CN209636837U - Pile foundation cast-in-place concrete caisson - Google Patents

Pile foundation cast-in-place concrete caisson Download PDF

Info

Publication number
CN209636837U
CN209636837U CN201920010341.5U CN201920010341U CN209636837U CN 209636837 U CN209636837 U CN 209636837U CN 201920010341 U CN201920010341 U CN 201920010341U CN 209636837 U CN209636837 U CN 209636837U
Authority
CN
China
Prior art keywords
place concrete
pile foundation
cast
concrete caisson
drainage layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920010341.5U
Other languages
Chinese (zh)
Inventor
顾文华
张彬
张鹏飞
盖明宇
宁世欣
李萌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201920010341.5U priority Critical patent/CN209636837U/en
Application granted granted Critical
Publication of CN209636837U publication Critical patent/CN209636837U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)

Abstract

The utility model is a kind of pile foundation cast-in-place concrete caisson, it is placed in a foundation pit, it is from the bottom to top sequentially that drainage layer, separation layer, caisset and bed course are constituted, the drainage layer is partial size stone, the separation layer is geotextiles, caisset includes plank sheathing, square steel tube, round steel pipe, steel sleeve, wherein, plank sheathing is primary structure, square steel tube is as formwork reinforcement secondary joist, round steel pipe is as formwork reinforcement main joist, and steel sleeve is in insertion drainage layer, and the bed course is high design strength concrete;The basic cast-in-place concrete caisset of the utility model is simple, easily operated, can effectively solve because level of ground water is higher to be constructed the phenomenon that.

Description

Pile foundation cast-in-place concrete caisson
Technical field
The utility model belongs to field of civil engineering, specially a kind of pile foundation cast-in-place concrete caisson.
Background technique
Concrete caisson is usually used in the more complicated muddy water hole of geological condition, drift sand hole, need to take routine to be a kind of The indeterminable foundation construction of Yield rainfall relation measure, existing construction site is located at seashore, and level of ground water is higher, lead to not into Row waterproof slab and subsequent job construction, so applicant develops a kind of new technology, to guarantee operation side.
Utility model content
In view of the deficiencies of the prior art, above-mentioned to solve the problems, such as, the utility model proposes a kind of pile foundation is cast-in-place Concrete caisson is mainly used in coastal area and the higher place of level of ground water, and the utility model structure is simple, is easy to grasp Make, can effectively solve because level of ground water is higher to be constructed the phenomenon that.
To achieve the above object, the utility model provides a kind of pile foundation cast-in-place concrete caisson, is placed in a foundation pit, It is characterized in that, is from the bottom to top sequentially that drainage layer, separation layer, caisset and bed course are constituted, the drainage layer is partial size Stone, the separation layer are geotextiles, and caisset includes plank sheathing, square steel tube, round steel pipe, steel sleeve, wherein wooden model Plate is primary structure, and square steel tube is as formwork reinforcement secondary joist, and for round steel pipe as formwork reinforcement main joist, steel sleeve is insertion In drainage layer, the bed course is high design strength concrete.
Preferably, the pile foundation cast-in-place concrete caisson, wherein the drainage layer is 3-5cm partial size stone Son.
Preferably, the pile foundation cast-in-place concrete caisson, wherein the size of the plank sheathing be 1830 × 915×14mm。
Preferably, the pile foundation cast-in-place concrete caisson, wherein the square steel tube is 40 × 40mm, each side The spacing 200mm of steel pipe.
Preferably, the pile foundation cast-in-place concrete caisson, wherein the round steel pipe is φ 48mm, each round steel Tube spacing 450mm.
Preferably, the pile foundation cast-in-place concrete caisson, wherein the steel sleeve is wall thickness 10mm, diameter 800mm。
A kind of pile foundation cast-in-place concrete caisson provided by the utility model, the beneficial effect is that, the utility model Basic cast-in-place concrete caisset is simple, easily operated, can effectively solve to construct because level of ground water is higher Phenomenon.
Detailed description of the invention
Figure 1A, 1B are the top view of the pile foundation cast-in-place concrete caisson of the utility model.
Fig. 2 is the cross-sectional view of the pile foundation cast-in-place concrete caisson 1-1 of Figure 1A, 1B.
Fig. 3 is the cross-sectional view of the pile foundation cast-in-place concrete caisson 2-2 of Figure 1A, 1B.
Fig. 4 is the cross-sectional view of the pile foundation cast-in-place concrete caisson 3-3 of Figure 1A, 1B.
Fig. 5 A, 5B are the construction schematic diagram of the pile foundation cast-in-place concrete caisson of the utility model.
Fig. 6 is the completion schematic diagram of the pile foundation cast-in-place concrete caisson of the utility model.
Specific embodiment
The preferred embodiment for cooperating schema and the utility model below, it is to reach to make a reservation in fact that the utility model, which is further described, The technological means taken with novel purpose.
The utility model provides a preferred embodiment, and as shown in Figure 1A, 1B to Fig. 6, the utility model is a kind of pile foundation Cast-in-place concrete caisson is placed in a foundation pit 10, is from the bottom to top sequentially drainage layer 20, separation layer 30, caisset 40 and pad Layer is constituted, and the drainage layer 20 is 3-5cm partial size stone, and the separation layer 30 is 200g/ ㎡ specification geotextiles, caisson Structure 40 includes plank sheathing, square steel tube, round steel pipe, steel sleeve, wherein the size of plank sheathing is 1830 × 915 × 14mm, side Steel pipe is 40 × 40mm, and as formwork reinforcement secondary joist, the spacing 200mm of each square steel tube, round steel pipe is φ 48mm, as template Main joist, each round steel tube spacing 450mm are reinforced, steel sleeve is wall thickness 10mm, diameter 800mm, steel bushing bottom of the tube insertion drainage layer In, the bed course is high design strength concrete (bleed resistance rust concrete is shunk in the early strong compensation of C30P6).
Complete that bottom surveying setting-out, earth excavation, template installation is reinforced, concrete changes after each process such as filling out, basis is cast-in-place The working procedure and technique of concrete caisson are as follows:
1, catch pit, elevator contour line are released;
2, according to drawing, catch pit, elevator are excavated;
3, it is excavating in the foundation pit completed, filling 500mm high 3cm-5cm stone is as drainage layer 2, stone top, lower section Geotextiles are laid with as separation layer 3, prevents concrete grout, soil from flowing into stone, influences concrete quality;
4, after the completion of stone is laid with, start template construction;
5, after the completion of formwork reinforcement, on the outside of template between the earthwork, diameter 800mm, wall thickness 2mm steel pipe, under steel pipe are placed Electric drill perforating within the scope of 1.5m is held, placement water pump, which does not rest, to draw water;
6, after the completion of steel pipe is placed, using high design strength concrete, (bleed resistance rust coagulation is shunk in the early strong compensation of C30P6 Soil) it is poured;
7, paving waterproof slab on the inside of caisson, pour the construction of the processes such as waterproof protective layer, assembling reinforcement;
8, when underplate concrete pours, the water pump of placement is taken out, will be poured in steel pipe using underplate concrete closely knit Steel pipe after the completion of pouring, is buckled using 1cm thickness 1m × 1m steel plate and carries out welded closure, can be completed and complete caisson knot by concrete Structure 4 is constructed.
The basic cast-in-place concrete caisset of the utility model is simple, easily operated, can effectively solve because of level of ground water It is higher and the phenomenon that can not be constructed.
The above is only the preferred embodiment of the utility model, is not done in any form to the utility model Limitation, although the utility model is disclosed above with preferred embodiment, is not intended to limit the utility model, any to be familiar with Professional and technical personnel, in the range of not departing from technical solutions of the utility model, when in the technology using the disclosure above Hold the equivalent embodiment made a little change or be modified to equivalent variations, but all without departing from technical solutions of the utility model Hold, any simple modification, equivalent change and modification made by the above technical examples according to the technical essence of the present invention, still It is within the scope of the technical solutions of the present invention.

Claims (6)

1. a kind of pile foundation cast-in-place concrete caisson, is placed in a foundation pit, which is characterized in that be sequentially from the bottom to top drainage layer, Separation layer, caisset and bed course are constituted, and the drainage layer is partial size stone, and the separation layer is geotextiles, caisson Structure includes plank sheathing, square steel tube, round steel pipe, steel sleeve, wherein plank sheathing is primary structure, and square steel tube is as template Secondary joist is reinforced, round steel pipe is as formwork reinforcement main joist, and steel sleeve is in insertion drainage layer, and the bed course is that high design is strong Spend concrete.
2. pile foundation cast-in-place concrete caisson according to claim 1, which is characterized in that the drainage layer is 3-5cm Partial size stone.
3. pile foundation cast-in-place concrete caisson according to claim 1, which is characterized in that the size of the plank sheathing is 1830×915×14mm。
4. pile foundation cast-in-place concrete caisson according to claim 1, which is characterized in that the square steel tube be 40 × 40mm, the spacing 200mm of each square steel tube.
5. pile foundation cast-in-place concrete caisson according to claim 1, which is characterized in that the round steel pipe is φ 48mm, each round steel tube spacing 450mm.
6. pile foundation cast-in-place concrete caisson according to claim 1, which is characterized in that the steel sleeve is wall thickness 10mm, diameter 800mm.
CN201920010341.5U 2019-01-04 2019-01-04 Pile foundation cast-in-place concrete caisson Active CN209636837U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920010341.5U CN209636837U (en) 2019-01-04 2019-01-04 Pile foundation cast-in-place concrete caisson

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920010341.5U CN209636837U (en) 2019-01-04 2019-01-04 Pile foundation cast-in-place concrete caisson

Publications (1)

Publication Number Publication Date
CN209636837U true CN209636837U (en) 2019-11-15

Family

ID=68477019

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920010341.5U Active CN209636837U (en) 2019-01-04 2019-01-04 Pile foundation cast-in-place concrete caisson

Country Status (1)

Country Link
CN (1) CN209636837U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111088842A (en) * 2019-12-30 2020-05-01 倡创(上海)咨询管理事务所 Comprehensive treatment construction method combining seepage prevention and drainage of foundation pit of elevator shaft

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111088842A (en) * 2019-12-30 2020-05-01 倡创(上海)咨询管理事务所 Comprehensive treatment construction method combining seepage prevention and drainage of foundation pit of elevator shaft

Similar Documents

Publication Publication Date Title
CN205742213U (en) Foundation pit supporting construction
CN105672348A (en) Construction method for cropping bridge pile foundation at sandy gravel stratum of abyssal region
CN106958256A (en) A kind of placement layer by layer, the open caisson construction technique repeatedly sunk
CN103821219A (en) Top pipe construction modification inspection well construction method
CN104846841B (en) Anti-floating construction method for basements without uplift piles
CN104895055A (en) Building grouting pile foundation construction method
CN104452829A (en) Piled raft foundation anti-floating structure and construction method
CN111395330B (en) Construction method for concrete cast-in-situ bored pile complete steel casing penetrating through underground gallery
CN107246005A (en) Super-large diameter bores and buries steel pipe hollow foundation pile and its construction method
CN101787701B (en) Construction method for supporting pine pile in elevator shaft foundation pit
CN104480929B (en) A kind of pile wall interaction construction method that interlocking pile is applied to permanent outer wall of basement
CN106245654B (en) Deposited reinforced concrete pile exempts from inter-pile soil excavation construction method
CN102926400A (en) Combined earth retaining wall structure and construction method thereof
CN111705786A (en) Method for vertical combination construction of composite stratum underground continuous wall and cast-in-situ bored pile
CN110670631A (en) Supporting structure and excavation method of comprehensive pipe gallery foundation pit
CN107326898B (en) I-shaped precast pile supporting structure with adjustable inserted rigidity in cement-soil wall and construction method thereof
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN109723055B (en) Underground diaphragm wall bottom reinforcing structure and construction method thereof
CN105155575B (en) Non-excavation cantilever retaining wall with embedded steel pipe and construction method of non-excavation cantilever retaining wall
CN110080779A (en) Tunnel tunnel bottom karst cave treatment construction method
CN209636837U (en) Pile foundation cast-in-place concrete caisson
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN113216215A (en) Deep groove support reverse construction method in complex environment
CN110805049B (en) Construction method of mountain slope ultra-thickness spray anchor permanent supporting structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant