CN209178986U - It is a kind of to exempt from broken apart concrete filling pile head - Google Patents

It is a kind of to exempt from broken apart concrete filling pile head Download PDF

Info

Publication number
CN209178986U
CN209178986U CN201821723647.7U CN201821723647U CN209178986U CN 209178986 U CN209178986 U CN 209178986U CN 201821723647 U CN201821723647 U CN 201821723647U CN 209178986 U CN209178986 U CN 209178986U
Authority
CN
China
Prior art keywords
pile
casing
framework
steel reinforcement
exempt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201821723647.7U
Other languages
Chinese (zh)
Inventor
朱正国
梁柱
高云河
吴代生
梁敏
蒲瑞新
黄雷云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanning College for Vocational Technology
Original Assignee
Nanning College for Vocational Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanning College for Vocational Technology filed Critical Nanning College for Vocational Technology
Priority to CN201821723647.7U priority Critical patent/CN209178986U/en
Application granted granted Critical
Publication of CN209178986U publication Critical patent/CN209178986U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

Exempt from broken apart concrete filling pile head, including bored concrete pile framework of steel reinforcement and concrete perfusion the utility model discloses a kind of, there are longitudinal reinforcement and stirrup in the pile foundation portion of the bored concrete pile framework of steel reinforcement, and there is longitudinal reinforcement in the pile crown portion of the bored concrete pile framework of steel reinforcement;Suit is longitudinally separated casing on the longitudinal reinforcement in the pile crown portion of the bored concrete pile framework of steel reinforcement, the bottom in the pile crown portion of the bored concrete pile framework of steel reinforcement is provided with lateral separation casing, the lateral separation casing is arranged in " well " font, and center reserves the vacancy of decentralization tremie;And casing protection reinforcing bar is equipped in the lateral separation casing.The utility model construction is simple, low cost, the energy quick separating filling pile head by the way of overall separation, it is high-efficient, noiseless, free from dust, pile crown can realize recycled in its entirety, it can be used as the clump weight of later period dead load test on pile foundation, using being mechanically pulverized as the raw material of brickmaking after also can be recycled, market application prospect is extensive.

Description

It is a kind of to exempt from broken apart concrete filling pile head
Technical field
The utility model relates to cast-in-place concrete pile technical field more particularly to a kind of exempt from broken apart filling concrete Pile head.
Background technique
Van Gogh's layer and super high-rise building, all common basis of the cast-in-place concrete pile as building, the basis of bridge is more Add and can't do without pile foundation.As the bored concrete pile on solitary building basis, quantity lacks then up to a hundred, how then thousands of, substantial amounts.Reinforcing bar When Concrete Grouting Pale, specification regulation bored concrete pile top mark height should be higher than that design 0.5~1.0m of stake top absolute altitude, to guarantee pile crown The quality of concrete, main cause are that the concrete of pile crown part contains mud coating, and there are unavoidable on instillation process Mass defect, can only reject, cannot directly as stake top, but be higher than design of pile top absolute altitude pile crown part, to pile body coagulation After native intensity reaches the 80% of design strength, it could be cut when subsequent handling is constructed, cut the work of this part pile crown concrete Work is called " broken pile head ".The mode of live broken pile head is mainly divided artificial and mechanical.It is artificial mainly to be made by air compressor machine and air drill For crushing plant, pounded manually except pile crown concrete, the size of a general pile crown is in 1m3It is more than concrete, pound completely except and it is clear Reason needs 1 worker at least time half a day, inefficiency, and noise and dust seriously polluted, and working condition is poor, to worker The damage of both hands is very big.In addition damage can be directly contributed to the reserved steel bar of pile crown part, when the phenomenon that pounding disconnected reinforcing bar, Later period also needs reinforcement by connection to handle;Machinery is pounded except being to smash pile crown by hydraulic device, the purer artificial height of crushing efficiency, but also Need a large amount of hand fit that could complete, especially in the straightening of the smooth and reinforcing bar of later period pile crown, the relatively pure people of cost Work is higher.
For building trade, land resource is more and more rare, and skyscraper is rised sheer from level ground in succession.Pile foundation construction must can not It is few, at present in the building trade in Guangxi or even the whole nation, for except pile crown being constructed by the way of broken mostly, construct Low efficiency, at high cost, worker's operating condition is arduous, and the pile crown concrete fragment smashed has no recovery value.
Utility model content
The purpose of this utility model is to provide a kind of saving of labor propose effect, energy conservation and environmental protection, can overall separation pile crown exempt to be crushed Isolated concrete filling pile head.
To achieve the goals above, the technical solution adopted in the utility model is as follows:
It is a kind of to exempt from broken apart concrete filling pile head, including bored concrete pile framework of steel reinforcement and concrete perfusion, it is described There are longitudinal reinforcement and stirrup in the pile foundation portion of bored concrete pile framework of steel reinforcement, and there is longitudinal reinforcement in the pile crown portion of the bored concrete pile framework of steel reinforcement; Suit is longitudinally separated casing, the stake of the bored concrete pile framework of steel reinforcement on the longitudinal reinforcement in the pile crown portion of the bored concrete pile framework of steel reinforcement The bottom on head is provided with lateral separation casing, and the lateral separation casing is arranged in " well " font, and center reserves decentralization coagulation The vacancy of native conduit;And casing protection reinforcing bar is equipped in the lateral separation casing, the later period extracts out as tensioned prestressing bar Perforation.
Preferably, the lateral separation casing includes the first lateral separation casing and the second lateral separation casing, described the One lateral separation casing and the second lateral separation casing are vertically installed in the bottom in the pile crown portion of bored concrete pile framework of steel reinforcement.
Preferably, the lateral separation casing length is greater than the stake diameter 10cm in the pile crown portion of bored concrete pile framework of steel reinforcement.
Preferably, the bottom in the pile crown portion of the bored concrete pile framework of steel reinforcement is also equipped with positioning ring, the positioning ring It is mounted on the outside of the framework of steel reinforcement in the pile crown portion of the bored concrete pile framework of steel reinforcement, the outer diameter of the positioning ring and the perfusion Pile head outer diameter is identical, and when disposing pile body steel reinforcement cage, the positioning ring is stake top elevation location.
Preferably, the lower end for being longitudinally separated casing and the lower end of positioning ring are in the same plane.
Preferably, the upper end for being longitudinally separated casing is flushed with the top of the longitudinal reinforcement in pile crown portion.
Preferably, the top adhesive tape sealing head for being longitudinally separated casing, adhesive tape packet header after longitudinal reinforcement is entangled in lower end, resistance Only when concreting cement slurry entrance.
Preferably, the diameter 16-20mm of the lateral separation casing, wall thickness 2mm;It is longitudinally separated casing diameter summary Greater than the diameter of the longitudinal reinforcement of pile crown steel essence cage, wall thickness is not less than 1mm.
Preferably, the casing and the material of lateral separation casing of being longitudinally separated is PVC plastic pipe.
The utility model is by adopting the above-described technical solution, have the advantages that
The utility model exempts from broken apart concrete filling pile head construction is simple, low cost, using overall separation Mode quick separating filling pile head, high-efficient, noiseless, free from dust, pile crown can realize recycled in its entirety, can be used as later period stake The clump weight of base static test, using being mechanically pulverized as the raw material of brickmaking after also can be recycled, market application prospect is extensive.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the pile crown framework of steel reinforcement of the utility model;
Fig. 2 is the structural schematic diagram for exempting from broken apart concrete filling pile head after the pouring of the utility model;
Fig. 3 is the solidifying native filling pile head separation process schematic diagram of the utility model;
Fig. 4 is overall separation schematic diagram after the fracture of the utility model concrete filling pile head;
Fig. 5 is force analysis figure of the utility model concrete filling pile head under separation anchorage effect.
In attached drawing, 1- longitudinal reinforcement, 2- stirrup, 3- is longitudinally separated casing, 4- lateral separation casing, and 401- first is laterally point From casing, 402- the second lateral separation casing, 5- positioning ring, 6- lifting lug, 7- cone anchorage, it is very heavy that 8- holds hydraulic punching Top.
Specific embodiment
For the purpose of this utility model, technical solution and advantage is more clearly understood, referring to the drawings and enumerate excellent Embodiment is selected, the utility model is further described.However, it is necessary to illustrate, many details listed in specification It is specific thin even without these just for the sake of making reader have a thorough explanation to one or more aspects of the present invention These aspects of the utility model also may be implemented in section.
Embodiment 1
As shown in Fig. 1 and 2, it is according to the present utility model it is a kind of exempt from broken apart concrete filling pile head, including fill There are longitudinal reinforcement 1 and stirrup 2, the filling in note stake framework of steel reinforcement and concrete perfusion, the pile foundation portion of the bored concrete pile framework of steel reinforcement There is longitudinal reinforcement 1 in the pile crown portion of note stake framework of steel reinforcement;It is set on the longitudinal reinforcement 1 in the pile crown portion of the bored concrete pile framework of steel reinforcement vertical To separation sleeve pipe 3, the bottom in the pile crown portion of the bored concrete pile framework of steel reinforcement is provided with lateral separation casing 4, the lateral separation 4 pipe of set is arranged in " well " font, and center reserves the vacancy of decentralization tremie;And set is equipped in the lateral separation casing 4 Protection of pipe reinforcing bar, prevents the extruding deviation of the concrete when pouring pile concrete, and later period extraction is used as tensioned prestressing bar Perforation;The lateral separation casing 4 include the first lateral separation casing 401 and the second lateral separation casing 402, described first Lateral separation casing 401 and the second lateral separation casing 402 are vertically installed in the bottom in the pile crown portion of bored concrete pile framework of steel reinforcement;Institute State stake diameter 10cm of 4 length of lateral separation casing greater than the pile crown portion of bored concrete pile framework of steel reinforcement;The bored concrete pile framework of steel reinforcement The bottom in pile crown portion is also equipped with positioning ring 5, and the positioning ring 5 is mounted on the pile crown portion of the bored concrete pile framework of steel reinforcement The outside of framework of steel reinforcement, the outer diameter of the positioning ring 5 is identical as the filling pile head outer diameter, when disposing pile body steel reinforcement cage, The positioning ring 5 is stake top elevation location.
Preferably, the lower end for being longitudinally separated casing 3 and the lower end of positioning ring 5 are in the same plane;The longitudinal direction The upper end of separation sleeve pipe 3 is flushed with the top of the longitudinal reinforcement 1 in pile crown portion;The top for being longitudinally separated casing 3 is sealed with adhesive tape Adhesive tape packet header after longitudinal reinforcement 1 is entangled in head, lower end, the entrance of cement slurry when preventing concreting;The lateral separation casing 4 Diameter 16-20mm, wall thickness 2mm;It is straight slightly larger than the longitudinal reinforcement of pile crown steel essence cage to be longitudinally separated 3 diameter of casing Diameter, wall thickness are not less than 1mm;The casing 3 and the material of lateral separation casing 4 of being longitudinally separated is common PVC plastic pipe.
As shown in Figs 1-4, the construction method for exempting from broken apart concrete filling pile head of the utility model are as follows:
(1) the bored concrete pile framework of steel reinforcement according to measured priming concrete pile hole length and diameter processing, the bored concrete pile The pile foundation portion of framework of steel reinforcement includes longitudinal reinforcement 1 and stirrup 2, and the pile crown portion of the bored concrete pile framework of steel reinforcement includes longitudinal reinforcement 1;
(2) suit is longitudinally separated casing 3 on the longitudinal reinforcement 1 in the pile crown portion, is longitudinally separated the top glue of casing 3 Adhesive tape packet header after longitudinal reinforcement 1 is entangled in band end socket, lower end, the entrance of cement slurry, bored concrete pile reinforcing bar when preventing concreting Positioning ring 5 is installed in the bottom in the pile crown portion of frame, and positioning ring 5 is mounted on the reinforcing bar in the pile crown portion of the bored concrete pile framework of steel reinforcement The outside of skeleton, the outer diameter of the positioning ring 5 is identical as the filling pile head outer diameter, described when disposing pile body steel reinforcement cage Positioning ring 5 is stake top elevation location;
(3) lateral separation is set in the corresponding position of bottom positioning ring 5 in the pile crown portion of the bored concrete pile framework of steel reinforcement Casing 4,4 pipe of lateral separation set are arranged in " well " font, and center reserves the middle section that decentralization concreting conduit passes through, horizontal It is slightly larger than stake holes diameter to the length of separation sleeve pipe 4, then protects reinforcing bar toward the inside threading of lateral separation casing, and can Pre-buried lifting lug 6;
(4) the bored concrete pile framework of steel reinforcement is placed in the priming concrete pile hole, filling pile head template is set, to Concrete perfusion in priming concrete pile hole generates bored concrete pile, conserves process into bored concrete pile;
(5) conserve to after reaching design strength requirement that (generally concrete strength of pile reaches design after the bored concrete pile After the 80% of intensity), the soil around pile crown is opened in cleaning, exposes reserved lateral separation casing, is extracted out in lateral separation casing Casing protection reinforcing bar (later period is reusable), then penetrate prestressed reinforcement of tensioning (the every prestressing force of diameter 15.7mm Muscle can bear 30 tons or more of pulling force), cone anchorage 7 is installed at both ends, in conjunction with hand-held hydraulic feed-through jack 8, to pile crown point From the prestressing force that position applies lateral brisement, pile crown is pulled up, arrangement separation can be realized;Or often have in conjunction with building-site Lifting equipment, such as tower crane or digging machine, tensioning lock out operation can be realized in 1 operating personnel.
Separating feasibility theory analysis
Mechanical Calculation and Analysis is carried out so that 1m commonly uses stake diameter as an example:
As shown in figure 5, tension standard value is ftk=2.01MPa, because of pile crown position if concrete strength of pile is C30 Longitudinal reinforcement has casing protection, do not bond with concrete, then entire pile body breaks internal force are as follows: 1571KN converts into 157 Ton.Four groups to draw cone anchorage on, every vertical extruding internal force punished is about 20 tons at 8.And hydraulic punching is very heavy at this time The stretching force that top need to only provide 5.22 tons can meet, and hydraulic feed-through jack maximum is held on open market can generate 26 tons Pulling force.In addition, the concrete sheet after hardening, as fragile material, there is cracking in one section of part, entire cross section can be run through immediately, And then the effect of the overall separation of pile crown can be achieved completely.As seen from the above analysis, the pile crown concrete of 1m diameter is separated, There are also very big to have more than needed for mechanical property provided by equipment, that is to say, that and the utility model can separate the pile crown of larger diameter, By being arranged to the different quantity for drawing anchorage, the pile crown overall separation under the various operating conditions of diameter 0.8m to 2m is fully met.
The utility model implement only need a small-sized hand-held centre-hole jack and it is some may be reused match Part, such as cone anchorage and the lifting equipment often having to drawing reinforcing bar, cooperation building-site, such as tower crane or digging machine, 1 operating personnel Tensioning lock out operation can be realized, consumptive material is mainly reflected in plastic tube, and 20 meters of plastic tubes of each pile crown mean consumption are calculated, expended 30 yuan of cost, but overall efficacy is high, it is at low cost, there is biggish competition potential.It is pure artificial with the current most common building trade Broken pile crown is reference, and every cubic metre of pile head breaking needs artificial and machinery expenses at least at 200 yuan or more, and uses this item If purpose scheme is implemented, work efficiency can improve at least 10 times or more, and noiseless and dust pollution, the pile crown of rejecting can also return It receives and utilizes, have high economic benefit and prospect.
The above is only the preferred embodiment of the utility model, it is noted that for the common skill of the art For art personnel, without departing from the principle of this utility model, can also make several improvements and retouch, these improve and Retouching also should be regarded as the protection scope of the utility model.

Claims (9)

1. a kind of exempt from broken apart concrete filling pile head, it is characterised in that: mixed including bored concrete pile framework of steel reinforcement and perfusion There are longitudinal reinforcement and stirrup in solidifying soil, the pile foundation portion of the bored concrete pile framework of steel reinforcement, and the pile crown portion of the bored concrete pile framework of steel reinforcement has Longitudinal reinforcement;Suit is longitudinally separated casing, the bored concrete pile steel on the longitudinal reinforcement in the pile crown portion of the bored concrete pile framework of steel reinforcement The bottom in the pile crown portion of tendons skeleton is provided with lateral separation casing, and the lateral separation casing is arranged in " well " font, and center is stayed The vacancy of tremie is transferred out;And casing protection reinforcing bar is equipped in the lateral separation casing.
A kind of exempt from broken apart concrete filling pile head 2. according to claim 1, it is characterised in that: the transverse direction Separation sleeve pipe includes the first lateral separation casing and the second lateral separation casing, and the first lateral separation casing and second is laterally Separation sleeve pipe is vertically installed in the bottom in the pile crown portion of bored concrete pile framework of steel reinforcement.
A kind of exempt from broken apart concrete filling pile head 3. according to claim 1 or 2, it is characterised in that: described Lateral separation casing length is greater than the stake diameter 10cm in the pile crown portion of bored concrete pile framework of steel reinforcement.
A kind of exempt from broken apart concrete filling pile head 4. according to claim 1, it is characterised in that: the perfusion The bottom in the pile crown portion of stake framework of steel reinforcement is also equipped with positioning ring, and the positioning ring is mounted on the bored concrete pile framework of steel reinforcement Pile crown portion framework of steel reinforcement outside, the outer diameter of the positioning ring is identical as the filling pile head outer diameter, dispose pile body When steel reinforcement cage, the positioning ring is stake top elevation location.
A kind of exempt from broken apart concrete filling pile head 5. according to claim 4, it is characterised in that: the longitudinal direction The lower end of separation sleeve pipe and the lower end of positioning ring are in the same plane.
A kind of exempt from broken apart concrete filling pile head 6. according to claim 1, it is characterised in that: the longitudinal direction The upper end of separation sleeve pipe is flushed with the top of the longitudinal reinforcement in pile crown portion.
A kind of exempt from broken apart concrete filling pile head 7. according to claim 1, it is characterised in that: the longitudinal direction Adhesive tape packet header after longitudinal reinforcement is entangled in the top adhesive tape sealing head of separation sleeve pipe, lower end, cement slurry when preventing concreting Into.
A kind of exempt from broken apart concrete filling pile head 8. according to claim 1 or 2, it is characterised in that: described The diameter 16-20mm of lateral separation casing, wall thickness 2mm;It is vertical slightly larger than pile crown steel essence cage to be longitudinally separated casing diameter To the diameter of reinforcing bar, wall thickness is not less than 1mm.
A kind of exempt from broken apart concrete filling pile head 9. according to claim 1, it is characterised in that: the longitudinal direction The material of separation sleeve pipe and lateral separation casing is PVC plastic pipe.
CN201821723647.7U 2018-10-24 2018-10-24 It is a kind of to exempt from broken apart concrete filling pile head Withdrawn - After Issue CN209178986U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821723647.7U CN209178986U (en) 2018-10-24 2018-10-24 It is a kind of to exempt from broken apart concrete filling pile head

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821723647.7U CN209178986U (en) 2018-10-24 2018-10-24 It is a kind of to exempt from broken apart concrete filling pile head

Publications (1)

Publication Number Publication Date
CN209178986U true CN209178986U (en) 2019-07-30

Family

ID=67361888

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821723647.7U Withdrawn - After Issue CN209178986U (en) 2018-10-24 2018-10-24 It is a kind of to exempt from broken apart concrete filling pile head

Country Status (1)

Country Link
CN (1) CN209178986U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109183783A (en) * 2018-10-24 2019-01-11 南宁职业技术学院 It is a kind of to exempt from broken apart concrete filling pile head

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109183783A (en) * 2018-10-24 2019-01-11 南宁职业技术学院 It is a kind of to exempt from broken apart concrete filling pile head
CN109183783B (en) * 2018-10-24 2023-10-24 南宁职业技术学院 Breaking-free separated pile head of concrete filling pile

Similar Documents

Publication Publication Date Title
CN109183783A (en) It is a kind of to exempt from broken apart concrete filling pile head
CN101634146B (en) Manually digging hole full-steel cylinder-wall protecting construction device for building pile foundation and construction method thereof
CN207974103U (en) The isolating device of cast-in-situ bored pile pile crown
CN104563147B (en) Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation
CN209178986U (en) It is a kind of to exempt from broken apart concrete filling pile head
CN202039368U (en) Simple hand-operated spiral soil borrowing device for reinforcement of prestressed tubular pile core
CN201826302U (en) Boring device for large-diameter cast-in-situ thin-walled concrete composite pile
CN106088123B (en) A kind of sand geology steel tube well drop water level device and its construction method
CN102345287A (en) Construction method of large-diameter cast-in-situ thin-wall concrete composite pile and special hole forming device
CN101892764A (en) Method for building enclosing wall
CN201236340Y (en) Novel tool type hanging steel bar
CN208379601U (en) A kind of recoverable foundation pit supporting pile and attaching/detaching apparatus
CN103334433B (en) A kind of construction method of pile pulling
CN218029036U (en) Protection structure for construction on inclined plate
CN208685607U (en) A kind of PHC tubular pole aperture plugging structure
CN103132511A (en) Pile-forming method and pile-forming device for static pressure immersed tube expanded-base cast-in-place pile
CN206279529U (en) A kind of concrete pre-separate device
CN205576902U (en) Pile foundation of stress tube in advance of removable screw rod
CN208854833U (en) A kind of prefabricated components reserve the grouting of hanging ring hole and use formwork structure
CN207092089U (en) A kind of pile foundation pile crown auxiliary cuts device
CN208776189U (en) A kind of Combined detachable steel reinforcement cage hanging steel bar device
CN208733632U (en) A kind of quick broken pile head device of cast-in-place concrete pile
CN2811394Y (en) Soil-cement pile and spile integrated pile driver
CN108086309B (en) Mini pile reinforcement cage installation method
CN206736919U (en) A kind of filling pile head quickly abolishes device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned
AV01 Patent right actively abandoned

Granted publication date: 20190730

Effective date of abandoning: 20231024

AV01 Patent right actively abandoned

Granted publication date: 20190730

Effective date of abandoning: 20231024