CN209384033U - A kind of penetration type connection reinforcing structure of concrete filled steel tube and sleeper block - Google Patents

A kind of penetration type connection reinforcing structure of concrete filled steel tube and sleeper block Download PDF

Info

Publication number
CN209384033U
CN209384033U CN201822104222.4U CN201822104222U CN209384033U CN 209384033 U CN209384033 U CN 209384033U CN 201822104222 U CN201822104222 U CN 201822104222U CN 209384033 U CN209384033 U CN 209384033U
Authority
CN
China
Prior art keywords
concrete filled
filled steel
sleeper
reinforcer
steel tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822104222.4U
Other languages
Chinese (zh)
Inventor
孙立
王森荣
李秋义
杨艳丽
朱彬
李启航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201822104222.4U priority Critical patent/CN209384033U/en
Application granted granted Critical
Publication of CN209384033U publication Critical patent/CN209384033U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses the penetration type connection reinforcing structures of a kind of concrete filled steel tube and sleeper block, for in the concrete filled steel tube sleeper of non-fragment orbit, the concrete filled steel tube sleeper includes the more concrete filled steel tubes (2) that two or more sleeper blocks (1) connect above-mentioned sleeper block (1) with track transverse direction, the sleeper block (1) is formed by concreting, the concrete filled steel tube (2) is configured in the manufacture mold for being arranged in two sleeper blocks (1) adjacent to each other using hollow steel pipe, it pours and is integrated with the sleeper block (1) in the casting process of the sleeper block (1), concrete is filled in the hollow steel pipe simultaneously;It is characterized by: the parts transversely in hollow steel pipe insertion sleeper block (1) is provided with aperture, lateral reinforcer (3) partly or entirely are being worn in the aperture of hollow steel pipe two-by-two, to reinforce the connection between concrete filled steel tube (2) and sleeper block (1).

Description

A kind of penetration type connection reinforcing structure of concrete filled steel tube and sleeper block
Technical field
The utility model belongs to non-fragment orbit correlative technology field, is related to a kind of using the multiple coagulations of concrete filled steel tube connection The block-like technology of soil, relates more specifically to the penetration type connection reinforcing structure of a kind of concrete filled steel tube and sleeper block.
Background technique
In railway ballastless track system, there is a kind of prefabricated sleeper, sleeper is mounted in railway roadbed or using concrete It pours and is integrated with railway roadbed, be used to fastener for installing, further fix the rail of top, and need to keep good connection with railway roadbed Performance.
Chinese patent literature CN105463948B discloses a kind of concrete filled steel tube sleeper suitable for non-fragment orbit, uses steel Connecting component of the pipe concrete as sleeper block, compared with the connection of general Combined type reinforced truss, globality is stronger, can be effective Alleviate deformation of concrete sleeper durings storage, transport etc.;Pass through concrete filled steel tube and the one of sleeper concrete block simultaneously It is body formed, i.e., while pouring sleeper concrete block realize concrete filled steel tube forming, and by concrete filled steel tube be designed to by More hollow steel pipe compositions, are effectively increased sleeper track geometry holding capacity, reduce amount of reinforcement, improving can construct Property, it can directly construct at the scene, meet the requirement of sleeper bending-twisting ability.
However, further study showed that, above-mentioned sleeper still remains following problems:
Concrete filled steel tube is formed after pouring concrete within steel pipe, concrete filled steel tube surface is relatively smooth steel face, After the materials such as direct Transducers Embedded in Concrete, reclaimed rubber, resin material, the bond stress being in contact with it is limited;With two outer diameter 40mm Steel pipe insertion 200mm depth concrete sleeper block in for, the bond stress that is formed between concrete is 2.5t, and steel pipe is mixed There are also to be strengthened for connection between solidifying soil and sleeper block.
Prefabricated double-block type concrete filled steel tube sleeper is tied up, is lifted and heap is left with during being transported to construction site In difficulty.
After prefabricated concrete sleeper is transported to railway line construction site, during the cast in situs of road bed board, sleeper The railway roadbed board concrete that the inlet part of block is poured with after connect not secured enough, and there are endurance issues, meetings between New-old concrete The diseases such as crack, these all could be improved raising.
Utility model content
For at least one of prior art the above defects or improvement requirements, it is mixed that the utility model provides a kind of steel pipe The penetration type connection reinforcing structure of solidifying soil and sleeper block, through setting reinforcer in the hollow steel pipe of concrete filled steel tube, such as The works such as reinforcing bar, and the position of reinforcer is specifically designed, so that the concrete etc. of concrete filled steel tube and sleeper block Combination between material is more secured.
To achieve the above object, according to the one aspect of the utility model, a kind of concrete filled steel tube and sleeper block are provided Penetration type connection reinforcing structure, in the concrete filled steel tube sleeper of non-fragment orbit, the concrete filled steel tube sleeper includes two A or more sleeper block connects more concrete filled steel tubes of above-mentioned sleeper block with track transverse direction, and the sleeper block is by concrete It pours, the concrete filled steel tube is configured to be arranged in the manufacture mold of two sleeper blocks adjacent to each other using hollow steel pipe It is interior, it pours and is integrated with the sleeper block in the casting process of the sleeper block, while filling coagulation in the hollow steel pipe Soil;
The parts transversely of hollow steel pipe insertion sleeper block is provided with aperture, partly or entirely hollow steel pipe is opened two-by-two Lateral reinforcer is worn in hole, and is partial to described in interior direction, eccentric setting in outermost two sleeper blocks from center Reinforcer, thus in the concrete that the reinforcer is at least partially buried sleeper block in the casting process of the sleeper block, with Reinforce the connection between concrete filled steel tube and sleeper block.
Preferably, the rod iron of radial direction is further fixed on the outer wall of the concrete filled steel tube;The rod iron setting exists The position not conflicted with the aperture and the reinforcer;And it is partial to interior side from center in outermost two sleeper blocks To rod iron described in, eccentric setting.
Preferably, the aperture of two hollow steel pipes is located in the same perpendicular of track longitudinal direction, and the reinforcer is just Extend transversely through two concrete filled steel tubes;
The rod iron includes multiple, the circumferentially distributed outer wall in the concrete filled steel tube, and with the reinforcer in track On longitudinal same perpendicular, or with the reinforcer on multiple and different perpendiculars of track longitudinal direction.
Preferably, the aperture of two hollow steel pipes is located in multiple and different perpendiculars of track longitudinal direction, is oblique aperture, The reinforcer tiltedly extends transversely through two concrete filled steel tubes;
The rod iron includes multiple, the circumferentially distributed outer wall in the concrete filled steel tube, and is located at the oblique aperture institute On the oblique perpendicular being in, or it is not located on oblique perpendicular locating for the oblique aperture.
Preferably, the reinforcer is vertical bar shaped;Including at least such one group of chiasma type reinforcer, that is, two difference are oblique The reinforcer being laterally arranged is arranged in the plane locating for the axial line of two concrete filled steel tubes in X-type cross.
Preferably, on the longitudinal direction of track, the both ends of the reinforcer are stretched out the two sides of the sleeper block, are exposed Two concrete filled steel tubes are not only run through in end, by this method, the reinforcer, also extend through sleeper block, thus pouring in road bed board During building, the exposing end of sleeper block, concrete filled steel tube, reinforcer is poured and is integrated.
Preferably, the reinforcer includes multiple, and setting is successively spaced along the longitudinal direction of the concrete filled steel tube;It is multiple described As a whole, integral central is from interior direction is partial at the center of outermost two sleeper blocks, bias is set for reinforcer It sets.
Preferably, multiple reinforcers are divided into two groups up and down in different height, and multiple apertures are also accordingly divided into Two groups up and down in different height, that is, both include be applied in two concrete filled steel tubes, the reinforcement in the aperture of top Part, but including being applied in two concrete filled steel tubes, reinforcer in the aperture of lower section, and upper and lower two groups of reinforcers are along the steel The longitudinal direction of pipe concrete successively replaces, is spaced setting, i.e., one on the other, longitudinally successively replaces, is spaced setting.
Preferably, the shape design of the reinforcer is, with header structure is amplified, the amplification header structure is arranged at The size at the both ends of the reinforcer, the amplification header structure is greater than the size of the reinforcer other positions.
Preferably, part of the reinforcer between two concrete filled steel tubes, axial line are at least locally wave Shape wave or fold-line-shaped or spiral shape;
Alternatively, the reinforcer only has one end, axial line is locally at least waveform or fold-line-shaped or spiral shape.
Above-mentioned preferred feature can be combined with each other as long as they do not conflict with each other.
In general, have the above technical solutions conceived by the present invention are compared with the prior art, with following Beneficial effect:
1, the penetration type connection reinforcing structure of the concrete filled steel tube of the utility model and sleeper block, in two connector of steel tube Between be provided through the works such as lateral reinforcer, such as reinforcing bar, sleeper block is embedded to during the cast in situs of in-orbit bolster In, pour and be integrated, while concrete is filled in hollow steel pipe so that the materials such as concrete of concrete filled steel tube and sleeper block it Between combination it is more secured.
2, in the penetration type connection reinforcing structure of the concrete filled steel tube of the utility model and sleeper block, to reinforcer in sleeper Specific location in block is specifically designed respectively;Further study show that the reality of the concrete filled steel tube sleeper of non-fragment orbit In the application of border, steel pipe is forced outwardly, and steel pipe protrudes into that the shallower part stress of sleeper block is larger, and disease is more, and the discovery is also It there are no prior art report;Based on this discovery, reinforcer is partial to sleeper block as far as possible and is arranged in the inner part, specifically, from rail The reinforcer of interior direction, eccentric setting is partial at bolster center, the inside 50-100mm apart from sleeper block, steel pipe at the position The locking effect generated between concrete and sleeper block is best, after train operation, can effectively reduce concrete filled steel tube and sleeper block The disease of junction.Equally in the concrete sleeper block of the steel pipe of two outer diameter 40mm insertion 200mm depth, pass through reality Border test, applies after the load of 8t until concrete rupture steel pipe is not still extracted.By the setting of above-mentioned both sides, by steel pipe It is locked with materials such as concrete, since the perforative reinforcing bar of steel duct has extended transversely into concrete when pulling out steel pipe outward The inside of equal materials, greatly improves the binding force of the materials such as steel pipe and concrete.
3, the penetration type connection reinforcing structure of the concrete filled steel tube of the utility model and sleeper block is reinforced by circumferential welding The construction of small rod iron and being specifically designed for eccentric position, are used in combination with through reinforcing bar, strengthen resultant effect;Basis is passed through simultaneously The variation for wearing reinforcing bar and reinforcing positional relationship between small rod iron, arranging quantity, realizes the adjusting of reinforcement structure bonding strength, obtains The synthesis reinforcing effect for obtaining multistage gradient, adapts to the intensity requirement of different regions, while balance is obtained in terms of loss of weight.
4, the penetration type connection reinforcing structure of the concrete filled steel tube of the utility model and sleeper block, passes through the straight of stiffener Stripwise construction, manufacture easy to process, and by the setting of oblique reinforcing bar, stiffener is increased in the sleeper block of unit-sized Length, connection fastening force is increased, especially by the structure of the X-type cross reinforcing bar in the axial line plane of two concrete filled steel tubes Make, other than with steel pipe transverse component, also have steel pipe longitudinal component, form planar space, can effectively resist and The vibration in train operation is transmitted, disease is reduced.
5, the penetration type connection reinforcing structure of the concrete filled steel tube of the utility model and sleeper block, it is also outstanding with one Feature has extended not only through two concrete filled steel tubes through reinforcing bar, has also extended through sleeper block, in this way by double-block type concrete filled steel tube rail During pillow is transported to railway roadbed construction site, the reinforcing bar stretched out on the outside of sleeper block is conducive to carry, and can be used as artificial or rope The stress supporting point of the tools such as rope can pass through the reinforcing bar of outer stretching by suspenders such as ropes also during transportation come bundling rail Sleeper is fixed in pillow or stacking process, the number of plies of an other side can be more, and single freight volume is bigger, and sleeper is transported Safety and stability during defeated storage.During the concrete cast in situs of road bed board, by sleeper block, concrete filled steel tube, add The exposing end of strong part, which pours, to be integrated, and the lower part of sleeper block is directly directly poured with road bed board no longer as the prior art, But by pre-buried reinforcing bar extension end, the bonding strength between sleeper block and road bed board is strengthened.
6, the penetration type connection reinforcing structure of the concrete filled steel tube of the utility model and sleeper block, is made by multiple reinforcers It plays a role for the construction of an entire combination, and various whole interconnection schemes can be combined into, such as both can be along steel pipe The longitudinal direction of concrete is successively spaced, is arranged in parallel, and can also be realized by the variation of aperture height and one on the other, longitudinally successively be handed over It replaces, be spaced setting, from there through the dislocation resultant force of up and down direction, avoid the connection of many places crackle on sustained height from generating and run through Long crack is further promoted and reinforces intensity, meanwhile, still follow the arrangement principle of eccentric setting.
7, the penetration type connection reinforcing structure of the concrete filled steel tube of the utility model and sleeper block, passes through putting for stiffener The design of big structure and its position, similar to the amplifying head of Screw Pile bottom, in the work for locally playing basis and resistance sluggishness With, it is therefore prevented that the movement of reinforcing bar.
8, the penetration type connection reinforcing structure of the concrete filled steel tube of the utility model and sleeper block, passes through stiffener itself In the middle part of the unique design of various configuration on extending direction, an especially reinforcer or end, partially or fully waveform, broken line The configurations such as shape, screw thread shape increase the contact length of stiffener and concrete in the sleeper block of unit-sized, improve tight Gu power to improve the bond stress between concrete filled steel tube and sleeper concrete, while ensure that the configuration of above-mentioned curve not Interfere the operation across two steel pipes.
Detailed description of the invention
When Fig. 1 is double block sleeper in the concrete filled steel tube of the utility model and the penetration type connection reinforcing structure of sleeper block Schematic diagram;
When Fig. 2 is three blocks of sleepers in the concrete filled steel tube of the utility model and the penetration type connection reinforcing structure of sleeper block Schematic diagram;
Fig. 3 is in the concrete filled steel tube of the utility model and the penetration type connection reinforcing structure of sleeper block through reinforcer Side schematic cross-sectional view;
Fig. 4 is rod iron reinforcer in the concrete filled steel tube of the utility model and the penetration type connection reinforcing structure of sleeper block Side schematic cross-sectional view;
Fig. 5 is that reinforcer runs through rail in the concrete filled steel tube of the utility model and the penetration type connection reinforcing structure of sleeper block Side schematic cross-sectional view when bolster;
Fig. 6 is that the concrete filled steel tube of the utility model is put with reinforcer end in the penetration type connection reinforcing structure of sleeper block The side schematic cross-sectional view of big structure;
Fig. 7 be in the concrete filled steel tube of the utility model and the penetration type connection reinforcing structure of sleeper block reinforcer end and The side schematic cross-sectional view of middle part enlarged structure.
Specific embodiment
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, below in conjunction with attached drawing and implementation Example, the present invention will be further described in detail.It should be appreciated that specific embodiment described herein is only used to explain The utility model is not used to limit the utility model.In addition, institute in the various embodiments of the present invention described below The technical characteristic being related to can be combined with each other as long as they do not conflict with each other.With reference to embodiment to this Utility model is further described.
The utility model provides the connection reinforcing structure of a kind of concrete filled steel tube and sleeper block, the steel pipe for non-fragment orbit In concrete sleeper, the concrete filled steel tube sleeper includes two or more sleeper blocks 1 and more steel for connecting above-mentioned sleeper block 1 Pipe concrete 2, the sleeper block 1 are formed by concreting, and the concrete filled steel tube 2 is configured to be arranged in using hollow steel pipe In the manufacture mold of two sleeper blocks 1 adjacent to each other, during the cast in situs of the sleeper block 1 with the sleeper block 1 It pours and is integrated, while filling concrete in the hollow steel pipe;Setting connection adds between concrete filled steel tube 2 and sleeper block 1 Connection reinforcing structure is set between strong structure and/or in-orbit bolster 1 and railway roadbed.
As shown in figs. 1-7, the parts transversely of hollow steel pipe insertion sleeper block 1 is provided with aperture, part or all of two Lateral reinforcer 3 (as shown in Figure 3) is worn in the aperture of two hollow steel pipes, is preferably welded through tapping, and most It is partial to reinforcer 3 (as shown in Figure 1) described in interior direction, eccentric setting from center in two sleeper blocks 1 in outside, thus institute It states in the concrete that reinforcer 3 is at least partially buried sleeper block in the casting process of the sleeper block 1, to reinforce steel tube concrete Connection between soil 2 and sleeper block 1.As shown in Fig. 2, there are three if (or more) sleeper block, such as at track switch, due to mid-rail Bolster and two sides sleeper block have connection, and the reinforcer in mid-rail bolster can be divided into two groups, still follow above-mentioned bias and set The case where setting principle, respectively correspond the sleeper block of two sides, the one group of reinforcer in deviation left side is illustrated only in Fig. 2.Certainly, reinforcer Setting should avoid pre-embedded bolt casing.
The penetration type connection reinforcing structure of the concrete filled steel tube of the utility model and sleeper block, two connector of steel tube it Between be provided through the works such as lateral reinforcer, such as reinforcing bar, be embedded in sleeper block during the cast in situs of in-orbit bolster, It pours and is integrated, while filling concrete in hollow steel pipe, so that between the materials such as concrete of concrete filled steel tube and sleeper block Combination it is more secured.In the concrete filled steel tube of the utility model and the penetration type connection reinforcing structure of sleeper block, to reinforcer Specific location in in-orbit bolster is specifically designed respectively;Further study show that the concrete filled steel tube rail of non-fragment orbit In the practical application of pillow, steel pipe is forced outwardly, and steel pipe protrudes into that the shallower part stress of sleeper block is larger, and disease is more, should It was found that yet there are no prior art report;Based on this discovery, reinforcer is partial to sleeper block as far as possible and is arranged in the inner part, specifically Ground is partial to the reinforcer of interior direction, eccentric setting, the inside 50-100mm apart from sleeper block, the position from sleeper block center The locking effect generated between the place's of setting concrete filled steel tube and sleeper block is best, after train operation, can effectively reduce concrete filled steel tube With the disease of sleeper block junction.Equally to be in the concrete sleeper block of the steel pipe insertion 200mm depth of two outer diameter 40mm Example is applied after the load of 8t until concrete rupture steel pipe is not still extracted by actual test.It is set by above-mentioned both sides It sets, lock the materials such as steel pipe and concrete, since the perforative reinforcing bar of steel duct has laterally been stretched when pulling out steel pipe outward Enter the binding force that the materials such as steel pipe and concrete are greatly improved to the inside of the materials such as concrete.
Preferably, as shown in figure 4, being further fixed on the rod iron 4 of radial direction on the outer wall of the concrete filled steel tube 2;Institute It states rod iron 4 and the position not conflicted with the aperture and the reinforcer 3 is set;And in outermost two sleeper blocks 1 therefrom The heart is partial to rod iron 4 described in interior direction, eccentric setting.Preferably, the aperture of two hollow steel pipes is located at the same of track longitudinal direction In one perpendicular, the reinforcer 3 is just extending transversely through two concrete filled steel tubes 2;The rod iron 4 is including multiple, The even circumferentially distributed outer wall in the concrete filled steel tube 2, and the same perpendicular with the reinforcer 3 in track longitudinal direction On, or with the reinforcer 3 on multiple and different perpendiculars of track longitudinal direction.The concrete filled steel tube and rail of the utility model The penetration type connection reinforcing structure of bolster reinforces the construction of small rod iron and being specifically designed for eccentric position by circumferential welding, with It is used in combination through reinforcing bar, strengthens resultant effect;Simultaneously according to positional relationship, arrangement between reinforcing bar and the small rod iron of reinforcement The variation of quantity realizes the adjusting of reinforcement structure bonding strength, obtains the synthesis reinforcing effect of multistage gradient, adapts to different The intensity requirement in area, while balance is obtained in terms of loss of weight.
Preferably, the aperture of two hollow steel pipes is located in multiple and different perpendiculars of track longitudinal direction, is oblique aperture (not shown), the reinforcer 3 tiltedly extend transversely through two concrete filled steel tubes 2;The rod iron 4 is circumferentially distributed including multiple In the outer wall of the concrete filled steel tube 2, and it is located on oblique perpendicular at the oblique aperture, or is not located at institute It states on oblique perpendicular locating for oblique aperture.Preferably, the reinforcer 3 is vertical bar shaped;Including at least such one group of friendship Forked type reinforcer, that is, the reinforcer that two difference are tiltedly laterally arranged is in the plane locating for the axial line of two concrete filled steel tubes 2 X-type cross setting.The concrete filled steel tube of the utility model and the penetration type connection reinforcing structure of sleeper block, pass through stiffener Vertical bar shaped construction, manufacture easy to process, and by the setting of oblique reinforcing bar, reinforcement steel is increased in the sleeper block of unit-sized The length of muscle increases connection fastening force, especially by the X-type cross reinforcing bar in the axial line plane of two concrete filled steel tubes Construction also has steel pipe longitudinal component, forms planar space, can effectively resist other than with steel pipe transverse component Vibration in transmitting train operation, reduces disease.
Preferably, as shown in figure 5, on the longitudinal direction of track, the sleeper block 1 is stretched out at the both ends of the reinforcer 3 Two sides, expose end, by this method, the reinforcer 3 not only run through two concrete filled steel tubes 2, also extend through sleeper block 1, To in the casting process of road bed board, the exposing end of sleeper block 1, concrete filled steel tube 2, reinforcer 3 is poured and is integrated.This The penetration type connection reinforcing structure of the concrete filled steel tube of utility model and sleeper block, also have the characteristics that one it is prominent, through steel Muscle has extended not only through two concrete filled steel tubes, has also extended through sleeper block, is in this way transported to double-block type concrete filled steel tube sleeper During bed construction site, the reinforcing bar stretched out on the outside of sleeper block is conducive to carry, and can be used as the tools such as artificial or rope Stress supporting point can be passed through the reinforcing bar of outer stretching by suspenders such as ropes also during transportation come bundling sleeper, or be stacked In the process fix sleeper, the number of plies of an other side can be more, and single freight volume is bigger, and make sleeper transport storage during Safety and stability.During the concrete cast in situs of road bed board, by sleeper block, concrete filled steel tube, reinforcer bared end Head, which pours, to be integrated, and the lower part of sleeper block is directly directly poured with road bed board no longer as the prior art, but by pre-buried Reinforcing bar extension end, strengthen the bonding strength between sleeper block and road bed board.
Preferably, as shown in Figs. 1-2, the reinforcer 3 include it is multiple, along the longitudinal direction of the concrete filled steel tube 2 successively between Every setting;Multiple reinforcers 3 as a whole, be partial to from the center of outermost two sleeper blocks by integral central Interior direction, eccentric setting.Preferably, the reinforcer 3 is vertical bar shaped;Including at least such one group of parallel reinforcer, that is, Along the longitudinal direction of the concrete filled steel tube 2, two reinforcers successively are parallel to each other.Preferably, multiple reinforcers 3 divide for place In two groups up and down of different height, multiple apertures are also accordingly divided into two groups up and down in different height, that is, both include running through In two concrete filled steel tubes 2, the reinforcer in the aperture of top, and including being applied in two concrete filled steel tubes 2, Reinforcer in the aperture of lower section, and upper and lower two groups of reinforcers successively replace along the longitudinal direction of the concrete filled steel tube 2, are spaced setting, i.e., One on the other, longitudinal successively to replace, be spaced setting.The concrete filled steel tube of the utility model and the penetration type connection reinforcement of sleeper block Structure is played a role by construction that multiple reinforcers combine as a whole, and can be combined into various whole interconnection Scheme, such as both can successively be spaced, be arranged in parallel along the longitudinal direction of concrete filled steel tube, it can also be real by the variation of aperture height Now one on the other, longitudinally successively replace, be spaced setting, from there through the dislocation resultant force of up and down direction, avoiding more on sustained height The connection for locating crackle, which generates, runs through long crack, is further promoted and reinforces intensity, meanwhile, the arrangement for still following eccentric setting is former Then.
Preferably, as shown in fig. 6-7, the shape design of the reinforcer 3 is with amplification header structure 5, the amplifying head Structure 5 is arranged at the both ends of the reinforcer, and the size of the amplification header structure 5 is greater than the reinforcer other positions Size.For example, reinforcer 3 is after steel pipe, the amplifying head of end can be bolt screw on or welding, the amplification at middle part Head can be the rod iron of welding or the bolt of welding etc..The concrete filled steel tube of the utility model is connect with the penetration type of sleeper block to be added Strong structure is locally being risen by the enlarged structure of stiffener and its design of position similar to the amplifying head of Screw Pile bottom The effect of basis and resistance sluggishness is arrived, it is therefore prevented that the movement of reinforcing bar.
Preferably, part of the reinforcer 3 between two concrete filled steel tubes 2, axial line are at least locally Waveform or fold-line-shaped or spiral shape (not shown);Alternatively, the reinforcer 3 only has one end, axial line is at least locally wave Shape wave or fold-line-shaped or spiral shape (not shown).8, the penetration type connection reinforcement of the concrete filled steel tube of the utility model and sleeper block Structure, by the unique design of various configuration on stiffener itself extending direction, especially in the middle part of a reinforcer or end, The partially or fully configurations such as waveform, fold-line-shaped, screw thread shape increase stiffener and coagulation in the sleeper block of unit-sized The contact length of soil, improves fastening force, to improve the bond stress between concrete filled steel tube and sleeper concrete, protects simultaneously The configuration for having demonstrate,proved above-mentioned curve does not interfere the operation across two steel pipes.
As it will be easily appreciated by one skilled in the art that the above is only the preferred embodiment of the utility model only, not To limit the utility model, any modification made within the spirit and principle of the present invention, equivalent replacement and change Into etc., it should be included within the scope of protection of this utility model.

Claims (10)

1. the penetration type connection reinforcing structure of a kind of concrete filled steel tube and sleeper block, the concrete filled steel tube sleeper for non-fragment orbit In, the concrete filled steel tube sleeper includes that two or more sleeper blocks (1) connect above-mentioned sleeper block (1) with track transverse direction More concrete filled steel tubes (2), the sleeper block (1) are formed by concreting, and the concrete filled steel tube (2) is configured to utilize sky Heart steel pipe is arranged in the manufacture mold of two sleeper blocks (1) adjacent to each other, in the casting process of the sleeper block (1) with The sleeper block (1), which pours, to be integrated, while filling concrete in the hollow steel pipe;It is characterized by:
The parts transversely of hollow steel pipe insertion sleeper block (1) is provided with aperture, partly or entirely hollow steel pipe is opened two-by-two It is worn in hole lateral reinforcer (3), and from interior direction is partial at center, bias is set in outermost two sleeper blocks (1) The reinforcer (3) are set, so that the reinforcer (3) is at least partially buried sleeper in the casting process of the sleeper block (1) In the concrete of block, to reinforce the connection between concrete filled steel tube (2) and sleeper block (1).
2. the penetration type connection reinforcing structure of concrete filled steel tube as described in claim 1 and sleeper block, it is characterised in that:
The rod iron (4) of radial direction is further fixed on the outer wall of the concrete filled steel tube (2);The rod iron (4) is arranged not The position to conflict with the aperture and the reinforcer (3);And it is partial to inside from center in outermost two sleeper blocks (1) Rod iron described in direction, eccentric setting (4).
3. the penetration type connection reinforcing structure of concrete filled steel tube as claimed in claim 2 and sleeper block, it is characterised in that:
The aperture of two hollow steel pipes is located in the same perpendicular of track longitudinal direction, and the reinforcer (3) is just extending transversely through Two concrete filled steel tubes (2);
The rod iron (4) includes multiple, the circumferentially distributed outer wall in the concrete filled steel tube (2), and exists with the reinforcer (3) On the same perpendicular of track longitudinal direction, or with the reinforcer (3) on multiple and different perpendiculars of track longitudinal direction.
4. the penetration type connection reinforcing structure of concrete filled steel tube as claimed in claim 2 and sleeper block, it is characterised in that:
The aperture of two hollow steel pipes is located in multiple and different perpendiculars of track longitudinal direction, is oblique aperture, the reinforcer (3) two concrete filled steel tubes (2) are tiltedly extended transversely through;
The rod iron (4) includes multiple, the circumferentially distributed outer wall in the concrete filled steel tube (2), and is located at the oblique aperture On positioned oblique perpendicular, or it is not located on oblique perpendicular locating for the oblique aperture.
5. the penetration type connection reinforcing structure of concrete filled steel tube as claimed in claim 4 and sleeper block, it is characterised in that:
The reinforcer (3) is vertical bar shaped;Including at least such one group of chiasma type reinforcer, that is, two difference are tiltedly laterally arranged Reinforcer in the plane locating for the axial line of two concrete filled steel tubes (2) in X-type cross be arranged.
6. such as the penetration type connection reinforcing structure of the described in any item concrete filled steel tubes of claim 1-2 and sleeper block, feature It is:
On the longitudinal direction of track, the both ends of the reinforcer (3) stretch out the two sides of the sleeper block (1), expose end, By this method, the reinforcer (3) not only runs through two concrete filled steel tubes (2), sleeper block (1) is also extended through, thus in road bed board Casting process in, the exposing end of sleeper block (1), concrete filled steel tube (2), reinforcer (3) is poured and is integrated.
7. the penetration type connection reinforcing structure of concrete filled steel tube as claimed in claim 2 and sleeper block, it is characterised in that:
The reinforcer (3) include it is multiple, setting is successively spaced along the longitudinal direction of the concrete filled steel tube (2);Multiple reinforcements As a whole, integral central is from interior direction is partial at the center of outermost two sleeper blocks, bias is set for part (3) It sets.
8. the penetration type connection reinforcing structure of concrete filled steel tube as claimed in claim 7 and sleeper block, it is characterised in that:
Multiple reinforcers (3) are divided into two groups up and down in different height, and multiple apertures are also accordingly divided into difference Two groups up and down of height, that is, not only include be applied in two concrete filled steel tubes (2), the reinforcer in the aperture of top, but also packet Include be applied in two concrete filled steel tubes (2), reinforcer in the aperture of lower section, and upper and lower two groups of reinforcers are mixed along the steel pipe The longitudinal direction of solidifying soil (2) successively replaces, is spaced setting, i.e., one on the other, longitudinally successively replaces, is spaced setting.
9. the penetration type connection reinforcing structure of concrete filled steel tube as claimed in claim 2 and sleeper block, it is characterised in that:
The shape design of the reinforcer (3) is, with header structure (5) are amplified, the amplification header structure (5) is arranged at institute The both ends of reinforcer are stated, the size of amplification header structure (5) is greater than the size of the reinforcer other positions.
10. the penetration type connection reinforcing structure of concrete filled steel tube as claimed in claim 6 and sleeper block, it is characterised in that:
Part of the reinforcer (3) between two concrete filled steel tubes (2), axial line at least locally for waveform or Fold-line-shaped or spiral shape;
Alternatively, the reinforcer (3) only has one end, axial line is locally at least waveform or fold-line-shaped or spiral shape.
CN201822104222.4U 2018-12-14 2018-12-14 A kind of penetration type connection reinforcing structure of concrete filled steel tube and sleeper block Active CN209384033U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822104222.4U CN209384033U (en) 2018-12-14 2018-12-14 A kind of penetration type connection reinforcing structure of concrete filled steel tube and sleeper block

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822104222.4U CN209384033U (en) 2018-12-14 2018-12-14 A kind of penetration type connection reinforcing structure of concrete filled steel tube and sleeper block

Publications (1)

Publication Number Publication Date
CN209384033U true CN209384033U (en) 2019-09-13

Family

ID=67871991

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822104222.4U Active CN209384033U (en) 2018-12-14 2018-12-14 A kind of penetration type connection reinforcing structure of concrete filled steel tube and sleeper block

Country Status (1)

Country Link
CN (1) CN209384033U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109457548A (en) * 2018-12-14 2019-03-12 中铁第四勘察设计院集团有限公司 A kind of penetration type connection reinforcing structure of concrete filled steel tube and sleeper block

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109457548A (en) * 2018-12-14 2019-03-12 中铁第四勘察设计院集团有限公司 A kind of penetration type connection reinforcing structure of concrete filled steel tube and sleeper block

Similar Documents

Publication Publication Date Title
CN109457550A (en) Groove type connection reinforcing structure and construction method between a kind of sleeper block and railway roadbed
CN207260628U (en) A kind of walls with brick masonry structure ruggedized construction
CN109457548A (en) A kind of penetration type connection reinforcing structure of concrete filled steel tube and sleeper block
CN108330823B (en) Assembled steel reinforced concrete composite beam bridge floorings longitudinal joint connecting structure and construction method
CN104264594B (en) A kind of self-balancing tied arch system for improving PSC continuous box girder bridge bearing ability and the method using it to reinforce
CN105821750B (en) A kind of precast prestressed T plate and its application method
CN109457551B (en) Combined frame type connection reinforcing structure between sleeper block and ballast bed and construction method
CN109457549A (en) Frame-type connection reinforcing structure between the concrete filled steel tube and sleeper block of non-fragment orbit
CN209384033U (en) A kind of penetration type connection reinforcing structure of concrete filled steel tube and sleeper block
CN109457547A (en) A kind of bridging type connection reinforcing structure of concrete filled steel tube and sleeper block
CN108560419A (en) Steel reinforced concrete combines the L-shaped side slot UHPC floorings of negative moment section of beam and its longitudinally connected
CN209412616U (en) Group frame type connection reinforcing structure between sleeper block and railway roadbed
CN207091835U (en) A kind of cast-in-place sleeper plate-type ballastless track
CN106088412A (en) L-type steel beam column
CN206438380U (en) The long overhanging crossbeam bridge structure of one kind
CN209412615U (en) A kind of groove type connection reinforcing structure between sleeper block and railway roadbed
CN209652659U (en) Frame-type connection reinforcing structure between the concrete filled steel tube and sleeper block of non-fragment orbit
CN209384032U (en) A kind of bridging type connection reinforcing structure of concrete filled steel tube and sleeper block
CN107882271A (en) A kind of marine sand concrete superposed column using UHPC outsourcings
CN207260375U (en) A kind of steel plate concrete combined shear wall
CN207934904U (en) A kind of connection structure for double-deck lining cutting duct pieces of shield tunnel and liner
CN207793771U (en) Middle low speed magnetic suspension traffic engineering is low to set circuit support rail beam
CN206554385U (en) Combining structure for assembled architecture
CN109184741A (en) A kind of high-bearing capacity shield tunnel segment joint structure
CN104612173B (en) A kind of seamless bridge neotectonics and construction method thereof that adopts ultra-high performance concrete stake

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant