CN208965800U - Prefabricated concrete board mounts node - Google Patents
Prefabricated concrete board mounts node Download PDFInfo
- Publication number
- CN208965800U CN208965800U CN201821540263.1U CN201821540263U CN208965800U CN 208965800 U CN208965800 U CN 208965800U CN 201821540263 U CN201821540263 U CN 201821540263U CN 208965800 U CN208965800 U CN 208965800U
- Authority
- CN
- China
- Prior art keywords
- prefabricated concrete
- node
- concrete board
- weights
- hoist
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The utility model discloses a kind of prefabricated concrete board mounting node.Prefabricated concrete board mounting node provided by the utility model includes: prefabricated concrete board, is provided with pre-buried external member;The weights-hoist is fixedly attached to the pre-buried external member by hanger system, including weights-hoist, hanging seat and connector, the connector, and the weights-hoist is hung on the hanging seat.Therefore easy for installation.
Description
Technical field
The utility model relates to assembled architecture fields, mount node more particularly to a kind of prefabricated concrete board.
Background technique
Currently, wideling popularize with assembled architecture policy, precast facade using more and more common.
The structural system of exterior wall also compares more, structure made of installing for example including multiple prefabricated concrete boards.Currently on the market
The big hanging plate of such concrete slab mounts node, one is most common GRC (Glass fiber Reinforced Concrete,
Glass concrete) mounting node, GRC connecting node is relatively simple, be by way of Bar Anchorage by hanging plate with
Steel joist is born to be connected.
But the above-mentioned generally existing plate installation of mounting node is inconvenient, adjusts the small defect in space.
Utility model content
One purpose of the utility model is, provides a kind of prefabricated concrete board mounting node, facilitates installation.
In order to solve the above technical problems, the utility model provides a kind of prefabricated concrete board mounting node, comprising:
Prefabricated concrete board is provided with pre-buried external member;
The weights-hoist is fixedly attached to described pre-buried by hanger system, including weights-hoist, hanging seat and connector, the connector
External member, the weights-hoist are hung on the hanging seat.
Optionally, node is mounted for the prefabricated concrete board, the connector includes bolt, and the pre-buried external member has
Screw thread, the bolt and the screw thread of the pre-buried external member screw up.
Optionally, node is mounted for the prefabricated concrete board, is additionally provided with position adjusting mechanism on the weights-hoist, to adjust
The relative position of the whole hanging seat and the weights-hoist.
Optionally, node is mounted for the prefabricated concrete board, the adjusting of the weights-hoist is provided through on the weights-hoist
Bolt, the adjusting bolt are removable towards the hanging seat.
Optionally, node is mounted for the prefabricated concrete board, the hanger system includes keel, in the phase of the keel
Multiple hanging seats are symmetrically arranged with to two sides.
Optionally, node is mounted for the prefabricated concrete board, the keel include first adapter, and the second adapter is logical
The fixation corresponding with the first adapter of the first fixing piece is crossed, second adapter is solid by the second fixing piece and the hanging seat
It is fixed.
Optionally, node is mounted for the prefabricated concrete board, the first adapter and second adapter include
Angle steel.
Optionally, node is mounted for the prefabricated concrete board, first fixing piece and second fixing piece all wrap
Include screw bolt and nut.
Optionally, node mounted for the prefabricated concrete board, the weights-hoist has First terrace, the first side wall and the
One baffle, the hanging seat have second step face, second sidewall and second baffle, and the first baffle is located at the second step
Face is connected with the second sidewall and in the second angle for limiting, and the second baffle is located at the First terrace and described
The first side wall is connected and in the first angle for limiting, the opening direction phase at the angle of first angle and second angle
It is different.
Optionally, node mounted for the prefabricated concrete board, the weights-hoist further includes the first cross connecting plate, first vertical
To connecting plate and the first positioning plate, the side of the side of the first baffle and the first longitudinal direction connecting plate is respectively arranged at institute
The opposite sides of the first cross connecting plate is stated, to limit the first interval, institute between first baffle and first longitudinal direction connecting plate
The side of the other side and first positioning plate of stating first longitudinal direction connecting plate is separately connected the both sides of first angle;
The hanging seat further includes the second cross connecting plate, second longitudinal direction connecting plate and the second positioning plate, the second baffle
Side and the side of the second longitudinal direction connecting plate be respectively arranged at the opposite sides of second cross connecting plate,
The second interval, the other side of the second longitudinal direction connecting plate and described second are limited between two baffles and second longitudinal direction connecting plate
The side of positioning plate is separately connected the both sides of second angle;
At least described second positioning plate is just located in first interval, and at least described first positioning plate is just located at described the
In two intervals.
Prefabricated concrete board provided by the utility model mounts node, comprising: prefabricated concrete board is provided with pre-buried external member;Pendant system
The weights-hoist is fixedly attached to the pre-buried external member, the weights-hoist by system, including weights-hoist, hanging seat and connector, the connector
It is hung on the hanging seat.Compared with prior art, the prefabricated concrete board mounting node of the utility model has the advantage that
1, prefabricated concrete board is provided with pre-buried external member, avoids the plate size of artificial cutting, the punching and size of lithotome
Limitation be more uniformly stressed, structure is safer so that it is higher to install ultimate bearing capacity of joints;
2, the node can be universally used in big prefabricated concrete board and small prefabricated concrete board, can all install in factory, particularly with small pre-
The arrangement of hanging plate processed, the node can preferably realize the accuracy that plate is arranged in factory, to live integral hoisting, guarantee item
Mesh meets requirement of the present policy to building assembly rate.
Detailed description of the invention
Fig. 1 is the structural schematic diagram that prefabricated concrete board mounts node in an embodiment of the present invention;
Fig. 2 is the structural schematic diagram that prefabricated concrete board mounts node in an embodiment of the present invention;
Fig. 3 is the partial enlarged view of weights-hoist and hanging seat in an embodiment of the present invention.
Specific embodiment
It is described in more detail below in conjunction with prefabricated concrete board mounting node of the schematic diagram to the utility model, wherein table
Shown the preferred embodiment of the utility model, it should be appreciated that those skilled in the art can modify described herein it is practical new
Type, and still realize the advantageous effects of the utility model.Therefore, following description should be understood as those skilled in the art
It is widely known, and be not intended as limitations of the present invention.
The utility model is more specifically described by way of example referring to attached drawing in the following passage.According to following explanation and power
The advantages of sharp claim, the utility model and feature will become apparent from.It should be noted that attached drawing be all made of very simplified form and
Non-accurate ratio is used, only to convenient, lucidly aid illustration the utility model embodiment purpose.
As described above, existing prefabricated concrete board mounting node installation is constant, to improve this situation, the utility model proposes
A kind of prefabricated concrete board mounts node.
As depicted in figs. 1 and 2, the prefabricated concrete board of the utility model embodiment mounts node, comprising:
Prefabricated concrete board 10 is provided with pre-buried external member 11;
The weights-hoist 21 is fixedly connected by hanger system, including weights-hoist 21, hanging seat 23 and connector 22, the connector 22
To the pre-buried external member 11, the weights-hoist 21 is hung on the hanging seat 23.
In one embodiment, the prefabricated concrete board 10 is mainly concrete material, such as in factory's casting concrete plate
The pre-buried external member 11 of customization is accurately positioned in Transducers Embedded in Concrete when block, after to be solidified, can be realized pre-buried external member 11 with it is prefabricated
The good combination of hanging plate 10.
The pre-buried external member 11 for example can be embedded sleeve barrel.For example, having screw thread inside the pre-buried external member 11.
Further, the pre-buried external member 11 is stainless steel material, is not easy to get rusty, and avoids generating concrete decorative cover dirty
Dye.
Correspondingly, the connector 22 includes bolt, the bolt and the screw thread of the pre-buried external member 11 are screwed up.
In one embodiment, as shown in Fig. 2, position adjusting mechanism 28 is additionally provided on the weights-hoist 21, to adjust
State the relative position of hanging seat 23 and the weights-hoist 21.
Wherein Fig. 2 schematically shows position adjusting mechanism 28 on the weights-hoist 21 of lower section, and on the weights-hoist 21 of top
Position adjusting mechanism 28 is not showed that, but this is not intended to limit the scope of the present invention, according to actual demand, each weights-hoist 21
On can be provided with position adjusting mechanism 28, be also possible to that position adjusting mechanism can be set on a certain (a little) weights-hoists 21
28。
For example, being provided through the adjusting bolt of the weights-hoist 21 on the weights-hoist 21, the adjusting bolt is described in
Hanging seat 23 is removable.As a result, by turning adjusting bolt, it will be able to the relative position between weights-hoist 21 and hanging seat 23 is adjusted,
The position of prefabricated concrete board 10 can be changed.
It is understood that the position adjusting mechanism also can be set on hanging seat 23, or weights-hoist is set simultaneously
21 and hanging seat 23 on.Weights-hoist 21 and hanging seat 23 can be hereinafter described in detail, be more conducive to understand the position of the utility model
Set the design and principle of regulating mechanism.
The hanger system includes keel 20, is symmetrically arranged with multiple hanging seats in the opposite sides of the keel 20
23。
Specifically, the keel 20 include first adapter 27, the second adapter 24 by the first fixing piece 26 with it is described
First adapter 27 is corresponding to fix, and second adapter 24 is fixed by the second fixing piece 25 and the hanging seat 23.
In one embodiment, for example, the first adapter 27 and second adapter 24 include angle steel.
The first adapter 27 can be to be arranged across the keel 20, be also possible to 20 one of the keel at
Type can also be and be welded on the keel 20.
In one embodiment, for example, first fixing piece 26 and second fixing piece 25 all include bolt and spiral shell
It is female.
It further, further include gasket, the bolt of first fixing piece 26 passes through the gasket, and described first is solid later
The nut and the bolt for determining part 26 screw up, the gasket play protection, it is anti-skidding the effects of.
As shown 4 prefabricated concrete boards 10 in Fig. 1 and Fig. 2, each can be it is prefabricated after be fixed on hanger system.
Polyethylene stick 30 and sealant 31 can be set between contiguous prefabricated hanging plate 10, sealing function can be played.
Fig. 3 is turned next to, the weights-hoist has First terrace 213, the first side wall 212 and first baffle 211, described
Hanging seat has second step face 233, second sidewall 232 and second baffle 231, and the first baffle 211 is located at described second
Terrace 233 is connected with the second sidewall 232 and in the second angle 234 for limiting, and the second baffle 231 is located at described the
One step surface 213 is connected with the first side wall 212 and in the first angle 214 for limiting, first angle 214 and described
The opening direction at the angle of the second angle 234 is different.
In one embodiment, the First terrace 213 and the first side wall 212 are vertically arranged, i.e., and described first
Angle 214 is right angle;The second step face 233 and the second sidewall 232 are vertically arranged, i.e., described second angle 234 is
Right angle.
Also, after weights-hoist is hung on hanging seat, the plane where the First terrace 213 is parallel to the second step
Plane where face 233, the plane where the first side wall 212 is parallel to the plane where the second sidewall 232, described
Plane where first baffle 211 is parallel to the plane where the second baffle 231.
In addition, the weights-hoist further includes the first cross connecting plate 217, first longitudinal direction connecting plate 216 and the first positioning plate
215, the side of the side of the first baffle 211 and the first longitudinal direction connecting plate 216 is respectively arranged at described first laterally
The opposite sides of connecting plate 217, it is described to limit the first interval between first baffle 211 and first longitudinal direction connecting plate 216
The other side of first longitudinal direction connecting plate 216 and the side of first positioning plate 215 are separately connected the two of first angle 214
(other side of the i.e. described first longitudinal direction connecting plate 216 connects the side of the First terrace 213, the First terrace on side
213 other side connects the side of the first side wall 212, the other side connection of the first side wall 212 first positioning
The side of plate 215);
The hanging seat further includes the second cross connecting plate 237, second longitudinal direction connecting plate 236 and the second positioning plate 235, described
The side of second baffle 231 and the side of the second longitudinal direction connecting plate 236 are respectively arranged at second cross connecting plate 237
Opposite sides, to limit the second interval, the second longitudinal direction between second baffle 231 and second longitudinal direction connecting plate 236
The other side of connecting plate 236 and the side of second positioning plate 235 are separately connected both sides (the i.e. institute of second angle 234
The other side for stating second longitudinal direction connecting plate 236 connects the side in the second step face 233, the second step face 233 it is another
Side connects the side of the second sidewall 232, and the other side of the second sidewall 232 connects second positioning plate 235
Side);
At least described second positioning plate 235 is just located in first interval, and at least described first positioning plate 215 is just located at
In second interval.As seen from Figure 3, the first side wall 212 and second sidewall 232 can also be located at second interval
In first interval.
The equivalent width or almost the same for being just located at the width and positioning plate for referring to being spaced, it is almost the same
Situation include according to actual needs and set such as permissible error or compensation space.
In this way, can guarantee preferable stability after weights-hoist and hanging seat are hung up, prevent from sliding, shaking etc..
In the present invention, involved in the prefabricated concrete board 10 in addition to concrete material, other structures can be using gold
Belong to structure, such as steel construction, such as alloy structure (aluminium alloy etc.), to have preferably endurance and stability.
In conclusion compared with prior art, the prefabricated concrete board mounting node of the utility model has the advantage that
1, prefabricated concrete board is provided with pre-buried external member, avoids the plate size of artificial cutting, the punching and size of lithotome
Limitation be more uniformly stressed, structure is safer so that it is higher to install ultimate bearing capacity of joints;
2, the node can be universally used in big prefabricated concrete board and small prefabricated concrete board, can all install in factory, particularly with small pre-
The arrangement of hanging plate processed, the node can preferably realize the accuracy that plate is arranged in factory, to live integral hoisting, guarantee item
Mesh meets requirement of the present policy to building assembly rate;
3, the pre-buried external member is stainless steel material, is not easy to get rusty, and avoids generating pollution to concrete decorative cover.
Obviously, it is practical without departing from this can to carry out various modification and variations to the utility model by those skilled in the art
Novel spirit and scope.If in this way, these modifications and variations of the present invention belong to the utility model claims and
Within the scope of its equivalent technologies, then the utility model is also intended to include these modifications and variations.
Claims (10)
1. a kind of prefabricated concrete board mounts node characterized by comprising
Prefabricated concrete board (10) is provided with pre-buried external member (11);
The weights-hoist is fixedly attached to by hanger system, including weights-hoist (21), hanging seat (23) and connector (22), the connector
The pre-buried external member, the weights-hoist are hung on the hanging seat.
2. prefabricated concrete board as described in claim 1 mounts node, which is characterized in that the connector (22) includes bolt, institute
Pre-buried external member is stated with screw thread, the bolt and the screw thread of the pre-buried external member screw up.
3. prefabricated concrete board as described in claim 1 mounts node, which is characterized in that be additionally provided with position adjusting on the weights-hoist
Mechanism, to adjust the relative position of the hanging seat and the weights-hoist.
4. prefabricated concrete board as claimed in claim 3 mounts node, which is characterized in that be provided through the extension on the weights-hoist
The adjusting bolt (28) of code, the adjusting bolt are removable towards the hanging seat.
5. prefabricated concrete board as described in claim 1 mounts node, which is characterized in that the hanger system includes keel (20),
Multiple hanging seats are symmetrically arranged in the opposite sides of the keel.
6. prefabricated concrete board as claimed in claim 5 mounts node, which is characterized in that the keel include first adapter
(27), the second adapter (24) is fixed by the way that the first fixing piece (26) are corresponding with the first adapter, second adapter
It is fixed by the second fixing piece (25) with the hanging seat.
7. prefabricated concrete board as claimed in claim 6 mounts node, which is characterized in that the first adapter and second turn described
Fitting includes angle steel.
8. prefabricated concrete board as claimed in claim 6 mounts node, which is characterized in that first fixing piece and described second is consolidated
Determining part all includes screw bolt and nut.
9. prefabricated concrete board as described in claim 1 mounts node, which is characterized in that the weights-hoist has First terrace
(213), the first side wall (212) and first baffle (211), the hanging seat have second step face (233), second sidewall (232)
With second baffle (231), the first baffle be located at the second step face be connected with the second sidewall and limit
In two angles (234), the second baffle be located at the First terrace be connected with the first side wall and limit first
In angle (214), the opening direction at the angle of first angle and second angle is different.
10. prefabricated concrete board as claimed in claim 9 mounts node, which is characterized in that the weights-hoist further includes that the first transverse direction connects
Fishplate bar (217), first longitudinal direction connecting plate (216) and the first positioning plate (215), the side of the first baffle (211) and described
The side of first longitudinal direction connecting plate (217) is respectively arranged at the opposite sides of first cross connecting plate, in first baffle
The first interval, the other side of the first longitudinal direction connecting plate and first positioning plate are limited between first longitudinal direction connecting plate
Side be separately connected the both sides of first angle (214);
The hanging seat further includes the second cross connecting plate (237), second longitudinal direction connecting plate (236) and the second positioning plate (235), institute
The side of the side and the second longitudinal direction connecting plate (237) of stating second baffle (231) is respectively arranged at described second and laterally connects
The opposite sides of fishplate bar, to limit the second interval between second baffle and second longitudinal direction connecting plate, the second longitudinal direction connects
The other side of fishplate bar and the side of second positioning plate are separately connected the both sides of second angle;
At least described second positioning plate (235) is just located in first interval, and at least described first positioning plate (215) is just located at
In second interval.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821540263.1U CN208965800U (en) | 2018-09-20 | 2018-09-20 | Prefabricated concrete board mounts node |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821540263.1U CN208965800U (en) | 2018-09-20 | 2018-09-20 | Prefabricated concrete board mounts node |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208965800U true CN208965800U (en) | 2019-06-11 |
Family
ID=66758062
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821540263.1U Active CN208965800U (en) | 2018-09-20 | 2018-09-20 | Prefabricated concrete board mounts node |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208965800U (en) |
-
2018
- 2018-09-20 CN CN201821540263.1U patent/CN208965800U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206942035U (en) | A kind of metope integration installation structure | |
CN211172571U (en) | Three-dimensional adjusting device of unitized curtain wall | |
CN2654759Y (en) | Regulatable plane installing construction unit | |
WO2020143222A1 (en) | Fabricated suspended ceiling structure and installation method therefor | |
CN205444780U (en) | General system of hanging futilely of wall of interchangeable surface course material | |
CN207878727U (en) | The attachment device and curtain wall system of curtain wall and building structure | |
CN106760092B (en) | Seamless hanging system for ceramic thin plate-glass composite plate | |
CN112064856A (en) | Suspended ceiling pre-hanging piece and floor structure of building with same | |
CN208965800U (en) | Prefabricated concrete board mounts node | |
CN210737376U (en) | Bent cap template with adjustable side direction angle | |
CN217871456U (en) | Cornice structure for building | |
CN205444782U (en) | Install pendant structure of wall ceramic tile fast | |
CN212001797U (en) | Prefabricated external wall panel connecting assembly and connecting structure of prefabricated external wall panel | |
CN209129235U (en) | Ceiling structure and hanger system for ceiling structure | |
CN209568582U (en) | A kind of dry-hang pottery rod curtain wall system | |
CN208749088U (en) | A kind of floor support plate oblique pull support construction | |
JPH0336441B2 (en) | ||
CN209025258U (en) | Assembly concrete Decorative hanging board exchanging structure | |
CN213418056U (en) | Shear force wall stores pylon | |
CN207812926U (en) | A kind of decoration of exterior wall board mounting assembly | |
CN206512895U (en) | A kind of ceramic thin plate glass composite board is seamless to mount system | |
CN209227858U (en) | A kind of Novel stone hanging device | |
CN212641905U (en) | U-shaped double-buckle edging middle hole nut external adjustment keel connecting pendant | |
CN216865672U (en) | Suspended ceiling assembling structure | |
CN218779666U (en) | Suspended ceiling top hanging connection structure suitable for light steel structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |