CN209587384U - A kind of steel bell structure connecing Prestressed concrete cylinder pipe - Google Patents

A kind of steel bell structure connecing Prestressed concrete cylinder pipe Download PDF

Info

Publication number
CN209587384U
CN209587384U CN201920142376.4U CN201920142376U CN209587384U CN 209587384 U CN209587384 U CN 209587384U CN 201920142376 U CN201920142376 U CN 201920142376U CN 209587384 U CN209587384 U CN 209587384U
Authority
CN
China
Prior art keywords
steel
plate
ring flat
transition ring
cylinder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920142376.4U
Other languages
Chinese (zh)
Inventor
张钰
穆迅
赵昕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Water Planning Survey and Design Co., Ltd
Original Assignee
TIANJIN WATER RESOURCES SURVEY AND DESIGN INSTITUTE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN WATER RESOURCES SURVEY AND DESIGN INSTITUTE filed Critical TIANJIN WATER RESOURCES SURVEY AND DESIGN INSTITUTE
Priority to CN201920142376.4U priority Critical patent/CN209587384U/en
Application granted granted Critical
Publication of CN209587384U publication Critical patent/CN209587384U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rigid Pipes And Flexible Pipes (AREA)

Abstract

The utility model discloses a kind of steel bell structure for connecing Prestressed concrete cylinder pipe; including internal layer steel construction and outer protective layer; the internal layer steel construction includes the steel cylinder of cylindrical shape and the transition ring flat-plate for being welded on described steel cylinder one end; the transition ring flat-plate and socket hoop are welded to connect, and the floor that reinforcement is welded at the position in L shape portion is formed by between the transition ring flat-plate and the steel cylinder;The outer protective layer include the steel fabric sheet being laid on outside the internal layer steel construction and be sprayed on the steel fabric sheet it is outer by the steel fabric sheet be coated in predetermined thickness cement mortar.The rigidity of structure that the floor of steel bellmouth and reinforcement, reinforced concrete floor is collectively formed in the utility model increases, and deformation is almost the same with corresponding Prestressed concrete cylinder pipe socket after by native load action, avoids deformation inconsistent the problem of causing leak.

Description

A kind of steel bell structure connecing Prestressed concrete cylinder pipe
Technical field
The utility model relates to a kind of steel bell structures for connecing Prestressed concrete cylinder pipe.
Background technique
Prestressed concrete cylinder pipe (PCCP pipe) is to be twined using the strong concrete tube core with steel cylinder as liner The water-supply-pipe that fine and close cement mortar protective course is formed is sprayed after ring orientation prestress steel wire, general every root canal is 5-6 meters long.But it is right Landform adaptability is weaker, generallys use steel pipe in topography variation section and is laid with, to make Prestressed concrete cylinder pipe road and steel pipe It is linked to be water delivery line, generally requires between steel pipe and cylinder concrete pipe and connected using bell and spigot.Wherein socket is and tube body one Rise it is molding, the steel bellmouth of lengths of steel pipes generally uses steel plate welding fabrication.But since the steel plate of welding fabrication is than relatively thin, rigidity Small, the effect deformation ratio Prestressed concrete cylinder pipe socket by native load is big, causes gap at bell and spigot to become larger, leak occurs Situation.
Utility model content
The purpose of this utility model is to be directed to technological deficiency existing in the prior art, and provide one kind and connect pre-stress steel cylinder The steel bell structure of pipe of concrete.
It is for technical solution used by realization the purpose of this utility model:
A kind of steel bell structure connecing Prestressed concrete cylinder pipe, including internal layer steel construction and outer protective layer, The internal layer steel construction includes cylindric steel cylinder and the transition ring flat-plate for being welded on described steel cylinder one end, the transition ring flat-plate with Socket hoop is welded to connect, and the internal diameter of the transition ring flat-plate is consistent with the internal diameter of the steel cylinder and outer diameter is greater than the outer of the steel cylinder Diameter, the internal diameter of the socket hoop is greater than the internal diameter of the transition ring flat-plate and outer diameter is less than the outer diameter of the transition ring flat-plate, the mistake Cross the floor that reinforcement is welded at the position for being formed by L shape portion between ring flat-plate and the steel cylinder;The outer protective layer packet It includes the steel fabric sheet being laid on outside the internal layer steel construction and is sprayed on outside the steel fabric sheet and coat the steel fabric sheet The cement mortar of predetermined thickness inside.
The outer protective layer forms the first inclined plane part, transition part and the second inclined plane part in the position of corresponding steel bellmouth, First inclined plane part and the second inclined plane part are connected by the transition part, the medial surface and the rib of first inclined plane part One end of plate is connected, and the outboard end of second inclined plane part is connected with the end face of the socket hoop.
The floor be it is multiple, uniform intervals are arranged at the position in L shape portion.
The transition ring flat-plate, steel pipe and socket hoop are coaxially arranged mounting connection structure.
Compared with prior art, the utility model has the beneficial effects that
The rigidity of structure that the floor of steel bellmouth and reinforcement, reinforced concrete floor is collectively formed in the utility model increases Greatly, deformation is almost the same with corresponding socket after by native load action, avoids deformation inconsistent the problem of causing leak.
Detailed description of the invention
Fig. 1 is the schematic diagram of the steel bell structure for connecing Prestressed concrete cylinder pipe of the utility model.
Specific embodiment
The utility model is described in further detail below in conjunction with the drawings and specific embodiments.It should be appreciated that this place The specific embodiment of description is only used to explain the utility model, is not used to limit the utility model.
As shown in Figure 1, a kind of steel bell structure for connecing Prestressed concrete cylinder pipe of the utility model, including internal layer Steel construction 1 and outer protective layer 2, the internal layer steel construction include cylindric steel cylinder and are welded on described steel cylinder one end Transition ring flat-plate 5, the transition ring flat-plate and socket hoop 6 are welded to connect, the internal diameter of the transition ring flat-plate and the internal diameter one of the steel cylinder It causes and outer diameter is greater than the outer diameter of the steel cylinder, the internal diameter of the socket hoop is greater than the internal diameter of the transition ring flat-plate and outer diameter is less than institute The outer diameter of transition ring flat-plate is stated, is formed by between the transition ring flat-plate and the steel cylinder at the position in L shape portion and is welded with reinforcement use Floor 7;The outer protective layer includes the steel fabric sheet 3 that winding is laid on outside the internal layer steel construction and is sprayed on described The outer cement mortar 4 that the steel fabric sheet is coated on to interior predetermined thickness of steel fabric sheet.
Wherein, the transition ring flat-plate, steel pipe and socket hoop are coaxially arranged mounting connection structure.
Wherein, the outer protective layer forms the first inclined plane part 9 in the position of corresponding steel bellmouth, and transition part is with 11 and the Two inclined plane parts 10, first inclined plane part and the second inclined plane part are connected by the transition part, first inclined plane part it is interior Side is connected with one end of the floor, and the outboard end of second inclined plane part is connected with the end face of the socket hoop.
Wherein, the floor is multiple, and uniform intervals are arranged at the position in L shape portion, for example eight pieces, ontology three Horn shape connect with the steel cylinder and connect with transition ring flat-plate for convenience, with the mating connection of outer protective layer, corresponding three The corner at a angle end is cut off, and to increase welding contact area, or prevents from destroying outer protective layer.
The steel bell structure for connecing cylinder concrete pipe of the utility model, by welding excessive 5 He of ring flat-plate on steel cylinder After socket hoop 6 forms steel bellmouth 8, first is that increasing floor 7 outside the excessive ring of steel bellmouth to adjust bellmouth steel loop stress, floor 7 is uniformly distributed using 8 pieces of steel plate;Reinforce second is that spraying fine and close cement mortar after being laid with steel fabric sheet 3 outside steel bellmouth 8 and floor 7 Layer forms protective layer, plays protective layer 2 and increases thickness, to achieve the purpose that increase rigidity.In this way, steel bellmouth and floor, The rigidity of structure that reinforced concrete floor is collectively formed increases, and deforms and corresponding Prestressed concrete cylinder pipe after by native load action Socket is almost the same, avoids deformation inconsistent the problem of causing leak.
The above is only the preferred embodiment of the utility model, it is noted that for the general of the art For logical technical staff, without departing from the principle of this utility model, several improvements and modifications can also be made, these change It also should be regarded as the protection scope of the utility model into retouching.

Claims (4)

1. a kind of steel bell structure for connecing Prestressed concrete cylinder pipe, which is characterized in that including internal layer steel construction and outside Layer protective layer, the internal layer steel construction include cylindric steel cylinder and the transition ring flat-plate for being welded on described steel cylinder one end, described Transition ring flat-plate and socket hoop are welded to connect, and the internal diameter of the transition ring flat-plate is consistent with the internal diameter of the steel cylinder and outer diameter is greater than described in The outer diameter of steel cylinder, the internal diameter of the socket hoop is greater than the internal diameter of the transition ring flat-plate and outer diameter is less than the outer of the transition ring flat-plate Diameter is formed by the floor that reinforcement is welded at the position in L shape portion between the transition ring flat-plate and the steel cylinder;The outer layer Protective layer includes the steel fabric sheet being laid on outside the internal layer steel construction and is sprayed on the steel wire outside the steel fabric sheet Mesh sheet is coated on the cement mortar of interior predetermined thickness.
2. connecing the steel bell structure of Prestressed concrete cylinder pipe as described in claim 1, which is characterized in that the outer layer is protected Sheath forms the first inclined plane part, transition part and the second inclined plane part in the position of corresponding steel bellmouth, first inclined plane part and Second inclined plane part is connected by the transition part, and the medial surface of first inclined plane part is connected with one end of the floor, institute The outboard end for stating the second inclined plane part is connected with the end face of the socket hoop.
3. connecing the steel bell structure of Prestressed concrete cylinder pipe as described in claim 1, which is characterized in that the floor is Multiple, uniform intervals are arranged at the position in L shape portion.
4. connecing the steel bell structure of Prestressed concrete cylinder pipe as described in claim 1, which is characterized in that the transition Ring flat-plate, steel pipe and socket hoop are coaxially arranged mounting connection structure.
CN201920142376.4U 2019-01-28 2019-01-28 A kind of steel bell structure connecing Prestressed concrete cylinder pipe Active CN209587384U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920142376.4U CN209587384U (en) 2019-01-28 2019-01-28 A kind of steel bell structure connecing Prestressed concrete cylinder pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920142376.4U CN209587384U (en) 2019-01-28 2019-01-28 A kind of steel bell structure connecing Prestressed concrete cylinder pipe

Publications (1)

Publication Number Publication Date
CN209587384U true CN209587384U (en) 2019-11-05

Family

ID=68380892

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920142376.4U Active CN209587384U (en) 2019-01-28 2019-01-28 A kind of steel bell structure connecing Prestressed concrete cylinder pipe

Country Status (1)

Country Link
CN (1) CN209587384U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116146802A (en) * 2023-02-22 2023-05-23 水利部交通运输部国家能源局南京水利科学研究院 Prestressed steel cylinder concrete pipe connecting structure and installation method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116146802A (en) * 2023-02-22 2023-05-23 水利部交通运输部国家能源局南京水利科学研究院 Prestressed steel cylinder concrete pipe connecting structure and installation method
CN116146802B (en) * 2023-02-22 2023-08-29 水利部交通运输部国家能源局南京水利科学研究院 Prestressed steel cylinder concrete pipe connecting structure and installation method

Similar Documents

Publication Publication Date Title
CN205877455U (en) Prestressing force steel cylinder concrete pipe
CN209587384U (en) A kind of steel bell structure connecing Prestressed concrete cylinder pipe
CN204062217U (en) A kind of embed-type cylinder concrete pipe carrying direct drinking
CN105909885A (en) Prestressed cylinder concrete and plastic composite pipe and construction method thereof
JP5202768B2 (en) Synthetic resin pipe with joint and its connection structure
CN206299921U (en) Pipeline
CN207343720U (en) A kind of core rod of the flanged hollow cast steel thin-winding pipe casting mould in both ends
CN207333993U (en) Heavy caliber anticracking PE is managed
CN108953781A (en) A kind of reinforcing bar winding steel cylinder pressure pipe and aqueduct
CN108916512A (en) A kind of glass steel storage tank adapter tube with Wrapping formed panel reinforcement
CN209213217U (en) A kind of reinforcing bar winding steel cylinder pressure pipe and aqueduct
CN209705444U (en) Double-walled internal-rib fiberglass sandwich concrete high-strength degree compound pipeline complex pipeline
CN204062218U (en) A kind of lined cylinder concrete pipe carrying direct drinking
CN102235558A (en) Steel fiber reinforced concrete pipe with ribbed thin wall
WO2021003861A1 (en) Textile-reinforced concrete-steel pipe-frp composite pipe and manufacturing method therefor
CN205745700U (en) A kind of prestress steel cylinder concrete and compound plastic pipe
CN205919021U (en) Inside lining formula prestressing force steel cylinder concrete pipe with full anticorrosive coating of glass steel
CN105065796A (en) Prestressed concrete PE steel sleeve pipe
CN104896208A (en) Novel hydropower station giant pressure pipeline
CN216158498U (en) Prestressed concrete cylinder pipe and prestressed concrete pipe
CN220414641U (en) Dome opening structure of air film bin
CN201373180Y (en) Unbonded prestressed concrete pipe
CN217519395U (en) Lining steel pipe
CN210316623U (en) Exposed steel bar protection structure of concrete pouring structure
CN201028146Y (en) Steel faucet steel cylinder longitudinal rib prestressed concrete pipe

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 300204 No. 217 Racecourse Road, Tianjin, Hexi District

Patentee after: Tianjin Water Planning Survey and Design Co., Ltd

Address before: 300204 No. 217 Racecourse Road, Tianjin, Hexi District

Patentee before: TIANJIN WATER RESOURCES SURVEY AND DESIGN INSTITUTE