CN209446662U - Relay protection sample examination system based on synchronous data collection technology - Google Patents

Relay protection sample examination system based on synchronous data collection technology Download PDF

Info

Publication number
CN209446662U
CN209446662U CN201822151903.6U CN201822151903U CN209446662U CN 209446662 U CN209446662 U CN 209446662U CN 201822151903 U CN201822151903 U CN 201822151903U CN 209446662 U CN209446662 U CN 209446662U
Authority
CN
China
Prior art keywords
module
terminal
voltage
current
cpu module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822151903.6U
Other languages
Chinese (zh)
Inventor
唐凡
孟睿铮
赵耀民
牛志民
李琳
芦佳硕
刘喆
冉然
葛嫚
张毅静
赵悦
伍艳
金丽萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Baoding Power Supply Co of State Grid Hebei Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Baoding Power Supply Co of State Grid Hebei Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Hebei Electric Power Co Ltd, Baoding Power Supply Co of State Grid Hebei Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201822151903.6U priority Critical patent/CN209446662U/en
Application granted granted Critical
Publication of CN209446662U publication Critical patent/CN209446662U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Emergency Protection Circuit Devices (AREA)

Abstract

The relay protection sample examination system based on synchronous data collection technology that the utility model discloses a kind of comprising current synchronization terminal and voltage synchronous terminal;Current synchronization terminal and voltage synchronous terminal include clock synchronization module, punctual module, CPU module, wireless communication module, human-computer interaction module;Current synchronization terminal further includes strong current generator and current measurement module, and strong current generator is electrically connected CPU module through current measurement module;Voltage synchronous terminal further includes voltage changer and voltage measurement module, and voltage changer is electrically connected CPU module through voltage measurement module;CPU module is connect with wireless communication module, and human-computer interaction module is connected with CPU module by bus;Clock synchronization module is being needed to constantly with the connection of CPU module, punctual module is connect clock synchronization with CPU module after the completion.Complicated grid switching operation is carried out when the utility model eliminates power transmission to carry out phasor inspection, substantially reduces electric power feeding time, reduces power grid risk.

Description

Relay protection sample examination system based on synchronous data collection technology
Technical field
The relay protection sample examination system based on synchronous data collection technology that the utility model relates to a kind of is applied to become The phasor inspection of route optical difference protection, belongs to electric relay protection technical field in power station relay protection work.
Background technique
The simulation phasor test in substation is using the simulation phasor vehicle of DianKeYuan research and development at present, it can generate very big Electric current run through primary equipment, achieve the purpose that simulate phasor inspection.But there are the following problems:
1) it is limited to the length of test wire, is unable to complete the survey of circuit longitudinal optical difference protection simulation phasor between station and station Amount;
2) costly --- disregard the electric energy expended when test, only 100,000 yuan/day of instrument cost of use;
3) quantity is few --- and Southern Hebei Network, which only saves, at present send power transformation and DianKeYuan to have, and other prefecture-level units all do not have. Costly and quantity limits its use scope less, when only 220kV and above newly-built station put into operation, can just make With, stand in newly-increased line segregation or when main transformer interval, not will use.
4) test connection heavy workload.It generally requires to drag 10mm2 test wire when test and walks tens meters or even up to a hundred meters Distance.
5) there is potential high pressure Danger Electric shock risk.The electric current of peaces up to a hundred is passed through in very long test wire, once test wire is exhausted Edge is damaged, it will constitutes great threat to the safety of on-site personnel.
And when the phasor of vertical connection optical fiber differential protective is tested at present mainly by primary equipment power transmission between substation, use load Electric current is examined.There are the following problems:
1) test effect is limited by actual load size.When power transmission, load current is too small (< %5 rated current), electric current It is error-prone without legal phase or phase-unstable.
2) increase operation maintenance personnel grid switching operation workload, extend electric power feeding time.Operation maintenance personnel needs to be simulated according to transfer order each The kind method of operation, operating procedure is more, and electric power feeding time is long, even more so for complicated wiring, while also increasing dangerous when power transmission Property.
3) it is not easy to change.Phasor inaccuracy is found when power transmission, needs to pull open switch power transmission again, it will extend power transmission Time causes to compare passively situation.
Therefore the simulation phasor inspection for route optical difference protection, is currently a blank, is used when can only rely on power transmission negative Charged current inspection.Simultaneously because the popularization of intelligent station, is inserted into combining unit between current transformer and route protection, there is electricity For signal to the conversion of optical signal, link is more, and route optical difference protection is made to be easier to go wrong.
Utility model content
It is high, easy to operate based on same step number that the technical problem to be solved by the utility model is to provide a kind of accuracys rate According to the relay protection sample examination system of acquisition technique.
The utility model adopts the technical scheme that
A kind of relay protection sample examination system based on synchronous data collection technology comprising current synchronization terminal and electricity Press synchronous terminal;
The current synchronization terminal and voltage synchronous terminal include clock synchronization module, punctual module, CPU module, channel radio Believe module, human-computer interaction module;The current synchronization terminal further includes strong current generator and current measurement module, the big electricity Input terminal of the output end of flow-generator through current measurement module electrical connection CPU module;The voltage synchronous terminal further includes electricity Buckling parallel operation and voltage measurement module, the output end of the voltage changer is through the defeated of voltage measurement module electrical connection CPU module Enter end;
The CPU module is connected by measured value output end thereon and theoretical value input terminal with wireless communication module, The human-computer interaction module is connected with CPU module by bus;
The clock synchronization module is needing to be connected to the clock synchronization signal receiving end constantly with CPU module, institute after the completion of clock synchronization Punctual module is stated to be connected with the punctual signal receiving end of CPU module.
Further, the invention also includes the power modules for powering to current synchronization terminal and voltage synchronous terminal.
Further, the current measurement module and voltage measurement module include filter circuit and analog to digital conversion circuit, The output end of the strong current generator is successively electrically connected the input terminal of CPU module after filter circuit and analog to digital conversion circuit, The output end of the voltage changer is successively electrically connected the input terminal of CPU module after filter circuit and analog to digital conversion circuit.
Further, the invention also includes data servers and display terminal;The current synchronization terminal and voltage synchronous The output end of terminal is communicated with the receiving end of data server respectively;The display output end of the data server and display are eventually The input signal end at end communicates.
Further, the clock synchronization module is connected with time source, and the time source includes GPS network network clock synchronization server, north Struggle against any one of server, CDMA server and B code server.
Further, the display terminal includes the equipment that can remotely access cloud terminal.
Further, the data server, major function include: 1. communication function: can receive first station by wireless network Next voltage, current data with the display transmission of second station, data format are considered as GB/T26865.2 association when PMU transmission data View, suitably simplifies data frame format;2. calculation function: because the data sent on the end of station have markers, by synchronization Data operation, described point can simultaneously be shown under polar coordinate system, be calculatedU 1WithI 1,U 1WithI 2Between angle and route protect Protect current difference current and stalling current;3. graphical representation function: sampled value calculated result is carried out figure in polar coordinates Change and show, and obtains first station and the report of second station sampled value;4. data storage and printing function: being installed with large capacity in server and deposit Storage media can store multiple sampled value inspection results;5. the retransmission function of sampled value result: the sampled value result that will be calculated The display terminal in station is returned to, expected results are compared service personnel with the actual sampled value of protective device, and judgement is adopted Whether each link of sample is correct.Data server uses cloud terminal, mainly software development.
Further, the display terminal can visualize the result that the sampled value that data server passback comes calculates. Expected results are compared service personnel with the actual sampled value of protective device, judge whether sampled value is correct;Display terminal It can be Android mobile phone, tablet computer or laptop, the equipment that can remotely access cloud terminal can all become display terminal.
The beneficial effects of the utility model are as follows:
The thought of automated data distributed collection, centralized processing is applied to protection sample examination by the utility model, to rise It flows device and replaces power rectifier inverter, the development cost that relay protection sampling globality checks equipment is greatly reduced, reduces Test connection workload and risk.
The utility model is under capital construction state to protective current, mutual relation of electric voltage correctness and to be associated with multi-compartment differential The consistency check and verifying of protective current sample polarity provide platform, instead of electric with load when can only pass through power transmission in the past The status that stream and operating voltage are examined.Complicated grid switching operation is carried out when eliminating power transmission to carry out phasor inspection, is contracted significantly Short electric power feeding time reduces power grid risk.In addition, this programme is illustrated by taking route optical difference protection as an example, for main transformer in standing Protection, bus protection, the program stand good.
Detailed description of the invention
Fig. 1 is the structural principle block diagram of current synchronization terminal in the present invention.
Fig. 2 is the structural principle block diagram of voltage synchronous terminal in the present invention.
Fig. 3 is the relay protection sample examination schematic diagram based on synchronous data collection technology.
Specific embodiment
To keep the purpose of this utility model, technical solution and advantage clearer, 1-3 and specific implementation with reference to the accompanying drawing Example carries out clear, complete description to utility model.
As shown in Figure 1-Figure 3, the present embodiment is related to a kind of relay protection sample examination based on synchronous data collection technology System comprising current synchronization terminal and voltage synchronous terminal;
The current synchronization terminal and voltage synchronous terminal include clock synchronization module, punctual module, CPU module, channel radio Believe module, human-computer interaction module;The current synchronization terminal further includes strong current generator and current measurement module, the big electricity Input terminal of the output end of flow-generator through current measurement module electrical connection CPU module;The voltage synchronous terminal further includes electricity Buckling parallel operation and voltage measurement module, the output end of the voltage changer is through the defeated of voltage measurement module electrical connection CPU module Enter end;
The CPU module is connected by measured value output end thereon and theoretical value input terminal with wireless communication module, The human-computer interaction module is connected with CPU module by bus;
The clock synchronization module is needing to be connected to the clock synchronization signal receiving end constantly with CPU module, institute after the completion of clock synchronization Punctual module is stated to be connected with the punctual signal receiving end of CPU module.
Further, the present embodiment further includes the power supply mould for powering to current synchronization terminal and voltage synchronous terminal Block.
Further, the current measurement module and voltage measurement module include filter circuit and analog to digital conversion circuit, The output end of the strong current generator is successively electrically connected the input terminal of CPU module after filter circuit and analog to digital conversion circuit, The output end of the voltage changer is successively electrically connected the input terminal of CPU module after filter circuit and analog to digital conversion circuit.
Further, the present embodiment further includes data server and display terminal;The current synchronization terminal and voltage are same The output end of step terminal is communicated with the receiving end of data server respectively;The display output end of the data server and display The input signal end of terminal communicates.
Further, the clock synchronization module is connected with time source, and the time source includes GPS network network clock synchronization server, north Struggle against any one of server, CDMA server and B code server.
Further, the display terminal includes the equipment that can remotely access cloud terminal.
The thought of automated data distributed collection, centralized processing is applied to protection sample examination by the utility model, to rise It flows device and replaces power rectifier inverter, the development cost that relay protection sampling globality checks equipment is greatly reduced, reduces Test connection workload and risk.
To protective current, mutual relation of electric voltage correctness and multi-compartment differential protection electric current can be associated under capital construction state The consistency of sample polarity is checked and is verified, and is examined instead of load current when can only pass through power transmission in the past and operating voltage The status tested.Complicated grid switching operation is carried out when eliminating power transmission to carry out phasor inspection, electric power feeding time is substantially reduced, subtracts Minor scale power net risk.
The utility model is at present in 220kV electricity paddy station, the north 220kV poplar station and the main transformer infrastructure project of king 110kV shop 1 Middle carry out engineering test, application effect is good, and test accuracy rate is up to 100%.
During 2017.10-2018.03, work in conjunction with power transmission, to the clear Wu I line of 220kV, the clear Wu II line of 220kV, 220kV Nine outlet electric power feeding times such as Northern Mountain line are counted, and calculating average electric power feeding time is 4.3 hours.Using simulation vector inspection After looking into system, so far 2018.04, work in conjunction with power transmission to 220kV Qi Yang line, the clear poplar line of 220kV, the Northern Mountain 110kV line etc. nine Outlet electric power feeding time statistics, calculating average electric power feeding time is 1.4 hours.Averagely shorten electric power feeding time 2.9 hours, promotes work Make efficiency 67.4%.Every year the economic benefit more than 2,000,000 can be brought for a prefecture-level power supply company.
Finally, it should be noted that above embodiments are only to illustrate the technical solution of the utility model, rather than its limitations; Although the utility model is described in detail with reference to the foregoing embodiments, those skilled in the art should understand that: It can still modify to technical solution documented by previous embodiment, or be equal to part of technical characteristic Replacement;And these are modified or replaceed, the utility model embodiment technical solution that it does not separate the essence of the corresponding technical solution Spirit and scope.

Claims (6)

1. a kind of relay protection sample examination system based on synchronous data collection technology, it is characterised in that: it includes that electric current is same Walk terminal and voltage synchronous terminal;
The current synchronization terminal and voltage synchronous terminal include clock synchronization module, punctual module, CPU module, radio communication mold Block and human-computer interaction module;The current synchronization terminal further includes strong current generator and current measurement module, the high current Input terminal of the output end of generator through current measurement module electrical connection CPU module;The voltage synchronous terminal further includes voltage Converter and voltage measurement module, the output end of the voltage changer is through the input of voltage measurement module electrical connection CPU module End;
The CPU module is connected by measured value output end thereon and theoretical value input terminal with wireless communication module, described Human-computer interaction module is connected with CPU module by bus;
The clock synchronization module is needing to be connected to the clock synchronization signal receiving end constantly with CPU module, described after the completion of clock synchronization to keep When module be connected with the punctual signal receiving end of CPU module.
2. the relay protection sample examination system according to claim 1 based on synchronous data collection technology, feature exist In: it further includes the power module for powering to current synchronization terminal and voltage synchronous terminal.
3. the relay protection sample examination system according to claim 1 based on synchronous data collection technology, feature exist It include filter circuit and analog to digital conversion circuit in: the current measurement module and voltage measurement module, the high current occurs The output end of device is successively electrically connected the input terminal of CPU module, the voltage changer after filter circuit and analog to digital conversion circuit Output end successively after filter circuit and analog to digital conversion circuit be electrically connected CPU module input terminal.
4. the relay protection sample examination system according to claim 1 based on synchronous data collection technology, feature exist In: it further includes data server and display terminal;The output end of the current synchronization terminal and voltage synchronous terminal respectively and The receiving end of data server communicates;The display output end of the data server and the input signal end of display terminal communicate Letter.
5. the relay protection sample examination system according to claim 1 based on synchronous data collection technology, feature exist In: the clock synchronization module is connected with time source, and the time source includes GPS network network clock synchronization server, Beidou server, CDMA clothes Business any one of device and B code server.
6. the relay protection sample examination system according to claim 4 based on synchronous data collection technology, feature exist In: the display terminal includes the equipment that can remotely access cloud terminal.
CN201822151903.6U 2018-12-21 2018-12-21 Relay protection sample examination system based on synchronous data collection technology Active CN209446662U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822151903.6U CN209446662U (en) 2018-12-21 2018-12-21 Relay protection sample examination system based on synchronous data collection technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822151903.6U CN209446662U (en) 2018-12-21 2018-12-21 Relay protection sample examination system based on synchronous data collection technology

Publications (1)

Publication Number Publication Date
CN209446662U true CN209446662U (en) 2019-09-27

Family

ID=68014850

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822151903.6U Active CN209446662U (en) 2018-12-21 2018-12-21 Relay protection sample examination system based on synchronous data collection technology

Country Status (1)

Country Link
CN (1) CN209446662U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109444531A (en) * 2018-12-21 2019-03-08 国家电网有限公司 Relay protection sample examination system and its sample examination method based on synchronous clock synchronization

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109444531A (en) * 2018-12-21 2019-03-08 国家电网有限公司 Relay protection sample examination system and its sample examination method based on synchronous clock synchronization

Similar Documents

Publication Publication Date Title
CN103105550B (en) A kind of intelligent relay protection device detection method and system
CN101900777B (en) Monitoring method and device of power system
CN207895024U (en) A kind of medium voltage distribution network fault fast positioning device
CN102567603B (en) Method for automatically generating BPA calculation file based on actual measurement topology and measured data
CN102520288B (en) Primary-rising based current differential protection synchronization performance testing system and testing method
CN104020374A (en) Intelligent substation secondary equipment site-wide simulation test system
CN103149547B (en) Transformer substation measurement return circuit on-line monitoring system and state maintenance method
CN203117313U (en) Dynamic simulation and emulation detecting platform for intelligent substation secondary system
CN103076520A (en) Dynamic analogue simulation detection platform and analogue simulation method for secondary system of intelligent substation
CN105467277B (en) A kind of power distribution network mixed fault distance measuring method and device based on PMU
CN201732120U (en) Power consumption information collecting and monitoring system in base station
CN101692104A (en) Power quality and synchronized phasor monitoring device for power system
CN107741549A (en) The intelligent substation synchronism tester synchronously occurred based on analog quantity and digital quantity
CN106443347B (en) A kind of electric network fault Section Location based on fault transient travelling wave attenuation components
CN112305340B (en) True type test platform of low-voltage power distribution Internet of things
CN105203870A (en) Intelligent transformer substation secondary equipment integrated test system based on power line communication
CN109444531A (en) Relay protection sample examination system and its sample examination method based on synchronous clock synchronization
CN202929117U (en) Positive-sequence impedance parameter measure apparatus for transmission line
CN103138388A (en) Power distribution station management system
CN104007410A (en) Digital electric energy meter verifying device
CN209446662U (en) Relay protection sample examination system based on synchronous data collection technology
CN104361796A (en) Electric energy metering device simulation training platform
CN104101806A (en) ARM and DSP based multi-circuit power quality online monitoring device
CN202057747U (en) Intelligent secondary circuit vector analyzer
CN202153246U (en) Direct current system grounding and ring network fault positioning system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant