CN208902817U - The test platform of current transformer - Google Patents

The test platform of current transformer Download PDF

Info

Publication number
CN208902817U
CN208902817U CN201821697794.1U CN201821697794U CN208902817U CN 208902817 U CN208902817 U CN 208902817U CN 201821697794 U CN201821697794 U CN 201821697794U CN 208902817 U CN208902817 U CN 208902817U
Authority
CN
China
Prior art keywords
current transformer
inverter controller
real
reactor
switch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821697794.1U
Other languages
Chinese (zh)
Inventor
刘闯
阮景锋
段了然
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Goldwind Science and Creation Windpower Equipment Co Ltd
Original Assignee
Beijing Goldwind Science and Creation Windpower Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Goldwind Science and Creation Windpower Equipment Co Ltd filed Critical Beijing Goldwind Science and Creation Windpower Equipment Co Ltd
Priority to CN201821697794.1U priority Critical patent/CN208902817U/en
Application granted granted Critical
Publication of CN208902817U publication Critical patent/CN208902817U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Inverter Devices (AREA)

Abstract

The embodiment of the present application provides a kind of test platform of current transformer, for testing inverter controller, comprising: current transformer monitors debugging system and real-time digital simulator;Current transformer circulation test model has been built in real-time digital simulator in advance;Current transformer monitors debugging system and inverter controller communication connection;Inverter controller and real-time digital simulator communication connection, real-time digital simulator is used to the switch state signal of current transformer circulation test model and analog signals being sent to inverter controller, and receives inverter controller and send control instruction to current transformer circulation test model.The embodiment of the present application is by testing inverter controller; and then it realizes to the basic function of current transformer, control algolithm, the complete detection of failsafe characteristics; more convenient and fast means of testing is provided for the research and development of novel current transformer, and then improves the efficiency of research and development of current transformer.

Description

The test platform of current transformer
Technical field
This application involves converter topology fields, specifically, this application involves a kind of test platforms of current transformer.
Background technique
To meet the requirement that current transformer scene is put into operation, topological structure and field application operating condition according to current transformer are needed, is taken Test platform is built to detect the various performance indicators of current transformer.At present circulation test platform be current transformer mainstream test platform it One, its main feature is that replacing wind power generating set by transformer, carries corresponding current transformer and tested.
The inventors of the present application found that existing in flexibility and owing currently, the preliminary preparation of circulation test platform is cumbersome It lacks, the Curve guide impeller to inverter controller under different scenes and parameter tuning can not test in real time.
Utility model content
The application is directed to the shortcomings that existing way, proposes a kind of test platform of current transformer, surveys to solve the prior art Trying platform, that there are flexibilities is poor, and the technical issues of can not be tested for inverter controller under different scenes.
First aspect, the embodiment of the present application provide a kind of test platform of current transformer, for inverter controller It is tested, comprising: current transformer monitors debugging system and real-time digital simulator;It has been built in advance in real-time digital simulator Current transformer circulation test model;
Current transformer monitors debugging system and inverter controller communication connection;
Inverter controller and real-time digital simulator communication connection, real-time digital simulator is for surveying current transformer circulation The switch state signal and analog signals of die trial type are sent to inverter controller, and receive inverter controller to unsteady flow The control instruction that device circulation test model is sent.
In the embodiment of the application, current transformer monitor between debugging system and inverter controller through Ethernet and Interchanger communication connection.
Inverter controller is provided with digital output interface, digital input interface and simulation input interface;
Real-time digital simulator is provided with digital output card, digital input card and analog output card;
Digital output interface, digital input interface and simulation input interface respectively correspond and digital input card, number Measure output board card and analog output card communication connection.
In the embodiment of the application, digital output interface, digital input interface and simulation input interface, respectively with number It is connected between word amount input card, digital output card and analog output card using conducting wire.
In the embodiment of the application, current transformer circulation test model includes power grid, breaker, the first transformer, becomes Flow device major loop, the first reactor, the second transformer;
Power grid, breaker, the first transformer, current transformer major loop, the first reactor and the second transformer are successively electrically connected It connects, and the other end of the second transformer is connected between the first transformer and current transformer major loop.
In the embodiment of the application, current transformer major loop includes first switch, second switch, third switch, capacitor Device, the second reactor, converter module, third reactor and the 5th switch;
First switch, the second reactor, converter module, third reactor and the 5th switch are sequentially connected in series;
Second switch is connected in parallel with first switch;
One end of capacitor is connected to the node between first switch and the second reactor, and the other end is connect with ground terminal.
In the embodiment of the application, converter module includes the grid-side converter being sequentially connected electrically, brake circuit, puts Electrical circuit and generator-side converter wear;
Grid-side converter is electrically connected with the second reactor, and generator-side converter wear is electrically connected with third reactor.
In the embodiment of the application, the quantity and the number of windings phase of current transformer of the first reactor and the second transformer Match.
Technical solution bring advantageous effects provided by the embodiments of the present application are:
The application by building current transformer circulation test model in advance in real-time digital simulator, then with current transformer control Device processed carries out data interaction, and cooperates current transformer monitoring debugging system that emulation is made to form organic whole with test, due to The test platform of the current transformer of the embodiment of the present application is for testing inverter controller, inverter controller and in real time number Word emulating instrument communication connection, real-time digital simulator are used for the switch state signal of current transformer circulation test model and simulation Amount signal is sent to inverter controller, and receives inverter controller and refer to the control that current transformer circulation test model is sent It enables, therefore by the test to inverter controller, the basic function, control algolithm, error protection to current transformer may be implemented Characteristic carries out complete detection, and then provides more convenient and fast means of testing for the research and development of novel current transformer, can shorten current transformer The test period of In-Plant Test, improve efficiency of research and development, and can test early detection current transformer there are the problem of, preferably finger Lead equipment research and development;And current transformer circulation test model can change application scenarios in real time in the embodiment of the present application, so that current transformer Test platform flexibly inverter controller under different scenes can be tested.
The additional aspect of the application and advantage will be set forth in part in the description, these will become from the following description It obtains obviously, or recognized by the practice of the application.
Detailed description of the invention
The application is above-mentioned and/or additional aspect and advantage will become from the following description of the accompanying drawings of embodiments Obviously and it is readily appreciated that, in which:
Fig. 1 is a kind of overall structure diagram of the test platform of current transformer provided by the embodiments of the present application;
Fig. 2 is a kind of block schematic illustration of current transformer circulation test model provided by the embodiments of the present application;
Fig. 3 is a kind of frame signal of current transformer circulation test model of clipped module provided by the embodiments of the present application Figure.
Specific embodiment
The application is described below in detail, the example of embodiments herein is shown in the accompanying drawings, wherein identical from beginning to end Or similar label indicates same or similar component or component with the same or similar functions.In addition, if known technology Detailed description the application shown is characterized in unnecessary, then omit it.Below with reference to attached drawing description Embodiment is exemplary, and is only used for explaining the application, and cannot be construed to the limitation to the application.
Those skilled in the art of the present technique are appreciated that unless otherwise defined, all terms used herein (including technology art Language and scientific term), there is meaning identical with the general understanding of those of ordinary skill in the application fields.Should also Understand, those terms such as defined in the general dictionary, it should be understood that have in the context of the prior art The consistent meaning of meaning, and unless idealization or meaning too formal otherwise will not be used by specific definitions as here To explain.
Those skilled in the art of the present technique are appreciated that unless expressly stated, singular " one " used herein, " one It is a ", " described " and "the" may also comprise plural form.It is to be further understood that being arranged used in the description of the present application Diction " comprising " refer to that there are the feature, integer, step, operation, element and/or component, but it is not excluded that in the presence of or addition Other one or more features, integer, step, operation, element, component and/or their group.It should be understood that when we claim member Part is " connected " or when " coupled " to another element, it can be directly connected or coupled to other elements, or there may also be Intermediary element.In addition, " connection " used herein or " coupling " may include being wirelessly connected or wirelessly coupling.It is used herein to arrange Diction "and/or" includes one or more associated wholes for listing item or any cell and all combinations.
How the technical solution of the application and the technical solution of the application are solved with specifically embodiment below above-mentioned Technical problem is described in detail.
The embodiment of the present application provides a kind of test platform of current transformer, for testing inverter controller 102, The structural schematic diagram of the test platform of the current transformer is as shown in Figure 1, comprising:
Current transformer monitors debugging system 101 and real-time digital simulator 103;It is taken in advance in real-time digital simulator 103 Have current transformer circulation test model;
Current transformer monitors debugging system 101 and 102 communication connection of inverter controller;
Inverter controller 102 and 103 communication connection of real-time digital simulator, real-time digital simulator 103 will be for that will become The switch state signal and analog signals for flowing device circulation test model are sent to inverter controller 102, and receive unsteady flow The control instruction that device controller 102 is sent to current transformer circulation test model.
For example, as shown in Figure 1, current transformer monitoring debugging system 101 can be installed in computer, and current transformer monitors It can be realized between the two by Ethernet and interchanger communication connection between debugging system 101 and inverter controller 102 Real time data interaction.Such as wired or wirelessly communication connection can be passed through between the two.But the embodiment of the present application Specific connection type between the two is not limited, those skilled in the art can voluntarily select connection side according to actual condition Formula.
Current transformer has been built in advance in real-time digital simulator (Real Time Digtal Simulator, RTDS) 103 Circulation test model;Inverter controller 102 and 103 communication connection of real-time digital simulator, real-time digital simulator 103 are used for The switch state signal of current transformer circulation test model and analog signals are sent to inverter controller 102, and received The control instruction that inverter controller 102 is sent to current transformer circulation test model.Inverter controller 102 can be using practical Current transformer control framework, and use physical controller, carry circulation test program.It should be noted that, the application is implemented herein Example does not limit the concrete type of real-time digital simulator, can use a plurality of types of real-time digital simulator types, in This is repeated no more.
The application by using building current transformer circulation test model, inverter controller in advance in real-time digital simulator Debugging system communication connection is monitored with real-time digital simulator and current transformer respectively.The excellent of Real-time Simulation Technology can be given full play to Gesture interconnects current transformer circulation test model and inverter controller, in current transformer R&D process by controlling current transformer And the test of control strategy provides more so that current-variable controller and strategy agree with current transformer hardware perfection for current transformer The testing process for sticking on nearly practical circulation system, is particularly suitable for before actual rings current test to the contained operation journey of inverter controller The research of the l-G simulation test of sequence and its hardware.
The application will emulate and form organic whole with test, and the base to current transformer may be implemented according to Its Relevant Technology Standards This function, control algolithm, failsafe characteristics carry out complete detection, provide more convenient and fast survey for the research and development of novel current transformer Trial work section can shorten the test period of current transformer In-Plant Test, improve efficiency of research and development, and can be in test early detection current transformer There are the problem of, preferably guidance equipment research and development.
In the embodiment of the application, inverter controller 102 be provided with digital output interface, digital input interface and Simulation input interface;Real-time digital simulator 103 is provided with digital output card, digital input card and analog output Board;Digital output interface, digital input interface and simulation input interface respectively correspond and digital input card, digital quantity Output board card and analog output card communication connection.
As shown in Figure 1, optionally, inverter controller is provided with digital output interface (Digital Output, DO), number Word input interface (Digital Input, DI) and simulation input interface (Analogy Input, AI);Real-time digital simulator 103 are provided with digital output card (Gigabit Transceiver Digital Output Card, GTDO), digital quantity Input card (Gigabit Transceiver Digital Input Card, GTDI) and analog output card (Gigabit Transceiver Analogy Output Card, GTAO);Digital output interface DO, digital input interface DI and simulation input Interface AI is communicated with digital input card GTDI, digital output card GTDO and analog output card GTAO connect respectively It connects.By above-mentioned connection type, real-time digital simulator 103 is by the switch state signal of current transformer circulation test model and simulation Signal is exported to inverter controller 102, while receiving the switch control signal and pulse width of the output of inverter controller 102 Modulated signal.
Optionally, real-time digital simulator 103 can include at least a cabinet bracket (RACK), several real-time digitals are imitated The true dedicated digital input card of instrument (Gigabit Transceiver Digital Input Card, GTDI), one piece of reality When Digital Simulation instrument dedicated digital output card (Gigabit Transceiver Digital Output Card, GTDO), several real-time digital simulator die for special purpose analog quantity output board card (Gigabit Transceiver Analogy Output Card, GTAO).
The converter switches control signal and pulse that GTDI in the embodiment of the present application is used to export inverter controller The signal of width modulated is sent to current transformer circulation test model;GTDO is used for the switch shape for feeding back current transformer circulation test model State signal is sent to inverter controller;GTAO is used to send the analog signals of current transformer circulation test model to current transformer and control Device.It should be noted that the application is not limited thereto, those skilled in the art can be according to the type of real-time digital simulator Carry out option board Card Type.
In the embodiment of the application, digital output interface, digital input interface and simulation input interface, respectively with number It is connected between word amount input card, digital output card and analog output card using conducting wire.Use conducting wire connection can be with Effectively ensure the transmission of signal, improves the reliability and stability of the application connection.
In the embodiment of the application, as shown in Fig. 2, current transformer circulation test model includes power grid, breaker, first Transformer, current transformer major loop, the first reactor, the second transformer;Power grid, breaker, the first transformer, current transformer master return Road, the first reactor and the second transformer are sequentially connected electrically, and the other end of the second transformer be connected to the first transformer with Between current transformer major loop.
When practical application, electricity is taken from power grid first, and electric energy is sent through breaker to the first transformer, and the first transformer is by electric energy It send to current transformer major loop;Current transformer major loop send the three-phase alternating current that inversion exports to the first reactor, the first reactor Three-phase alternating current is filtered, filtered three-phase alternating current is sent through the second transformer to the first transformer.Thus the application The entire test macro of current transformer circulation test model form circulation circuit, power not feed-in power grid, breaker is for controlling electricity The division of net and circulation circuit.
In the embodiment of the application, as shown in figure 3, current transformer major loop includes first switch, second switch, third Switch, capacitor, the second reactor, converter module, third reactor and the 5th switch;First switch, the second reactor, Converter module, third reactor and the 5th switch are sequentially connected in series;Second switch is connected in parallel with first switch;Capacitor One end be connected to the node between first switch and the second reactor, the other end is connect with ground terminal.
Further, converter module includes the grid-side converter being sequentially connected electrically, brake circuit, discharge loop and machine Side current transformer;Grid-side converter is electrically connected with the second reactor, and generator-side converter wear is electrically connected with third reactor.
Specifically, in conjunction with shown in Fig. 1 and Fig. 3, current transformer circulation test model is based on real-time digital simulator 103 and takes It builds, real-time digital simulator can be according to current transformer power grid environment, converter topology, inverter type, control logic, different simulations Amount acquisition signal carries out flexible programming.When carrying out the current transformer circulation emulation testing of different type, different topology structure, only need The control circuit for changing current transformer major loop, switch, keeps it consistent with true current transformer.Therefore the embodiment of the present application is not only flexible Property is stronger, but also may be implemented to become under the current transformer to different voltages grade, different topology structure and different scenes in real time The Curve guide impeller and parameter tuning of stream device control are tested.
It should be noted that the application does not limit the topological structure of current transformer circulation test model, such as some other Embodiment in, current transformer circulation test model can be chosen according to actual set type, and double PWM converter moulds such as can be used Type can also use the PWM converter (i.e. uncontrollable rectifier+Boost+PWM of uncontrollable rectifier combination Boost (boost chopper) Current transformer), therefore the application is not limited thereto.
Optionally, when current transformer voltage class difference to be measured, can be cooperated by the first transformer and the second transformer, So that voltage adjusted is met the requirement of current transformer voltage class, further improves the flexibility and applicability of the application.
As shown in Fig. 2, in the present embodiment, real-time digital simulator 103 can be by GTDI board from inverter controller 102 obtain the control signal of switch, so that the control circuit to control switch may be implemented to own in current transformer major loop Switch is controlled;Real-time digital simulator 103 can export the status signal switched to current transformer by GTDO board simultaneously Controller 102.
In the embodiment of the application, as shown in Fig. 2, the first transformer, current transformer major loop, the first reactor and Second transformer is established in small step-length model, and power grid and the first breaker are established in big step-length model.Wherein small step-length mould The step-length of type is 2 microseconds, and the step-length of big step-length model is 50 microseconds.It can be designed so that the embodiment of the present application control using this That makes is finer, improves the test effect of the embodiment of the present application.
As shown in figure 3, in the embodiment of the application, the second reactor, capacitor and the first transformer composition the One filter, first filter are used to filter out the harmonic wave of grid-side converter inversion generation.Third reactor, the first reactor and The equivalent reactance and capacitor of two transformers, the first transformer form second filter, and second filter is for filtering out pusher side change Flow the harmonic wave that device generates.First filter and second filter may each be LCL filter, but the application not as Limit.
In the embodiment of the application, the quantity and the number of windings phase of current transformer of the first reactor and the second transformer Match.The applicability and flexibility that the application can be effectively improved using above-mentioned setting, further improve the scope of application of the application.
In the embodiment of the application, in conjunction with referring to figs. 1 to Fig. 3, inverter controller 102 and current transformer test model Between be formed with a plurality of communication data stream, and a plurality of communication data flow direction is that unidirectional and its communication modes are logical for number News.Wherein the first data flow D1 and the second data flow D2 passes through the progress signal transmission of GTDI board.First data flow D1 be from Inverter controller 102 flows to real-time digital simulator 103, and communication main signal is the control signal of switch, including first opens The control signal that pass, second switch, third switch, the 4th switch and the 5th switch.
Second data flow D2 is that real-time digital simulator 103 is flowed to from inverter controller 102, and communication main signal is to use In control grid-side converter, generator-side converter wear, brake circuit pulse signal.
Third data flow D3 is inverter controller 102 to be flowed to from real-time digital simulator 103, and third data flow passes through GTDO board carries out signal transmission.Communication main signal is switch state signal, including first switch, second switch, third are opened The status signal of pass, the 4th switch and the 5th switch.
4th data flow D4 is inverter controller 102 to be flowed to from real-time digital simulator 103, and the 4th data flow passes through GTAO board carries out signal transmission.Communication main signal is the analog signals that flows device controller and need to detect, including net side A phase electricity Pressure, net side B phase voltage, net side C phase voltage, net side IGBT A phase current, net side IGBT B phase current, net side IGBT C phase electricity Stream, capacitor branches A phase current, capacitor branches B phase current, capacitor branches C phase current, brake circuit electric current, direct current Pressure, pusher side A phase voltage, pusher side B phase voltage, pusher side C phase voltage, pusher side IGBT A phase current, pusher side IGBT B phase current, pusher side IGBT C phase current.
It should be noted that the above communication signal is fundamental quantity needed for realizing the embodiment of the present application, in some other realities It applies in example, it may be necessary to which extension increases other communication signals, therefore the application is not limited thereto.
Using the embodiment of the present application, at least can be realized it is following the utility model has the advantages that
The application by using building current transformer circulation test model, inverter controller in advance in real-time digital simulator Debugging system communication connection is monitored with real-time digital simulator and current transformer respectively.By to current transformer control and control strategy Test can give full play to Real-time Simulation Technology so that current-variable controller and strategy agree with current transformer hardware perfection Current transformer circulation test model and inverter controller are interconnected, are provided more for current transformer in current transformer R&D process by advantage The testing process for sticking on nearly practical circulation system, is particularly suitable for before actual rings current test to the contained operation journey of inverter controller The research of the l-G simulation test of sequence and its hardware.
Further, current transformer test platform provided by the present application can be identical as practical current transformer circulation operating condition, can It realizes real-time current transformer circulation test, provides more convenient and fast means of testing for the exploitation of novel current transformer.The application can be with It realizes by modification any node, any loop voltage, the sampled value of electric current, so that it is collected to influence inverter controller Voltage, current signal realize current transformer voltage, electric current, frequency class fault test, such as over-voltage, under-voltage, overcurrent, frequency height, frequency Low failure, therefore the application may be implemented to test the current transformer of the full specification of total power.In addition the application also achieves pair The flexible control of switch provides basis etc. for inverter controller basic function, the test of Switch error protection.
Term " first ", " second " be used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance or Implicitly indicate the quantity of indicated technical characteristic." first " is defined as a result, the feature of " second " can be expressed or imply Ground includes one or more of the features.In the description of the present invention, unless otherwise indicated, the meaning of " plurality " is two It is a or more than two.
In the description of the present application, it should be noted that unless otherwise clearly defined and limited, term " connection " should be done It broadly understood, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can be directly connected, The connection inside two elements can also be can be indirectly connected through an intermediary.For those of ordinary skill in the art For, the concrete meaning of above-mentioned term in the present invention can be understood with concrete condition.
The above is only some embodiments of the application, it is noted that for the ordinary skill people of the art For member, under the premise of not departing from the application principle, several improvements and modifications can also be made, these improvements and modifications are also answered It is considered as the protection scope of the application.

Claims (8)

1. a kind of test platform of current transformer, for testing inverter controller (102), which is characterized in that the change The test platform of stream device includes: current transformer monitoring debugging system (101) and real-time digital simulator (103);The real-time number Current transformer circulation test model has been built in word emulating instrument (103) in advance;
Current transformer monitoring debugging system (101) and the inverter controller (102) communication connection;
The inverter controller (102) and the real-time digital simulator (103) communication connection, the real-time digital simulator (103) for the switch state signal of the current transformer circulation test model and analog signals to be sent to the current transformer Controller (102), and the control for receiving the transmission of the inverter controller (102) Xiang Suoshu current transformer circulation test model refers to It enables.
2. the test platform of current transformer as described in claim 1, which is characterized in that the current transformer monitors debugging system (101) pass through Ethernet and interchanger communication connection between the inverter controller (102).
3. the test platform of current transformer as described in claim 1, which is characterized in that inverter controller (102) setting There are digital output interface, digital input interface and simulation input interface;
The real-time digital simulator (103) is provided with digital output card, digital input card and analog output Card;
The digital output interface, the digital input interface and the simulation input interface, respectively correspond and the digital quantity Input card, the digital output card and the analog output card communication connection.
4. the test platform of current transformer as claimed in claim 3, which is characterized in that the digital output interface, the number Input interface and the simulation input interface, respectively with the digital input card, the digital output card and described It is connected between analog output card using conducting wire.
5. the test platform of current transformer according to any one of claims 1 to 4, which is characterized in that the current transformer ring Current test model includes power grid, breaker, the first transformer, current transformer major loop, the first reactor, the second transformer;
The power grid, breaker, the first transformer, current transformer major loop, the first reactor and the second transformer are successively electrically connected It connects, and the other end of second transformer is connected between first transformer and the current transformer major loop.
6. the test platform of current transformer as claimed in claim 5, which is characterized in that the current transformer major loop is opened including first Pass, second switch, third switch, capacitor, the second reactor, converter module, third reactor and the 5th switch;
The first switch, second reactor, the converter module, the third reactor and it is described 5th switch according to Secondary series connection;
The second switch is connected in parallel with the first switch;
One end of the capacitor is connected to the node between the first switch and second reactor, the other end and ground connection End connection.
7. the test platform of current transformer as claimed in claim 6, which is characterized in that the converter module includes successively being electrically connected Grid-side converter, brake circuit, discharge loop and the generator-side converter wear connect;
The grid-side converter is electrically connected with second reactor, and the generator-side converter wear is electrically connected with the third reactor It connects.
8. the test platform of current transformer as claimed in claim 6, which is characterized in that first reactor and second change The quantity of depressor and the number of windings of current transformer match.
CN201821697794.1U 2018-10-18 2018-10-18 The test platform of current transformer Active CN208902817U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821697794.1U CN208902817U (en) 2018-10-18 2018-10-18 The test platform of current transformer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821697794.1U CN208902817U (en) 2018-10-18 2018-10-18 The test platform of current transformer

Publications (1)

Publication Number Publication Date
CN208902817U true CN208902817U (en) 2019-05-24

Family

ID=66576242

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821697794.1U Active CN208902817U (en) 2018-10-18 2018-10-18 The test platform of current transformer

Country Status (1)

Country Link
CN (1) CN208902817U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110673508A (en) * 2019-09-02 2020-01-10 南方电网科学研究院有限责任公司 Method and device for building closed loop test platform suitable for various scenes
CN111722037A (en) * 2020-06-11 2020-09-29 天津瑞能电气有限公司 Single-phase cascade converter test platform

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110673508A (en) * 2019-09-02 2020-01-10 南方电网科学研究院有限责任公司 Method and device for building closed loop test platform suitable for various scenes
CN110673508B (en) * 2019-09-02 2023-04-14 南方电网科学研究院有限责任公司 Method and device for building closed-loop test platform suitable for multiple scenes
CN111722037A (en) * 2020-06-11 2020-09-29 天津瑞能电气有限公司 Single-phase cascade converter test platform

Similar Documents

Publication Publication Date Title
CN104076693B (en) Flexible direct current transmission real-time simulation system and simulation method thereof
CN103268117B (en) MMC flexible direct-current control device testing system and method based on RTDS
US9659114B2 (en) Real time dynamic physics simulation device of flexible DC transmission system
CN104155616B (en) Photovoltaic system current transformer test platform
CN102403916B (en) Design method of simulation accelerating circuit
CN104953582B (en) A kind of three phase network disturbing generating device and its control method
CN103345162B (en) A kind of power level digital-analog hybrid simulation system
CN109709363B (en) Control method and system of cascade type converter multi-submodule multi-working-condition simulation device
CN106814263A (en) A kind of grid-connected detecting system of HWIL simulation and method
CN103257314A (en) Power grid adaptability testing system of mobile wind turbine generator
CN208902817U (en) The test platform of current transformer
CN107315112A (en) A kind of MW class wide-band impedance measurement apparatus and its control method
CN201749157U (en) Frequency converter power module test circuit of wind driven generator
CN102253296A (en) Method for testing comprehensive device of transformer
CN206471834U (en) Distribution transforming three-phase imbalance governing system
CN104063536B (en) Soft start simulation method for modular multi-level converter
CN109190320A (en) Parallel Heterogeneous simulation method suitable for ADPSS double-fed blower closed-loop test
CN108957292A (en) A kind of common type of power module testing circuit, system and test method
CN105134506B (en) A kind of performance test emulation platform of double-feedback aerogenerator group frequency-variable controller
CN103475016A (en) Simulation method for converter station in HVDC (high voltage direct current) electric power transmission project
CN106291207A (en) A kind of chain type SVG module test system, platform and method
CN105513903A (en) Debugging platform of circuit breaker
CN203164379U (en) Movable wind turbine electric-grid adaptability test system
CN103312188A (en) Power supply and testing method used for testing performance of electric reactor in power electronic device
CN103338025B (en) A power frequency induction adjustable resonance apparatus and a frequency modulation method thereof for determining a power frequency in-series resonant condition

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant