CN209398930U - A kind of Pipe installing adjustable-size antidetonation suspension and support - Google Patents

A kind of Pipe installing adjustable-size antidetonation suspension and support Download PDF

Info

Publication number
CN209398930U
CN209398930U CN201920057065.8U CN201920057065U CN209398930U CN 209398930 U CN209398930 U CN 209398930U CN 201920057065 U CN201920057065 U CN 201920057065U CN 209398930 U CN209398930 U CN 209398930U
Authority
CN
China
Prior art keywords
connecting rod
rod
framework
clip
cuff
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920057065.8U
Other languages
Chinese (zh)
Inventor
曾锃
王新宇
马久
张帆
阳维果
戴俊
季纯静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Delt Technology Co Ltd
Original Assignee
Sichuan Delt Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Delt Technology Co Ltd filed Critical Sichuan Delt Technology Co Ltd
Priority to CN201920057065.8U priority Critical patent/CN209398930U/en
Application granted granted Critical
Publication of CN209398930U publication Critical patent/CN209398930U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Clamps And Clips (AREA)

Abstract

The utility model discloses a kind of Pipe installing adjustable-size antidetonation suspension and supports, are related to antidetonation suspension and support technical field, solve the problems, such as that a variety of various sizes of para-seismic supports is needed to cause installation cost excessively high when the prior art installs various sizes of pipeline.Including clip and first connecting rod, the connection of the bottom of first connecting rod and floor, the other end of first connecting rod and clamp connection, clip includes upper cuff and lower cuff, upper cuff and lower cuff pass through locking device detachable connection, upper cuff include two framework framves, two framework framves by second connecting rod connection, two framework framves can be slided on second connecting rod so that two framework framves close to or far from.The utility model is by upper cuff and the cooperation of lower cuff by including Pipe installing, while the distance between the distance between two framework framves and upper cuff and lower cuff are all alterable, so that clip can adapt to the installation of a variety of various sizes of pipelines.

Description

A kind of Pipe installing adjustable-size antidetonation suspension and support
Technical field
The utility model relates to antidetonation suspension and support technical fields, specifically, refer to a kind of for installing architecture pipe Pipe installing adjustable-size antidetonation suspension and support.
Background technique
Now currently, basement or tunnel internal in building are both provided with various pipelines, for example it is used for cloth If pipelines such as the gantry of electric wire, the air hose for ventilation and the water pipes for water supply, these pipelines be required to suspension and support into Row support, allows them to be mounted on building, and be generally mounted in the floor slab bottoms of building.
In the prior art, the pipe that suspension and support mostly uses greatly antidetonation suspension and support to support these pipelines, but install in building The size in road be not it is monolithic, different location region installation line size can difference, existing mounting means be Various sizes of pipeline is installed by customizing the antidetonation suspension and support of different size, installation cost can be increased in this way.
Utility model content
In view of this, providing a kind of Pipe installing size the purpose of the utility model is to overcome the deficiencies in the prior art Adjustable antidetonation suspension and support, to solve to need a variety of various sizes of antidetonations when installing various sizes of pipeline in the prior art The problem that bracket causes installation cost excessively high.
The technical scheme adopted by the utility model to solve the technical problem is as follows:
A kind of Pipe installing adjustable-size antidetonation suspension and support, including clip and first connecting rod, the first connecting rod are provided It is connect with the bottom of floor, the other end of the first connecting rod and the clamp connection, the clip includes upper cuff and lower hoop By locking device detachable connection, the upper cuff includes two framework framves, two institutes for set, the upper cuff and lower cuff It states framework frame to connect by second connecting rod, two framework framves can be slided on the second connecting rod so that two frames Body frame has structure identical with the upper cuff close to or far from, the lower cuff, and two framework framves of the lower cuff are logical The second locking device is crossed to fix.
Based on the above technical solution, the utility model can also do following improvement.
Further, one end of the first connecting rod is connect with the second connecting rod, the other end and building of the first connecting rod The bottom of plate connects, and the two sides of the first connecting rod have auxiliary rod, and one end of the auxiliary rod and the floor slab bottoms are slided Connection, the other end of the auxiliary rod and the clamp connection.
Further, there are two the first connecting rods, one end of two first connecting rods respectively with two framework framves The basal sliding of connection, the other end and floor of two first connecting rods connects, and the two sides of the first connecting rod have auxiliary Bar, one end of the auxiliary rod are slidably connected with the floor slab bottoms, the other end of the auxiliary rod and the clamp connection.
Further, the utility model further includes the sliding rail that floor slab bottoms are arranged in, and one end of the auxiliary rod is in the cunning Sliding, the other end of the auxiliary rod and the clamp connection in rail.
Further, the first connecting rod is telescopic rod, and the auxiliary rod is turnably connect with the clip, the sliding rail On be additionally provided with locating piece, the locating piece is located at the auxiliary rod close to the side of the first connecting rod, and the locating piece is used In the blocking auxiliary rod.
Further, the inner wall of the sliding rail is provided with sliding slot, is provided with support rod in the sliding slot, and the one of the auxiliary rod End cap is on the support rod.
Further, elastic component is set on the support rod, one end of the elastic component is contacted with the inner wall of the sliding rail, The other end of the elastic component is contacted with the auxiliary rod.
Further, the locking device includes that bolt and setting are used to install spiral shell in the upper cuff and lower cuff two sides The bolt mounting portion of bolt.
Further, it is provided with round tube fixed frame in the framework frame, the round tube fixed frame includes arc panel and fixed link, The arc panel is by the fixed link and the framework frame detachable connection, and the concave surface of the arc panel is far from the fixation Bar.
Further, safety rope is connected on the clip, the other end of the safety rope is connect with floor slab bottoms, described The length of safety rope is greater than the length of the first connecting rod.
Compared with prior art, the utility model has the beneficial effect that
The utility model by upper cuff and the cooperation of lower cuff by including Pipe installing, since upper cuff is by two frameworks Frame composition, while the distance between the distance between two framework framves and upper cuff and lower cuff are all alterable, so that Clip can adapt to the installation of a variety of various sizes of pipelines, solve previous building Pipe installing need to customize it is various sizes of The problem that antidetonation suspension and support causes Pipe installing cost excessively high.
Detailed description of the invention
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only It is some embodiments of the utility model, for those of ordinary skill in the art, in the premise not made the creative labor Under, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is the schematic diagram of the utility model;
Fig. 2 is the schematic diagram of first connecting rod in the 3rd embodiment of the utility model;
Fig. 3 is the schematic diagram of sliding rail in the fourth embodiment of the utility model;
Fig. 4 is the schematic diagram of locating piece in the 5th embodiment of utility model;
Fig. 5 is the schematic diagram of round tube fixed frame in the sixth embodiment of the utility model.
Wherein, the above drawings include the following reference numerals:
1-clip;110-upper cuffs;111-framework framves;112-second connecting rods;120-lower cuffs;130-the first spiral shell Bolt mounting portion;140-the second bolt mounting portion;2-first connecting rods;210-shaft mounting portions;3-auxiliary rods;4-sliding rails; 410-sliding slots;420-support rods;430-elastic components;5-locating pieces;510-positioning bolts;6-round tube fixed frames;610— Arc panel;620-fixed links;7-safety ropes.
Specific embodiment
To keep the purpose of this utility model, technical solution and advantage clearer, below by the technology to the utility model Scheme is described in detail.Obviously, the described embodiments are only a part of the embodiments of the utility model, rather than comprehensively Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are not before making creative work Obtained all other embodiment is put, the range that the utility model is protected is belonged to.
Embodiment 1:
A kind of Pipe installing adjustable-size antidetonation suspension and support, as shown in Figure 1, including first connecting rod 2 and clip 1, first Connecting rod 2 is connect with the bottom of floor, and the other end of first connecting rod 2 is connect with clip 1, and the clip 1 includes upper cuff 110 under Cuff 120, upper cuff 110 and lower cuff 120 can be used by locking device detachable connection, the first locking device in upper hoop The bolt mounting portion 130 of the two sides of set 110 and lower cuff 120 setting, is realized by being inserted into bolt into bolt mounting portion 130 Upper cuff 110 is fixedly connected with lower cuff 120.Upper cuff 110 includes two framework framves 111, and two framework framves 111 pass through the The connection of two connecting rods 112, two framework framves 111 can be slided on second connecting rod 112 so that two framework framves 111 are close or remote From lower cuff 120 has structure identical with upper cuff 110, and lower cuff 120 is also to be made of two framework framves 111.With at present The second locking device is provided on two framework framves 111 of cuff 120, the second locking device, which uses, is arranged in lower cuff 120 The second bolt mounting portion 140 on two framework framves 111, by the way that bolt to be mounted in the second bolt mounting portion 140 to real Now two framework framves 111 positioning of cuff 120, prevents two framework framves 111 of lower cuff 120 the second of lower cuff 120 It is slided on connecting rod 112, two framework framves 111 of upper cuff 110 are also therewith after the two of cuff 120 framework frame 111 is fixed instantly It is fixed.When the pipeline for needing installation dimension big, two framework framves 111 can be pulled to the two sides of second connecting rod 112, while upper hoop It can also be close to or far to realize the installation of different size pipelines between set 110 and lower cuff 120.
Embodiment 2:
In order to optimize above-mentioned technical proposal, as shown in Figure 1, one end of first connecting rod 2 is connect with second connecting rod 112, first The other end of connecting rod 2 and the bottom of floor connect, and the two sides of first connecting rod 2 have auxiliary rod 3, one end of auxiliary rod 3 and floor Basal sliding connection, the other end of auxiliary rod 3 are connect with clip 1, and auxiliary rod 3 can further strengthen the fixed effect of clip 1, To be further ensured that the stabilization of pipeline, when the size of clip 1, when specially width changes, auxiliary rod 3 is relative to floor Basal sliding can guarantee that auxiliary rod 3 has the effect of being fixedly connected always.
Embodiment 3:
In order to optimize above-mentioned technical proposal, as shown in Fig. 2, there are two first connecting rods 2, one end point of two first connecting rods 2 It is not connect with two framework framves 111, the other end of two first connecting rods 2 and the bottom of floor are rotatably connected, first connecting rod 2 Two sides have auxiliary rod 3, and one end and the floor slab bottoms of auxiliary rod 3 are slidably connected, and the other end of auxiliary rod 3 is connect with clip 1, when When the width of clip 1 changes, two first connecting rods 2 can be moved with the movement of framework frame 111, to make the first company Bar 2 can play the role of connection support clip 1 always.
Embodiment 4:
As shown in figure 3, the bottom of floor is provided with sliding rail 4, one end of auxiliary rod 3 is slided in sliding rail 4, auxiliary rod 3 The other end is connect with clip 1, specifically, the inner wall of sliding rail 4 is provided with sliding slot 410, support rod 420 is provided in sliding slot 410, One end of auxiliary rod 3 is sleeved on support rod 420, therefore auxiliary rod 3 can be mobile next in sliding slot 410 with support rod 420 Realization is moved on sliding rail 4.
In order to improve the damping effect of the utility model, elastic component 430 is set on support rod 420, elastic component 430 has Spring can be used in body, and one end of elastic component 430 is contacted with the inner wall of sliding rail 4, and the other end of elastic component 430 is contacted with auxiliary rod 3, When generating vibration, elastic component 4 can slow down the vibration axially generated along support plate 420, strengthen the stability of auxiliary rod 3, To strengthen the anti seismic efficiency of the utility model.
Embodiment 5:
In order to optimize above-mentioned further scheme, as shown in figure 4, telescopic rod of the first connecting rod 2 using extension type, auxiliary rod 3 turnably connect with clip 1.Specifically, may be provided with shaft mounting portion 210 on clip 1, set on shaft mounting portion 210 It is equipped with the axis hole for installing shaft, one end that auxiliary rod 3 is connect with clip 1 is sleeved in shaft, to realize that auxiliary rod 3 blocks The turnably connection of hoop 1, clip 1 is by the height of the adjustable clip 1 that stretches of first connecting rod 2, during height adjustment, One end of auxiliary rod 3 can be slided on sliding rail 4, if the height of clip 1 increases, the angle between two auxiliary rods 3 becomes larger, It is on the contrary then become smaller.Locating piece 5 is additionally provided on sliding rail 4, locating piece 5 is located at auxiliary rod 3 close to the side of first connecting rod 2, positioning Block 5 is used to limit auxiliary rod 3, after the height of clip 1 determines, by the way that locating piece 5 is fixed on sliding rail 4 and contacts blocking Auxiliary rod 3 can be realized the positioning to auxiliary rod 3, so that the height of clip 1 no longer changes, locating piece 5 is can be in sliding rail The sliding block slided on 4, the mounting hole for installing positioning bolt 510 is provided on locating piece 5, and positioning bolt 510 is screwed into fixed One end of the mounting hole post-positioning bolt 510 of position block 5 is abutted with the inner wall of sliding rail 4, to pass through positioning bolt 510 and sliding rail 4 The frictional force of inner wall realizes the positioning function of locating piece 5.
Embodiment 6:
As shown in figure 5, being provided with round tube fixed frame 6 in framework frame 111, round tube fixed frame 6 includes arc panel 610 and fixes Bar 620, arc panel 610 is by fixed link 620 and 111 detachable connection of framework frame, and the concave surface of arc panel 610 is far from fixed link 620, if need to install section is circular pipeline, arc panel 610 can be preferably bonded with the outer wall that section is circular pipeline, Preventing section is that the outer wall of circular pipeline is collided with.
Embodiment 7:
As shown in Figures 1 and 2, safety rope 7 is connected on clip 1, the other end of safety rope 7 is connect with floor slab bottoms, is protected The length of danger rope 7 is greater than the length of first connecting rod 2, and safety rope 7 is typically at doughy state, leads to the first company when vibration is too strong When bar 2 and auxiliary rod 3 are broken, safety rope 7 is in hard straight state and connects support clip 1, prevents pipeline from falling.
Above description is only a specific implementation of the present invention, but the protection scope of the utility model is not limited to In this, anyone skilled in the art within the technical scope disclosed by the utility model, can readily occur in variation Or replacement, it should be covered within the scope of the utility model.

Claims (10)

1. a kind of Pipe installing adjustable-size antidetonation suspension and support, for lifting pipeline, which is characterized in that including clip (1) and First connecting rod (2), the first connecting rod (2) connect with the bottom of floor, the other end and the clip of the first connecting rod (2) (1) it connects, the clip (1) includes upper cuff (110) and lower cuff (120), the upper cuff (110) and lower cuff (120) By the first locking device detachable connection, the upper cuff (110) includes two framework framves (111), two frameworks Frame (111) is connected by second connecting rod (112), and two framework framves (111) can be slided on the second connecting rod (112) So that two framework framves (111) are close to or far from the lower cuff (120) has identical with the upper cuff (110) Two framework framves (111) of structure, the lower cuff (120) are fixed by the second locking device.
2. Pipe installing adjustable-size antidetonation suspension and support according to claim 1, which is characterized in that the first connecting rod (2) one end is connect with the second connecting rod (112), and the other end of the first connecting rod (2) and the bottom of floor connect, described The two sides of first connecting rod (2) have auxiliary rod (3), and one end of the auxiliary rod (3) is slidably connected with the floor slab bottoms, described The other end of auxiliary rod (3) is connect with the clip (1).
3. Pipe installing adjustable-size antidetonation suspension and support according to claim 1, it is characterised in that: the first connecting rod (2) there are two, one end of two first connecting rods (2) is connect with two framework framves (111) respectively, and two described first The basal sliding of the other end and floor of connecting rod (2) connects, and the two sides of the first connecting rod (2) have auxiliary rod (3), described auxiliary One end of bar (3) is helped to be slidably connected with the floor slab bottoms, the other end of the auxiliary rod (3) is connect with the clip (1).
4. Pipe installing adjustable-size antidetonation suspension and support according to claim 2 or 3, which is characterized in that further include setting The sliding rail (4) in floor slab bottoms is set, one end of the auxiliary rod (3) is slided in the sliding rail (4), the auxiliary rod (3) The other end is connect with the clip (1).
5. Pipe installing adjustable-size antidetonation suspension and support according to claim 4, which is characterized in that the first connecting rod It (2) is telescopic rod, the auxiliary rod (3) turnably connect with the clip (1), is additionally provided with positioning on the sliding rail (4) Block (5), the locating piece (5) are located at side of the auxiliary rod (3) close to the first connecting rod (2), and the locating piece (5) is used In the blocking auxiliary rod (3).
6. Pipe installing adjustable-size antidetonation suspension and support according to claim 5, which is characterized in that the sliding rail (4) Inner wall be provided with sliding slot (410), is provided with support rod (420) in the sliding slot (410), an end cap of the auxiliary rod (3) On the support rod (420).
7. Pipe installing adjustable-size antidetonation suspension and support according to claim 6, which is characterized in that the support rod (420) it is set on elastic component (430), one end of the elastic component (430) is contacted with the inner wall of the sliding rail (4), the bullet The other end of property part (430) is contacted with the auxiliary rod (3).
8. Pipe installing adjustable-size antidetonation suspension and support according to claim 7, which is characterized in that the locking device It is used to install the bolt mounting portion of bolt in the upper cuff (110) and lower cuff (120) two sides including bolt and setting (130)。
9. antidetonation suspension and support according to claim 1, which is characterized in that it is solid to be provided with round tube in the framework frame (111) Determine frame (6), the round tube fixed frame (6) includes arc panel (610) and fixed link (620), and the arc panel (610) passes through described Fixed link (620) and framework frame (111) detachable connection, the concave surface of the arc panel (610) is far from the fixed link (620)。
10. antidetonation suspension and support according to claim 1, which is characterized in that safety rope (7) are connected on the clip (1), The other end of the safety rope (7) is connect with floor slab bottoms, and the length of the safety rope (7) is greater than the first connecting rod (2) Length.
CN201920057065.8U 2019-01-14 2019-01-14 A kind of Pipe installing adjustable-size antidetonation suspension and support Active CN209398930U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920057065.8U CN209398930U (en) 2019-01-14 2019-01-14 A kind of Pipe installing adjustable-size antidetonation suspension and support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920057065.8U CN209398930U (en) 2019-01-14 2019-01-14 A kind of Pipe installing adjustable-size antidetonation suspension and support

Publications (1)

Publication Number Publication Date
CN209398930U true CN209398930U (en) 2019-09-17

Family

ID=67898382

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920057065.8U Active CN209398930U (en) 2019-01-14 2019-01-14 A kind of Pipe installing adjustable-size antidetonation suspension and support

Country Status (1)

Country Link
CN (1) CN209398930U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110848462A (en) * 2019-11-05 2020-02-28 中船黄埔文冲船舶有限公司 Clamp formula elastic support device
CN111578024A (en) * 2020-05-26 2020-08-25 合肥同源化工科技有限公司 Reinforced three-way pipe fitting

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110848462A (en) * 2019-11-05 2020-02-28 中船黄埔文冲船舶有限公司 Clamp formula elastic support device
CN111578024A (en) * 2020-05-26 2020-08-25 合肥同源化工科技有限公司 Reinforced three-way pipe fitting
CN111578024B (en) * 2020-05-26 2021-12-14 圣大管业(芜湖)科技有限公司 Reinforced three-way pipe fitting

Similar Documents

Publication Publication Date Title
CN209398930U (en) A kind of Pipe installing adjustable-size antidetonation suspension and support
CN205536429U (en) Air conditioner tube hanger
CN106969208A (en) A kind of gate antidetonation suspension and support
CN206874971U (en) A kind of gate antidetonation suspension and support
CN207421538U (en) One kind is directed to suspension and support erecting device
CN210890395U (en) Anti-seismic support is stabilized to high strength
CN206377099U (en) Pin-and-hole connector, shock-resistant slant bar assembly and the antidetonation suspension bracket of brace are shaken for bilateral monoclonal antibody
CN210766873U (en) Circular piping lane support
CN204529015U (en) A kind of V-type elevator wall-attached frame
CN208982781U (en) Air hose mounting bracket in truss
CN108105476B (en) Anti-shaking fixing method for siphon drain pipe crossing grid structure
CN206377128U (en) Keyhole connector, shock-resistant slant bar assembly and the antidetonation suspension bracket of brace are shaken for bilateral monoclonal antibody
CN215721265U (en) Horizontal pipeline support device for rail transit fire engineering
CN208720469U (en) The horizontal soft binding structure of air hose with shock insulation compensation function
CN210344551U (en) Vertical hoisting device for ultra-long air pipe
CN209146691U (en) A kind of antidetonation connecting elements and antidetonation suspension and support
CN208311669U (en) A kind of single tube antidetonation suspension and support
CN209164759U (en) A kind of building pipe suspended fixing component
CN208267847U (en) A kind of shield machine shock bracket
CN219588287U (en) Shock-resistant support and hanger for ventilating duct
CN109882657B (en) Pipeline flexible support and inner and outer pipeline mounting structure
CN206646838U (en) Self-interacting type steel plate wall corrects trivet
CN219196830U (en) Anti-seismic reinforcing structure for building support
CN212080356U (en) Galvanized steel pipe with stronger suspension stability
CN216242699U (en) Pipeline supporting and hanging frame

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant