CN209353151U CN201821318773.4U CN201821318773U CN209353151U CN 209353151 U CN209353151 U CN 209353151U CN 201821318773 U CN201821318773 U CN 201821318773U CN 209353151 U CN209353151 U CN 209353151U
Authority
CN
China
Prior art keywords
monitoring element
line
drag
duct
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821318773.4U
Other languages
Chinese (zh)
Inventor
朱万旭
周红梅
庞晰中
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
LIUZHOU HANXIMING BUILDING MATERIAL DEVELOPMENT Co.,Ltd.
Guilin University of Technology
Original Assignee
Liuzhou Han Xi Building Materials Development Co Ltd Of Ringing
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Liuzhou Han Xi Building Materials Development Co Ltd Of Ringing filed Critical Liuzhou Han Xi Building Materials Development Co Ltd Of Ringing
Priority to CN201821318773.4U priority Critical patent/CN209353151U/en
Application granted granted Critical
Publication of CN209353151U publication Critical patent/CN209353151U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of smart stay cable of interchangeable monitoring element, it is most including monitoring element and drag-line two, the drag-line includes finished guy cable and site operation installation drag-line, at least one duct of overall length along the longitudinal direction in the drag-line, there is a monitoring element in the duct, monitoring element is connected by data line with the external world;The monitoring element includes the monitoring element component being made of fiber-optic grating sensor, Brillouin fiber optic or vibrating wire sensor and the strain gauge of other forms, Temperature Humidity Sensor;Monitoring element is by duct is penetrated again after design requirement tensioning to design force value in finished guy cable manufacturing process, and both ends are locked after applying certain tensile force;Or construction and installation drag-line is completed after constructing by design requirement tensioning to design force value at the scene, then penetrates duct, and both ends are locked after applying certain tensile force.The smart stay cable energy real-time monitoring Cable power situation of change, can be convenient for changing the sensing system of all kinds of monitoring drag-line states in drag-line during military service.

Description

A kind of smart stay cable of interchangeable monitoring element
Technical field
The utility model relates to a kind of smart stay cable more particularly to a kind of smart stay cables of interchangeable monitoring element.
Background technique
Bridge cable plays a crucial role in structure stress, due to environmental corrosion, fatigue damage, military service Internal Force Redistribution etc. Reason, drag-line is easily impaired, does not install under long-acting monitoring system situation, the not readily apparent practical health status of drag-line;Fiber grating Measuring technology is the absolute measurement techniques based on wavelength information, has good, good, corrosion-and high-temp-resistant of durability of electrical insulating property etc. all More advantages;Domestic early in 2003 just to have carried out the development work of smart stay cable, multinomial utility application technology is successive Some optical fiber grating intelligent draglines for guy systems such as suspension cable, arched bridge pre-stressed boom, cable, suspension bridges are disclosed, are had certainly Dynamic monitoring Cable forces function;But the above patent application technical solution has a common ground, in rope processed by optical fiber light Gate sensor and drag-line are made as an entirety, and in Cable forces, fiber-optic grating sensor stress synchronous with drag-line measures rope Power;But optical fiber is fragile material, and stress post-tensioning dependent variable is less than steel, and the above patent application technology all has embedded fibers Afterwards, the case where rope calibration process processed or engineering fail after a period of use;Therefore, such product fails high-volume and pushes city to ?.By prior art, it is less than if using monitoring element instead Brillouin fiber optic and equally existing optic fibre force post-tensioning dependent variable Steel problem;If monitoring element to be used instead to the strain gauge of vibrating wire sensor or other forms, there is also in long-acting monitoring process because Loose the problem of causing dynamometry inaccurate or failure, monitoring element are difficult to synchronous with the drag-line service life, once failure or dynamometry are inaccurate, tie Preset monitoring function can not then work in component.
Summary of the invention
The purpose of this utility model is that: the intelligence for providing a kind of a kind of interchangeable monitoring element of civil engineering structure is drawn The smart stay cable of rope, this kind of interchangeable monitoring element uses fiber-optic grating sensor, Brillouin fiber optic, vibrating wire sensor or other shapes The sensitive components real-time monitoring Cable power situation of change that can monitor drag-line state of formula, can be convenient for changing all kinds of energy in drag-line The sensing system for monitoring drag-line state not only can detect the variation of Cable power during military service, can also monitor temperature and humidity change Change situation, in the sensing system of more transducing monitoring drag-line state, corrosion condition inside introscope observation cable body also can be used. It is prepared, construction method of installation is simple, high-efficient.
The technical solution to solve the above problems is: a kind of smart stay cable of interchangeable monitoring element, including monitoring element and drawing Rope two is most, and the drag-line includes finished guy cable and site operation installation drag-line, it is characterised in that:
There are a monitoring element, monitoring element at least one duct of overall length along the longitudinal direction in the drag-line in the duct It is connected by data line with the external world;
The monitoring element include fiber-optic grating sensor monitoring element component, Brillouin fiber optic monitoring element component, Vibrating wire sensor monitoring element component and the strain gauge of other forms, Temperature Humidity Sensor or other drag-line states that can monitor The monitoring element component that sensitive components is constituted;
Monitoring element is to apply in finished guy cable manufacturing process by duct is penetrated again after design requirement tensioning to design force value Both ends after certain tensile force are added to be locked;Or construction and installation drag-line is complete to design force value by design requirement tensioning at the scene After construction, then duct is penetrated, both ends are locked after applying certain tensile force.
Its further technical solution is: the drag-line is chill casting formula steel wire finished product rope, chill casting squash type steel strand finished rope Or when squash type steel strand finished rope, at least one duct of overall length along the longitudinal direction in each finished product rope, monitoring element be In finished guy cable manufacturing process, when chill casting formula steel wire finished product rope, chill casting squash type steel strand finished rope or squash type steel strand wires at By duct is then passed through after design requirement tensioning to design force value, the carrier of monitoring element is fixed product rope again after being reinforced;It constitutes Chill casting formula steel wire finished product rope smart stay cable, chill casting formula steel strand finished smart stay cable or the squash type steel strand wires of interchangeable monitoring element Finished product rope smart stay cable.
Its further technical solution or: the drag-line be site operation installation clip type guy of twisted steel cable, in intermediate plate Overall length is at least reserved with a through-hole along the longitudinal direction in the both ends anchorage of formula guy of twisted steel cable, square along longitudinal direction in drag-line cable body A duct is at least reserved with to overall length, monitoring element passes through through-hole and duct, is connected by data line with the external world;
The monitoring element is after completing steel stranded wire penetrating adapter, tensioning, adjustment rope work, then to be threaded into folder in construction In chip guy of twisted steel cable, the carrier of monitoring element is fixed again after being reinforced;The clip type steel for constituting interchangeable monitoring element twists Line drag-line smart stay cable.
Further technical solution is for it: the monitoring element is fiber-optic grating sensor monitoring element component, the light Fiber grating sensor monitoring element component includes carrier, optical fiber, nut, and it is recessed to be vertically arranged at least one on optic fibre carrier Slot, optical fiber are placed in groove, and grating is carved on optical fiber, and fiber grating and optic fibre carrier are reliably coupled in its groove.
Further technical solution or: the monitoring element is Brillouin fiber optic monitoring element component, the Brillouin Fiber-optic monitoring component element includes carrier, optical fiber, nut, is vertically arranged at least one groove on optic fibre carrier, optical fiber is put It sets in groove, and is reliably coupled by adhesive or crimping with carrier, there is screw thread at carrier both ends.
Further technical solution or: the monitoring element is vibrating wire sensor monitoring element component, which passes Sensor monitoring element component includes carrier, vibrating wire sensor, nut, is vertically arranged at least one groove, vibratory string on carrier Sensor is placed in groove, and both ends are welded and fixed.
Its further technical solution is: the carrier is steel wire carbon fiber rod or Fiber glass rod;
In the anchorage zone of drag-line, the duct is steel pipe, plastic tube or other enough tubing of intensity, in the rope of drag-line Body portion is the tubular space or plastic tube of the spiral wire pipe with enough Telescopics, steel band formation;
The diameter in the duct is 1mm~20mm, and duct cross sectional shape is polygon, ellipse, circle or oval ring.
Due to taking above structure, the utility model its " a kind of smart stay cable of interchangeable monitoring element " has beneficial below Effect:
1, when drag-line service phase is overhauled, without the i.e. replaceable monitoring element that suspends traffic, and can be to drag-line inner case It is detected and is protected, operation pipe is facilitated to support:
Since overall length is reserved at least one along the longitudinal direction in the smart stay cable of the interchangeable monitoring element of the utility model Duct 2, there is a monitoring element 3 in the duct 2, and finished guy cable or site operation installation drag-line are pressed design requirement tensioning when construction Duct is penetrated to after design force value, then by monitoring element, both ends are fixed, therefore monitoring element 3 can easily take out at any time, and can To use interior view check-up drag-line inner case using duct 2;When humidity over limit in Cable body, duct 2 is alternatively arranged as The channel of logical dry-air blast removes rope moisture in vivo, carries out moreover, it is also possible to be passed through inert gas or vacuumize to cable body principal rod material Protection.
2, the service life of the smart stay cable of the interchangeable monitoring element of the utility model is long, can be synchronous with the drag-line service life:
Smart stay cable in the prior art is all made of the mode of monitoring element rope processed together with drag-line in the production process, Synchronous installation, synchronous stress, since the detecting element of use can meet with stresses respectively less than drag-line material, system survival rate can not be protected Card;Secondly as the monitoring element mode of rope processed, monitoring element together with drag-line are fixed on inside drag-line or fix with drag-line Connection can not be replaced when monitoring element failure;
And overall length is reserved at least one duct along the longitudinal direction in the smart stay cable of the interchangeable monitoring element of the utility model 2, have a monitoring element 3 in the duct 2, when construction by finished guy cable or site operation installation drag-line by design requirement tensioning to setting After dynamometric value, then monitoring element penetrated into duct, both ends are fixed;This construction method of installation can guarantee monitoring element 100% effectively It survives;In addition, applying pulling force locking to monitoring element, strain not less than drag-line actual measurement strain value and its minimum possible strain value Difference, as a result, monitoring element can under lower strain level, monitor improved strain state Cable forces, improve monitoring The service life of element;And can replace at any time, it is synchronous with the drag-line service life.
3, transport, construction and installation are convenient:
The utility model factory production can it is in-service replacement monitoring element chill casting formula steel wire finished product rope smart stay cable, The pore-forming pipe of the finished products rope such as chill casting squash type steel strand finished rope smart stay cable and squash type steel strand finished rope smart stay cable Road is the tubular space formed by the steel wire with spiral or steel band, as shown in Figure 6, Figure 7, can with drag-line coil, together by Power elongation, transport, construction and installation are convenient;Duct can also be transparent plastic tube, and band-like pipe or plastic tube can also be in tube walls Punching facilitates operation pipe to support as venthole.
It is special to a kind of technology of the smart stay cable of interchangeable monitoring element of the utility model with reference to the accompanying drawings and examples Sign is described further.
Detailed description of the invention
Fig. 1 is that the chill casting formula steel wire finished product rope smart stay cable of the interchangeable monitoring element of the utility model and chill casting squash type steel twist Line finished product rope smart stay cable structural schematic diagram;
Fig. 2 is monitoring element structural schematic diagram;
Fig. 3 is the right view of Fig. 2;
Fig. 4 is the squash type steel strand finished rope smart stay cable structural schematic diagram of interchangeable monitoring element;
Fig. 5 is the clip type guy of twisted steel cable smart stay cable structural schematic diagram of interchangeable monitoring element;
Fig. 6 is the spiral wire pipe pore-forming pipeline configuration schematic diagram with enough Telescopics;
Fig. 7 is the tubular space pore-forming pipeline configuration schematic diagram that the steel band with venthole is formed thereon;
Fig. 8 is the monitoring element component structure diagram for being equipped with fiber grating and Temperature Humidity Sensor;
Fig. 9 is the monitoring element component structure diagram for being equipped with Brillouin fiber optic;
Figure 10 is the right view of Fig. 9;
Figure 11 is the monitoring element component structure diagram for being equipped with vibrating wire sensor,
Figure 12 is the right view of Figure 11;
Figure 13 be the interchangeable monitoring element of the utility model steel wire finished product rope smart stay cable cable body cross section structure schematic diagram it One (having 1 duct at drag-line cable body center);
Figure 14 is the steel strand finished rope smart stay cable cable body cross section structure schematic diagram of the interchangeable monitoring element of the utility model One of (having 1 duct at drag-line cable body center);
Figure 15, Figure 17 are the steel wire finished product rope smart stay cable cable body cross section structure signals of the interchangeable monitoring element of the utility model Two (having 3 ducts in drag-line cable body) of figure;
Figure 16, Figure 18 are that the steel strand finished rope smart stay cable cable body cross section structure of the interchangeable monitoring element of the utility model shows Two (having 2 ducts in drag-line cable body) of intention;
Figure 19: the chill casting formula steel wire finished product rope smart stay cable and chill casting squash type steel of the interchangeable monitoring element of the utility model twist Line finished product rope smart stay cable.
In figure:
1- drag-line, 1a- chill casting formula steel wire finished product rope smart stay cable or chill casting squash type steel strand finished rope smart stay cable, 1b- squash type steel strand finished rope smart stay cable, 1c- clip type guy of twisted steel cable smart stay cable;The duct 2-, 21- spiral wire Pipe pore-forming pipeline, 22- have the steel band pore-forming pipeline of venthole, 221- venthole;
3- monitoring element;4- nut;5- screw thread;6- groove, 7- carrier, 8- grating, 9- optical fiber, 10- viscose glue;
11- data line, 12- humidity sensor, 13- preformed hole;14- steel wire, the outer PE set of 15- steel wire finished product rope, 16- steel twist Line, the outer PE set of 17- steel strand finished rope;
18- Brillouin fiber optic, 19- vibrating wire sensor.
Specific embodiment
The smart stay cable of interchangeable monitoring element described in the utility model, including two major part of monitoring element and drag-line, it is described Drag-line includes finished guy cable and site operation installation drag-line, and overall length is at least reserved with a duct 2 along the longitudinal direction in drag-line 1, There is a monitoring element 3 in the duct 2, monitoring element 3 is connected by data line 11 with the external world;
The monitoring element 3 include fiber-optic grating sensor monitoring element component, Brillouin fiber optic monitoring element component, Vibrating wire sensor monitoring element component and the strain gauge of other forms, Temperature Humidity Sensor or other drag-line states that can monitor The monitoring element component that sensitive components is constituted;
Monitoring element can be penetrates hole to after designing force value by design requirement tensioning in finished guy cable manufacturing process again Road 2, both ends are locked after applying certain tensile force;It is also possible to construction and installation drag-line at the scene to arrive by design requirement tensioning It designs force value to complete after constructing, then penetrates duct 2, both ends are locked after applying certain tensile force.
Hereinafter, being that finished guy cable or site operation install drag-line combination attached drawing and make its structure feature according to drag-line type It further illustrates.
Embodiment one
A kind of the chill casting formula steel wire finished product rope smart stay cable and chill casting squash type steel of the interchangeable monitoring element in factory's production Twisted wire finished product rope smart stay cable:
As shown in Figure 1, the drag-line is chill casting formula steel wire finished product rope or chill casting squash type steel strand finished rope, in chill casting formula Steel wire finished product rope or chill casting squash type steel strand finished rope center overall length are reserved with a duct 2,
There is a monitoring element 3 in the duct 2, monitoring element 3 is connected by data line 11 with the external world;
As shown in Fig. 2, the monitoring element 3 includes steel wire 7, optical fiber 9, nut 4 as optic fibre carrier, on carrier 7 It is vertically arranged at least one groove 6, optical fiber 9 is placed in groove (referring to Fig. 3), grating 8 is carved on optical fiber, by durable Property good adhesive or mechanical crimp method fiber grating and optic fibre carrier are reliably coupled in its groove;
Above-mentioned monitoring element 3 is in production, when chill casting formula steel wire finished product rope, chill casting squash type steel strand finished rope are by setting Meter requires tensioning to be passed through duct 2 again to after designing force value, the steel wire 7 of the optic fibre carrier of monitoring element 3 reinforced after again by It is fixed;The chill casting formula steel wire finished product rope smart stay cable or chill casting squash type steel strand finished rope for constituting interchangeable monitoring element are intelligently drawn Its structure of rope 1a(is referring to Fig. 1, and the sectional view of cable body is referring to Figure 13, Figure 14).
It is that squash type steel strand finished rope is fabricated to for drag-line as a kind of transformation of the utility model embodiment one The basic structure of chill casting squash type steel strand finished rope smart stay cable 1a described in squash type steel strand finished rope and embodiment one Be it is the same, at the center squash type steel strand finished rope smart stay cable 1b, overall length is reserved with a duct 2, has one in the duct 2 Monitoring element 3, the monitoring element 3 are connected by data line 11 with the external world;The monitoring element 3 is as shown in Fig. 2, above-mentioned Monitoring element 3 be production when, when squash type steel strand finished rope by design requirement tensioning to design force value after be passed through again Duct 2, the carrier 7 of monitoring element 3 are fixed again after being reinforced;Constitute the squash type steel strand finished Suo Zhi of interchangeable monitoring element Energy drag-line 1b(is referring to fig. 4).
The structural schematic diagram of the cable body of the smart stay cable of above-mentioned various interchangeable monitoring elements is referring to Figure 13, Figure 14, Tu13Shi The steel wire finished product rope smart stay cable cable body cross section structure schematic diagram of interchangeable monitoring element, Figure 14 is the steel strand wires of interchangeable monitoring element Finished product rope smart stay cable cable body cross section structure schematic diagram.
Embodiment two
A kind of smart stay cable --- clip type guy of twisted steel cable smart stay cable of the interchangeable monitoring element of site operation installation:
It is reserved with through-hole at the both ends anchorage center of clip type guy of twisted steel cable, overall length is reserved with one at drag-line cable body center A duct 2, monitoring element 3 pass through through-hole and duct, are connected by data line 11 with the external world;
As shown in Fig. 2, the monitoring element 3 includes carrier 7, optical fiber 9, nut 4, be vertically arranged on carrier 7 to A few groove 6, optical fiber 9 are placed in groove (referring to Fig. 3), grating 8 are carved on optical fiber, fiber grating is pasted onto optic fibre carrier In groove;
Monitoring element 3 is after completing the work such as steel stranded wire penetrating adapter, tensioning, adjustment rope, then to be threaded into intermediate plate in construction In formula guy of twisted steel cable, the carrier 7 of monitoring element 3 is fixed again after being reinforced;The clip type steel for constituting interchangeable monitoring element twists Line drag-line smart stay cable (referring to Fig. 5).
In the various embodiments described above, the duct is divided into two kinds of rigidity and flexibility, in the anchorage zone of drag-line, the duct It is steel pipe, plastic tube or other enough tubing of intensity, avoids the influence due to reserving hole channel to anchoring property;In the rope of drag-line Body portion is the tubular space or transparent plastic tube of the spiral wire pipe with enough Telescopics, steel band formation, avoids drawing Suo Shouli is flexible to cause pipe collapse to squeeze monitoring element.
In order to reduce influence to cable body outer diameter and convenient for penetrating monitoring element, the diameter in the duct is 1mm~20mm, Duct cross sectional shape is polygon (including rectangle, square, hexagon), ellipse, round or oval ring (racetrack).
As a kind of transformation of the embodiment of the present invention one, embodiment two, overall length setting along the longitudinal direction in the drag-line 1 Duct 2 can also be 1 more than, can be 2,3,4,5 or more, depending on according to drag-line diameter and needing, hole The position in road 2 can be at 1 center of drag-line, also can be set at other positions of drag-line, referring to Figure 15, Figure 16, Figure 17 and Figure 18, Figure 15, Tu17Zhong, there is 3 ducts in drag-line cable body, and 1 is located at that 1 center of drag-line, other two is symmetrically located in Figure 15 Both sides;In Figure 17,1 be located at 1 center of drag-line, other two be symmetrically located at both sides;Figure 16, Tu18Zhong, in drag-line cable body Have 2 ducts, in Figure 16 1 be located at 1 center of drag-line, in addition 1 be located at drag-line cable body edge;In Figure 18,2 ducts are all located at Drag-line cable body edge.
As a kind of transformation of the utility model embodiment one, embodiment two, the monitoring element component also can be in cloth Deep fiber-optic monitoring component element, the strain gauge of vibrating wire sensor monitoring element component and other forms, Temperature Humidity Sensor or The monitoring element component that other sensitive components that can monitor drag-line state are constituted;
Fig. 9, Figure 10 are the monitoring element component structure diagrams for being equipped with Brillouin fiber optic;
Figure 11, Figure 12 are the monitoring element component structure diagrams for being equipped with vibrating wire sensor;
The installation side of the strain gauges of other forms, Temperature Humidity Sensor or other sensitive components that can monitor drag-line state Method is that those skilled in the art can implement, and details are not described herein again.

Claims (7)

1. a kind of smart stay cable of interchangeable monitoring element, including two major part of monitoring element and drag-line, the drag-line includes finished product Drag-line and site operation install drag-line, it is characterised in that:
At least one duct (2) of overall length along the longitudinal direction in the drag-line (1) has a monitoring element (3) in the duct (2), Monitoring element (3) is connected by data line (11) with the external world;
The monitoring element (3) includes fiber-optic grating sensor monitoring element component, Brillouin fiber optic monitoring element component, vibration Chord sensor monitoring element component and strain gauge, Temperature Humidity Sensor can monitor what the sensitive components of drag-line state was constituted Monitoring element component;
When the drag-line is chill casting formula steel wire finished product rope, chill casting squash type steel strand finished rope or squash type steel strand finished rope When, at least one duct (2) of overall length along the longitudinal direction in each finished product rope;
When the drag-line is the clip type guy of twisted steel cable of site operation installation, in the both ends anchorage of clip type guy of twisted steel cable In along the longitudinal direction overall length be at least reserved with a through-hole, overall length is at least reserved with a hole along the longitudinal direction in drag-line cable body Road (2), monitoring element (3) pass through through-hole and duct, are connected by data line (11) with the external world.
2. a kind of smart stay cable of interchangeable monitoring element according to claim 1, it is characterised in that: the monitoring element Fiber-optic grating sensor monitoring element component, the fiber-optic grating sensor monitoring element component include carrier (7), optical fiber (9), Nut (4) is vertically arranged at least one groove (6) on carrier, and optical fiber is placed in groove, and grating (8) are carved on optical fiber, Fiber grating and carrier are reliably coupled in its groove.
3. a kind of smart stay cable of interchangeable monitoring element according to claim 1, it is characterised in that: the monitoring element It is Brillouin fiber optic monitoring element component, which includes carrier (7), optical fiber (9), nut (4), At least one groove (6) is vertically arranged on carrier, optical fiber is placed in groove, and passes through adhesive or crimping and carrier (7) it is reliably coupled, carrier (7) both ends have screw thread (5).
4. a kind of smart stay cable of interchangeable monitoring element according to claim 1, it is characterised in that: the monitoring element Vibrating wire sensor monitoring element component, the vibrating wire sensor monitoring element component include carrier (7), vibrating wire sensor (19), Nut (4) is vertically arranged at least one groove (6) on carrier, and vibrating wire sensor is placed in groove, and both ends welding is solid It is fixed.
5. according to the smart stay cable of interchangeable monitoring element described in claim 2,3 or 4, it is characterised in that: the carrier It (7) is steel wire carbon fiber rod Fiber glass rod or assorted fibre stick.
6. the smart stay cable of interchangeable monitoring element according to claim 1, it is characterised in that: in the anchorage zone of drag-line, institute The duct stated is steel pipe, plastic tube or other enough tubing of intensity, is to have enough Telescopics in the cable body part of drag-line Spiral wire pipe, steel band formed tubular space or plastic tube.
7. the smart stay cable of interchangeable monitoring element according to claim 1, it is characterised in that: the diameter in the duct is 1mm~20mm, duct cross sectional shape are polygon, ellipse, circle or oval ring.
CN201821318773.4U 2018-08-15 2018-08-15 A kind of smart stay cable of interchangeable monitoring element Active CN209353151U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821318773.4U CN209353151U (en) 2018-08-15 2018-08-15 A kind of smart stay cable of interchangeable monitoring element

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821318773.4U CN209353151U (en) 2018-08-15 2018-08-15 A kind of smart stay cable of interchangeable monitoring element

Publications (1)

Publication Number Publication Date
CN209353151U true CN209353151U (en) 2019-09-06

Family

ID=67779373

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821318773.4U Active CN209353151U (en) 2018-08-15 2018-08-15 A kind of smart stay cable of interchangeable monitoring element

Country Status (1)

Country Link
CN (1) CN209353151U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111442735A (en) * 2020-04-03 2020-07-24 广西大学 Method for manufacturing polymer rubber-insulated-wire fiber grating strain sensor and intelligent cable
CN114526685A (en) * 2022-02-15 2022-05-24 柳州欧维姆机械股份有限公司 Replaceable fiber grating intelligent inhaul cable and replacement method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111442735A (en) * 2020-04-03 2020-07-24 广西大学 Method for manufacturing polymer rubber-insulated-wire fiber grating strain sensor and intelligent cable
CN114526685A (en) * 2022-02-15 2022-05-24 柳州欧维姆机械股份有限公司 Replaceable fiber grating intelligent inhaul cable and replacement method thereof
CN114526685B (en) * 2022-02-15 2023-06-13 柳州欧维姆机械股份有限公司 Replaceable fiber bragg grating intelligent inhaul cable and replacement method thereof

Similar Documents

Publication Publication Date Title
CN101435779B (en) Intelligent steel strand based on optical fiber Brillouin sensing and preparation and full dimension monitoring method thereof
CN103292721B (en) A kind of fiber grating wide range strain transducer of monitoring prestress steel twist line strain
CN105300305B (en) Couple the wide range intelligence high tensile steel wire and preparation method thereof of fiber grating
CN101210983A (en) Optical fiber grating intelligent steel strand and its manufacture method
CN110835864A (en) Intelligent inhaul cable with replaceable monitoring element and manufacturing, installing and constructing method thereof
CN209353151U (en) A kind of smart stay cable of interchangeable monitoring element
CN104196258A (en) Post-tensioning prestressing intelligent reinforcement system based on fiber grating sensing technology
CN108221670B (en) Intelligent parallel steel wire rope suitable for stay ropes, suspension ropes and hanging rod ropes
CN106949996A (en) Optical fiber grating intelligent steel strand and its monitoring system and scaling method
CN106639158A (en) Integrated intelligent anchorage device and manufacturing method thereof
CN105442758A (en) Wide-range FRP (fiber reinforced plastic) embedded steel wire composite optical fiber smart rebar and preparation method thereof
CN202403851U (en) Fiber Bragg grating load cell of anchor cable frame composite structure
CN204252026U (en) A kind of fiber grating post-tensioned prestressing intelligence ruggedized construction
CN208533368U (en) A kind of parallel steel wire intelligence rope suitable for suspension cable, suspension cable and sunpender rope
CN111174662B (en) Displacement sensing device and application thereof
CN213927094U (en) A slowly bond wisdom steel strand wires for building prestressed concrete structure
CN109958056A (en) Smart stay cable, smart stay cable preparation method and smart stay cable safe condition detection method
CN106291852A (en) A kind of Intelligent Composite muscle of built-in fiber bragg grating
CN107024305A (en) The method of bridge structure intelligence reinforcement assembly and fiber-optic grating sensor compoiste adhering
CN116356888A (en) Optical fiber-based piston type large-deformation prestressed anchor cable monitoring device and construction method
CN113008422B (en) Distributed monitoring structure and method for anchoring state of prestressed tendon group
KR101754400B1 (en) 7-wire strand with fiber-optic sensor encapsulated helical wire and method for manufacturing of the same
CN206173724U (en) Optical fibre and grating intelligent steel twist joint
CN210571747U (en) Intelligent steel strand cable capable of realizing damage self-diagnosis and self-positioning
CN201738241U (en) FRP rib and steel strand connector and composite inhaul cable

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zhu Wanxu

Inventor after: Zhou Hongmei

Inventor after: Pang Xizhong

Inventor after: Liang Shiyuan

Inventor after: Zhu Shicong

Inventor before: Zhu Wanxu

Inventor before: Zhou Hongmei

Inventor before: Pang Xizhong

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200715

Address after: 541004 the Guangxi Zhuang Autonomous Region Guilin Construction Road No. 12

Co-patentee after: LIUZHOU HANXIMING BUILDING MATERIAL DEVELOPMENT Co.,Ltd.

Patentee after: GUILIN University OF TECHNOLOGY

Address before: 545616 No. 5-17, Third Training Building, Lushan College, Guangxi University of Science and Technology, 99 Xinliu Avenue, Liuzhou City, Guangxi Zhuang Autonomous Region

Patentee before: LIUZHOU HANXIMING BUILDING MATERIAL DEVELOPMENT Co.,Ltd.