CN209583418U - Hanging device - Google Patents

Hanging device Download PDF

Info

Publication number
CN209583418U
CN209583418U CN201822273486.2U CN201822273486U CN209583418U CN 209583418 U CN209583418 U CN 209583418U CN 201822273486 U CN201822273486 U CN 201822273486U CN 209583418 U CN209583418 U CN 209583418U
Authority
CN
China
Prior art keywords
tunnel
supporting part
lifting
hanging device
support bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822273486.2U
Other languages
Chinese (zh)
Inventor
李占先
王焕
宋德果
贾开民
赵海涛
陈爽
高始军
刘磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 14th Bureau Group Co Ltd
Original Assignee
China Railway 14th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 14th Bureau Group Co Ltd filed Critical China Railway 14th Bureau Group Co Ltd
Priority to CN201822273486.2U priority Critical patent/CN209583418U/en
Application granted granted Critical
Publication of CN209583418U publication Critical patent/CN209583418U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model provides a kind of hanging device.The hanging device includes supporting part, support portion, running part and lifting portion, length direction of the supporting part along tunnel is extended, support portion is multiple, length direction of multiple support portions along tunnel is positioned apart from, multiple support portions are connected with supporting part, at least one of running part and multiple support portions are connected, so that running part drives corresponding support portion to move in tunnel, lifting portion is movably connected with supporting part, lifting portion is for lifting inverted arch prefabricated section, lifting portion is used to inverted arch prefabricated section being moved to predeterminated position along the length direction in tunnel or the width direction in tunnel.By the way that running part is arranged on support portion, to drive supporting part mobile, and lifting portion is movably disposed on supporting part, and the displacement on opposite tunnel width direction and length of tunnel direction can be generated by supporting part, so that inverted arch prefabricated section can neatly be placed predeterminated position by lifting portion, the efficiency of installation is improved.

Description

Hanging device
Technical field
The utility model relates to tunnel equipment technology field of transport, in particular to a kind of hanging device.
Background technique
Component part of the tunnel inverted arch as liner structure plays a significant role to supporting and protecting system of tunnel stabilization.Inverted arch Digging process be into tunnel process be easy cause safety accident stage, inverted arch build quality more with the hair of tunnel defect Raw rate is closely bound up.In recent years, the special line for passenger trains tunnel excavation section built is big, and working procedure is cumbersome, tunnel structure by Power is also increasingly complex, especially most complicated with tunnel inverted arch portion, and abutment wall bottom and inverted arch junction stress are relatively concentrated, simultaneously as tunnel Inverted arch structure, which is in for a long time under Train induced load effect and groundwater erosion adverse circumstances, to be highly prone to destroy, and causes substrate heavy Fall into, railway roadbed such as is risen soil at the diseases, influence operation security, traditional inverted arch builds technology, and oneself is extremely difficult to safety, durability With the high request of waterproofness.
However, inverted arch component, because itself is thick and heavy, existing haulage equipment is difficult to flexibly transport inverted arch component in tunnel Need destination locations to be mounted.
Utility model content
The main purpose of the utility model is to provide a kind of hanging devices, to solve to be difficult in tunnel in the prior art Flexibly the problem of transport inverted arch component.
To achieve the goals above, one aspect according to the present utility model provides a kind of hanging device, comprising: hold Load portion, length direction of the supporting part along tunnel are extended;Support portion, support portion are multiple, length of multiple support portions along tunnel Degree direction is positioned apart from, and multiple support portions are connected with supporting part;In running part, running part and multiple support portions at least One is connected, so that running part drives corresponding support portion to move in tunnel;Lifting portion, lifting portion and supporting part are removable Ground is connected, and lifting portion is used for inverted arch prefabricated section for lifting inverted arch prefabricated section, lifting portion along the length direction or tunnel in tunnel The width direction in road is moved to predeterminated position.
Further, supporting part includes the first load bearing beam and the second load bearing beam, the first load bearing beam and the equal edge of the second load bearing beam The length direction in tunnel is extended, and the width direction of the first load bearing beam and the second load bearing beam along tunnel is positioned apart from, and first Attachment beam is provided between load bearing beam and the second load bearing beam.
Further, it is provided with the first sliding rail on the first load bearing beam, the second sliding rail, lifting portion are provided on the second load bearing beam It is cooperatively connected with the first sliding rail and the second sliding rail.
Further, lifting portion includes: lifting pedestal, lifts pedestal and the first sliding rail and the second sliding rail is cooperatively connected, hang Filling pedestal has traverse rod, and width direction of the traverse rod along tunnel is arranged;Ontology is lifted, lifting ontology and traverse rod are cooperatively connected, lifting Ontology is movably disposed along traverse rod.
Further, multiple support portions include: the first support portion, and the first end of the first support portion is connected with supporting part, The second end of first support portion is connected with running part;Second support portion, the second support portion and the first support portion interval are arranged, the The first end of two support portions is connected with supporting part, and the second end of the second support portion and the ground in tunnel touch.
Further, the first support portion includes: the first upper support bar, and the first upper support bar is to prop up on two, two first Strut is oppositely disposed in the two sides of supporting part, and two the first upper support bars are connected with supporting part;First lower support bar, the One lower support bar is two, and two the first lower support bars are arranged correspondingly with two the first upper support bars, under two first Support rod is connected with running part, and the first receiving portion is offered on the first lower support bar, and the first upper support bar is movably set It is placed in the first receiving portion of corresponding first lower support bar;First driving portion, the first driving portion are two, two first drives Dynamic portion is arranged and connect correspondingly with two the first lower support bars, two the first driving portions and two the first upper support bars one One is accordingly drivingly connected.
Further, the second support portion includes: the second upper support bar, and the second upper support bar is to prop up on two, two second Strut is oppositely disposed in the two sides of supporting part, and two the second upper support bars are connected with supporting part;Second lower support bar, the Two lower support bars are two, and two the second upper support bars are arranged correspondingly with two the second lower support bars, the second lower support The second receiving portion is offered on bar, the second upper support bar is movably disposed in the second receiving of corresponding second lower support bar In portion;Rubber pad, rubber pad are two, and two rubber pads are arranged and are located at correspondingly with two the second lower support bars The bottom of two the second lower support bars;Second driving portion, the second driving portion are two, under two the second driving portions and two second Support rod is arranged and connects correspondingly, two the second driving portions and two the second upper support bars company of driving correspondingly It connects.
Further, hanging device further include: control unit, control unit are electrically connected with lifting portion, to control lifting portion along tunnel The length direction in road is mobile or the width direction along tunnel moves.
Further, hanging device further include: infrared positioning region, infrared positioning region are electrically connected with control unit, infrared positioning Portion determines the default installation site of inverted arch prefabricated section by transmitting infrared ray.
Further, hanging device further include: horizontal measuring instrument, horizontal measuring instrument are electrically connected with control unit, horizontal measurement Instrument is used to measure the horizontal accuracy of the inverted arch prefabricated section in the state that is installed.
Using the technical solution of the utility model, by the way that running part is arranged on support portion, to drive supporting part mobile, and Lifting portion is movably disposed on supporting part, and opposite tunnel width direction and length of tunnel side can be generated by supporting part Upward displacement improves the efficiency of installation so that inverted arch prefabricated section can neatly be placed predeterminated position by lifting portion.
Detailed description of the invention
The accompanying drawings constituting a part of this application is used to provide a further understanding of the present invention, this is practical Novel illustrative embodiments and their description are not constituteed improper limits to the present invention for explaining the utility model. In the accompanying drawings:
Fig. 1 shows the first visual angle schematic diagram of the embodiment of hanging device according to the present utility model;
Fig. 2 shows the second visual angle schematic diagrames of the embodiment of hanging device according to the present utility model.
Wherein, the above drawings include the following reference numerals:
10, supporting part;11, the first load bearing beam;12, the second load bearing beam;13, attachment beam;
20, support portion;21, the first support portion;211, the first upper support bar;212, the first lower support bar;22, the second support Portion;221, the second upper support bar;222, the second lower support bar;223, rubber pad;
30, running part;
40, lifting portion;41, pedestal is lifted;42, ontology is lifted.
Specific embodiment
It should be noted that in the absence of conflict, the features in the embodiments and the embodiments of the present application can phase Mutually combination.The utility model will be described in detail below with reference to the accompanying drawings and embodiments.
Specifically, as depicted in figs. 1 and 2, the hanging device, including supporting part 10, support portion 20, running part 30 and lifting Portion 40, length direction of the supporting part 10 along tunnel are extended, and support portion 20 is multiple, length of multiple support portions 20 along tunnel Direction is positioned apart from, and multiple support portions 20 are connected with supporting part 10, in running part 30 and multiple support portions 20 at least One is connected, so that running part 30 drives corresponding support portion 20 to move in tunnel, lifting portion 40 and supporting part 10 are removable It is connected dynamicly, lifting portion 40 is used for inverted arch prefabricated section for lifting inverted arch prefabricated section, lifting portion 40 along the length side in tunnel To or the width direction in tunnel be moved to predeterminated position.
In the present embodiment, mobile to drive supporting part by the way that running part is arranged on support portion, and it is removable to lift portion It is arranged on supporting part dynamicly, and the displacement on opposite tunnel width direction and length of tunnel direction can be generated by supporting part, So that inverted arch prefabricated section can neatly be placed predeterminated position by lifting portion, the efficiency of installation is improved.
As shown in Figure 1, supporting part 10 includes the first load bearing beam 11 and the second load bearing beam 12, the first load bearing beam 11 and second is held Carrier beam 12 is extended along the length direction in tunnel, and the first load bearing beam 11 and the second load bearing beam 12 are between the width direction in tunnel It is arranged every ground, is provided with attachment beam 13 between the first load bearing beam 11 and the second load bearing beam 12.It is arranged in this way so that lifting portion 40 can Moved along the first load bearing beam 11 and the second load bearing beam 12, and then inverted arch prefabricated section be hoisted in default fitting limit, so as into One step is accurately installed.
In the present embodiment, it is provided with the first sliding rail on the first load bearing beam 11, it is sliding that second is provided on the second load bearing beam 12 Rail, lifting portion 40 and the first sliding rail and the second sliding rail are cooperatively connected.Setting is easy to lift portion 40 in the first load bearing beam and the in this way Oriented movement on two load bearing beams 12.
As depicted in figs. 1 and 2, lifting portion 40 includes lifting pedestal 41 and lifting ontology 42, lifts pedestal 41 and first and slides Rail and the second sliding rail are cooperatively connected, and lifting pedestal 41 has traverse rod, and width direction of the traverse rod along tunnel is arranged;Lift ontology 42 with Traverse rod is cooperatively connected, and lifting ontology 42 is movably disposed along traverse rod.Setting is easy to lift pedestal 41 and lifting ontology 42 in this way It can be by being moved respectively along tunnel width direction and length of tunnel direction, and then realize the accurate lifting to inverted arch prefabricated section.
In addition, multiple support portions 20 include the first support portion 21 and the second support portion 22, the first end of the first support portion 21 It is connected with supporting part 10, the second end of the first support portion 21 is connected with running part 30, the second support portion 22 and the first support The setting of the interval of portion 21, the first end of the second support portion 22 are connected with supporting part 10, the second end and tunnel of the second support portion 22 Ground touching.Setting is convenient for driving supporting part 10 to be moved near installation site range using the first support portion 21 in this way, And then the second support portion 22 is recycled to play a supporting role, in order to lift portion's operation.
In the present embodiment, the first support portion 21 includes the first upper support bar 211, the first lower support bar 212 and the first drive Dynamic portion, the first upper support bar 211 are two, and two the first upper support bars 211 are oppositely disposed in the two sides of supporting part 10, two First upper support bar 211 is connected with supporting part 10, and the first lower support bar 212 is two, two the first lower support bars 212 with Two the first upper support bars 211 are arranged correspondingly, and two the first lower support bars 212 are connected with running part 30, and first The first receiving portion is offered on lower support bar 212, the first upper support bar 211 is movably disposed in the corresponding first lower support In first receiving portion of bar 212, the first driving portion is two, and two the first driving portions and two the first lower support bars 212 are one by one It is arranged in correspondence with and connects, two the first driving portions are drivingly connected correspondingly with two the first upper support bars 211.It sets in this way It sets convenient for changing the working depth position in lifting portion by the first driving portion according to the height in tunnel.
Further, the second support portion 22 includes the second upper support bar 221, the second lower support bar 222,223 and of rubber pad Second driving portion, the second upper support bar 221 are two, and two the second upper support bars 221 are oppositely disposed two in supporting part 10 Side, two the second upper support bars 221 are connected with supporting part 10, and the second lower support bar 222 is to support on two, two second Bar 221 is arranged correspondingly with two the second lower support bars 222, and the second receiving portion is offered on the second lower support bar 222, the Two upper support bars 221 are movably disposed in the second receiving portion of corresponding second lower support bar 222, and rubber pad 223 is Two, two rubber pads 223 and two the second lower support bars 222 are arranged correspondingly and are located at two second lower supports The bottom of bar 222, the second driving portion are two, and two the second driving portions are set correspondingly with two the second lower support bars 222 It sets and connects, two the second driving portions are drivingly connected correspondingly with two the second upper support bars 221.Root is convenient in setting in this way The working depth position in lifting portion is changed by the first driving portion and the cooperation of the second driving portion according to the height in tunnel, and passes through setting Rubber pad 223 improve hanging device achieve the goal position when body stability, be not easy to lead to machine because of the operation in lifting portion The relative movement of body.
In the present embodiment, hanging device further includes control unit, and control unit is electrically connected with lifting portion 40, to control lifting portion 40 length direction along tunnel moves or the width direction along tunnel moves.Setting is convenient for user according to actual job ring in this way Border is remotely controlled 40 operation of lifting portion by control unit.
In addition, hanging device further includes infrared positioning region, infrared positioning region is electrically connected with control unit, and infrared positioning region passes through Emit infrared ray to determine the default installation site of inverted arch prefabricated section.Setting improves the accurate of inverted arch prefabricated section installation in this way Property.
Further, hanging device further includes horizontal measuring instrument, and horizontal measuring instrument is electrically connected with control unit, horizontal measuring instrument For measuring the horizontal accuracy for being in the inverted arch prefabricated section for the state that is installed.Setting improves the installation of inverted arch prefabricated section in this way Operation quality.
The above descriptions are merely preferred embodiments of the present invention, is not intended to limit the utility model, for this For the technical staff in field, various modifications and changes may be made to the present invention.It is all in the spirit and principles of the utility model Within, any modification, equivalent replacement, improvement and so on should be included within the scope of protection of this utility model.

Claims (10)

1. a kind of hanging device characterized by comprising
Supporting part (10), length direction of the supporting part (10) along tunnel are extended;
Support portion (20), the support portion (20) be it is multiple, multiple support portions (20) are between the length direction in the tunnel It is arranged every ground, multiple support portions (20) are connected with the supporting part (10);
Running part (30), at least one of the running part (30) and multiple described support portions (20) are connected, so that described Running part (30) drives the corresponding support portion (20) to move in tunnel;
Lifting portion (40), the lifting portion (40) are movably connected with the supporting part (10), and the lifting portion (40) is used In lifting inverted arch prefabricated section, the lifting portion (40) is used for inverted arch prefabricated section along the length direction or the tunnel in the tunnel Width direction be moved to predeterminated position.
2. hanging device according to claim 1, which is characterized in that the supporting part (10) includes the first load bearing beam (11) With the second load bearing beam (12), the length direction of first load bearing beam (11) and second load bearing beam (12) along tunnel extends Setting, the width direction of first load bearing beam (11) and second load bearing beam (12) along the tunnel are positioned apart from, institute It states and is provided with attachment beam (13) between the first load bearing beam (11) and second load bearing beam (12).
3. hanging device according to claim 2, which is characterized in that it is sliding to be provided with first on first load bearing beam (11) Rail is provided with the second sliding rail, the lifting portion (40) and first sliding rail and described second on second load bearing beam (12) Sliding rail is cooperatively connected.
4. hanging device according to claim 3, which is characterized in that the lifting portion (40) includes:
It lifts pedestal (41), the lifting pedestal (41) and first sliding rail and second sliding rail are cooperatively connected, described to hang Filling pedestal (41) has traverse rod, and width direction of the traverse rod along the tunnel is arranged;
It lifts ontology (42), the lifting ontology (42) and the traverse rod are cooperatively connected, and the lifting ontology (42) is along the cross Rail is movably disposed.
5. hanging device according to claim 1, which is characterized in that multiple support portions (20) include:
The first end of first support portion (21), first support portion (21) is connected with the supporting part (10), and described first The second end of support portion (21) is connected with the running part (30);
Second support portion (22), second support portion (22) and first support portion (21) interval are arranged, and described second The first end of support part (22) is connected with the supporting part (10), second end and the tunnel of second support portion (22) Ground touching.
6. hanging device according to claim 5, which is characterized in that first support portion (21) includes:
First upper support bar (211), first upper support bar (211) are two, two the first upper support bar (211) phases Be set to the two sides of the supporting part (10) over the ground, two first upper support bars (211) with the supporting part (10) phase Connection;
First lower support bar (212), first lower support bar (212) are two, two first lower support bars (212) with Two first upper support bars (211) are arranged correspondingly, two first lower support bars (212) with the walking Portion (30) is connected, and the first receiving portion is offered on first lower support bar (212), first upper support bar (211) can It is actively set in first receiving portion of corresponding first lower support bar (212);
First driving portion, first driving portion are two, two first driving portions and two first lower support bars (212) it is arranged and connects correspondingly, two first driving portions and two first upper support bars (211) one is a pair of It is drivingly connected with answering.
7. hanging device according to claim 5, which is characterized in that second support portion (22) includes:
Second upper support bar (221), second upper support bar (221) are two, two the second upper support bar (221) phases Be set to the two sides of the supporting part (10) over the ground, two second upper support bars (221) with the supporting part (10) phase Connection;
Second lower support bar (222), second lower support bar (222) are two, two second upper support bars (221) with Two second lower support bars (222) are arranged correspondingly, offer the second receiving on second lower support bar (222) Portion, second upper support bar (221) are movably disposed in described the second of corresponding second lower support bar (222) In receiving portion;
Rubber pad (223), the rubber pad (223) are two, two rubber pads (223) and two described second lower supports Bar (222) is arranged correspondingly and is located at the bottom of two second lower support bars (222);
Second driving portion, second driving portion are two, two second driving portions and two second lower support bars (222) it is arranged and connects correspondingly, two second driving portions and two second upper support bars (221) one is a pair of It is drivingly connected with answering.
8. hanging device according to claim 1, which is characterized in that the hanging device further include:
Control unit, the control unit are electrically connected with the lifting portion (40), to control the lifting portion (40) along the length in tunnel Direction is mobile or the width direction along tunnel moves.
9. hanging device according to claim 8, which is characterized in that the hanging device further include:
Infrared positioning region, the infrared positioning region are electrically connected with the control unit, and the infrared positioning region passes through transmitting infrared ray With the default installation site of the determination inverted arch prefabricated section.
10. hanging device according to claim 8, which is characterized in that the hanging device further include:
Horizontal measuring instrument, the horizontal measuring instrument are electrically connected with the control unit, and the horizontal measuring instrument is for measuring in peace Fill the horizontal accuracy of the inverted arch prefabricated section of completion status.
CN201822273486.2U 2018-12-30 2018-12-30 Hanging device Active CN209583418U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822273486.2U CN209583418U (en) 2018-12-30 2018-12-30 Hanging device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822273486.2U CN209583418U (en) 2018-12-30 2018-12-30 Hanging device

Publications (1)

Publication Number Publication Date
CN209583418U true CN209583418U (en) 2019-11-05

Family

ID=68351572

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822273486.2U Active CN209583418U (en) 2018-12-30 2018-12-30 Hanging device

Country Status (1)

Country Link
CN (1) CN209583418U (en)

Similar Documents

Publication Publication Date Title
CN201580915U (en) Tyre-type gantry crane
CN204627625U (en) Automatic walking lining trolley
CN105000482B (en) Tower crane with walking mechanism
CN201010858Y (en) Device especially for bridge detecting and maintaining
CN105016223B (en) Cross beam supporting system used for tower crane
CN103147370A (en) Device and method for replacing track slab of slab ballastless track
CN204823883U (en) Trolley -bus gantry crane
CN109281323A (en) A kind of roadbed side slope rockbolt installation device
CN103510864B (en) One kind three saves hydraulically extensible suit derrick
CN104060835A (en) Lifting-sliding construction method for single plane truss
CN206800215U (en) Bridge incremental launching Bridge Erector
CN107059609A (en) Bridge maintenance system span formula steel structure platform
CN209583418U (en) Hanging device
CN204170002U (en) A kind of artificial digging pile safety apparatus
CN206625845U (en) A kind of inverted arch trestle
CN206529691U (en) Bridge maintenance system steel construction inspection platform
CN206815943U (en) A kind of pole upside-down mounting group founds lifting device
CN203007843U (en) Variable amplitude deck derrick crane
CN209838445U (en) Tunnel preliminary bracing rapid construction trolley
CN205170224U (en) Crawler -type moves tower crane
CN209635762U (en) Lamp box installs vehicle
CN208686396U (en) Tunnel inverted arch trestle walking rack
CN104988921B (en) Multifunction guard rail breakdown van
CN209143537U (en) Rubber-tyred tunnel tracklaying crane
CN207312996U (en) A kind of high aerial rail road lifting gear

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant