- CN209369063U CN209369063U CN201821889633.2U CN201821889633U CN209369063U CN 209369063 U CN209369063 U CN 209369063U CN 201821889633 U CN201821889633 U CN 201821889633U CN 209369063 U CN209369063 U CN 209369063U
- Authority
- CN
- China
- Prior art keywords
- layer
- stainless steel
- ground
- waterproof
- warm device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Road Paving Structures (AREA)
Abstract
The utility model discloses a kind of for being equipped with the shower house ground waterproof structure of ground warm device; including concrete base layer, the top of the concrete base layer is equipped with cement mortar screeding layer, the first waterproof layer, floor heating structural layer, cement mortar protective course, the second waterproof layer, earth material screed-coat, earth material layer from lower to upper.Waterproof construction is equipped between the floor heating structural layer and cement mortar protective course, the waterproof construction includes the first heat-conducting glue layer being laid with from lower to upper, stainless steel plate, the second heat-conducting glue layer.The stainless steel plate is surrounded by molding stainless steel side plate in conjunction, and the lower end surface of the stainless steel side plate and stainless steel plate are welded to connect, and upper surface is located in earth material screed-coat.The utility model enhances the waterproof performance on shower house ground by improving the waterproof construction above ground warm device, reduces the maintenance cost of later period ground warm device.
Description
Technical field
The utility model relates to shower house ground waterproof fields more particularly to a kind of for being equipped with the shower of ground warm device
Premises face waterproof construction.
Background technique
Floor heating is by the heating agent in radiating layer, to be evenly heated entire ground using entire ground as radiator, recycle ground
The rule that the accumulation of heat in face itself and heat radiate upwards is conducted from the bottom to top, to achieve the purpose that heating.It is spread in shower house
If floor heating not only can increase body-sensing comfort level, but also can solve the problem of ground humidity, therefore more and more family's selections exist
Floor heating is laid in shower house.When using shower house, most water is flowed into construction drainage pipe by ground leaking drainage pipe, small
Partial water can be by ground absorption.It is entered in ground warm device, needs in ground warm device by the water of ground absorption in order to prevent
Top be laid with one layer of waterproof layer, but existing waterproof layer after long-term use can due to ground warm device heating and cooling and go out
Now expanding with heat and contract with cold repeatedly so that waterproof layer fails, and then causes water to be flowed into the damage for causing ground warm device in ground warm device,
Increase the maintenance cost of later period ground warm device.
Utility model content
To overcome disadvantages mentioned above, the purpose of this utility model is to provide a kind of for being equipped with the shower house of ground warm device
Ground waterproof structure improves the waterproof performance on shower house ground, reduces by improving the waterproof construction above ground warm device
The maintenance cost of later period ground warm device.
In order to reach the goals above, the technical solution adopted in the utility model is: a kind of for being equipped with ground warm device
Shower house ground waterproof structure, including concrete base layer, the top of the concrete base layer are equipped with cement mortar from lower to upper
Screed-coat, the first waterproof layer, floor heating structural layer, cement mortar protective course, the second waterproof layer, earth material screed-coat, plane materiel
The bed of material.Waterproof construction is equipped between the floor heating structural layer and cement mortar protective course, the waterproof construction includes from lower to upper
First heat-conducting glue layer of laying, stainless steel plate, the second heat-conducting glue layer, being surrounded by for the stainless steel plate are in conjunction molding
Stainless steel side plate, the lower end surface of the stainless steel side plate and stainless steel plate are welded to connect, and upper surface is located at earth material screed-coat
It is interior.
Furthermore, it is understood that first heat-conducting glue layer, the second heat-conducting glue layer with a thickness of 1-2mm.Pass through the first heat-conducting glue
Layer, the second heat-conducting glue layer can be improved heating transmission efficiency, heating heat stream caused by reducing structure sheaf above floor heating excessively
It loses.
Furthermore, it is understood that it is 1cm that the stainless steel side plate, which is higher by the second waterproof layer, the transverse flow of water can be effectively prevented
It is logical.
Furthermore, it is understood that the lower end surface of the stainless steel plate is equipped with the fabricating drainpipe made from stainless steel of insertion construction drainage pipe, it is described
The ground leaking drainage pipe being connected to earth material layer, construction drainage pipe is equipped in fabricating drainpipe made from stainless steel.Pass through fabricating drainpipe made from stainless steel
It can will leak into the water on stainless steel plate directly to drain into construction drainage pipe, it is ensured that water will not be flowed into floor heating from drainpipe
In structure sheaf.
Furthermore, it is understood that first waterproof layer, the second waterproof layer are all made of JS composite water-proof paint.Pass through the first waterproof
Layer and the second waterproof layer further enhance the waterproof performance on shower house ground.
Furthermore, it is understood that the floor heating structural layer includes insulating layer, peastone layer from bottom to top, it is laid in the peastone layer
There is floor heating pipe.The heating on shower house ground can be realized by floor heating structural layer.
It is penetrated into the utility model has the beneficial effects that: being effectively prevented water by increase stainless steel plate, stainless steel side plate
Into floor heating structural layer, reduce the maintenance cost of later period ground warm device;It is improved by the first heat-conducting glue layer, the second heat-conducting glue layer
The transmission efficiency of heating, reduce because structure sheaf above floor heating excessively caused by heating heat be lost.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model embodiment.
In figure:
1- concrete base layer;10- earth material layer;11- construction drainage pipe;The ground 12- leaking drainage pipe;2- cement mortar screeding
Layer;The first waterproof layer of 3-;41- insulating layer;42- peastone layer;43- floor heating pipe;The first heat-conducting glue layer of 51-;The second heat-conducting glue of 52-
Layer;61- stainless steel plate;62- stainless steel side plate;63- fabricating drainpipe made from stainless steel;7- cement mortar protective course;The second waterproof layer of 8-;
9- earth material screed-coat
Specific embodiment
The preferred embodiment of the utility model is described in detail with reference to the accompanying drawing, so that the advantages of the utility model
It can be easier to be readily appreciated by one skilled in the art with feature, to make the protection scope of the utility model apparent clear
Define.
Embodiment
Referring to figure 1, the utility model is a kind of for being equipped with the shower house ground waterproof structure of ground warm device,
Including concrete base layer 1, the top of the concrete base layer 1 is equipped with cement mortar screeding layer 2, floor heating structure from lower to upper
Layer, cement mortar protective course 7, earth material screed-coat 9, earth material layer 10.The concrete base layer 1 is equipped with to be arranged with building
The construction drainage pipe 11 of aquaporin connection, the cement mortar screeding layer 2, floor heating structural layer, cement mortar protective course 7, ground
Material screed-coat 9, earth material layer 10 are equipped with the drainage channel being connected to construction drainage pipe.
The first waterproof layer 3, the cement mortar protection are equipped between the cement mortar screeding layer 7 and floor heating structural layer
It is equipped with the second waterproof layer 8 between layer 7 and earth material screed-coat 9, first waterproof layer 3, the second waterproof layer 8 are all made of JS
Waterproof composite material coats twice.
The floor heating structural layer includes insulating layer 41, peastone layer 42 from bottom to top, is laid in the peastone layer 42 useful
In the floor heating pipe 43 of heat dissipation.Waterproof construction is equipped between the peastone layer 42 and cement mortar protective course 7, for stopping water to leak
Into ground warm device.
The waterproof construction includes the first heat-conducting glue layer 51, stainless steel plate 61, the second heat-conducting glue layer being laid with from lower to upper
52.First heat-conducting glue layer 51, the second heat-conducting glue layer 52 coating thickness be 1-2mm.The surrounding of the stainless steel plate 61 is set
There is molding stainless steel side plate 62 in conjunction, the lower end of the stainless steel side plate 62 and stainless steel plate 61 are welded to connect, upper end
It sequentially passes through cement mortar protective course 7, the second waterproof layer 8 and is located in earth material screed-coat 9, the stainless steel side plate 62
Upper surface be higher by the second waterproof layer 8 be 1cm.
The stainless steel plate 61 is located at the fabricating drainpipe made from stainless steel 63 that connection construction drainage pipe 11 is equipped at drainage channel, institute
State the ground leaking drainage pipe 12 for being equipped in fabricating drainpipe made from stainless steel 63 and being connected to earth material layer 10, construction drainage pipe 11.Pass through ground
Ponding on earth material layer 10 can be drained into construction drainage pipe 11 by leaking drainage pipe 12, can be incited somebody to action by fabricating drainpipe made from stainless steel 63
Ponding on stainless steel plate 61 is drained into construction drainage pipe 11.
The specific work process of the present embodiment is as follows:
When having ponding on local cover material layer 10, most water enters construction drainage pipe 11 by ground leaking drainage pipe 12
In;The water of fraction leaks on earth material screed-coat 9 from earth material layer 10, and then leaks on the second waterproof layer 8, the
Two waterproof layers 8 preliminarily stop percolating water;The water fallen is not stopped to continue downwards into cement mortar protective course 7,
And then enter on stainless steel plate 61, due to the barrier effect of stainless steel plate 61, water can only lateral flow, and due to stainless steel side
The barrier effect of plate 62, water can not leak downwards from the surrounding of stainless steel plate 61, can only flow to and build from fabricating drainpipe made from stainless steel 63
In drainpipe 11, thus water is prevented to flow into floor heating structural layer;When floor heating structural layer heating, heating is thermally conductive by first
Glue-line 51 is transmitted on stainless steel plate 61, then is transmitted to by the second heat-conducting glue layer 52 to cement mortar protective course 7, transmitting
Onto earth material screed-coat 9, earth material layer 10.
Embodiment of above is only to illustrate the technical ideas and features of the present invention, and its object is to allow be familiar with this skill
The people of art understands the content of the utility model and is implemented, and does not limit the protection scope of the present invention, and all
According to the equivalent change or modification that the spirit of the present invention is substantially done, should all cover within the protection scope of the present utility model.
Claims (6)
1. a kind of for being equipped with the shower house ground waterproof structure of ground warm device, including concrete base layer (1), the concrete
The top of base (1) is equipped with cement mortar screeding layer (2), the first waterproof layer (3), floor heating structural layer, cement bonded sand from lower to upper
Starch protective layer (7), the second waterproof layer (8), earth material screed-coat (9), earth material layer (10);It is characterized by: describedly
Equipped with waterproof construction between warm structure sheaf and cement mortar protective course (7), the waterproof construction includes the be laid with from lower to upper
One heat-conducting glue layer (51), stainless steel plate (61), the second heat-conducting glue layer (52);The stainless steel plate (61) be surrounded by with one of
Body formed stainless steel side plate (62), the lower end surface and stainless steel plate (61) of the stainless steel side plate (62) are welded to connect, upper end
Face is located in earth material screed-coat (9).
2. according to claim 1 for being equipped with the shower house ground waterproof structure of ground warm device, it is characterised in that: institute
State the first heat-conducting glue layer (51), the second heat-conducting glue layer (52) with a thickness of 1-2mm.
3. according to claim 2 for being equipped with the shower house ground waterproof structure of ground warm device, it is characterised in that: institute
Stating stainless steel side plate (62) and being higher by the second waterproof layer (8) is 1cm.
4. according to claim 3 for being equipped with the shower house ground waterproof structure of ground warm device, it is characterised in that: institute
The lower end surface for stating stainless steel plate (61) is equipped with the fabricating drainpipe made from stainless steel (63) of insertion construction drainage pipe (11), the stainless steel draining
The ground leaking drainage pipe (12) being connected to earth material layer (10), construction drainage pipe (11) is equipped in pipe (63).
5. according to claim 4 for being equipped with the shower house ground waterproof structure of ground warm device, it is characterised in that: institute
State the first waterproof layer (3), the second waterproof layer (8) is all made of JS composite water-proof paint.
6. according to claim 5 for being equipped with the shower house ground waterproof structure of ground warm device, it is characterised in that: institute
Stating floor heating structural layer includes insulating layer (41), peastone layer (42) from bottom to top, is equipped with floor heating pipe in the peastone layer (42)
(43)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821889633.2U CN209369063U (en) | 2018-11-15 | 2018-11-15 | For being equipped with the shower house ground waterproof structure of ground warm device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821889633.2U CN209369063U (en) | 2018-11-15 | 2018-11-15 | For being equipped with the shower house ground waterproof structure of ground warm device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209369063U true CN209369063U (en) | 2019-09-10 |
Family
ID=67836523
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821889633.2U Active CN209369063U (en) | 2018-11-15 | 2018-11-15 | For being equipped with the shower house ground waterproof structure of ground warm device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209369063U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115370104A (en) * | 2022-08-12 | 2022-11-22 | 日照市水务工程建设有限公司 | Waterproof partition structure in building and construction method |
-
2018
- 2018-11-15 CN CN201821889633.2U patent/CN209369063U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115370104A (en) * | 2022-08-12 | 2022-11-22 | 日照市水务工程建设有限公司 | Waterproof partition structure in building and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206337739U (en) | A kind of heat insulating and water proof structure of parapet root | |
CN208363452U (en) | A kind of double-layer drainage structure of heat-insulating roof | |
CN201228427Y (en) | Dry-type hot-water heating floor | |
CN209369063U (en) | For being equipped with the shower house ground waterproof structure of ground warm device | |
CN205153456U (en) | Mounting structure warms up with spreading formula stone material futilely | |
CN208718112U (en) | Novel anti-ponding structure based on toilet geothermal heating ground surface finishing | |
CN201883549U (en) | Concrete structure capable of improving energy accumulation and heat insulation of building ground surface | |
CN206267490U (en) | A kind of extrusion molding floor heating positions keel structure | |
CN203487679U (en) | Prefabricated combined type heat preservation module radiation heating and cooling air-conditioning floor | |
CN210122763U (en) | Underground heat exchange type water-through heat-preservation wooden outer wall | |
CN205776819U (en) | A kind of passive type building floor structure at ventilation shaft | |
CN201865303U (en) | Ground thermal-insulation system for improving temperature of first floor of civil building | |
CN207647049U (en) | A kind of multilayered structure roof drainage structure | |
CN205425266U (en) | Warm up stealthy humidifier | |
CN105442814B (en) | A kind of construction method of bathroom floor structure | |
CN202509615U (en) | Returning and overflowing-proof floor drain for balcony | |
CN110735534A (en) | Installation method of water floor heaters | |
CN210165498U (en) | Roof heat exchange system suitable for existing building flat roof | |
CN208456124U (en) | A kind of drainage pipeline passes through the pre-embedded device of floor | |
CN212478316U (en) | Heat-proof bridge heat-insulation connecting structure of energy-saving building awning | |
CN207194380U (en) | A kind of novel ground heater timber floor | |
CN211850596U (en) | Waterproof structure of ground heating area | |
CN216865750U (en) | Waterproof connecting node structure for roof outlet pipeline | |
JP2003336865A (en) | Floor heating and skeleton cooling system for building using coldness of tap water | |
CN214091088U (en) | Concrete anti-cracking control equipment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |