CN209011314U - A kind of novel fabricated primary and secondary beam connecting node - Google Patents

A kind of novel fabricated primary and secondary beam connecting node Download PDF

Info

Publication number
CN209011314U
CN209011314U CN201821532017.1U CN201821532017U CN209011314U CN 209011314 U CN209011314 U CN 209011314U CN 201821532017 U CN201821532017 U CN 201821532017U CN 209011314 U CN209011314 U CN 209011314U
Authority
CN
China
Prior art keywords
secondary beam
bolt
cushion cap
connecting node
primary
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821532017.1U
Other languages
Chinese (zh)
Inventor
刘运林
陈旭东
王若愚
王子恒
廖凯
程小乾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui University of Architecture
Original Assignee
Anhui University of Architecture
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui University of Architecture filed Critical Anhui University of Architecture
Priority to CN201821532017.1U priority Critical patent/CN209011314U/en
Application granted granted Critical
Publication of CN209011314U publication Critical patent/CN209011314U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model discloses a kind of novel fabricated primary and secondary beam connecting nodes, including girder and secondary beam, the girder two sides offer secondary beam cushion cap, the girder, which is located in the middle part of secondary beam cushion cap, is provided with pre-embedded bolt, prepared screw-bolt hole is offered inside the secondary beam, the position of the prepared screw-bolt hole matches with pre-embedded bolt, fastening nut is provided on rear side of the prepared screw-bolt hole, permanent opening is offered at the top of the secondary beam, the secondary beam cushion cap height and width are identical as secondary beam, the secondary beam cushion cap and pre-embedded bolt are symmetrical arranged, the utility model relates to fabricated construction technical fields.The novel fabricated primary and secondary beam connecting node and attaching method thereof, effectively increase the production efficiency of assembled industry, avoid the cast-in-place of the binding of reinforcing bar when primary-secondary beam in fabricated construction at this stage connects and concrete, improve assembly rate, fabricated structure level is improved, advancing for architectural industrialization has been pushed.

Description

A kind of novel fabricated primary and secondary beam connecting node
Technical field
The utility model relates to fabricated construction technical field, specially a kind of novel fabricated primary and secondary beam connecting node.
Background technique
Beam is the component often occurred in building structure.In frame structure, beam is integral the column connection of all directions; In wall construction, two wall limbs are connected, are allowed to work together by coupling beam above hole.As the important of Aseismic Design Component plays a part of the first line of defence.In frame shear wall structure, effect in Liang Jiyou frame structure, while also having Effect in shear wall structure, the connector for prefabricated overlapping primary-secondary beam connection is a kind of hidden bracket in the prior art, this is dark Bracket is connected and composed by two pieces of parallel rectangular steel plates, rectangular steel plates both ends bottom weld cushion block, the outside of rectangular steel plates also It is welded with the reinforcing bar extended downwardly, Bar Anchorage is in prefabricated overlapping secondary beam.Connection of the hidden bracket as prefabricated overlapping primary-secondary beam Part, low with the bond strength of beam, anti-pulling ability is poor;And reinforcing bar is fixed on the outside of steel plate using welding manner, is existed certain Hidden danger of quality, and production efficiency is low, and assembly rate is low, assembling structure level error.
Summary of the invention
(1) the technical issues of solving
In view of the deficiencies of the prior art, the utility model provides a kind of novel fabricated primary and secondary beam connecting node and its company Method is connect, reinforcing bar is solved and is fixed on the outside of steel plate using welding manner, there are certain hidden danger of quality, and production efficiency The problem of low, assembly rate is low, assembling structure level error.
(2) technical solution
In order to achieve the above object, the utility model is achieved by the following technical programs: a kind of novel fabricated primary and secondary Beam connecting node, including girder and secondary beam, the girder two sides offer secondary beam cushion cap, and the girder is located in secondary beam cushion cap Portion is provided with pre-embedded bolt, offers prepared screw-bolt hole inside the secondary beam, the position of the prepared screw-bolt hole with pre-buried spiral shell Bolt matches, and fastening nut is provided on rear side of the prepared screw-bolt hole, offers permanent opening at the top of the secondary beam.
A kind of novel fabricated primary and secondary beam connecting node, it is characterised in that: the secondary beam cushion cap height and width It is identical as secondary beam.
Preferably, the secondary beam cushion cap and pre-embedded bolt are symmetrical arranged.
Preferably, the secondary beam is symmetrical arranged, and the quantity of the secondary beam internal reservation bolt hole matches with pre-embedded bolt.
Preferably, locating piece is arranged in the pre-embedded bolt outer wall.
A kind of connection method of novel fabricated primary and secondary beam connecting node, comprising the following steps:
Step 1: the pre-embedded bolt that will be opened up on the prepared screw-bolt hole alignment girder on secondary beam, by the reserved bolt of secondary beam Hole is promoted along pre-embedded bolt toward girder;
Step 2: bolt is tightened to be formed in the opening by secondary beam top after the secondary beam cushion cap of secondary beam push-in girder Connector;
Step 3: remaining gap is filled out with high-intensitive slurry finally, being blocked the opening on secondary beam top with cement mortar It mends.
Preferably, the pre-embedded bolt and prepared screw-bolt hole carry out reserved setting according to actual needs.
Preferably, the high-intensitive slurry in the step 3 uses high viscosity waterproof material.
Preferably, the fastening nut of connector is formed in the step 2 and pre-embedded bolt is all made of high-hardness corrosion-resistant material Material.
Preferably, the permanent opening is set as trapezoidal, and is greater than bottom at the top of permanent opening.
(3) beneficial effect
The utility model provides a kind of novel fabricated primary and secondary beam connecting node and attaching method thereof.Have following beneficial Effect:
The novel fabricated primary and secondary beam connecting node and attaching method thereof, will be on the prepared screw-bolt hole alignment girder on secondary beam The pre-embedded bolt opened up promotes the prepared screw-bolt hole of secondary beam along pre-embedded bolt, when the secondary beam of secondary beam push-in girder toward girder After cushion cap, by tightening bolt to form connector in the permanent opening on secondary beam top, finally, with cement mortar by secondary beam top Opening block, remaining gap is filled up with high-intensitive slurry, and the production that this kind of technology effectively increases assembled industry is imitated Rate avoids the cast-in-place of the binding of reinforcing bar when primary-secondary beam in fabricated construction at this stage connects and concrete, improves assembly Rate improves fabricated structure level, has pushed advancing for architectural industrialization.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model entirety;
Fig. 2 is the structural schematic diagram of the utility model integral head plane.
In figure: 1 girder, 2 secondary beam cushion caps, 3 pre-embedded bolts, 4 secondary beams, 5 permanent openings, 6 prepared screw-bolt holes.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
The utility model provides a kind of technical solution referring to FIG. 1-2: a kind of novel fabricated primary and secondary beam connecting node, Including girder 1 and secondary beam 4,1 two sides of girder offer secondary beam cushion cap 2, girder 1 be located in the middle part of secondary beam cushion cap 2 be provided with it is pre-buried Bolt 3 offers prepared screw-bolt hole 6 inside secondary beam 4, and the position of prepared screw-bolt hole 6 matches with pre-embedded bolt 3, reserves spiral shell It is provided with fastening nut on rear side of keyhole 6, permanent opening 5 is offered at the top of secondary beam 4.
2 height of secondary beam cushion cap and width are identical as secondary beam 4.
Secondary beam cushion cap 2 and pre-embedded bolt 3 are symmetrical arranged.
Secondary beam 4 is symmetrical arranged, and the quantity of 4 internal reservation bolt hole 6 of secondary beam matches with pre-embedded bolt 3.
Locating piece is arranged in 3 outer wall of pre-embedded bolt.
A kind of connection method of novel fabricated primary and secondary beam connecting node, comprising the following steps:
Step 1: the pre-embedded bolt that will be opened up on the prepared screw-bolt hole alignment girder on secondary beam, by the reserved bolt of secondary beam Hole is promoted along pre-embedded bolt toward girder;
Step 2: bolt is tightened to be formed in the opening by secondary beam top after the secondary beam cushion cap of secondary beam push-in girder Connector;
Step 3: remaining gap is filled out with high-intensitive slurry finally, being blocked the opening on secondary beam top with cement mortar It mends.
Pre-embedded bolt 3 and prepared screw-bolt hole 6 carry out reserved setting according to actual needs.
High-intensitive slurry in step 3 uses high viscosity waterproof material.
The fastening nut of connector is formed in step 2 and pre-embedded bolt 3 is all made of high-hardness corrosion-resistant material.
Permanent opening 5 is set as trapezoidal, and is greater than bottom at the top of permanent opening 5.
In use, the prepared screw-bolt hole 6 on secondary beam 4 to be directed to the pre-embedded bolt 3 opened up on girder 1, by the reserved of secondary beam 4 Bolt hole 6 is promoted along pre-embedded bolt 3 toward girder 1, after secondary beam 4 is pushed into the secondary beam cushion cap 2 of girder 1, passes through 2 top of secondary beam Permanent opening 5 in bolt is tightened to form connector, finally, the opening on 4 top of secondary beam is blocked with cement mortar, remaining seam Gap is filled up with high-intensitive slurry, this kind of technology effectively increases the production efficiency of assembled industry, avoids and fills at this stage With formula construction in primary-secondary beam connection when reinforcing bar binding and concrete it is cast-in-place, improve assembly rate, improve fabricated Structure level has pushed advancing for architectural industrialization.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.In the absence of more restrictions.By sentence " element limited including one ..., it is not excluded that There is also other identical elements in the process, method, article or apparatus that includes the element ".
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (7)

1. a kind of novel fabricated primary and secondary beam connecting node, including girder (1) and secondary beam (4), it is characterised in that: the girder (1) two sides offer secondary beam cushion cap (2), and the girder (1), which is located in the middle part of secondary beam cushion cap (2), is provided with pre-embedded bolt (3), institute State and offer prepared screw-bolt hole (6) inside secondary beam (4), the position of the prepared screw-bolt hole (6) with pre-embedded bolt (3) phase Match, fastening nut is provided on rear side of the prepared screw-bolt hole (6), offers permanent opening (5) at the top of the secondary beam (4).
2. a kind of novel fabricated primary and secondary beam connecting node according to claim 1, it is characterised in that: the secondary beam cushion cap (2) highly identical as secondary beam (4) with width.
3. a kind of novel fabricated primary and secondary beam connecting node according to claim 1, it is characterised in that: the secondary beam cushion cap (2) it is symmetrical arranged with pre-embedded bolt (3).
4. a kind of novel fabricated primary and secondary beam connecting node according to claim 1, it is characterised in that: the secondary beam (4) It is symmetrical arranged, quantity and the pre-embedded bolt (3) of secondary beam (4) the internal reservation bolt hole (6) match.
5. a kind of novel fabricated primary and secondary beam connecting node according to claim 1, it is characterised in that: the pre-embedded bolt (3) locating piece is arranged in outer wall.
6. a kind of novel fabricated primary and secondary beam connecting node according to claim 1, it is characterised in that: the pre-embedded bolt (3) and prepared screw-bolt hole (6) carries out reserved setting according to actual needs.
7. a kind of novel fabricated primary and secondary beam connecting node according to claim 1, it is characterised in that: the permanent opening (5) it is set as trapezoidal, and is greater than bottom at the top of permanent opening (5).
CN201821532017.1U 2018-09-19 2018-09-19 A kind of novel fabricated primary and secondary beam connecting node Expired - Fee Related CN209011314U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821532017.1U CN209011314U (en) 2018-09-19 2018-09-19 A kind of novel fabricated primary and secondary beam connecting node

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821532017.1U CN209011314U (en) 2018-09-19 2018-09-19 A kind of novel fabricated primary and secondary beam connecting node

Publications (1)

Publication Number Publication Date
CN209011314U true CN209011314U (en) 2019-06-21

Family

ID=66833612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821532017.1U Expired - Fee Related CN209011314U (en) 2018-09-19 2018-09-19 A kind of novel fabricated primary and secondary beam connecting node

Country Status (1)

Country Link
CN (1) CN209011314U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108978888A (en) * 2018-09-19 2018-12-11 安徽建筑大学 A kind of novel fabricated primary and secondary beam connecting node and attaching method thereof
CN110331817A (en) * 2019-07-11 2019-10-15 江西建工第二建筑有限责任公司 A kind of assembled combination beam time beam construction
CN113818630A (en) * 2021-09-14 2021-12-21 中国建筑西南设计研究院有限公司 Wood structure roof cantilever secondary beam structure combining mortise and tenon joints and self-tapping screws

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108978888A (en) * 2018-09-19 2018-12-11 安徽建筑大学 A kind of novel fabricated primary and secondary beam connecting node and attaching method thereof
CN110331817A (en) * 2019-07-11 2019-10-15 江西建工第二建筑有限责任公司 A kind of assembled combination beam time beam construction
CN113818630A (en) * 2021-09-14 2021-12-21 中国建筑西南设计研究院有限公司 Wood structure roof cantilever secondary beam structure combining mortise and tenon joints and self-tapping screws

Similar Documents

Publication Publication Date Title
CN108978888A (en) A kind of novel fabricated primary and secondary beam connecting node and attaching method thereof
CN209011314U (en) A kind of novel fabricated primary and secondary beam connecting node
CN105297887B (en) The D light Steel Structure that two-way continuous twin beams is constituted
CN102995756B (en) Concrete-filled rectangular steel tube column-box girder full-bolt connection node and construction method
CN205369542U (en) Concrete beam longitudinal reinforcement and steel column connection structure
CN207211444U (en) A kind of mounting clip pieces coordinated with groove and tognue type Light trabses
CN207469451U (en) Connection node of assembled steel frame beam column
CN208293763U (en) Outer ring plate type beam column connecting device
CN2496949Y (en) Shape steel and steel reinforced concrete sheear wall integrated load-bearing shear wall structure
CN107130734B (en) Corrugated plate dst Horizontal H-shaped structure beam and its construction method
CN207003641U (en) A kind of low layer assembling frame structural system
CN104863267A (en) Novel beam column reinforced node with variable-thickness beam end flange
CN106121055B (en) A kind of steel box column and beams of concrete connecting node and its construction method
CN211621953U (en) Prefabricated beam column connected node structure
KR200469319Y1 (en) Construction structure for joining steel or reinforced steel concrete column and beam with reinforcing end part
CN208918001U (en) The beam-column connection of mounting square tube column
CN217998414U (en) Connecting device for quickly assembling horizontal seams of multi-cavity steel pipes
CN108867872A (en) One kind is for rigidly connected node structure of beam column of steel structure and preparation method thereof, Housing Structure System
CN214461405U (en) Connecting joint of prefabricated H-shaped steel column and steel frame light external wall panel
CN210086794U (en) Assembly type structure and steel wire rope unloading structure suitable for assembly type structure
CN205134981U (en) Core pattern tradition local -style dwelling houses wall body reinforced structure is filled out to immature soil
CN209457418U (en) A kind of quick positioning connection structure of assembled architecture light plate shear wall
CN209975752U (en) Integrated prefabricated wallboard house structure
CN110016966A (en) A kind of prefabricated overlapping coupled column T-type assembling type node of pre-erection combination beam-
CN207568074U (en) A kind of secondary structure member reinforcing steel bar connecting node

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190621

Termination date: 20210919