Prior art keywords
building
pipeline
equipment
main building
subterranean layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920133128.3U
Other languages
Chinese (zh)
Inventor
汪洋文杰
傅祺
杨勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Cci Architectural Design Co Ltd
Original Assignee
Beijing Cci Architectural Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Cci Architectural Design Co Ltd filed Critical Beijing Cci Architectural Design Co Ltd
Priority to CN201920133128.3U priority Critical patent/CN209482454U/en
Application granted granted Critical
Publication of CN209482454U publication Critical patent/CN209482454U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model discloses a kind of building subterranean layer pipeline arrangement frameworks, including main building, pipeline and the power-equipment being integrated in equipment building, main building and equipment building are partially connected with each other by pipeline passway on the ground, power-equipment pipeline matched with main building enters the pipe well in main building by pipeline passway after extending upwardly on ground, then extends from the vertical pipe well of main building to its subterranean layer, is laid with.The framework scheme stretches out basement by equipment room gut line vertical direction, it is high to save building storey for layer high higher floor laying horizontal pipe in part on the ground, take full advantage of invalid plane domain, from plane and sterically there is the effect of optimization, development and optimization are played to the pipeline layout of architectural design.

Description

A kind of building subterranean layer pipeline arrangement framework
Technical field
The application belongs to architectural design field of engineering technology, especially for each of existing construction area or Group Buildings A kind of building subterranean layer pipeline arrangement framework that kind pipeline arrangement proposes.
Background technique
In existing architectural design, pipeline layout and framework as main building are perfect one of Integral design for building A important indicator.Especially for the groups of building in modern city, the pipeline in building not only includes the public affairs such as water, electricity, warm With equipment installation, and various data, communication, network of pipeline are more added significantly to the difficulty of pipe installation.Pipeline layout and structure Frame also becomes the whether reasonable important characterization of Technologies in Construction Planning Design.Emerging groups of building are usually by main building and various Equipment building independently designs, and equipment building requires to be configured according to conditions for equipment use, to ensure safety that equipment uses. This results in the equipment center installed in equipment building it must be realized connection with each main building by pipeline.This equipment Building and main building separate design, the mode of construction are commonly referred to as equipment island layout.After using such equipment island layout type, Pipeline is usually laterally to be laid with to extend to each main building subterranean layer by underground, then pass through vertical pipe well after summarizing by each layer It arranges to each layer on the ground.Above-mentioned pipe installation mode often payes attention to the basic function wiring of plane, but not to mechanical discipline pipeline Comprehensively consider.Usually occur since function division is unreasonable, device rooms position inaccuracy causes pipeline to be concentrated, pipeline forces down layer High situation occurs.In order to hardness avoid it is this force down the high hidden danger of layer, engineering construction side can only increase investment, at the beginning of design Biggish altitude margin just is remained to building height to meet using upper requirement, to cause resource unrestrained on solid space Take.In construction, since construction party is in strict accordance with drawing construction, cause pipeline function division and arrangement it is unreasonable often Occur the case where some region will appear the laying of three-layer pipe road or clear height is unsatisfactory for 2.2m, this is more or less belonged to Fault is designed caused by early period design concept defect.
A kind of method that improving above-mentioned design be equipment dynamic center is layed in two layers of basement one or underground, and Hot-water heating electricity professional equipment room centralized arrangement, this mode spatially result in the centralized arrangement of pipeline, and integral layer height increases.Together When also increase the complexity of pipeline underground framework, therefore be typically now by the position of equipment dynamic and main building phase point From i.e. equipment island mode.
Separation main building and equipment center after, how more effective fruit, reasonably carry out various pipeline layouts and framework It is the frontier nature research and development direction in modern architecture group design.Especially in conjunction with the layout and construction actually built, propose A kind of reasonable layout type is just more aobvious for the design of main building, and its is important.Technical scheme be exactly to it is existing not Perfect building pipeline framework proposes bold improvement, proposes a kind of new framework mode, the framework mode in practical operation and Meet building pipeline layout requirements in.
Utility model content
The technical solution of the application predominantly solves in existing building that pipeline layout is unreasonable to cause layer height by compression defect, When especially selection pipeline is laid with upwards to the framework scheme of each layer in the ground of main building from basement, underground chamber region will be by To pipe installation move towards influence cause its longitudinal space compress, thus influence underground layer function realize and building cost it is increased Defect.
The application is to overcome the defect of above-mentioned existing pipeline layout, and application adopts the technical scheme that
A kind of building subterranean layer pipeline arrangement framework, including main building, pipeline and the power being integrated in equipment building Equipment, main building and equipment building are partially connected with each other by pipeline passway on the ground, power-equipment matched with main building Pipeline enters the pipe well in main building by pipeline passway after extending upwardly on ground, then passes through the vertical of main building Pipe well extends to its subterranean layer, is laid with.In above-mentioned technical proposal, pipeline from power-equipment come out after be not by underground piping into Horizontal layout is carried out after entering main building subterranean layer, but is introduced into the aerial layer of main building, according to subterranean layer pipeline requirements, The pipeline into subterranean zone will be needed to be laid with by vertical pipe well to underground, carried out in subterranean layer using the side wall of subterranean layer Level is laid with, to ensure that the longitudinal space that the number of lines into subterranean zone is minimum, and underground transverse direction pipeline installation occupies Minimum, realization optimizes pipeline framework mode.
In above-mentioned pipeline framework scheme, the pipeline into subterranean layer is only the pipeline that each layer in underground needs to be laid with, each on the ground Layer needs the pipeline being laid with that can directly be constructed.The great advantage of this mode is to reduce the pipeline number into underground Amount, saves space and the length of pipeline of pipe installation.
In above-mentioned pipeline framework scheme, equipment building and main building are the adjacent building of segmentation, and equipment building is also with ground The under ground portion of the building of flowering structure, under ground portion and main building is interconnected;The interconnected mode in this underground is more Pipeline state convenient for being transmitted to each layer in main building underground to equipment output is overhauled and is safeguarded, ensure that subterranean layer pipeline The safety of arrangement.
In above-mentioned pipeline framework scheme, the central apparatus of water, electricity, heating equipment can be not only accommodated in equipment building, but also Including the various host computer communication equipment to guarantee main building network and data communication, these central apparatus need to divide according to environment It is not independently arranged at the different location in equipment building.
In above-mentioned pipeline framework scheme, the vertical pipe well of main building is adjacent and parallel with it with elevator pipe well, in this way may be used Pipeline layout is carried out with the more efficiently wasted space using lift well.In addition, for being made of multiple main buildings One residential group, an equipment room can provide necessary pipeline designs simultaneously for multiple main buildings, pipeline layout at this time Using parallel way, the pipeline that each main building is gone in laying first is extended upward from equipment to the superstructure on ground Afterwards, in parallel to extend to different building bodies by connecting pipe respectively, then carry out the pipeline laying inside different building bodies.
In the way of the framework of the application, pipeline is first whole from the floor that ground region enters building ground, then root It needs for necessary pipeline to be laid with by pipe shaft to subterranean layer according to subterranean layer pipeline function, pipeline enters after subterranean layer along ground Lower layer's side wall carries out lateral laying, greatly reduces the occupancy in lateral line laying to subterranean layer longitudinal direction height, saves and build The design cost for building subterranean zone simplifies the laying of subterranean layer gut line.
Detailed description of the invention
Fig. 1 is the building subterranean layer pipeline arrangement framework schematic diagram of the present utility model application;
In figure: 1, equipment building;2, power-equipment;3, pipeline;4, main building.
Specific embodiment
The technical solution of the application is carried out below by the pipeline arrangement mode introduction in specific building underground garage It explains and illustrates.
As shown in Figure 1, the groups of building include an equipment building 1 and a main building 4 adjacent thereto, equipment building is also wrapped Aerial part and under ground portion are included, the under ground portion of main part is mainly four layer garage structures.Due to equipment building and main body Build adjacent, under ground portion can be interconnected, and personnel easy to repair carry out pipeline maintenance.Various water, electricity in equipment building, The power-equipments 2 such as warm, communication need to be distributed in different zones in equipment building, the pipe that each equipment is connected according to its varying environment Vertical shaft along equipment building is laid with to certain floor on ground after line 3 converges first, and pipeline concentrates the top layer for extending to equipment building in attached drawing 1 (third layer), the pipeline passway that the third layer in equipment building has the pipeline vertical shaft of transverse direction and main building to connect, pipeline is by being somebody's turn to do Lateral line channel enters the third layer region of main building, vertical pipe of the pipeline that basement needs herein along main building Well is laid with to underground garage region, and pipeline, which enters after subterranean zone, carries out landscape layout using the side wall of underground garage.Especially In the present embodiment, fire extinguisher canvas hose line takes full advantage of storage area below car ramp locating for the fire cistern of underground garage Domain, fire hydrant endless tube part cyclization layout, the occupancy for reducing longitudinal height.Therefore from the point of view of the topology layout of whole pipeline, Clear superiority is:
Equipment room gut line vertical direction stretches out basement, and layer high higher floor in part just lays horizontal tube on the ground Road.(1) basement pipeline is vertically arranged, and it is high to save building storey;(2) fire cistern utilizes water storage below car ramp, fire water Pump house arrangement utilizes ring ramp center;(3) fire hydrant endless tube part cyclization, it is possible to reduce plane pipeline is reduced investment outlay, and is increased Use space;(4) automatic sprinkler system pipeline walks main pipeline using parking stall rear, increases parking stall upper space and uses.Above-mentioned layout knot Structure not only reduces subterranean layer height, is also fully utilized by invalid plane domain, from plane and sterically there is the effect of optimization. Therefore, which is to play development and optimization to the pipeline layout of architectural design.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any to repair Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (6)

  1. The framework 1. a kind of building subterranean layer pipeline is arranged, including main building (4), pipeline (3) and to be integrated in equipment building (1) interior Power-equipment (2), main building and equipment building partially pass through pipeline passway interconnection on the ground, which is characterized in that with master Body, which is built after matched power-equipment pipeline extends upwardly on ground, enters the pipe well in main building by pipeline passway, Extend from the vertical pipe well of main building to its subterranean layer, be laid with.
  2. The framework 2. building subterranean layer pipeline according to claim 1 is arranged, which is characterized in that the vertical pipe well of main building Extend to the pipeline that the pipeline of its subterranean layer needs to be laid with for each layer in underground.
  3. The framework 3. building subterranean layer pipeline according to claim 1 is arranged, which is characterized in that the under ground portion in equipment building It is interconnected with the under ground portion of main building.
  4. The framework 4. building subterranean layer pipeline according to claim 1 is arranged, which is characterized in that power-equipment be water, electricity, The equipment center of heating equipment.
  5. The framework 5. building subterranean layer pipeline according to claim 1 is arranged, which is characterized in that the vertical pipe of main building Well is adjacent and parallel with it with elevator pipe well.
  6. The framework 6. building subterranean layer pipeline according to claim 1 is arranged, which is characterized in that main building is more buildings When, the pipeline into each main building is parallel connection.
CN201920133128.3U 2019-01-25 2019-01-25 A kind of building subterranean layer pipeline arrangement framework Active CN209482454U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920133128.3U CN209482454U (en) 2019-01-25 2019-01-25 A kind of building subterranean layer pipeline arrangement framework

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920133128.3U CN209482454U (en) 2019-01-25 2019-01-25 A kind of building subterranean layer pipeline arrangement framework

Publications (1)

Publication Number Publication Date
CN209482454U true CN209482454U (en) 2019-10-11

Family

ID=68132750

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920133128.3U Active CN209482454U (en) 2019-01-25 2019-01-25 A kind of building subterranean layer pipeline arrangement framework

Country Status (1)

Country Link
CN (1) CN209482454U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113293857A (en) * 2021-07-06 2021-08-24 文佳 Basement for reducing floor height by laying channels through overall pipelines

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113293857A (en) * 2021-07-06 2021-08-24 文佳 Basement for reducing floor height by laying channels through overall pipelines

Similar Documents

Publication Publication Date Title
CN205296224U (en) Air intake, hoist and mount mouthful and mouthful combined layout's utility tunnel node structure of fleing
CN205329721U (en) Air exit and mouthful combined layout's that flees utility tunnel node structure
CN103195083B (en) A kind of pipe gallery crossover node structure
CN103195440A (en) Three-layer-structure subway double-line single-pipe circular tunnel
CN103147461B (en) A kind of pipe gallery and control centre's connecting joint structure
Al-Kodmany Guidelines for tall buildings development
CN209482454U (en) A kind of building subterranean layer pipeline arrangement framework
CN110107972A (en) Cabin-type refrigerating plant room and its construction method
CN106337436A (en) Rectangular concrete comprehensive pipe gallery prefabricated pipe sections and machining method
CN105178565B (en) Underground power house cable outlet also serves as the vertical shaft of safe escape passage
CN207700219U (en) A kind of pipe gallery in more cabins
CN207296521U (en) A kind of flame-out in flight building
CN107975065A (en) A kind of pipe gallery in more cabins
CN104404862B (en) Steel pipe rack people's row Pipeline Bridge
CN207110632U (en) It is a kind of to be provided with the underground garage for sharing piping lane
CN209227606U (en) Wall construction plate and shell connecting node in assembly concrete pipe gallery
CN209145605U (en) The round more cabin pipe galleries of shield-tunneling construction
CN205557570U (en) Prestressing force divides and adds series pipe storehouse formula underground pipe gallery side by side
CN206346540U (en) Compound underground garage
CN206784502U (en) The portable water supply installation of floor water and fire demand water in high-building construction
CN206599792U (en) A kind of semi-underground type garage parking
CN209227601U (en) Wall construction plate in the double-deck assembly concrete pipe gallery
CN109372021A (en) Assembly concrete bilayer pipe gallery shell and media layer damage plate connecting node
CN209227608U (en) Wall construction plate and media layer damage plate connecting node in concrete pipe gallery
CN205646701U (en) Outlet structure of transformer substation's cable intermediate layer

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant