CN209193564U - Ammonium acid fluoride efficient crystallization equipment - Google Patents
Ammonium acid fluoride efficient crystallization equipment Download PDFInfo
- Publication number
- CN209193564U CN209193564U CN201822077492.0U CN201822077492U CN209193564U CN 209193564 U CN209193564 U CN 209193564U CN 201822077492 U CN201822077492 U CN 201822077492U CN 209193564 U CN209193564 U CN 209193564U
- Authority
- CN
- China
- Prior art keywords
- pipe
- water
- staving
- water tank
- cooling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Devices That Are Associated With Refrigeration Equipment (AREA)
Abstract
The utility model provides a kind of ammonium acid fluoride efficient crystallization equipment, including staving and bung, and staving is equipped with screw rod, and the sliding block of screw rod is equipped with disk-shaped push plate, and push plate outer wall is supported with inner wall of barrel;Bung is equipped with a plurality of cooling tube, is equipped with drinking-water pipe in each cooling tube, drinking-water pipe is connected to through collecting pipe and the 4th pipeline with the second water pump;The outer sheath of staving is equipped with cooling dome, clip cavity is equipped in cooling dome, the top of clip cavity is connected to the first water tank by outlet pipe, bottom is connected to by water inlet pipe with the first water pump, first water tank is connected to the second water tank by first pipe, the side wall of second water tank is equipped with cooling piece, first water pump is connected to the second water tank by second pipe, and the first water pump is connected to water inlet pipe;Second water pump is connected to the first water tank by third pipeline, and collecting pipe is connected to water inlet pipe by the 5th pipeline, and cooling tube is corresponded in push plate equipped with multiple through-holes;It uses water-cooled cooling mode to cool down ammonium hydrogen fluoride solution, improves production efficiency.
Description
Technical field
The utility model relates to ammonium acid fluoride crystallization arts, more particularly to a kind of ammonium acid fluoride efficient crystallization equipment.
Background technique
Ammonium acid fluoride is a kind of with corrosive chemical substance, can dissolve glass, be slightly soluble in alcohol, be highly soluble in cold
Water, and be very easy to deliquesce, it is mainly used for glass etching agent, disinfectant, surface treating agent of silicon element steel plate etc..
It needs for ammonium acid fluoride aqueous solution to be concentrated during wet production ammonium acid fluoride, crystallisation by cooling, traditional knot
Brilliant device is that the liquid after concentration is both carried out nature in an open trough or forced ventilation is cold using slot type crystallisation by cooling
But, crystallize out ammonium acid fluoride, but slot type cooler crystallizer takes up a large area, in order to improve cooling effect, the knot of use
Brilliant slot is height trough very low and very big with air contact surfaces;Unlimited crystallization makes the dust and other impurities in air be easily accessible production
In product, keep the stain in product higher, influence the quality of product, it is difficult to meet the product requirement of high-quality;Since slot type crystallizes
Using air-cooled, cooling effect is undesirable, and crystallization time is long, and production capacity is few.
Utility model content
In order to overcome the drawbacks of the prior art, the technical problem to be solved by the utility model is to propose a kind of hydrogen fluoride
Ammonium efficient crystallization equipment, structure novel cool down ammonium hydrogen fluoride solution using water-cooled cooling mode, provide it is enough just
In the region of ammonium hydrogen fluoride solution crystallisation by cooling, accelerate crystallisation by cooling, improves production efficiency.
For this purpose, the following technical solution is employed for the utility model:
The utility model provides a kind of ammonium acid fluoride efficient crystallization equipment, including rack and is fixed in the rack
Staving, staving bottom connection is equipped with feeder pipe, and the feeder pipe is equipped with baiting valve, and the top cover of the staving is equipped with
Bung, the bung are fixedly connected with the staving by screw, the bung be equipped with commissioning pipe, described commissioning pipe one end with
Connection, the other end are covered with sealing cover inside the staving;The bottom interior wall of the staving is fixedly installed with support frame, the branch
Screw rod is equipped with by bearing between support and the bung, the bung and and driving motor are run through in the top of the screw rod
Output shaft connected by shaft coupling, the driving motor is fixedly mounted in the rack, is arranged on the screw rod along institute
The sliding block of screw rod sliding is stated, push plate is fixed on the outside of the sliding block, the push plate is in disk-shaped and outer wall and the staving
Inner wall sliding supports;
The bung is equipped with a plurality of cooling tube being vertically arranged, and the low side of the cooling tube seals and protrudes into the bucket
Internal portion, the top of the cooling tube are welded and fixed with the bung, the open top of the cooling tube and be located at the bung
Outside;Drinking-water pipe is equipped in each cooling tube, the bottom end of the drinking-water pipe is protruded into the cooling tube and close to described
The top of the bottom of cooling tube, the bung is equipped with collecting pipe, and the top of each drinking-water pipe is connected to the collecting pipe;Institute
The outer sheath for stating staving is equipped with cooling dome, and the cooling dome covers the staving side wall and bottom, is equipped with folder in the cooling dome
Chamber, the shape of the clip cavity are adapted with the cooling hood shape, and the top sidewall of the cooling dome is fixed with and the folder
The outlet pipe of chamber connection, the bottom sidewall of the cooling dome are fixed with the water inlet pipe being connected to the clip cavity, the water inlet pipe
It is equipped with the first solenoid valve, the first water tank and the second water tank are fixedly installed in the rack, first water tank is located at described
The bottom sidewall of the top of second water tank and first water tank and the top sidewall of second water tank are connected by first pipe
Logical, the first pipe is equipped with second solenoid valve, and the top of first water tank is connected with the clip cavity by the outlet pipe
It is logical, cooling piece is installed, the chill surface of the cooling piece is towards setting inside second water tank on the side wall of second water tank
It sets;The lower section of second water tank is equipped with the first water pump, and first water pump is fixedly mounted in the rack, first water
The water inlet of pump is connected to the bottom of second water tank by second pipe, the water outlet of first water pump and the water inlet
Pipe is connected to by No.1 tee tube;The top of first water tank is equipped with the second water pump, and second water pump is fixedly mounted on institute
It states in rack, the water outlet of second water pump is connected to the top of first water tank by third pipeline, second water
The water inlet connection of pump is equipped with the 4th pipeline, and the 4th pipeline is equipped with third solenoid valve, the other end of the 4th pipeline
It is connected to the collecting pipe by No. two tee tubes, passes through the 5th pipeline between No. two tee tubes and the No.1 tee tube
Connection, the 5th pipeline are equipped with the 4th solenoid valve;
The cooling tube is corresponded in the push plate equipped with multiple through-holes, the bottom of each through-hole is correspondingly provided with ring-type
The first scraping block, the inner wall of first scraping block and the outer wall sliding of the cooling tube support.
In the utility model preferred technique scheme, the bottom margin of the push plate is fixed with the second scraping block, and described
The inclined bottom surface of two scraping block is arranged and inclination lower end supports the inner wall of barrel;The bottom margin of first scraping block tilts
It is arranged and tilts the outer wall that lower end supports the cooling tube.
In the utility model preferred technique scheme, the bottom of the screw rod is fixed with strut, one end of the strut
Be fixedly welded with the screw rod, the other end is fixed with scraper plate, the sliding of the scraper plate and the staving bottom interior wall supports.
In the utility model preferred technique scheme, the staving bottom structure funnel-shaped, the scraper plate and the bucket
Body bottom shape is adapted and supports the staving bottom interior wall.
In the utility model preferred technique scheme, the side wall of the feeder pipe is equipped with drain pipe, and the drain pipe is located at
The top of the baiting valve, the drain pipe are equipped with switch valve.
The utility model has the following beneficial effects:
A kind of ammonium acid fluoride efficient crystallization equipment provided by the utility model, structure novel, cooling dome, clip cavity, water outlet
Matching between pipe, water inlet pipe, drinking-water pipe, collecting pipe, the first water tank, the second water tank, cooling piece, the first water pump and the second water pump
It closes, constitutes a water-cooling circulating system, provide enough areas convenient for crystallisation by cooling for the ammonium hydrogen fluoride solution inside staving
Domain, effectively acceleration crystallisation by cooling, improve production efficiency;And driving motor, screw rod, push plate cooperation, can will be adhered to cooling tube
The crystalline solid of outer wall and inner wall of barrel scrapes, and prevents crystalline solid accumulation, covering, avoid influencing normal crystallisation by cooling it is normal into
Row, further increases production efficiency.
Detailed description of the invention
Fig. 1 is a kind of structural representation of the ammonium acid fluoride efficient crystallization equipment provided in specific embodiment of the utility model
Figure;
Fig. 2 is the water-cooling cover provided in specific embodiment of the utility model, the first water tank, the second water tank, drinking-water pipe phase
The structural schematic diagram mutually cooperated;
Fig. 3 is the structural schematic diagram of the push plate provided in specific embodiment of the utility model.
In figure:
100, rack;200, staving;210, feeder pipe;220, baiting valve;230, support frame;240, drain pipe;241, it opens
Close valve;300, bung;310, commissioning pipe;320, sealing cover;330, cooling tube;400, screw rod;410, sliding block;420, push plate;
430, through-hole;440, the first scraping block;450, the second scraping block;460, strut;470, scraper plate;500, driving motor;610, the first pipe
Road;611, second solenoid valve;620, second pipe;630, third pipeline;640, the 4th pipeline;641, third solenoid valve;650,
5th pipeline;651, the 4th solenoid valve;660, drinking-water pipe;670, collecting pipe;680, No.1 tee tube;690, No. two tee tubes;
700, cooling dome;710, clip cavity;720, outlet pipe;730, water inlet pipe;731, the first solenoid valve;810, the first water tank;820,
Two water tanks;821, cooling piece;830, the first water pump;840, the second water pump.
Specific embodiment
Further illustrate the technical solution of the utility model below with reference to the accompanying drawings and specific embodiments.
As shown in Figure 1 and Figure 2, a kind of ammonium acid fluoride efficient crystallization equipment is disclosed in specific embodiment of the utility model,
Including rack 100 and the staving 200 being fixed in the rack 100,200 bottom of the staving connection is equipped with feeder pipe 210,
The feeder pipe 210 is equipped with baiting valve 220, and the top cover of the staving 200 is equipped with bung 300, the bung 300 with it is described
Staving 200 is fixedly connected by screw, and the bung 300 is equipped with commissioning pipe 310, described 310 one end of commissioning pipe and the bucket
Connection, the other end are covered with sealing cover 320 inside body 200;The bottom interior wall of the staving 200 is fixedly installed with support frame 230,
Screw rod 400 is equipped with by bearing between support frame as described above 230 and the bung 300, the top of the screw rod 400 is through described
It bung 300 and is connect with the output shaft of driving motor 500 by shaft coupling, the driving motor 500 is fixedly mounted on the machine
On frame 100, the sliding block 410 along the screw rod 400 sliding is arranged on the screw rod 400, the outside fixation of the sliding block 410 is set
There is push plate 420, the push plate 420 is supported in disk-shaped and outer wall and 200 inner wall of staving sliding;
The bung 300 is equipped with a plurality of cooling tube 330 being vertically arranged, and the low side of the cooling tube 330 is sealed and stretched
Enter inside the staving 200, the top of the cooling tube 330 is welded and fixed with the bung 300, the top of the cooling tube 330
End is opened wide and is located at the outside of the bung 300;Drinking-water pipe 660, the drinking-water pipe 660 are equipped in each cooling tube 330
Bottom end protrude into the bottom in the cooling tube 330 and close to the cooling tube 330,330 top of cooling tube and the pumping
Sealing-plug is equipped between the outer wall of water pipe 660;The top of the bung 300 is equipped with collecting pipe 670, each drinking-water pipe 660
Top is connected to the collecting pipe 670;The outer sheath of the staving 200 is equipped with cooling dome 700, and the cooling dome 700 covers
200 side wall of staving and bottom, the cooling dome 700 is interior to be equipped with clip cavity 710, the shape and the cooling of the clip cavity 710
700 shapes to be covered to be adapted, the top sidewall of the cooling dome 700 is fixed with the outlet pipe 720 being connected to the clip cavity 710,
The bottom sidewall of the cooling dome 700 is fixed with the water inlet pipe 730 being connected to the clip cavity 710, sets on the water inlet pipe 730
There is the first solenoid valve 731, the first water tank 810 and the second water tank 820, first water tank are fixedly installed in the rack 100
810 are located at the top of the top of second water tank 820 and the bottom sidewall of first water tank 810 and second water tank 820
Portion's side wall is connected to by first pipe 610, and the first pipe 610 is equipped with second solenoid valve 611, first water tank 810
Top and the clip cavity 710 be connected to by the outlet pipe 720, cooling piece is installed on the side wall of second water tank 820
821, the chill surface of the cooling piece 821 is towards being arranged inside second water tank 820;The lower section of second water tank 820 is set
There is the first water pump 830, first water pump 830 is fixedly mounted in the rack 100, the water inlet of first water pump 830
It is connected to the bottom of second water tank 820 by second pipe 620, the water outlet of first water pump 830 and the water inlet
Pipe 730 is connected to by No.1 tee tube 680;The top of first water tank 810 is equipped with the second water pump 840, second water pump
840 are fixedly mounted in the rack 100, and the water outlet of second water pump 840 and the top of first water tank 840 pass through
Third pipeline 630 is connected to, and the water inlet of second water pump 840, which is connected to, is equipped with the 4th pipeline 640, on the 4th pipeline 640
Equipped with third solenoid valve 641, the other end and the collecting pipe 670 of the 4th pipeline 640 are connected by No. two tee tubes 690
It is logical, it is connected between No. two tee tubes 690 and the No.1 tee tube 680 by the 5th pipeline 650, the 5th pipeline
650 are equipped with the 4th solenoid valve 651;
As shown in figure 3, corresponding to the cooling tube 330 in the push plate 420 equipped with multiple through-holes 430, each through-hole
430 bottom is correspondingly provided with cricoid first scraping block 440, and the inner wall of first scraping block 440 is outer with the cooling tube 330
Wall sliding supports.
A kind of above-mentioned ammonium acid fluoride efficient crystallization equipment, structure novel, the cooling dome 700, the clip cavity 710,
It is the outlet pipe 720, the water inlet pipe 730, the drinking-water pipe 660, the collecting pipe 670, first water tank 810, described
Cooperation between second water tank 820, the cooling piece 821, first water pump 830 and second water pump 840 constitutes one
Water-cooling circulating system provides enough regions convenient for crystallisation by cooling for the ammonium hydrogen fluoride solution inside the staving 200, has
Effect accelerates crystallisation by cooling, improves production efficiency;And the driving motor 500, the screw rod 400, the push plate 420 cooperation,
The crystalline solid for being adhered to 200 inner wall of 330 outer wall of cooling tube and the staving can be scraped, prevent crystalline solid accumulation, covering,
It avoids influencing being normally carried out for normal crystallisation by cooling, further increases production efficiency.
Further, the bottom margin of the push plate 420 is fixed with the second scraping block 450, the bottom of second scraping block 450
Face, which is obliquely installed and tilts lower end, supports 200 inner wall of staving;The bottom margin of first scraping block 440 is obliquely installed,
And tilt the outer wall that lower end supports the cooling tube 330;The design of second scraping block 450 can be by 200 inner wall of staving
Crystalline solid scrape, the structure of second scraping block 450 and first scraping block 440, which is as above arranged, can be improved scraping for crystalline solid
Speed, and guarantee to scrape effect, it is ensured that the normal crystallization process of crystal region, to improve production efficiency.
Further, the bottom of the screw rod 400 is fixed with strut 460, one end of the strut 460 and the screw rod
400 are fixedly welded, the other end is fixed with scraper plate 470, and the scraper plate 470 is supported with 200 bottom interior wall of staving sliding;Institute
On the one hand the design for stating strut 460 and the scraper plate 470 can stir the solution staving 200 inside, acceleration solution with it is described
The contact of 330 outer wall of 200 inner wall of staving and the cooling tube, to promote crystallization process;On the other hand institute can will be then adhered to
The crystalline solid for stating 200 inner wall bottom of staving scrapes, and prevents crystalline solid from covering cooled region, avoids influencing normal crystallization process.
Further, 200 bottom of staving structure funnel-shaped, the scraper plate 470 and 200 bottom shape of staving
It is adapted and supports 200 bottom interior wall of staving;200 bottom of staving is funnel-shaped to be facilitated inside the staving 200
The outlet of solution and crystalline solid, the scraper plate 470 is adapted with 200 bottom shape of staving can be convenient for adhering to and the bucket
200 bottom of body fluorination sodium crystal scrapes, and prevents from accumulating.
Further, the side wall of the feeder pipe 210 is equipped with drain pipe 240, and the drain pipe 240 is located at the baiting valve
220 top, the drain pipe 240 are equipped with switch valve 241;The drain pipe 240 is located at the top of the baiting valve 220,
The drain pipe 240 is equipped with switch valve 241;The design of the drain pipe 240 can be convenient for the discharge of surplus solution after reacting,
Then it is convenient for the collection of sodium fluoride crystalline solid;It should be noted that the connectivity part of the drain pipe 240 and the feeder pipe 210
Equipped with strainer.
Working principle:
When the utility model at work, through the commissioning pipe 310 toward launching a certain amount of saturation inside the staving 200
Ammonium acid fluoride aqueous solution then starts the cooling piece 821 and carries out one end time to the coolant liquid in second water tank 820
Cooling starts first water pump 830 after preset cooling time reaches, and opens the 4th solenoid valve 651, and described the
One water pump 830 feeds the coolant liquid in second water tank 820 through freezing in the cooling tube 330, reaches to preset time
Afterwards, the 4th solenoid valve 651 is closed, first solenoid valve 731 is and then opened, the coolant liquid of low temperature enters the clip cavity
In 710, after preset time reaches, first water pump 830 is closed, the cryogenic liquid of the first batch, which supplies, to be completed;Then
The second solenoid valve 611 is opened, the room temperature cooling liquid in first water tank 810 enters second water tank 820, described
Freezed under the action of cooling piece 821, cooled down;At the same time, the driving motor 500 starts, and drives 420 edge of push plate
400 vertical movable of screw rod drives the scraper plate 420 along the 200 inner wall lower rotation of staving, in the staving 200
The ammonium acid fluoride aqueous solution in portion is contacted with the outer wall of 200 inner wall of staving, the cooling tube 330, crystallisation by cooling, and crystalline solid is viscous
It is attached to the outer wall of the cooling tube 330 and the inner wall of the staving 200, crystalline solid is in the push plate 420 and the scraper plate 470
It is detached under effect from 330 outer wall of cooling tube and 200 inner wall of the staving;Presetting for cryogenic liquid to the first batch is cold
But after time arrival, start second water pump 840, open the third solenoid valve 641, second water pump 840 passes through institute
Drinking-water pipe 660 is stated to pump the coolant liquid in the cooling tube 330 to first water tank 810, after preset time arrival,
The third solenoid valve 641 and second water pump 840 are closed, first water pump 830 is and then started, opens the described 4th
Solenoid valve 651, first water pump 830 will be described in the coolant liquid infeeds of the second batch through freezing in second water tank 820
In cooling tube 330, after preset time arrival, the 4th solenoid valve 651 is closed, and then opens first solenoid valve
731, the coolant liquid of the low temperature of the second batch enters in the clip cavity 710, and excessive coolant liquid goes out described in the clip cavity 710
Water pipe 720 flows in first water tank 810, the crystallization process in the replacement process of coolant liquid, inside the staving 200
And scraping process is always in progress;The replacement process of above-mentioned coolant liquid is so repeated, until default crystallisation by cooling duration, stops
The only cooling piece 821 closes the driving motor 500, then opens the switch valve 241, and the solution after reaction is discharged,
It after solution is drained, opens the driving motor 500 and opens the baiting valve 220, ammonium acid fluoride crystal is from the baiting valve
220 discharges, complete the preparation of ammonium acid fluoride crystal;Wherein, it before stopping the driving motor 500, needs the cooling tube
Coolant liquid in 330 is pumped into first water tank 810, for next batch ammonium hydrogen fluoride solution carry out crystallization prepare;
It should be noted that the driving motor 500, first water pump 830, second water pump 840, the cooling piece 821, institute
State the first solenoid valve 731, the second solenoid valve 611, the third solenoid valve 641, the 4th solenoid valve 651 with control
Device electrically connects, and the button of multiple each electrical part start and stop of control is provided on the controller.
The utility model is described with reference to the preferred embodiments, and those skilled in the art know, is not departing from this reality
In the case where with novel spirit and scope, various changes or equivalence replacement can be carried out to these features and embodiment.This reality
It is not limited to the particular embodiment disclosed with novel, other embodiments fallen into claims hereof all belong to
In the range of the utility model protection.
Claims (5)
1. a kind of ammonium acid fluoride efficient crystallization equipment, including rack (100) and the staving being fixed on the rack (100)
(200), staving (200) the bottom connection is equipped with feeder pipe (210), and the feeder pipe (210) is equipped with baiting valve (220),
It is characterized by:
The top cover of the staving (200) is equipped with bung (300), and the bung (300) and the staving (200) are solid by screw
Fixed connection, the bung (300) are equipped with commissioning pipe (310), and described commissioning pipe (310) one end and the staving (200) are internal
Connection, the other end are covered with sealing cover (320);The bottom interior wall of the staving (200) is fixedly installed with support frame (230), institute
It states and is equipped with screw rod (400) between support frame (230) and the bung (300) by bearing, the top of the screw rod (400) is passed through
It wears the bung (300) and is connect with the output shaft of driving motor (500) by shaft coupling, the driving motor (500) is fixed
It is mounted on the rack (100), the sliding block (410) along the screw rod (400) sliding, institute is arranged on the screw rod (400)
It states and is fixed on the outside of sliding block (410) push plate (420), the push plate (420) is in disk-shaped and outer wall and the staving
(200) inner wall sliding supports;
The bung (300) be equipped with a plurality of cooling tube (330) being vertically arranged, the cooling tube (330) low side sealing and
It is internal to protrude into the staving (200), top and the bung (300) of the cooling tube (330) are welded and fixed, the cooling tube
(330) open top and the outside positioned at the bung (300);Drinking-water pipe is equipped in each cooling tube (330)
(660), the bottom in the cooling tube (330) and close to the cooling tube (330) is protruded into the bottom end of the drinking-water pipe (660),
The top of the bung (300) be equipped with collecting pipe (670), the top of each drinking-water pipe (660) with the collecting pipe (670)
Connection;The outer sheath of the staving (200) is equipped with cooling dome (700), and the cooling dome (700) covers staving (200) side
Wall and bottom, the cooling dome (700) is interior to be equipped with clip cavity (710), the shape of the clip cavity (710) and the cooling dome (700)
Shape is adapted, and the top sidewall of the cooling dome (700) is fixed with the outlet pipe (720) being connected to the clip cavity (710),
The bottom sidewall of the cooling dome (700) is fixed with the water inlet pipe (730) being connected to the clip cavity (710), the water inlet pipe
(730) the first solenoid valve (731) are equipped with, are fixedly installed with the first water tank (810) and the second water tank on the rack (100)
(820), first water tank (810) is located at the top of second water tank (820) and the bottom of first water tank (810)
Side wall is connected to the top sidewall of second water tank (820) by first pipe (610), is set on the first pipe (610)
Have second solenoid valve (611), the top and the clip cavity (710) of first water tank (810) are connected by the outlet pipe (720)
It is logical, it is equipped with cooling piece (821) on the side wall of second water tank (820), the chill surface of the cooling piece (821) is described in
Setting inside second water tank (820);The lower section of second water tank (820) is equipped with the first water pump (830), first water pump
(830) it is fixedly mounted on the rack (100), the water inlet of first water pump (830) and second water tank (820)
Bottom is connected to by second pipe (620), and the water outlet of first water pump (830) and the water inlet pipe (730) pass through No.1
Tee tube (680) connection;The top of first water tank (810) is equipped with the second water pump (840), and second water pump (840) is solid
On the rack (100), the top of the water outlet of second water pump (840) and first water tank (810) is logical for Dingan County
Third pipeline (630) connection is crossed, the water inlet connection of second water pump (840) is equipped with the 4th pipeline (640), the 4th pipe
Road (640) is equipped with third solenoid valve (641), and the other end of the 4th pipeline (640) and the collecting pipe (670) pass through two
Number tee tube (690) connection, by the 5th pipeline between No. two tee tubes (690) and the No.1 tee tube (680)
(650) it is connected to, the 5th pipeline (650) is equipped with the 4th solenoid valve (651);
The cooling tube (330) are corresponded on the push plate (420) equipped with multiple through-holes (430), the bottom of each through-hole (430)
Portion is correspondingly provided with cricoid first scraping block (440), the inner wall of first scraping block (440) and the cooling tube (330) it is outer
Wall sliding supports.
2. a kind of ammonium acid fluoride efficient crystallization equipment according to claim 1, it is characterised in that:
The bottom margin of the push plate (420) is fixed with the second scraping block (450), the inclined bottom surface of second scraping block (450)
It is arranged and inclination lower end supports the staving (200) inner wall;The bottom margin of first scraping block (440) is obliquely installed,
And tilt the outer wall that lower end supports the cooling tube (330).
3. a kind of ammonium acid fluoride efficient crystallization equipment according to claim 1, it is characterised in that:
The bottom of the screw rod (400) is fixed with strut (460), and one end and the screw rod (400) of the strut (460) are solid
Fixed welding, the other end are fixed with scraper plate (470), and the scraper plate (470) supports with the sliding of the staving (200) bottom interior wall.
4. a kind of ammonium acid fluoride efficient crystallization equipment according to claim 3, it is characterised in that:
Staving (200) bottom structure funnel-shaped, the scraper plate (470) is adapted with the staving (200) bottom shape,
And support the staving (200) bottom interior wall.
5. a kind of ammonium acid fluoride efficient crystallization equipment according to claim 1, it is characterised in that:
The side wall of the feeder pipe (210) is equipped with drain pipe (240), and the drain pipe (240) is located at the baiting valve (220)
Top, the drain pipe (240) are equipped with switch valve (241).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822077492.0U CN209193564U (en) | 2018-12-11 | 2018-12-11 | Ammonium acid fluoride efficient crystallization equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822077492.0U CN209193564U (en) | 2018-12-11 | 2018-12-11 | Ammonium acid fluoride efficient crystallization equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209193564U true CN209193564U (en) | 2019-08-02 |
Family
ID=67428591
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822077492.0U Active CN209193564U (en) | 2018-12-11 | 2018-12-11 | Ammonium acid fluoride efficient crystallization equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209193564U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115727613A (en) * | 2022-11-16 | 2023-03-03 | 安徽龙华化工股份有限公司 | Production of phosphorus pentoxide is with cooling transport processing system that desublimates |
-
2018
- 2018-12-11 CN CN201822077492.0U patent/CN209193564U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115727613A (en) * | 2022-11-16 | 2023-03-03 | 安徽龙华化工股份有限公司 | Production of phosphorus pentoxide is with cooling transport processing system that desublimates |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210559482U (en) | Freezing crystallization sodium sulfate removal device | |
CN209193564U (en) | Ammonium acid fluoride efficient crystallization equipment | |
CN218793978U (en) | Novel crystallizing tank | |
KR101640693B1 (en) | Method for treating of plastic substrates and a device for an at least partial regeneration of a treatment solution | |
CN113975848A (en) | External continuous cooling crystallization system of cooler | |
CN110772830B (en) | Cold crystallizer for chemical production | |
CN210698881U (en) | Continuous forced circulation cooling crystallizing tank | |
CN109701307B (en) | Honey impurity removing device and method | |
CN208700598U (en) | A kind of continuous crystallizing system of ferrous sulfate | |
CN206577413U (en) | A kind of menthol crystal system | |
CN204815766U (en) | Interior hot type evaporation crystallization equipment | |
CN210699122U (en) | Purification device is used in ethyl ferrocene production | |
CN221309603U (en) | Crystallizer for improving yield stability of fluoroethylene carbonate | |
CN208260233U (en) | A kind of oleic acid crystallization apparatus | |
CN207243863U (en) | improved fermentation tank | |
CN221267197U (en) | Mother liquor recovery device | |
CN209853770U (en) | Device for recovering high-purity sodium sulfate in mixed high-salt wastewater by freezing method | |
CN203653265U (en) | Kettle-type crystallizer for producing ammonium bifluoride | |
CN210683989U (en) | Galvanizing solution circulating cooling device | |
CN217312033U (en) | Crystallization device is used in ammonium bifluoride production | |
CN220878819U (en) | Crystallization device capable of realizing rapid cooling | |
CN211443568U (en) | Liquid caustic soda holding vessel | |
CN218507649U (en) | Clean drink machine scale removal system | |
CN219209039U (en) | Plate-type suspension crystallization purification system | |
CN218421118U (en) | Crystallization kettle for oxalate removal |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |