of CN209671140U publication Critical patent/CN209671140U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/728Onshore wind turbines

Landscapes

  • Wind Motors (AREA)

Abstract

The utility model discloses a kind of prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure systems, are related to land technical field of wind power generation.The system includes blower, top head tower, concrete-filled double skin steel tube tower, presstressed reinforcing steel, cushion cap, pile foundation.The concrete-filled double skin steel tube tower segmentation is prefabricated, is connected between each section using high-strength grout;It is connect in the concrete-filled double skin steel tube tower top pre-embedded bolt with top head tower.The presstressed reinforcing steel starts from concrete-filled double skin steel tube tower top, cushion cap cavity top is terminated in, using post-tensioned construction.In the annular horizontal steel plate of cushion cap cavity top the arrangement weld stud and vertical anti-shear steel plate.The System structure is simple, and overall stability is good, is a kind of completely new land wind-power tower and base form, is highly suitable for low wind speed high tower construction.Structural system uses assembly construction method, can significantly guarantee construction quality, improve construction efficiency, reduces working measure expense.

Description

A kind of prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system
Technical field
The utility model relates to land technical field of wind power generation more particularly to the high tower technical fields of low wind speed.
Background technique
The wind-powered electricity generation energy has been to be concerned by more and more people and payes attention to as a kind of clean renewable low-carbon energy.In recent years Carry out the sustained and rapid development with global wind power industry, the average height of blower alreadys exceed 80m, bigger impeller diameter and more High tower has become the main trend of Wind Power Development.Important component of the tower as wind-driven generator, main function are Impeller and cabin are supported, and generating set is sent at design height and obtains enough wind energy drive electrical power generators.
Mainstream structure type of the steel tower drum as Large-scale Wind Turbines tower, presently, there are following some problems: Cost increases with the increase exponentially rule of tower height;Amplitude is larger when tower height increases, frequencies go lower, easily and wind-powered electricity generation Unit resonates;By taking 2MW unit as an example, when tower height be greater than 90m when, base diameter range be typically in 4m~ 4.7m has been more than the requirement of ordinary highway limit for height 4.5m, transport difficult;Steel tower drum is perishable, and maintenance cost is high.Therefore, it is The low wind speed of abundant exploitation, ultralow wind speed region wind power resources, need to make improvement to conventional steel tower form, develop The optimal novel tower barrel of performance and its base form.
Summary of the invention
The utility model proposes a kind of prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system, lower part tower is hollow Interlayer steel tube concrete structure, outer and inner tube replace distributing bar to play the role of construction mould, construction party while acting on Just, steel pipe thickness is effectively reduced, reduces steel using amount.Prestressing force is applied using post stretching to hollow sandwich steel pipe concrete tower, The compressive property of concrete is made full use of, the overall performance of structure is good.Cap design of pile uses the principle of composite structure, in cushion cap sky Top of chamber arranges that the annular horizontal steel plate of weld stud and vertical anti-shear steel plate, peg enhance concrete and annular horizontal steel plate Cementation, annular horizontal steel plate replace tension reinforcement alleviated while acting on concrete at anchorage stress concentrate it is existing As vertical anti-shear steel plate is instead of the effect of shear reinforcement, and the design of cushion cap is so that construction is more convenient.Structural system is all adopted With assembly construction method, it can significantly guarantee construction quality, improve construction efficiency, reduce working measure expense.
The technical solution of the utility model is as follows:
A kind of prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system, which includes blower, top head tower, hollow Interlayer steel tube concrete tower, presstressed reinforcing steel, cushion cap, pile foundation;The top head tower and concrete-filled double skin steel tube tower Cylinder is connected by screw bolts;The concrete-filled double skin steel tube tower segmentation is prefabricated, is connected between each section using high-strength grout It connects;Prestressing force is applied by post stretching in the concrete-filled double skin steel tube tower and cushion cap, hollow sandwich steel pipe is mixed It is connected between solidifying soil tower bottom and cushion cap using high-strength grout.
It is connect in the concrete-filled double skin steel tube tower top pre-embedded bolt with top head tower.
The duct of tensioned prestressing bar, presstressed reinforcing steel are reserved in the concrete-filled double skin steel tube tower and cushion cap Concrete-filled double skin steel tube tower top is started from, cushion cap cavity top is terminated in, using post-tensioned construction.
Reserving hole channel at the anchorage of the presstressed reinforcing steel configures steel pipe, realizes and makees to the local restriction of concrete With preventing the splitting of concrete.
In the annular horizontal steel plate of cushion cap cavity top the arrangement weld stud and vertical anti-shear steel plate.
The utility model has the advantages that compared with the existing technology
(1) lower part tower be concrete structure with hollow sandwich, outer and inner tube replace distributing bar act on while from Arrive the effect of construction mould, it is easy for construction, steel pipe thickness is effectively reduced, reduces steel using amount;
(2) prestressing force is applied using post stretching to hollow sandwich steel pipe concrete tower, makes full use of the resistance to compression of concrete The overall performance of performance, structure is good;
(3) cap design of pile uses the principle of composite structure, and annular horizontal steel plate replaces tension reinforcement to alleviate while acting on The stress concentration phenomenon of concrete at anchorage, vertical anti-shear steel plate instead of shear reinforcement effect, the design of cushion cap so that It is more convenient to construct.
(4) structural system all uses assembly construction method, can significantly guarantee construction quality, improve construction efficiency, drop Low working measure expense.
Detailed description of the invention
Fig. 1 is the overall schematic of the utility model;
Fig. 2 is the schematic diagram of the utility model middle and upper part head tower;
Fig. 3 is the sectional view of concrete-filled double skin steel tube tower in the utility model;
Fig. 4 is the schematic diagram that the utility model middle and upper part head tower is connect with concrete-filled double skin steel tube tower;
Fig. 5 is the schematic diagram of foundation in the utility model;
Fig. 6 is the sectional view of cushion cap and the schematic diagram of vertical anti-shear steel plate in the utility model.
In figure: 1- blower, the top 2- head tower, 3- concrete-filled double skin steel tube tower, 4- presstressed reinforcing steel, 5- cushion cap, 6- The outer steel pipe of concrete-filled double skin steel tube, the interior steel pipe of 7- concrete-filled double skin steel tube, 8- reserving hole channel, 9- ring flange, 10- bolt hole, 11- bolt, 12- anchorage, 13- steel pipe, 14- pile foundation, 15- concrete, 16- annular horizontal steel plate, 17- bolt Nail, the vertical anti-shear steel plate of 18-.
Specific embodiment
Below in conjunction with attached drawing, the utility model is further described.
As shown in Figure 1, a kind of prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system, the system include blower (1), Top head tower (2), concrete-filled double skin steel tube tower (3), cushion cap (5), pile foundation (14);The hollow sandwich steel pipe is mixed Solidifying soil tower (3) is segmented prefabricated, cast on-site high-strength grout connection between each section;The concrete-filled double skin steel tube Cast on-site high-strength grout is connect between tower (3) and cushion cap (5).
As shown in Figure 2, Figure 4 shows, the pre-embedded bolt (11) at the top of the concrete-filled double skin steel tube tower (3), scene It is connected thereto by the ring flange (9) of top head tower (2).
As shown in Figure 4, Figure 5, it is pre- that tensioning is reserved in the concrete-filled double skin steel tube tower (3) and cushion cap (5) The duct (8) of stress rib (4), presstressed reinforcing steel (4) start from the top of concrete-filled double skin steel tube tower (3), terminate in cushion cap (5) sky Top of chamber, using post-tensioned construction;Reserving hole channel (8) at the anchorage (12) of the presstressed reinforcing steel (4) configures steel pipe (13), it realizes and the local restriction of concrete is acted on, prevent the splitting of concrete.
As shown in Figure 5, Figure 6, in cushion cap (5) cavity top arrangement weld stud (17) and vertical anti-shear steel plate (18) annular horizontal steel plate (16), annular horizontal steel plate (16) can be used as the template of casting concrete when construction.
The utility model proposes a kind of prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system, System structure letters Single, overall stability is good, is highly suitable for low wind speed high tower construction.Structural system uses assembly construction method, can significantly protect Construction quality is demonstrate,proved, construction efficiency is improved, reduces working measure expense.
The above be only the utility model preferred embodiment, but the utility model be not limited to it is above-mentioned Specific embodiment.One skilled in the relevant art without departing from the principle of this utility model, can also make Several modifications supplement or use instead similar fashion substitution, these should also be regarded as the protection scope of the utility model.
Although being used more herein: 1- blower, the top 2- head tower, 3- concrete-filled double skin steel tube tower, 4- are pre- Stress rib, 5- cushion cap, the outer steel pipe of 6- concrete-filled double skin steel tube, interior steel pipe, the 8- of 7- concrete-filled double skin steel tube are pre- A possibility that terms such as boxing out, but being not precluded using other terms.The use of these items is only for more easily retouch The essence for stating and explaining the utility model is construed as any additional limitation all and is the spirit with the utility model It disagrees.

Claims (5)

1. a kind of prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system, the system include blower (1), top head tower (2), Concrete-filled double skin steel tube tower (3), presstressed reinforcing steel (4), cushion cap (5), pile foundation (14), it is characterised in that: described is upper Portion's head tower (2) is connect with concrete-filled double skin steel tube tower (3) using bolt (11);The concrete-filled double skin steel tube Tower (3) segmentation is prefabricated, is connected between each section using high-strength grout;In the concrete-filled double skin steel tube tower (3) Prestressing force is applied by post stretching in cushion cap (5), is adopted between concrete-filled double skin steel tube tower (3) bottom and cushion cap (5) It is connected with high-strength grout.
2. prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system according to claim 1, it is characterised in that: in institute Pre-embedded bolt (11) is connect with top head tower (2) at the top of the concrete-filled double skin steel tube tower (3) stated.
3. prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system according to claim 1, it is characterised in that: in institute The duct (8) of tensioned prestressing bar (4), presstressed reinforcing steel are reserved in the concrete-filled double skin steel tube tower (3) and cushion cap (5) stated (4) it starts from the top of concrete-filled double skin steel tube tower (3), cushion cap (5) cavity top is terminated in, using post-tensioned construction.
4. prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system according to claim 1, it is characterised in that: in institute Reserving hole channel (8) at the anchorage (12) for the presstressed reinforcing steel (4) stated configures steel pipe (13), realizes and makees to the local restriction of concrete With preventing the splitting of concrete.
5. prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system according to claim 1, it is characterised in that: in institute The annular horizontal steel plate (16) of cushion cap (5) cavity top arrangement weld stud (17) and vertical anti-shear steel plate (18) stated.
CN201821824642.3U 2018-11-06 2018-11-06 A kind of prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system Active CN209671140U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821824642.3U CN209671140U (en) 2018-11-06 2018-11-06 A kind of prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821824642.3U CN209671140U (en) 2018-11-06 2018-11-06 A kind of prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system

Publications (1)

Publication Number Publication Date
CN209671140U true CN209671140U (en) 2019-11-22

Family

ID=68561200

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821824642.3U Active CN209671140U (en) 2018-11-06 2018-11-06 A kind of prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system

Country Status (1)

Country Link
CN (1) CN209671140U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111364456A (en) * 2020-03-28 2020-07-03 江苏龙源振华海洋工程有限公司 Offshore generator pile and construction platform thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111364456A (en) * 2020-03-28 2020-07-03 江苏龙源振华海洋工程有限公司 Offshore generator pile and construction platform thereof
CN111364456B (en) * 2020-03-28 2021-10-15 江苏龙源振华海洋工程有限公司 Construction platform of offshore generator pile

Similar Documents

Publication Publication Date Title
CN109296502A (en) A kind of prestressing force concrete-filled double skin steel tube wind-power tower and combinations thereof formula basis
CN206917805U (en) The antifatigue combination steel construction wind tower of omnidirectional's prestressing force
CN208057316U (en) A kind of Wind turbines steel reinforced concrete tower prestress wire Opposite direction connection flange arrangement
CN102312799A (en) Pylon with tensioned cables
CN108316336A (en) A kind of novel lattice offshore wind turbine buoyant foundation composite structure
CN109404224A (en) It is a kind of based on edge put more energy into combined shell wind-powered electricity generation mix tower
CN106321367A (en) Cable-stayed prestressed steel and concrete combined type fan tower
JP2008537043A (en) Prefabricated modular tower
CN218597202U (en) Bearing platform foundation and wind power tower cylinder
CN209671140U (en) A kind of prestressing force concrete-filled double skin steel tube wind-powered electricity generation structure system
CN108385708A (en) It is a kind of that there is the dual anti-novel buoyant foundation structural system of offshore wind turbine for waving mechanism
CN109295994A (en) A kind of full assembled composite structure wind-power tower basis
CN208328972U (en) A kind of novel lattice offshore wind turbine buoyant foundation composite structure
CN108506169A (en) A kind of Wind turbines prestressing force stay-supported pylon increases method and structure
CN209671141U (en) A kind of mixing tower adapter ring based on composite structure technology
US20140133921A1 (en) Offshore installation method of a wind power generator and its fabrication segments
CN105756077B (en) Foundation ring Rock Bolt Foundation
CN206190458U (en) Prestressing force antifatigue combination steel construction wind tower of qxcomm technology
CN209398541U (en) It is a kind of based on edge put more energy into combined shell wind-powered electricity generation mix tower
CN208763818U (en) A kind of Wind turbines prestressing force stay-supported pylon heightening structure
CN208633991U (en) A kind of hybrid blower fan pylon of prefabricated PC lattice concrete filled steel tube
CN208219689U (en) Prefabricated components concrete tower fan foundation structure
CN209385287U (en) A kind of concrete filled steel tube lattice wind power tower based on corrugated steel web box beam
CN109707570A (en) A kind of hybrid blower fan pylon of prefabricated PC lattice concrete filled steel tube
CN206707932U (en) The antifatigue combining structure wind tower of prestressing force

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant