CN209670447U - A kind of quick-mounting formula electric power iron tower foundation - Google Patents

A kind of quick-mounting formula electric power iron tower foundation Download PDF

Info

Publication number
CN209670447U
CN209670447U CN201920358085.9U CN201920358085U CN209670447U CN 209670447 U CN209670447 U CN 209670447U CN 201920358085 U CN201920358085 U CN 201920358085U CN 209670447 U CN209670447 U CN 209670447U
Authority
CN
China
Prior art keywords
positioning
limit
pedestal
buried
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920358085.9U
Other languages
Chinese (zh)
Inventor
朱均凤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Andalu Heavy Industry Co Ltd
Original Assignee
Qingdao Andalu Heavy Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Andalu Heavy Industry Co Ltd filed Critical Qingdao Andalu Heavy Industry Co Ltd
Priority to CN201920358085.9U priority Critical patent/CN209670447U/en
Application granted granted Critical
Publication of CN209670447U publication Critical patent/CN209670447U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The utility model discloses a kind of quick-mounting formula electric power iron tower foundations, including three pre-buried pedestals in equilateral triangle distribution, it is connected between two neighboring pre-buried pedestal by balance connecting rod, it is connected between pre-buried pedestal and balance connecting rod by the first positioning plug-in unit, pre-buried base bottom edge is also equipped with the second positioning plug-in unit.The utility model forms steel tower bottom by three pre-buried pedestals in equilateral triangle distribution and stablizes brace foundation, by in pedestal casting concrete form extremely strong bearing capacity, the characteristics of stable structure, effectively improve service life, guarantee electric power tower using safe, structure is simple, easy for installation quick, has good practical and promotional value.

Description

A kind of quick-mounting formula electric power iron tower foundation
Technical field
The utility model belongs to electric power tower field, and in particular to a kind of quick-mounting formula electric power iron tower foundation.
Background technique
High-voltage power transmission line steel tower is pullled to resist wind load and defeated line equipment, prevents from toppling, need firm and stocky Basis.Not only volume is big for traditional iron tower foundation, and the steel material for needing to expend is more, and its bearing capacity is also not fully up to expectations, Basic stability can be lower as time goes by, and there is security risks.
Utility model content
The purpose of this utility model is to provide realize especially by following technical scheme:
A kind of quick-mounting formula electric power iron tower foundation, it is two neighboring pre-buried including three pre-buried pedestals in equilateral triangle distribution It is connected between pedestal by balance connecting rod, is connected between pre-buried pedestal and balance connecting rod by the first positioning plug-in unit, it is pre-buried Base bottom edge is also equipped with the second positioning plug-in unit;
The pre-buried pedestal includes support base and the pedestal for being mounted on support base center, and installation is limited among pedestal Position connection frame, limit connection frame center are connected by positioning bolt with support base, and limit connection frame side passes through the first limit Nut is connected with pedestal;
The pedestal includes two positioning rings of distribution symmetrical above and below, is along the circumferential direction evenly equipped with branch between two positioning rings Connecting rod is supportted, supporting linkage both ends are connected by the second stop nut with positioning ring;
The positioning ring surface is evenly equipped with positional punch, and supporting linkage both ends are symmetrically arranged with two positioning studs, support Connecting rod by-level is equipped with limit perforation, and positioning stud passes through positional punch and is connected with the second stop nut;
The limit connection frame includes the limit connecting screw for limiting central plate and being evenly arranged on limit central plate side, limit Position connecting screw passes through limit perforation and is connected with the first stop nut, and limit central plate center is equipped with center limit hole;Support bottom Seat includes support baseboard and the support post for being vertically set on support baseboard center, is equipped with positioning screw hole at the top of support post, Positioning bolt passes through center limit hole and is connected with positioning screw hole;Support baseboard marginal surface is set there are two the first positioning jack and one The angle of a second positioning jack, two the first positioning jacks and the connected straight line in support baseboard center is 60 degree, and two first fixed Position jack and second positioning jack are distributed in isosceles triangle;
The balance connecting rod both ends are symmetrically arranged with grafting perforation corresponding with the first positioning jack;First positioning plug-in unit Including positioning pluging rod, positioning pluging rod bottom end sequentially passes through grafting perforation, the first positioning jack is connected with cone-shaped plug, positioning pluging rod Top is equipped with limit jacking block;Second positioning plug-in unit includes the positioning intubation matched with the second positioning jack, positioning intubation top Equipped with annular stop protrusion.
It further, is to be slidably matched between second positioning jack and positioning intubation.
It further, is cunning between the positioning pluging rod and grafting perforation, between positioning pluging rod and the first positioning jack Dynamic cooperation.
Further, the sum of thickness of second stop nut and positioning ring is equal to the length of positioning stud.
The beneficial effects of the utility model are:
The utility model forms steel tower bottom by three pre-buried pedestals in equilateral triangle distribution and stablizes brace foundation, By in pedestal casting concrete form extremely strong bearing capacity, the characteristics of stable structure, effectively improve service life, guarantee Electric power tower using safe, structure is simple, it is easy for installation quickly, there is good practical and promotional value.
Detailed description of the invention
Attached drawing described herein is used to provide a further understanding of the present invention, and is constituted part of this application, Illustrative embodiments and their description of the invention do not constitute the improper limit to the utility model for explaining the utility model It is fixed.In the accompanying drawings:
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the partial structural diagram of the utility model;
Fig. 3 is the partial structural diagram of the utility model;
Fig. 4 is the partial structurtes explosive view of the utility model;
Fig. 5 is the partial structurtes explosive view of the utility model;
Fig. 6 is the partial structurtes explosive view of the utility model.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Referring to Fig. 1, a kind of quick-mounting formula electric power iron tower foundation, including three pre-buried pedestals 10 in equilateral triangle distribution, phase It is connected between adjacent two pre-buried pedestals 10 by balance connecting rod 20, passes through first between pre-buried pedestal 10 and balance connecting rod 20 It positions plug-in unit 30 to be connected, pre-buried 10 bottom margin of pedestal is also equipped with the second positioning plug-in unit 40;
Referring to fig. 2, pre-buried pedestal 10 including support base 1 and is mounted on the central pedestal 2 of support base 1, in pedestal 2 Between limit connection frame 3 is installed, limit connection frame 3 center is connected by positioning bolt 4 with support base 1, limit connection frame 3 weeks Side is connected by the first stop nut 5 with pedestal 2;
Referring to Fig. 3, two positioning rings 21 of pedestal 2 including distribution symmetrical above and below, circumferentially side between two positioning rings 21 To supporting linkage 22 is evenly equipped with, 22 both ends of supporting linkage are connected by the second stop nut 23 with positioning ring 21;
Referring to fig. 4,21 surface of positioning ring is evenly equipped with positional punch 211, and 22 both ends of supporting linkage are symmetrically arranged with two and determine Position stud 221,22 by-level of supporting linkage are equipped with limit perforation 222, and positioning stud 221 passes through positional punch 211 and the Two stop nuts 23 are connected;
Referring to Fig. 5, limiting connection frame 3 includes limit central plate 31 and the limit company for being evenly arranged on limit 31 side of central plate Screw rod 32 is connect, limit connecting screw 32 passes through limit perforation 222 and is connected with the first stop nut 5, and limit 31 center of central plate is set There is center limit hole 33;Support base 1 includes support baseboard 11 and the support post for being vertically set on 11 center of support baseboard 12, positioning screw hole 13 is equipped at the top of support post 12, positioning bolt 4 passes through center limit hole 33 and is connected with positioning screw hole 13;Branch Support 11 marginal surface of bottom plate is set there are two the first positioning jack 14 and second positioning jack 15, two the first positioning jacks 14 Angle with the connected straight line in 11 center of support baseboard is 60 degree, and two the first positioning jacks 14 and second positioning jack 15 are in Isosceles triangle distribution;
Referring to Fig. 6, balances 20 both ends of connecting rod and be symmetrically arranged with grafting perforation 201 corresponding with the first positioning jack 14; First positioning plug-in unit 30 includes positioning pluging rod 301, and 301 bottom end of positioning pluging rod sequentially passes through grafting the 201, first positioning jack of perforation 14 are connected with cone-shaped plug 302, and 301 top of positioning pluging rod is equipped with limit jacking block 303;Second positioning plug-in unit 40 includes determining with second The positioning intubation 401 that position jack 15 matches, 401 top of positioning intubation are equipped with annular stop protrusion 402.
Wherein, to be slidably matched between the second positioning jack 15 and positioning intubation 401, positioning pluging rod 301 and grafting are perforated Between 201, between positioning pluging rod 301 and the first positioning jack 14 be to be slidably matched, the second stop nut 23 and positioning ring 21 The sum of thickness be equal to the length of positioning stud 221.
The utility model forms steel tower bottom by three pre-buried pedestals in equilateral triangle distribution and stablizes brace foundation, By in pedestal casting concrete form extremely strong bearing capacity, the characteristics of stable structure, effectively improve service life, guarantee Electric power tower using safe, structure is simple, it is easy for installation quickly, there is good practical and promotional value.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (4)

1. a kind of quick-mounting formula electric power iron tower foundation, it is characterised in that: three pre-buried pedestals (10) including being in equilateral triangle distribution, Between two neighboring pre-buried pedestal (10) by balance connecting rod (20) be connected, pre-buried pedestal (10) and balance connecting rod (20) it Between by first positioning plug-in unit (30) be connected, pre-buried pedestal (10) bottom margin is also equipped with the second positioning plug-in unit (40);
The pre-buried pedestal (10) includes support base (1) and the pedestal (2) for being mounted on support base (1) center, pedestal (2) Centre is equipped with limit connection frame (3), and limit connection frame (3) center is connected with support base (1) by positioning bolt (4), is limited Position connection frame (3) side is connected by the first stop nut (5) with pedestal (2);
The pedestal (2) includes two positioning rings (21) of distribution symmetrical above and below, between two positioning rings (21) along the circumferential direction It is evenly equipped with supporting linkage (22), supporting linkage (22) both ends are connected by the second stop nut (23) with positioning ring (21);
Positioning ring (21) surface is evenly equipped with positional punch (211), and supporting linkage (22) both ends are symmetrically arranged with two positioning Stud (221), supporting linkage (22) by-level are equipped with limit perforation (222), and positioning stud (221) passes through positional punch (211) it is connected with the second stop nut (23);
Limit connection frame (3) includes limit central plate (31) and the limit connection for being evenly arranged on limit central plate (31) side Screw rod (32), limit connecting screw (32) pass through limit perforation (222) and are connected with the first stop nut (5), limit central plate (31) center is equipped with center limit hole (33);Support base (1) includes support baseboard (11) and is vertically set on support baseboard (11) central support post (12), support post (12) top are equipped with positioning screw hole (13), and positioning bolt (4) is limited across center Position hole (33) is connected with positioning screw hole (13);Support baseboard (11) marginal surface is set there are two the first positioning jack (14) and one The angle of second positioning jack (15), two the first positioning jacks (14) and the connected straight line in support baseboard (11) center is 60 degree, Two the first positioning jacks (14) and second positioning jack (15) are distributed in isosceles triangle;
Balance connecting rod (20) both ends are symmetrically arranged with grafting perforation (201) corresponding with the first positioning jack (14);The One positioning plug-in unit (30) includes positioning pluging rod (301), and positioning pluging rod (301) bottom end sequentially passes through grafting perforation (201), first fixed Position jack (14) is connected with cone-shaped plug (302), and positioning pluging rod (301) top is equipped with limit jacking block (303);Second positioning plug-in unit (40) include the positioning intubation (401) matched with the second positioning jack (15), be equipped with annular stop at the top of positioning intubation (401) Raised (402).
2. a kind of quick-mounting formula electric power iron tower foundation according to claim 1, it is characterised in that: second positioning jack It (15) is to be slidably matched between positioning intubation (401).
3. a kind of quick-mounting formula electric power iron tower foundation according to claim 1, it is characterised in that: the positioning pluging rod (301) Between grafting perforation (201), between positioning pluging rod (301) and the first positioning jack (14) be to be slidably matched.
4. a kind of quick-mounting formula electric power iron tower foundation according to claim 1, it is characterised in that: second stop nut (23) it is equal to the length of positioning stud (221) with the sum of the thickness of positioning ring (21).
CN201920358085.9U 2019-03-20 2019-03-20 A kind of quick-mounting formula electric power iron tower foundation Active CN209670447U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920358085.9U CN209670447U (en) 2019-03-20 2019-03-20 A kind of quick-mounting formula electric power iron tower foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920358085.9U CN209670447U (en) 2019-03-20 2019-03-20 A kind of quick-mounting formula electric power iron tower foundation

Publications (1)

Publication Number Publication Date
CN209670447U true CN209670447U (en) 2019-11-22

Family

ID=68572199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920358085.9U Active CN209670447U (en) 2019-03-20 2019-03-20 A kind of quick-mounting formula electric power iron tower foundation

Country Status (1)

Country Link
CN (1) CN209670447U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112593760A (en) * 2020-10-22 2021-04-02 国网山东省电力公司汶上县供电公司 Electric power tower convenient to install

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112593760A (en) * 2020-10-22 2021-04-02 国网山东省电力公司汶上县供电公司 Electric power tower convenient to install
CN112593760B (en) * 2020-10-22 2022-03-04 国网山东省电力公司汶上县供电公司 Electric power tower convenient to install

Similar Documents

Publication Publication Date Title
CN103132766B (en) Truss for lifting power transmission line tower connecting leg and erection method
CN209670447U (en) A kind of quick-mounting formula electric power iron tower foundation
CN211500013U (en) Reinforcing apparatus of single-pipe tower
CN205046911U (en) Triangle -shaped section steel pylons
CN210873828U (en) Suspension device of safety belt
CN202390088U (en) 220kv adjustable triangular holding pole
CN204897250U (en) Be suitable for small -size tower crane that uses in transformer substation
CN107559325A (en) A kind of bearing block of adjustable setting height(from bottom)
CN110311319B (en) Combined box-type substation
CN219910251U (en) Municipal construction is facility installation device along line
CN102134959A (en) Ladder leg stabilizer capable of adjusting support area
CN213064864U (en) Adjustable bottom support device for gas pipeline
CN205118450U (en) Concrete pump pipe fixing device
CN202322122U (en) Tower crane and foundation transition device thereof
CN212078878U (en) Communication tower fixing base for electronic information engineering
CN210263374U (en) Assembled steel structure frame and assembled steel structure house
CN207092670U (en) The skewed horizontal load of transformer station's outlet structure
CN202978141U (en) Combination support
CN221277375U (en) Fixed support equipment is used in construction of full prefabricated assembled transformer substation
CN219472252U (en) Position self-adjusting assembly of tower barrel
CN212359287U (en) Steep slope iron tower leg heightening structure
CN221346250U (en) Integral temporary pier operation platform
CN210756154U (en) Pipeline supporting frame capable of being positioned and adjusted
CN212836964U (en) Power transformation framework
CN211736264U (en) Civil engineering construction support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant