CN209129633U - Full section of tunnel construction integer support steel arch-shelf - Google Patents

Full section of tunnel construction integer support steel arch-shelf Download PDF

Info

Publication number
CN209129633U
CN209129633U CN201821745642.4U CN201821745642U CN209129633U CN 209129633 U CN209129633 U CN 209129633U CN 201821745642 U CN201821745642 U CN 201821745642U CN 209129633 U CN209129633 U CN 209129633U
Authority
CN
China
Prior art keywords
arch
flange disk
shelf
anchor pole
rack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821745642.4U
Other languages
Chinese (zh)
Inventor
谢强
仇瑞红
谢汶潘
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hebei Chuangheng Intelligent Equipment Technology Co Ltd
Original Assignee
Hebei Chuangheng Intelligent Equipment Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Chuangheng Intelligent Equipment Technology Co Ltd filed Critical Hebei Chuangheng Intelligent Equipment Technology Co Ltd
Priority to CN201821745642.4U priority Critical patent/CN209129633U/en
Application granted granted Critical
Publication of CN209129633U publication Critical patent/CN209129633U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model belongs to steel arch-shelf technical field, discloses a kind of full section of tunnel construction integer support steel arch-shelf.It is mainly characterized in that including upper arch, middle arch rack and lower arch, terminal pad is set between upper arch and middle arch rack and between middle arch rack and lower arch, terminal pad includes first flange disk and second flange disk, the first flange disk and second flange disk side are flexibly connected by bindiny mechanism, and connection bolt is provided in the connecting hole.In storage and transportational process, the steel arch-shelf connected by the terminal pad is folded, when transporting supporting position, it is mechanical from the picking-up of upper arch middle part with lifting, middle arch rack and lower arch are sagging under self gravitation effect, at this time, under the limit of bindiny mechanism, the connecting hole automatic aligning of first flange disk and second flange disk, staff is shortened in the operating time of supporting position, reduce because of falling rocks or the incidence to cause the accident of collapsing, and improve installation effectiveness, reduces labor intensity.

Description

Full section of tunnel construction integer support steel arch-shelf
Technical field
The utility model belongs to tunnel support steel arch-shelf technical field more particularly to a kind of whole branch of full section of tunnel construction Shield uses steel arch-shelf.
Background technique
For country's Tunnel Engineering frequently with composite lining structure, tunnel steel arch frame is the composition portion of Tunnel at present Point, main function is resistant to the initial stage convergent deformation that country rock is generated due to excavation disturbance.Steel arch-shelf is fragmented under normal conditions It is transported to construction site, the face after excavating manually is attached it to by worker, and using lock foot anchor tube at steel arch-shelf arch springing It is fixed, uses U-typed reinforcement welding between steel arch-shelf and lock foot anchor tube.The above method have the following deficiencies: first, due to Manually steel arch-shelf fragment is transported at the face after excavating and is installed, installation space is small, and installation difficulty is big, and due to face It is easy to appear falling rocks etc., increases accident rate;Second, being connected between fragment using ring flange, every steel arch-shelf weighs number Hundred kilograms, it is not easy to be aligned in small space, increases labor intensity;Third, due to being influenced by operating space is narrow, often The steel arch-shelf of secondary installation weighs hundreds of kilograms, is only manually often difficult to be lifted to, vault closely connected with tunnel vault country rock There are biggish gaps between country rock and steel arch-shelf apical margin;Arch locally will appear when multiple pneumatically placed concrete after steel arch-shelf is set up It comes to nothing phenomenon.In the case, steel arch-shelf will cannot play the work for resisting the convergence of arch country rock, deformation in certain deformation range With.
Utility model content
The technical problems to be solved in the utility model is just to provide that welding quality is good, full section of tunnel of high production efficiency is applied Work integer support steel arch-shelf.
To solve the above problems, the technical solution adopted in the utility model are as follows: including being located at the upper arch at middle part, being located at institute Two middle arch racks at arch both ends and the lower arch positioned at the middle arch rack both ends are stated, in the upper arch and the middle arch rack Between and terminal pad, the end of the upper arch, middle arch rack and lower arch be set between the middle arch rack and the lower arch Be fixedly connected with corresponding terminal pad, the terminal pad includes first flange disk and second flange disk, the first flange disk and Second flange disk side is flexibly connected by bindiny mechanism, is provided with connection on the first flange disk and second flange disk Hole is provided with connection bolt in the connecting hole.
Its additional technical feature are as follows:
The bindiny mechanism is the hinge shaft connecting with the first flange disk and second flange disk;
It is provided with anchor pole locating rack in the terminal pad, is provided with anchor pole guide sleeve on the anchor pole locating rack;
The fixation hole with connecting hole location matches is provided on the anchor pole locating rack, the anchor pole locating rack passes through company Connecting bolt is fixedly connected with first flange disk and second flange disk;
The lower end of described two lower arches is provided with jacking terminal pad, which includes solid with lower arch bottom Surely the bottom surface supporting plate connected is side supporting plate in the bottom surface supporting plate two sides, and the bottom surface supporting plate and side supporting plate are in " U " font, The upper end of described two side supporting plates is provided with foot's anchor pole guide sleeve.
Full section of tunnel provided by the utility model construction integer support with steel arch-shelf compared with prior art, have with Lower advantage: first, due to including the upper arch positioned at middle part, two middle arch racks positioned at the upper arch both ends and being located at described The lower arch at middle arch rack both ends, between the upper arch and the middle arch rack and between the middle arch rack and the lower arch Terminal pad is set, and the end of the upper arch, middle arch rack and lower arch is fixedly connected with corresponding terminal pad, the terminal pad packet First flange disk and second flange disk are included, the first flange disk and second flange disk side are flexibly connected by bindiny mechanism, It is provided with connecting hole on the first flange disk and second flange disk, connection bolt is provided in the connecting hole, in steel In arch production process, the steel arch-shelf both ends connected with the terminal pad will be needed to weld respectively with first flange disk and second flange disk It is connected together, first flange disk and second flange disk are flexibly connected by bindiny mechanism, when completing the process, will pass through the connection The steel arch-shelf of disk connection folds, and is fixed by holding clamp or rope, when transporting supporting position, by holding clamp Or rope is opened, with the mechanical picking-up in the middle part of upper arch is lifted, middle arch rack and lower arch are sagging under self gravitation effect, this When, under the limit of bindiny mechanism, the connecting hole automatic aligning of first flange disk and second flange disk, so that connection bolt holds very much Easily insertion, will connect bolt on nut tightening, shorten staff in the operating time of supporting position, reduce because The incidence that falling rocks or collapsing cause the accident, and installation effectiveness is improved, reduce labor intensity;Second, due to the company Connection mechanism is the hinge shaft connecting with the first flange disk and second flange disk;First flange disk and second flange disk and hinge shaft group At hinge structure, the connecting hole on such first flange disk and second flange disk is not easy to deviate, and installation speed is fast;Third, by In being provided with anchor pole locating rack in the terminal pad, it is provided with anchor pole guide sleeve on the anchor pole locating rack, according to working as The location of ground geologic structure and anchor pole set the direction of anchor pole guide sleeve, so that the anchoring direction of anchor pole is more reasonable, And anchor pole and steel arch-shelf are combined together by anchor pole guide sleeve, in conjunction with stronger, and are not had to again by anchor pole and steel arch Frame welding;Fourth, due to being provided with the fixation hole with connecting hole location matches, the anchor pole positioning on the anchor pole locating rack Frame is fixedly connected by connection bolt with first flange disk and second flange disk, and processing and installation is more convenient;Fifth, due to The lower end of described two lower arches is provided with jacking terminal pad, which includes the bottom being fixedly connected with lower arch bottom Face supporting plate is side supporting plate in the bottom surface supporting plate two sides, and the bottom surface supporting plate and side supporting plate are in " U " font, described two The upper end of side supporting plate is provided with foot's anchor pole guide sleeve, and bottom surface supporting plate side is provided with claw jack, described The claw lower end of claw jack is inserted into below the bottom surface supporting plate;It is provided with wedge-shaped steel plate below the claw jack, First steel arch-shelf is erected, below wedge-shaped steel plate insertion steel arch-shelf of the upper end with claw jack, bottom surface supporting plate is made to be located at pawl The claw of formula jack is lifted so that steel arch-shelf and tunnel vault country rock are closely connected upwards with claw jack, is pushed up in stopping, then Along foot's anchor pole guide sleeve direction drilling anchor rod aperture, foot's anchor pole is inserted into foot's anchor pole guide sleeve and bolthole, steel Together with arch is anchored with tunnel wall, claw jack and wedge-shaped steel plate are extracted out, it is more convenient to construct, will not be because of steel arch-shelf Sink and arch when multiple pneumatically placed concrete is caused locally to will appear phenomenon of coming to nothing, does not need to weld foot's anchor pole and steel arch-shelf, subtract Lack welding sequence, improves the bonding strength of anchor pole and steel arch-shelf.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model full section of tunnel construction integer support steel arch-shelf;
Fig. 2 is the structural schematic diagram of folded full section of tunnel construction integer support steel arch-shelf;
Fig. 3 is the structural schematic diagram of terminal pad;
Fig. 4 is the structural schematic diagram of the terminal pad with anchor pole locating rack;
Fig. 5 is the structural schematic diagram of anchor pole locating rack;
Fig. 6 is the lateral plan of the terminal pad with anchor pole locating rack;
Fig. 7 is the structural schematic diagram for jacking fixed device;
Fig. 8 is the structural schematic diagram of the fixed device of jacking with the lower arch in part.
Specific embodiment
With reference to the accompanying drawings and detailed description to the utility model full section of tunnel construction integer support steel arch-shelf Structure and be described in further details using principle.
As shown in Figure 1, Figure 2 and Figure 3, the structural representation of the utility model full section of tunnel construction integer support steel arch-shelf Figure, the utility model full section of tunnel construction integer support steel arch-shelf include positioned at the upper arch 1 at middle part, positioned at upper arch 1 Two middle arch racks 2 at both ends and lower arch 3 positioned at 2 both ends of middle arch rack, between upper arch 1 and middle arch rack 2 and in middle arch rack 2 Terminal pad 4 is set between lower arch 3, and the end of upper arch 1, middle arch rack 2 and lower arch 3 is fixed with corresponding terminal pad 4 to be connected It connects, terminal pad 4 includes first flange disk 5 and second flange disk 6, and first flange disk 5 and 6 side of second flange disk pass through connection machine Structure 7 is flexibly connected, and is provided with connecting hole 8 on first flange disk 5 and second flange disk 6, connection spiral shell is provided in connecting hole 8 Bolt 9.In steel arch-shelf production process, by the steel arch-shelf both ends for needing to be connected with the terminal pad 4 respectively with first flange disk 5 and Two ring flanges 6 weld together, and first flange disk 5 and second flange disk 6 are flexibly connected by bindiny mechanism 7.As shown in Fig. 2, When completing the process, the steel arch-shelf connected by the terminal pad 4 is folded, is fixed by holding clamp or rope, When transporting supporting position, holding clamp or rope are opened, held up in the middle part of upper arch 1 with machinery is lifted, middle arch rack 2 is under Arch 3 is sagging under self gravitation effect, at this point, under the limit of bindiny mechanism 7, first flange disk 5 and second flange disk 6 8 automatic aligning of connecting hole will connect the nut tightening on bolt 9, shorten work so that connection bolt 9 can be readily intercalated into Make personnel in the operating time of supporting position, reduces because of falling rocks or the incidence to cause the accident of collapsing, and improve installation Efficiency reduces labor intensity.
As shown in figure 3, bindiny mechanism 7 is the hinge shaft 10 connecting with first flange disk 5 and second flange disk 6;First flange Disk 5 and second flange disk 6 and hinge shaft 10 form hinge structure, the connecting hole 8 on such first flange disk 5 and second flange disk 6 It is not easy to deviate, installation speed is fast.
As shown in Figure 4, Figure 5 and Figure 6, it is provided with anchor pole locating rack 11 in terminal pad 4, is arranged on anchor pole locating rack 11 There is anchor pole guide sleeve 12, the direction of anchor pole guide sleeve 12 is set according to the location of local geologic structure and anchor pole, from And the anchoring direction of anchor pole is more reasonable, and anchor pole is combined together by anchor pole guide sleeve 12 with steel arch-shelf, in conjunction with more Securely, and do not have to again weld anchor pole and steel arch-shelf.
Anchor pole locating rack 11 is structure as a whole with first flange disk 5.Certainly, anchor pole locating rack 11 can also be as shown in Figure 5 Absolute construction, the fixation hole 13 with 8 location matches of connecting hole is provided on anchor pole locating rack 11, anchor pole locating rack 11 passes through Connection bolt 9 is fixedly connected with first flange disk 5 and second flange disk 6, and processing and installation is more convenient, it is of course also possible to such as Shown in Fig. 1, Fig. 7 and Fig. 8, the lower end of two lower arches 3 is provided with jacking terminal pad 14, which includes under The bottom surface supporting plate 15 that 3 bottom of arch is fixedly connected is side supporting plate 16, bottom surface supporting plate 15 and side in 15 two sides of bottom surface supporting plate Supporting plate 16 is in " U " font, the upper end of two side supporting plates 16 is provided with foot's anchor pole guide sleeve 17, the supporting plate 15 1 in bottom surface Side is provided with claw jack 18,19 lower end of claw insertion bottom surface supporting plate, 15 lower section of claw jack 18;In claw jack 18 lower sections are provided with wedge-shaped steel plate 20.First steel arch-shelf is erected, upper end is inserted into the wedge-shaped steel plate 20 of claw jack 18 Lower 3 lower section of arch makes bottom surface supporting plate 15 be located at 19 top of claw of claw jack 18, and being lifted upwards with claw jack 18 makes It obtains steel arch-shelf and tunnel vault country rock is closely connected, pushed up in stopping, it, will then along 17 direction drilling anchor rod aperture of foot's anchor pole guide sleeve Foot's anchor pole is inserted into foot's anchor pole guide sleeve and bolthole, and steel arch-shelf is together with tunnel wall anchoring, by claw jack 18 and wedge-shaped steel plate 20 extract out, it is more convenient to construct, will not because steel arch-shelf sinks and arch part when causing multiple pneumatically placed concrete It will appear phenomenon of coming to nothing, do not need to weld foot's anchor pole and steel arch-shelf, reduce welding sequence, improve anchor pole and steel arch-shelf Bonding strength.
The method of above-mentioned full section of tunnel construction integer support section-steel support, this method include the following steps:
This method includes the following steps:
The first step, arch 1, middle arch rack 2 and lower arch 3 in connection
By terminal pad 4 and corresponding upper arch 1, middle arch rack 2 and the lower arch between upper arch 1, middle arch rack 2 and lower arch 3 The welding of 3 end of frame, the connecting hole 8 after welding on the first flange disk 5 and second flange disk 6 of each terminal pad 4 are opposite;
Second step, transport to supporting position
Terminal pad 4 between upper arch 1, middle arch rack 2 and lower arch 3 is folded and is fixed by fixed mechanism, is used Transporting equipment is transported to supporting position;
Third step, supporting steel arch-shelf
Fixed mechanism is opened, is held up in the middle part of upper arch 1 with machinery is lifted, middle arch rack 2 and lower arch 3 are in self gravity It is sagging under effect;
4th step fixes first flange disk and second flange disk
The insertion connection bolt 9 in the connecting hole 8 of first flange disk 5 and second flange disk 6, will connect the spiral shell on bolt 9 Mother screws;
5th step, drilling anchor rod aperture simultaneously install anchor pole
In two sides drilling anchor rod aperture of terminal pad 4, and by rockbolt installation in bolthole;
6th step fixes anchor pole and supporting steel arch-shelf
Anchor pole is fixed with supporting steel arch-shelf by welding or other modes.
For being provided with anchor pole locating rack 11 in terminal pad 4, anchor pole guide sleeve is provided on anchor pole locating rack 11 For 12 full section of tunnel construction integer support steel arch-shelf, method for protecting support includes the following steps:
The first step, arch 1, middle arch rack 2 and lower arch 3 in connection
By terminal pad 4 and corresponding upper arch 1, middle arch rack 2 and the lower arch between upper arch 1, middle arch rack 2 and lower arch 3 The welding of 3 end of frame, the connecting hole 8 after welding on the first flange disk 5 and second flange disk 6 of each terminal pad 4 are opposite;
Second step, transport to supporting position
Terminal pad 4 between upper arch 1, middle arch rack 2 and lower arch 3 is folded and is fixed by fixed mechanism, is used Transporting equipment is transported to supporting position;
Third step, supporting steel arch-shelf
Fixed mechanism is opened, is held up in the middle part of upper arch 1 with machinery is lifted, middle arch rack 2 and lower arch 3 are in self gravity It is sagging under effect;
4th step fixes first flange disk and second flange disk
The insertion connection bolt 9 in the connecting hole 8 of first flange disk 5 and second flange disk 6, will connect the spiral shell on bolt 9 Mother screws;
5th step, drilling anchor rod aperture simultaneously install anchor pole
It is inserted into anchor pole guide sleeve 12 and bolthole along 12 direction drilling anchor rod aperture of anchor pole guide sleeve, and by anchor pole, Anchor pole tail portion is fixed in anchor pole guide sleeve 12.
For being provided with the fixation hole 13 with 8 location matches of connecting hole, anchor pole locating rack on the anchor pole locating rack 11 The 11 full section of tunnel construction integer support steel being fixedly connected by connecting bolt 9 with first flange disk 5 and second flange disk 6 For arch, method for protecting support includes the following steps:
The first step, arch 1, middle arch rack 2 and lower arch 3 in connection
By terminal pad 4 and corresponding upper arch 1, middle arch rack 2 and the lower arch between upper arch 1, middle arch rack 2 and lower arch 3 The welding of 3 end of frame, the connecting hole 8 after welding on the first flange disk 5 and second flange disk 6 of each terminal pad 4 are opposite;
Second step, transport to supporting position
Terminal pad 4 between upper arch 1, middle arch rack 2 and lower arch 3 is folded and is fixed by fixed mechanism, is used Transporting equipment is transported to supporting position;
Third step, supporting steel arch-shelf
Fixed mechanism is opened, is held up in the middle part of upper arch 1 with machinery is lifted, middle arch rack 2 and lower arch 3 are in self gravity It is sagging under effect;
First flange disk and second flange disk are fixed and anchor pole locating rack are fixed by the 4th step
Anchor pole locating rack 11 is placed among first flange disk 5 and second flange disk 6, so that the fixation of anchor pole locating rack 11 Hole 13 is aligned with the connecting hole 8 of first flange disk 5 and second flange disk 6, fixed in first flange disk 5, second flange disk 6 and anchor pole Insertion connection bolt 9 in the connecting hole 8 of position frame 11, will connect the nut tightening on bolt;
5th step, drilling anchor rod aperture simultaneously install anchor pole
It is inserted into anchor pole guide sleeve 12 and bolthole along 12 direction drilling anchor rod aperture of anchor pole guide sleeve, and by anchor pole, Anchor pole tail portion is fixed in anchor pole guide sleeve 12.
Full section of tunnel construction integer support for being provided with jacking terminal pad in the lower end of described two lower arches 3 is used For steel arch-shelf, method for protecting support includes the following steps:
The first step, arch 1, middle arch rack 2 and lower arch 3 in connection
By terminal pad 4 and corresponding upper arch 1, middle arch rack 2 and the lower arch between upper arch 1, middle arch rack 2 and lower arch 3 The welding of 3 end of frame, the connecting hole 8 after welding on the first flange disk 5 and second flange disk 6 of each terminal pad 4 are opposite;
Second step, transport to supporting position
Terminal pad 4 between upper arch 1, middle arch rack 2 and lower arch 3 is folded and is fixed by fixed mechanism, is used Transporting equipment is transported to supporting position;
Third step, supporting steel arch-shelf
Fixed mechanism is opened, is held up in the middle part of upper arch 1 with machinery is lifted, middle arch rack 2 and lower arch 3 are in self gravity It is sagging under effect;
First flange disk and second flange disk are fixed and anchor pole locating rack are fixed by the 4th step
Anchor pole locating rack 11 is placed among first flange disk 5 and second flange disk 6, so that the fixation of anchor pole locating rack 11 Hole 13 is aligned with the connecting hole 8 of first flange disk 5 and second flange disk 6, fixed in first flange disk 5, second flange disk 6 and anchor pole Insertion connection bolt 9 in the connecting hole 8 of position frame 11, will connect the nut tightening on bolt;
5th step jacks entire steel arch-shelf
Lower 3 lower end of arch is jacked with claw jack 18, drives entire steel arch-shelf to move up, until upper arch upper surface is close to Inner surface on tunnel top;
6th step bores foot's bolthole and installs foot's anchor pole
Foot's bolthole is bored along 17 direction of foot's anchor pole guide sleeve, and foot's anchor pole is inserted into foot's anchor pole guide sleeve In pipe 17 and foot's bolthole, foot's anchor pole tail portion is fixed in foot's anchor pole guide sleeve;
7th step, drilling anchor rod aperture simultaneously install anchor pole
It is inserted into anchor pole guide sleeve 12 and bolthole along 12 direction drilling anchor rod aperture of anchor pole guide sleeve, and by anchor pole, Anchor pole tail portion is fixed in anchor pole guide sleeve 12.
The protection scope of the utility model is not limited solely to above-described embodiment, as long as structure and the utility model tunnel are complete The section construction integer support same or similar range for just falling in the utility model protection of steel arch-shelf structure.

Claims (5)

  1. The integer support steel arch-shelf 1. full section of tunnel is constructed, including being located at the upper arch at middle part, being located at the upper arch both ends Two middle arch racks and lower arch positioned at the middle arch rack both ends, it is characterised in that: in the upper arch and the middle arch rack Between and terminal pad, the end of the upper arch, middle arch rack and lower arch be set between the middle arch rack and the lower arch Be fixedly connected with corresponding terminal pad, the terminal pad includes first flange disk and second flange disk, the first flange disk and Second flange disk side is flexibly connected by bindiny mechanism, is provided with connection on the first flange disk and second flange disk Hole is provided with connection bolt in the connecting hole.
  2. The integer support steel arch-shelf 2. full section of tunnel according to claim 1 is constructed, it is characterised in that: the connection machine Structure is the hinge shaft connecting with the first flange disk and second flange disk.
  3. The integer support steel arch-shelf 3. full section of tunnel according to claim 1 is constructed, it is characterised in that: in the connection It is provided with anchor pole locating rack on disk, is provided with anchor pole guide sleeve on the anchor pole locating rack.
  4. The integer support steel arch-shelf 4. full section of tunnel according to claim 3 is constructed, it is characterised in that: in the anchor pole The fixation hole with connecting hole location matches is provided on locating rack, the anchor pole locating rack passes through connection bolt and first flange disk It is fixedly connected with second flange disk.
  5. The integer support steel arch-shelf 5. full section of tunnel according to claim 1 is constructed, it is characterised in that: described two The lower end of lower arch is provided with jacking terminal pad, which includes the bottom surface supporting plate being fixedly connected with lower arch bottom, It is side supporting plate in the bottom surface supporting plate two sides, the bottom surface supporting plate and side supporting plate are in " U " font, in described two side supporting plates Upper end be provided with foot's anchor pole guide sleeve.
CN201821745642.4U 2018-10-26 2018-10-26 Full section of tunnel construction integer support steel arch-shelf Active CN209129633U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821745642.4U CN209129633U (en) 2018-10-26 2018-10-26 Full section of tunnel construction integer support steel arch-shelf

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821745642.4U CN209129633U (en) 2018-10-26 2018-10-26 Full section of tunnel construction integer support steel arch-shelf

Publications (1)

Publication Number Publication Date
CN209129633U true CN209129633U (en) 2019-07-19

Family

ID=67232772

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821745642.4U Active CN209129633U (en) 2018-10-26 2018-10-26 Full section of tunnel construction integer support steel arch-shelf

Country Status (1)

Country Link
CN (1) CN209129633U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109306870A (en) * 2018-10-26 2019-02-05 河北创恒智能装备科技有限公司 Full section of tunnel construction integer support steel arch-shelf and method for protecting support
CN110549055A (en) * 2019-09-29 2019-12-10 中国葛洲坝集团路桥工程有限公司 steel arch frame trial assembly die and connecting plate finish machining method
CN110566241A (en) * 2019-09-16 2019-12-13 四川睿铁科技有限责任公司 Quickly-assembled supporting shed frame
CN110608055A (en) * 2019-10-18 2019-12-24 中铁隧道局集团有限公司 Plug-and-play ball-hinge type steel arch connecting component capable of achieving quantitative yielding and use method
CN112983494A (en) * 2021-04-02 2021-06-18 中国铁建重工集团股份有限公司 Arch and arch are folding with hinge structure

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109306870A (en) * 2018-10-26 2019-02-05 河北创恒智能装备科技有限公司 Full section of tunnel construction integer support steel arch-shelf and method for protecting support
CN109306870B (en) * 2018-10-26 2024-05-03 河北创恒智能装备科技有限公司 Steel arch frame for whole support of tunnel full-section construction and support method
CN110566241A (en) * 2019-09-16 2019-12-13 四川睿铁科技有限责任公司 Quickly-assembled supporting shed frame
CN110549055A (en) * 2019-09-29 2019-12-10 中国葛洲坝集团路桥工程有限公司 steel arch frame trial assembly die and connecting plate finish machining method
CN110549055B (en) * 2019-09-29 2024-05-28 中国葛洲坝集团路桥工程有限公司 Steel arch trial assembly die and connecting plate finish machining method
CN110608055A (en) * 2019-10-18 2019-12-24 中铁隧道局集团有限公司 Plug-and-play ball-hinge type steel arch connecting component capable of achieving quantitative yielding and use method
CN110608055B (en) * 2019-10-18 2020-10-20 中铁隧道局集团有限公司 Plug-and-play ball-hinge type steel arch connecting component capable of achieving quantitative yielding and use method
CN112983494A (en) * 2021-04-02 2021-06-18 中国铁建重工集团股份有限公司 Arch and arch are folding with hinge structure
CN112983494B (en) * 2021-04-02 2023-03-10 中国铁建重工集团股份有限公司 Arch and arch are folding with hinge structure

Similar Documents

Publication Publication Date Title
CN209129633U (en) Full section of tunnel construction integer support steel arch-shelf
CN105926669B (en) A kind of Construction Method of Metro Station
CN103075020A (en) Steel tray supporting force transferring system
JP6681148B2 (en) Bridge construction method, pillars and guide means used in the bridge construction method
CN109505609A (en) Shallow buried covered excavation Urban Underground pipe gallery non-stand construction method and pipe gallery
CN104234447B (en) Deep foundation ditch tool-type hangs stair
CN104005569A (en) Construction method for supporting beam and removing columns
CN205476593U (en) Instrument formula foundation ditch packway
CN206233639U (en) movable shed
CN208982068U (en) The full section of tunnel construction integer support steel arch-shelf fixed device of jacking
KR101126009B1 (en) Jointing structure of steel pipes and steel pipe pole with the structure
CN202945798U (en) Overhanging type scaffold corner device
CN208982069U (en) A kind of gas tunnel soft stratum steel arch-shelf longitudinal connecting component
CN109306870A (en) Full section of tunnel construction integer support steel arch-shelf and method for protecting support
CN206360720U (en) A kind of novel flexible filling isolation barricade
CN111827648A (en) Construction device and method for down-supporting type overhanging scaffold
CN110552519A (en) Deep foundation pit assembled type safe passage construction method
CN108560566A (en) The recyclable steel pipe column of combined type and its method for supporting deep foundation pit
CN109812027A (en) A kind of discharging platform and its installation method
CN208517947U (en) Steel pipe column can be recycled in combined type
CN110552702B (en) Underground excavation construction method for assembled corrugated steel plate underground comprehensive pipe gallery
CN208441834U (en) A kind of rectangular top pipe reception sleeve arrangement
CN209067239U (en) Full section of tunnel construction integer support steel arch-shelf terminal pad
CN210888274U (en) Turnover base of steel pipe upright post frame
CN111525487A (en) Utility tunnel self-supporting pipeline support

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant